You are on page 1of 28

Bought by MR MARK SPINDLEY,Resdev Ltd,on 07/11/2012 08:38 Latest version. Not to be distributed/networked. For multi-user access www.bsigroup.

com/license © BSI

ICS 91.180; 97.150


BRITISH STANDARD

Code of practice for

floor coverings
Installation of resilient
+A1:2009
BS 8203:2001
BS 8203:2001+A1:2009
Bought by MR MARK SPINDLEY,Resdev Ltd,on 07/11/2012 08:38 Latest version. Not to be distributed/networked. For multi-user access www.bsigroup.com/license © BSI

Committees responsible for this


British Standard

The preparation of this British Standard was entrusted to Technical


Committee PRI/60, Resilient floor coverings, upon which the following bodies
were represented:

British Adhesives and Sealants Association


British Association for Chemical Specialities
British Railways Board
Contract Flooring Association
Cork Industry Federation
Department of Health
Health and Safety Executive
Industrial Cleaning Machine Manufacturers Association
Institute of Chartered Arbitrators
RAPRA Technology Ltd.
Soap and Detergent Industries Association
UK Resilient Flooring Association
Wood Panel Industries Federation

This British Standard, having


been prepared under the
direction of the Sector
Committee for Materials and
Chemicals, was published
under the authority of the
Standards Committee and
comes into effect on
15 January 2001

© BSI 2009 Amendments issued since publication


First published December 1987
Second edition June 1996 Amd. No. Date Comments
Third edition January 2001
A1 31 October 2009 See foreword
The following BSI references
relate to the work on this
standard:
Committee reference PRI/60
Drafts for commment
00/120381 DC
09/30174199 DC

ISBN 978 0 580 61089 9


BS 8203:2001+A1:2009
Bought by MR MARK SPINDLEY,Resdev Ltd,on 07/11/2012 08:38 Latest version. Not to be distributed/networked. For multi-user access www.bsigroup.com/license © BSI

Contents

Page
Committees responsible Inside front cover
Foreword ii
Section 1. General
1.1 Scope 1
1.2 References 1
1.3 Definitions 1
1.4 Exchange of information 3
Section 2. Materials
2.1 Underlays 5
2.2 Floor covering materials 5
2.3 Adhesives 6
Section 3. Design
3.1 Damp-proofing solid floors and eliminating construction moisture 7
3.2 Concrete and screed bases 8
3.3 Timber bases 8
3.4 Particleboard bases 8
3.5 Oriented strand board (OSB) bases 9
3.6 Floating floors 9
3.7 Other bases 9
3.8 Fabricated underlays 9
3.9 In situ underlays 10
3.10 Smoothing underlayments 10
3.11 Protection against heat 11
3.12 Fire hazard 11
3.13 Skirtings and covings 11
3.14 Edging and dividing strips 11
3.15 Stairs 11
Section 4. Installation
4.1 Liaison and workmanship 13
4.2 Storage 13
4.3 Underlays 13
4.4 Laying 14
4.5 Initial treatment and maintenance 17
4.6 Protection 17
4.7 Underfloor heating 17
Annex A (normative) Dampness testing 18
Annex B (normative) Assessment of levels and surface regularity 20
Figure 1 — Typical apparatus 19
List of references 21

© BSI 2009 i
BS 8203:2001+A1:2009
Bought by MR MARK SPINDLEY,Resdev Ltd,on 07/11/2012 08:38 Latest version. Not to be distributed/networked. For multi-user access www.bsigroup.com/license © BSI

Foreword

This British Standard has been prepared by Technical Committee


PRI/60. It is a revision of BS 8203:1996 which is withdrawn.
BS 8203:2001+A1:2009 supersedes BS 8203:2001, which is withdrawn.
The start and finish of text introduced or altered by Amendment No. 1:2009 is
indicated in the text by tags !".
As a code of practice, this British Standard takes the form of guidance and
recommendations. It should not be quoted as if it were a specification and
particular care should be taken to ensure that claims of compliance are
not misleading.
This publication does not purport to include all the necessary provisions
of a contract. Users are responsible for its correct application.
Compliance with a British Standard cannot confer immunity
from legal obligations.

