23.1(2) the Contractor sal give writen notve tothe Architect his intention toe
such extension of ime together with a inital estate ofthe extension of
me he may require supported wit ll particulars of the cause of delay. Such
‘notice must be given within twenty eight (28) Days from the date of the Al.
CCT or the commencemont of the Relevant Event, whichever is arin. Th
iving of such writen notice shall be a condition precedent to an entilement
brextension of me; and
23.1(8) within wen eight (28) Days of the end ofthe cause of dla, the Contactor
hall send to the Architect his final elim foe extension of ime duly supported
‘with ll particulars to enable the Architect to assess any extension of time o be
‘ranted, Ifthe Contractor fis to submit such particulars within the stated time
(or within such longer period as may be agreed in writing by the Architect), it
Shall be dcested at de Castanos ln asesoed il pls Relevant Br wll
‘not delay the completion ofthe Works beyond the Completion Date.
Delay by 22 Where the paiculars of the weten notice given under Clause 23.1 include references to
‘Nominated Sub- [Nominated Sub-Contractors, the Contactor shall frhwith send a copy of such writen
Contractor notice and particulars to the Nominated Suo-Contractoeconeemed,
Insufficient 233 If the Architect is of the opinion that the particulars submited by the Contractor are
information insufficient to enable him to decide on the application for extension of time, the Architect
shall within twenty eight (28) Days ffom receipt of the Conractor's paclars under
Cause 23.1(), inform him of any defieieey In his submission and may require the
Contractor 10 provide Such further particulars wihin a further twenty eight (28) Days or
vada pri Gn any Uae y de Avie wating
Certificate of 24 When the Contractor has submited sufficient particulars forthe Architects consideration,
Extension of the Architect shall subject to Clauses 23.5, 23.6 and 23.8, consider the Contractor's
Time submission and shall ether rejet the Contractor's application or issue a Certificate of
Extension of Time win sic (6) Weeks ftom the receipt of sufficient pariculars. The
Architect may issue the witen notice of rejection or the Certifies of Extension of Time
befor or afer the Completion Dae
Other 25 In assessing the extension oftime, the Architect may tke into account the fllowing:
‘consideration for
extension of time 235(@) the effector extent of any work omitted under the Contact, provided always
that the Architoct shall not fix a Completion Dats cuir than the Completion
Date stated in the Appendix; and
2356) any other Relevant Events which inthe Architect's opinion will have an effect
‘on the Contractor's entiement to an extension of tine.
Contractor to 236 ‘The Contractor shall constanly use his best endeavour to prevent or reduce delay inthe
prevent delay progress of the Works, and to do all that may reasonably be requied tothe satistion of
the Architect to prevent and reduce delay or further delay in the completion of the Wocks
beyond the Completion Date
237 The Architect shall notify every Nominated Sub-Contractr in writing ofeach decision of
the Architect when fixing alter Complation Date.
Relevant Events 238 The fllowing are the Relevant Events refered to in Cause 23.0:
23.8(@) FoweMajeue,
23.800) exceptionally inclement weather
23.5(@) loss andor damage cocasined ty one or more ofthe contingencies referred to
sn Clause 20, 201 of 2U.C a8 the ease may be, provided aways thatthe
same isnot due to any negligence, omission, default andor breach of contract
bythe Contactor andlor Nominated Sub-Contastors,
23.5(4) civil commotion, srk of lockout affecting any ofthe trades employed upon
‘he Works or any ofthe trdes engaged in the preparation, manufictare or
‘transportation of any materials and goods require forthe Works;
PAM Cana 2006 (it Quant)PAM Cesc 2006 (With Quantities)
7.800)
2.00)
29@
200)
280)
23.80)
23.8)
23.80)
2.8m)
23.8(0)
23.8(0)
23.80)
2350)
23.06)
23.869)
2280)
the Contractor not having eeeiued indi time the necessary Al Gnclding
those for or in egard to the expenditure of P.C, Sums and Provisional Sums,
fre drawings, details, levels and any other information) for which he had
specifically applied in weiing to the Architect. The Contact's appliation
rust be submited to the Architect insufficient time before the
commonecment of construction ofthe aftcted works o enable the Atchitst
to ssve the necessary AI within a period which would not materially affect the
progress of the affected works, having regard to the Completion Dae.
Provided always thatthe AT was not required as a result of any negligence,
comission, defult and/or breach of contract by the Contractor andlor
Nominated Sub-Contractors;
delay by the Bmployee in pving postssion af the Se or any ection of the
Sito in acordance with Clauses 21.1 and 21.2;
‘compliance with Al issued by the Architect under Clases 14, 11.2 and 21.45,
lay on the prt of Nominated Gub-Contastrs forthe sasous act out
‘Clauses 21.4) to 21.4(w) ofthe PAM Sub-Contact 2006;
e-nominaton of Nominated Sub-Contactors a set out in Classe 27.115
eley on the part of craftsmen, radesmen oF other contactors employed oF
engaged by the Employer in executing work not forming part of the Contract
vile anton acevde sich el:
ele or flue in the supply of materials and goods which the Employer had
‘greed to supply forthe Works;
the opening up for inspection of any work covered up, ting sty material
‘g0ods or executed work in accordance with Clause 6:3, unless the inspection
ortest
{is provided for inthe Contact Bills;
shows that the works, materials and goods were not in
sccordance withthe Contract of
is required by the Architect in consequence of some prior
negligence, omission, default and/or breach of contact by the
Contractor,
any act of prevention or breach of contract bythe Employer;
war damage under Clause 32.1;
compliance with AI issued in connection with the discovery of antiques
under Cause 33.1;
compliance with any changes to any lw, regulations, by-law or tems and
conditions of any Appropriste Authority and Service Provider,
delay caused by any Appropriate Authority and Servie Provider in carrying
‘out, o¢ file to cimy eu their work which affects the Contractor's work
progress, provided alvays that such delay is not due to any negligence,
‘omission, defuit andlor breach of conract by the Contactor andlor
"Nominated Sub-Contractors;
appointment of a replacement Person under Ales 3, 4,5 and
‘compliance with AI issued in connection with disputes with neighbouring
propery owners provided always that such dispute is not caused by
negligence, omission, defeult andlor breach of contact by the Contractor
and/or Nominated Sub-Contactors;
aley oa emt oF he mation of wore fe which Provisional Quan
included in the Contract Bills which in the opinion ofthe Archit i nat a
reasonably accurate forecast ofthe quantity of work required;
2s