Summary of pages
This document comprises a front cover, an inside front cover, pages i and ii,
pages 1 to 22, an inside back cover and a back cover.
The BSI copyright notice displayed in this document indicates when the
document was last issued.

ii © BSI 2009
BS 8203:2001+A1:2009
Bought by MR MARK SPINDLEY,Resdev Ltd,on 07/11/2012 08:38 Latest version. Not to be distributed/networked. For multi-user access www.bsigroup.com/license © BSI

Section 1. General 1

1.1 Scope 1.3.2


agglomerated composition cork with
This British Standard gives recommendations for polyvinyl chloride wear layer
the installation of the following floor coverings on
a floor covering whose main component is
both new and existing constructions:
agglomerated cork and whose wear layer is a
a) cork floor coverings; homogeneous polyvinyl chloride layer
b) linoleum floor coverings; 1.3.3
c) plastics floor coverings; base
the supporting structure to which the floor covering
d) rubber floor coverings.
is to be applied
Special measures are necessary for successful
installation of floor coverings such as those used for 1.3.4
static control, and are not included in this standard. concrete base slab
a concrete slab cast as part of the building
This British Standard does not cover the construction
installation of these floor coverings on access
flooring. 1.3.5
This British Standard does not include advice on cork floor covering
cleaning and maintenance (which is given a floor covering whose main component is
in BS 6263-2) but it does include guidance on the agglomerated cork and whose wear layer is intended
decisions which should be made at the design stage to be used with a finishing coat(s)
which will assist cleaning and maintenance and 1.3.6
enable the installation to give satisfactory service.
cork linoleum
1.2 References a product produced by calendering a homogeneous
mixture of linoleum cement, granulated cork,
1.2.1 Normative references pigment and inorganic filler onto a fibrous backing
This British Standard incorporates, by dated or 1.3.7
undated reference, provisions from other corkment
publications. These normative references are made
a product produced by a homogeneous mixture of
at the appropriate places in the text and the cited
linoleum cement, granulated cork, pigment and
publications are listed on page 21. For dated
references, only the edition cited applies; any inorganic fillers on a fibrous backing
subsequent amendments to or revisions of the cited 1.3.8
publication apply to this British Standard only cover joint
when incorporated in the reference by amendment a metallic or plastic finishing element which helps
or revision. For undated references, the latest to protect a junction between two floor coverings
edition of the cited publication applies, together which could be different in type and/or thickness
with any amendments.
1.3.9
1.2.2 Informative references
expanded polyvinyl chloride floor covering
This British Standard refers to other publications (cushioned polyvinyl chloride)
that provide information or guidance. Editions of a floor covering with a transparent wear layer over
these publications current at the time of issue of this a layer of foamed polyvinyl chloride carrying a
British Standard are listed on page 22, but reference printed pattern, which may be embossed in register
should be made to the latest editions. with the printed pattern
1.3 Definitions 1.3.10
For the purposes of this British Standard the fabricated underlay
definitions in BS 6100 and the following definitions a prefabricated board applied to a subfloor to
apply. provide a smooth, even surface suitable for the
installation of a floor covering
1.3.1
agglomerated composition cork 1.3.11
a compound of cork granules with a binder generally flexible
not derived from cork cells the generic term for floor coverings which can be
bent over a mandrel under specified conditions

© BSI 2009 1
BS 8203:2001+A1:2009 Section 1
Bought by MR MARK SPINDLEY,Resdev Ltd,on 07/11/2012 08:38 Latest version. Not to be distributed/networked. For multi-user access www.bsigroup.com/license © BSI

1.3.12 1.3.22
floor covering polyvinyl chloride floor covering on polyester
a product prefabricated in sheet or tile form, which felt with polyvinyl chloride backing
can be used to cover floors from wall to wall a floor covering consisting of a polyvinyl chloride
surface layer applied to a polyester felt with a
1.3.13 polyvinyl chloride backing
heterogeneous floor covering
a floor covering consisting of a wear layer and other 1.3.23
compact layers which differ in composition and/or polyvinyl chloride floor covering with cork
design and may contain a reinforcement based backing
a floor covering with a homogeneous or
1.3.14 heterogeneous polyvinyl chloride surface layer over
homogeneous floor covering a layer of corkment (see 1.3.5) or of cork with a
a floor covering with one or more layers of the same polyvinyl chloride binder
composition and colour, patterned throughout its
thickness 1.3.24
primer
1.3.15 a liquid product applied to a subfloor, or base, prior
linoleum to the application of either smoothing compound or
a product produced by calendering a homogeneous adhesive, to seal a porous base and aid adhesion of
mixture of linoleum cement, cork- and/or the subsequent application
wood-flour, pigments and inorganic filler onto a
fibrous backing 1.3.25
resilient
1.3.16 a material which is able to recover after
linoleum cement compression, e.g. plastics, rubber, cork or linoleum
the binder in linoleum, consisting of a mixture of
linseed oil and/or other vegetable drying oils, rosin 1.3.26
and normal drying oil catalysts, which is converted riser
to a semi-elastic mass by an oxidative curing process the vertical part of a step
1.3.17 1.3.27
machine direction rubber floor covering
the direction in which certain floor coverings are a floor covering in sheets or tiles, based on natural
manufactured or synthetic rubber
1.3.18 1.3.28
nosing screed
the projecting edge of a step or a metal or plastics a sand and cement topping applied over concrete
finishing profile fixed in this position base slab and finished to receive the floor covering
1.3.19 1.3.29
polyvinyl chloride floor covering semi-flexible polyvinyl chloride floor covering
a floor covering with surface layers which are a floor covering of tiles made from polyvinyl chloride
produced using polyvinyl chloride (and modifications thereof) which can only be
(and modifications thereof) as binder deflected under specified conditions
1.3.20 1.3.30
polyvinyl chloride floor covering on jute smoothing compound
backing a smoothing and/or levelling compound applied to a
a floor covering consisting of a polyvinyl chloride subfloor to provide a smooth, even surface suitable
layer applied to a jute felt backing for the installation of a floor covering
1.3.21 1.3.31
polyvinyl chloride floor covering on polyester subfloor
backing see “base” (1.3.3)
a floor covering consisting of a polyvinyl chloride
1.3.32
surface layer applied to a polyester felt backing
surface damp-proof membrane
a material applied to the surface of the subfloor to
inhibit the passage of water vapour

2 © BSI 2009
Section 1 BS 8203:2001+A1:2009
Bought by MR MARK SPINDLEY,Resdev Ltd,on 07/11/2012 08:38 Latest version. Not to be distributed/networked. For multi-user access www.bsigroup.com/license © BSI

1.3.33 1.4.3 Design


surface preparation The flooring layout, and specifications, based on
a set of operations carried out on the subfloor to building type and occupational uses should be
allow the floor covering to be laid correctly provided, e.g.:
1.3.34 a) type and density of foot and/or wheeled traffic;
tread
b) resilience characteristics;
the horizontal part of a step
c) acoustic absorption levels;
1.3.35
d) particulars of wet, corrosive, staining or
underlayment
potentially abrasive conditions.
a term used in this code to describe a smoothing
compound or a levelling compound 1.4.4 Floor details
1.3.36 The completed drawings/specification should
vinyl provide comprehensive information on:
a term commonly used to describe polyvinyl chloride a) whether upper floor, ground floor or below
ground level;
1.3.37
welding b) whether ground-supported or suspended
the formation of a sealed joint between sheets or construction;
tiles c) particulars of any under floor heating
1.3.38 installation or security installation;
welding rod d) position and treatment of expansion joints;
a material in the form of a cord, which is used to join e) curing and drying times of screeds and bases
sheets or tiles likely to be required before the installation of floor
1.4 Exchange of information coverings;
f) screed or base with finished floor level,
1.4.1 General permissible departure from datum and class of
In order for the correct floor covering to be installed surface regularity required;
in appropriate conditions, at the right time, etc., it is g) in refurbishment work, the type and condition
essential that all parties have a clear understanding of existing base or floor finish and any type of
of the requirements of the project, e.g. new build or treatment required;
refurbishment, and of the implications for all
concerned. To ensure that this is achieved, it is h) type of damp-proof membrane and position
essential that there is wide consultation between all within the floor construction, in particular, the
parties involved in the project, including need for surface applied membrane where likely
sub-contractors and materials suppliers. This drying times for the base exceed time available in
consultation should start early in the design stage the programme;
but will be necessary throughout the contract, i) choice of underlay, underlayments and
especially should requirements or time scales adhesives, or special requirements, e.g. seam
change and as new sub-contract work is initiated. welding and direction of material;
As each project will be unique it is impossible to give j) size, position and design of entrance flooring
a definitive list of the information to be exchanged, systems.
but the following are typical examples.
1.4.5 Entrance flooring systems
1.4.2 Project
Entrance flooring systems will reduce the dirt, grit
The name and location of projects and personnel and water carried into the building by foot traffic,
involved in pre-contract negotiations should be hence will reduce wear and the risk of slipping when
identified. the building is in service. The size, position and
design of entrance flooring systems should be
considered at the design stage (see BS 7953).

© BSI 2009 3
BS 8203:2001+A1:2009 Section 1
Bought by MR MARK SPINDLEY,Resdev Ltd,on 07/11/2012 08:38 Latest version. Not to be distributed/networked. For multi-user access www.bsigroup.com/license © BSI

1.4.6 Associated details 1.4.10 Responsibilities


Details of abutments, skirtings, services Responsibilities for cleaning the construction on
(embedded or sleeved), movement joints, separating completion and giving it initial protection should be
strips, pattern or border details and junctions with defined.
other adjacent flooring and door clearances should
be provided. 1.4.11 Maintenance
Clear written instructions on the recommended
1.4.7 Contract conditions
maintenance methods appropriate for the various
A programme for commencement and completion of floor coverings should be provided for the occupier
work should be defined, including any specific (see BS 6263-2).
requirement for sequenced completion
[see especially 1.4.4e)].
1.4.8 Special attendance
Access, unloading, hoisting and storage facilities,
heat, light and power and any additional items
considered necessary to expedite the work should be
provided.
1.4.9 Testing
For any conformity testing of the base, screed, floor
covering, etc. details should be provided and
responsibilities defined. For instance, it is essential
that the responsibility is defined for ensuring that
bases or screeds meet the specified standards for
level, smoothness, dryness and soundness (impact
crushing resistance) before any subsequent or
finishing trades are called to commence work. In
most circumstances this will be the responsibility of
the main contractor.

4 © BSI 2009
BS 8203:2001+A1:2009
Bought by MR MARK SPINDLEY,Resdev Ltd,on 07/11/2012 08:38 Latest version. Not to be distributed/networked. For multi-user access www.bsigroup.com/license © BSI

Section 2. Materials 2

2.1 Underlays 2.2 Floor covering materials


2.1.1 General 2.2.1 General
Guidance on the selection and use of underlays Resilient floor coverings should conform to the
appropriate to the various floor coverings and bases appropriate British/European Standards. Floor
is given in 3.6, 3.7 and 3.8. coverings of different specifications may become
available during the life of this British Standard
2.1.2 Fabricated underlays and separate standards may be issued to cover
Fabricated underlays should be selected from the them. Unless the manufacturers of these products
following: state to the contrary, the installation techniques
described in this British Standard will also be
a) plywood conforming to BS EN 636 !text
appropriate for these materials.
deleted" (see !3.8.2" );
b) particleboard Type P2 conforming to 2.2.2 Cork floor coverings
BS EN 312 !text deleted" , or if improved Cork tiles should conform to BS EN 12104.
bending strength and stiffness are required,
Type P4 conforming to BS EN 312 !text 2.2.3 Linoleum floor coverings
deleted" (see !3.4" ). The board Linoleum floor coverings should be one of the
should not have any surface treatment following types:
which might affect adhesion;
a) plain and decorative linoleum conforming
c) hardboard Type HB conforming to to BS EN 548;
BS EN 622-2 !text deleted" , high density
medium board Type MBH conforming to b) linoleum on a foam backing conforming
to BS EN 686;
BS EN 622-4 !text deleted" and medium
density fibreboard Type MDF conforming to c) linoleum with corkment backing conforming
BS EN 622-5 !text deleted" (see !3.8.4" ). to BS EN 687;
2.1.3 In situ underlays d) cork linoleum conforming to BS EN 688.
In situ underlays should be selected from the 2.2.4 Plastics floor coverings
following:
Plastics floor coverings should be one of the
a) mastic asphalt conforming to grade 1 of following:
BS 6925:1988;
a) homogeneous and heterogeneous flexible
b) cementitious underlay consisting of a specially unbacked polyvinyl chloride conforming
formulated blend of cement and binder and both to BS EN 649;
fine and coarse aggregates. The binder is
b) jute or polyester backed polyvinyl chloride and
commonly a natural rubber latex or synthetic
polyvinyl chloride on polyester felt with polyvinyl
polymer.
chloride backing conforming to BS EN 650;
2.1.4 Underlayments c) flexible polyvinyl chloride with polyvinyl
Underlayments should be selected from the chloride foam layer conforming to BS EN 651;
following: d) flexible polyvinyl chloride with cork based
a) cementitious underlayment consisting of a backing conforming to BS EN 652;
specially formulated blend of cement, binder and e) expanded (cushioned) polyvinyl chloride
fine aggregate. The binder is commonly a natural conforming to BS EN 653;
rubber or synthetic polymer dispersion;
f) semi-flexible polyvinyl chloride tiles conforming
b) powder/water mixes based on casein/cement or to BS EN 654;
polymer/cement and fine aggregate;
g) tiles on a base of agglomerated composition
c) epoxy or other resin compounds. cork with a polyvinyl chloride wear layer
conforming to BS EN 655.

© BSI 2009 5
BS 8203:2001+A1:2009 Section 2
Bought by MR MARK SPINDLEY,Resdev Ltd,on 07/11/2012 08:38 Latest version. Not to be distributed/networked. For multi-user access www.bsigroup.com/license © BSI

2.2.5 Rubber floor coverings 2.3 Adhesives


Rubber floor coverings should be one of the General guidance on the types of adhesive
following: commonly used for laying floor coverings is given in
a) homogeneous and heterogeneous smooth BS 5442-1. The choice of adhesive will be influenced
rubber with foam backing conforming by the floor covering material, the nature of the
to BS EN 1816; sub-floor and the underlay, if any, site conditions
during installation and service conditions.
b) homogeneous and heterogeneous smooth
rubber conforming to BS EN 1817; The special recommendations of the floor covering
and adhesives manufacturer should be followed. If
c) homogeneous and heterogeneous relief rubber these recommendations differ, further consultation
conforming to BS EN 12199. between the interested parties should take place.
For safety aspects see 4.4.3.4.
NOTE None of the adhesives can be considered effective as a
damp-proof membrane.

6 © BSI 2009
BS 8203:2001+A1:2009
Bought by MR MARK SPINDLEY,Resdev Ltd,on 07/11/2012 08:38 Latest version. Not to be distributed/networked. For multi-user access www.bsigroup.com/license © BSI

Section 3. Design 3

3.1 Damp-proofing solid floors and For thick concrete bases laid directly over a
eliminating construction moisture damp-proof membrane long drying times are
required. The time/thickness relationship used to
3.1.1 Damp-proofing solid floors predict the drying time of cement(s) and screeds
does not apply to concrete bases. In practice it has
As the floor coverings covered by this British
been found that even under good drying conditions
Standard together with many adhesives and
concrete bases 150 mm thick often take more than
smoothing compounds used with them may be
one year to dry from one face only. Moderate and
adversely affected by moisture, subfloors should be
heavy use of power-float/power-trowel finishing
so constructed as to protect the floor covering
methods further delays drying.
installation from moisture or water vapour from the
ground. Suspended concrete bases laid on to permanent
metal shuttering or other impermeable materials
Materials and methods for damp-proofing solid
will have similar drying times to those laid over
floors are described in CP 102 and BS 8102 and it
damp-proof membranes. For slabs which can dry
should not be assumed that existing
from both sides, about half the thickness can be
ground-supported concrete floors are adequately
considered to dry downwards.
damp-proofed. Where existing structures do not
incorporate adequate moisture protection Where screeds are laid directly on to the concrete
proprietary surface applied membranes or mastic bases, without a damp-proof membrane between
asphalt should be used. Integral waterproofers them, account should be taken of the time required
incorporated in the concrete or screed will not to dry the total thickness of the construction.
provide adequate damp protection for the floor Commonly, where floor coverings are to be laid, time
coverings and will retard the drying process. Beam schedules do not permit extended drying times for
and block construction floors, whether finished with concrete bases. The use of sandwich damp-proof
cement-sand, screed or particle board, should membranes between the base concrete and the
incorporate a vapour control layer. screed significantly reduces the time that needs to
3.1.2 Eliminating construction moisture be allowed for drying.
!Before moisture sensitive flooring is laid on a Proprietary systems either based on admixtures for
concrete base it is necessary to ensure, not only normal screed and concrete mixes or special
that the floor is constructed to prevent moisture cements are available to produce early drying
from reaching it from the ground, but also that screeds and concrete.
any excess water from construction is dissipated. 3.1.3 Protection against construction moisture
It is essential that the excess water in the base
Where time scales do not allow sufficient drying
(above any membrane) is allowed to evaporate,
times and the use of a sandwich damp-proof
and the time for this to happen should be taken
membrane is inappropriate the need for a surface
into account at the planning stage. damp-proof membrane to control the excess
The flooring should not be laid until a hygrometer construction moisture in the subfloor should be
test carried out in accordance with BS 8201:1987, taken into account at the design stage.
A.1, gives a reading of not more than 75% relative 3.1.4 Testing
humidity.
Cementitious subfloors should be tested by the
Estimated drying times are necessarily very method described in Annex A and the floor covering
approximate as drying is influenced by ambient not laid until readings have been obtained which
conditions, concrete quality, surface finish and indicate a relative humidity of 75 % or less.
thickness; of these, surface finish and thickness
Independent studies have shown that a
are the most important. non-invasive test of the type described in Annex A is
NOTE The moisture content of any supporting concrete can the only suitable method relevant for use in
be of great importance when impermeable floor coverings are conjunction with installation of resilient floor
to be laid over parts of a wood floor." coverings.
For cement-sand screeds laid directly over a
damp-proof membrane, one day should be allowed
for each millimetre of thickness for the first 50 mm,
followed by an increasing time for each millimetre
above this thickness. It is thus reasonable to expect
a screed 50 mm thick drying under good conditions,
to be sufficiently dry in 2 months.

© BSI 2009 7
BS 8203:2001+A1:2009 Section 3
Bought by MR MARK SPINDLEY,Resdev Ltd,on 07/11/2012 08:38 Latest version. Not to be distributed/networked. For multi-user access www.bsigroup.com/license © BSI

3.2 Concrete and screed bases This will act as a buffer and thereby help to
minimize movement in the boards which might
3.2.1 General affect the appearance of the floor covering.
The appearance and performance of the floor Uneven timber floors should be levelled by sanding,
coverings covered by this British Standard are planing or by patch-filling with a suitable
determined to a large extent by the quality of the cementitious smoothing underlayment before
prepared base or screed on which the various floor fabricated underlays are laid. Boarded floors nailed
coverings are laid. The subfloor should be into joists secured by clips set in concrete, or
constructed in accordance with the dovetailed battens set in concrete, or boards nailed
recommendations given in BS 8204-1. direct into concrete at ground level should be
Those responsible for the design and construction of adequately ventilated and protected by a
the subfloor should ensure that it meets the damp-proof membrane.
requirements for hardness, strength, soundness, 3.3.3 Wood blocks
levels and surface regularities (see BS 8204-1),
dryness and other design parameters before floor The laying of resilient floor coverings over bases of
covering installation is commenced. wood blocks may lead to problems. Any installation
should not be attempted unless the wood blocks
3.2.2 Surface treatments conform to the following:
3.2.2.1 Chemical hardening solutions a) the surface of the wood blocks is clean and free
from wax;
Chemical hardening solutions and resinous seals
should not be used on bases and screeds because of b) the condition of the floor is such that the blocks
the risk of interaction between the hardener and the are sound and firmly bonded;
floor covering adhesives. In cases where hardening c) the wood blocks are adequately protected
solutions have been used, it is essential that the against moisture.
treated surfaces are mechanically removed.
If the resilient floor covering is to be totally adhered,
3.2.2.2 Curing membranes consideration should be given to the possibility that
Curing membranes may affect adhesion and should the blocks could lift from the subfloor during the life
be mechanically removed. of the resilient floor covering and also when the
resilient floor covering is lifted for renewal.
3.2.2.3 Power floating/power trowelling of
The fixing of fabricated underlays listed in 2.1.2
directly finished concrete
may help to provide a smooth level surface.
Power floating/power trowelling of directly finished However, it is often found that the action of
concrete may affect adhesion and the advice of the installing the underlay causes the blocks to
adhesive manufacturer should be sought regarding fracture, or the wood block adhesive to fail,
the specification for surface preparation. particularly if it is embrittled by age. Because of
these problems, serious consideration should be
3.3 Timber bases given to the removal of the wood blocks and repair of
3.3.1 General the base prior to installation of the resilient floor
coverings. If any doubts exist regarding any of the
Timber bases should be sound, rigid, level and dry. conditions set out above, the wood blocks should be
The timber should be at equilibrium moisture removed.
content, i.e. the state of dryness it will attain in
normal service conditions, at the time it is covered. 3.4 Particleboard bases
In buildings where the wooden floors have received
an in-situ treatment for preservation, there may be !Text deleted"
an interaction between the preservative chemicals Particleboard should be free from surface sealers
and the adhesive or the floor covering. Advice such as wax, polyurethane of other types of seal
should be sought regarding suitable materials and and contaminants. Particleboard should be at the
remedial treatment. equilibrium moisture content it will have in
Suspended timber floors at ground level should be service at the time it is covered. A grade
adequately ventilated (see CP 102). appropriate for the construction of the floor,
nature of the building and the expected design
3.3.2 Board and strip floors loading should be ! either BS EN 312, Type
Where plain edged boards or tongued and grooved P4, Type P5, Type P6, or Type P7, or selected
boards have been nailed to joists or battens, the use from BS 8103-3 for domestic use. Fixing should
of one of the underlays listed in 2.1.2 is essential. conform to BS EN 12872 or the manufacturer’s

8 © BSI 2009
Section 3 BS 8203:2001+A1:2009
Bought by MR MARK SPINDLEY,Resdev Ltd,on 07/11/2012 08:38 Latest version. Not to be distributed/networked. For multi-user access www.bsigroup.com/license © BSI

requirements, where specified. " Boards should 3.7 Other bases


be tongued and grooved on at least two edges and
Some existing bases such as clay tiles, concrete tiles
the joints should be glued with a wood grade or terrazzo are unaffected by dampness, but may be
polyvinyl acetate (PVAc) adhesive, e.g. conforming sufficiently permeable to allow moisture to pass
to Class D1 of BS EN 204 !text deleted". through to the back of the floor covering. These
In situations where the gaps between adjacent bases, which should be otherwise sound, should be
boards are wider than 1 mm, consideration should damp-proofed when necessary by covering with a
be given to overlaying with a suitable fabricated surface damp-proof membrane or mastic asphalt.
underlay (see !3.8" ). Joints between tiles may cause problems with thin
surface damp-proof membranes.
!Text deleted"
Existing bases such as magnesium oxychloride
All particleboards should be primed as (magnesite) or those based on polyvinyl
recommended by the adhesive manufacturer. acetate/cement or gypsum based screeds are
adversely affected by dampness rising through
!Text deleted" concrete from the ground and should not be covered
with a damp-proof layer or with relatively
!3.5 Oriented strand board (OSB) impervious floor coverings. Unless it can be
established that there is an effective damp-proof
bases course below these materials, they should be
A flooring grade appropriate for the construction removed.
of the floor, nature of the building and the The practice of laying the floor coverings covered by
expected design loading should conform to this British Standard on top of existing sheet and
BS EN 300, Type OSB/2, Type OSB/3 or tile floor coverings is not recommended. Existing
Type OSB/4, and be covered with a suitable floor coverings and sufficient residual adhesive
fabricated underlay. should be removed to enable the subfloor to receive
the floor covering. The level of dryness of the base
3.6 Floating floors with regard to both rising moisture from the ground
The structural deck of the floating floor should be and residual moisture should be in accordance
of a suitable type and grade and fixed as specified with 3.1
by the designer of the floor.
3.8 Fabricated underlays
Where particleboard is employed as the top layer
of the floating floor, BS EN 312, Type P4, 3.8.1 General
Type P5, Type P6 or Type P7, flooring grade !Fabricated underlays should be laid where
within the scope of BS EN 13986 and of a required over existing timber bases (see 3.3).
thickness and type specified by the designer Wood-based fabricated underlays should be at the
should be used. Guidance on the installation of equilibrium moisture content they will have in
floating floors is given in the WPIF Industry service at the time they are covered. All fabricated
Standard 3/2008 [5] for particleboard and OSB, underlays should be not thicker than 9 mm
and in Annex B of BS EN 13810-1 for all board independent of material type. The thicker the
types. board, the greater its rigidity. Hardboard
NOTE It is permissible to sand off any raised areas of the underlays should not be used in areas intended
particleboard not exceeding 1 mm. If raised areas exceed 1 mm for public, commercial or light industrial use,
then additional levelling materials will be required." i.e. hardboard underlays should be used only in
areas of use classes 21, 22, 22+ and 23, as
classified in BS EN 685:2007.
NOTE Fibreboard underlays should be checked for suitability
for use in commercial and light industrial areas."

© BSI 2009 9
BS 8203:2001+A1:2009 Section 3
Bought by MR MARK SPINDLEY,Resdev Ltd,on 07/11/2012 08:38 Latest version. Not to be distributed/networked. For multi-user access www.bsigroup.com/license © BSI

3.8.2 Plywood 3.9.3.2 Synthetic polymer dispersion/cement


(aggregate filled)
Plywood should conform to BS EN 636 and should
be at least 4 mm thick. Where, due to the The properties of these materials vary widely in
irregularity of the base, improved rigidity is respect of, for example, water and solvent resistance
required, the use of 6 mm or thicker material should and resistance to point loading. The choice of
be considered. material should be made after considering the
manufacturer’s recommendations. Some of these
3.8.3 Fibreboards materials contain protein protected with
!Hardboards and MDFs should be at least antimicrobial and/or fungicidal additives.
3 mm thick and should conform to BS EN 622-2
and BS EN 622-5 respectively.
3.10 Smoothing underlayments
Hardboard underlay can be laid either mesh side 3.10.1 Natural rubber latex/cement
up or smooth side up. However, where it is critical This type is a general purpose smoothing
that there is no transfer of the pattern to the underlayment and should be used where foot and
surface, especially when using very thin floor light wheeled traffic only are anticipated. The
coverings, the underlay should be laid smooth side flexibility varies according to the formulation. The
up. higher the flexibility the greater the adhesion but
the lower the resistance to indentation. These
Hardboards should not be used as fabricated materials contain protein protected with
underlays for floor coverings of semi-flexible antimicrobial and/or fungicidal additives.
polyvinyl chloride tiles.
3.10.2 Synthetic polymer dispersion/cement
NOTE Historically, semi-flexible tiles have cracked and
rucked when laid over very thin hardboards with bitumen The properties of these materials vary widely in
adhesives." respect of, for example, water and solvent resistance
and resistance to point loading. The choice of
3.9 In situ underlays material should be made after considering the
manufacturer’s recommendations. Some of these
3.9.1 General materials contain protein protected with
antimicrobial and/or fungicidal additives.
In situ underlays may be used over cementitious
and similar bases. No single in situ underlayment is 3.10.3 Powder/water mixes
the most suitable for all conditions and selection will The properties of these materials vary very widely
depend on site conditions and occupational use. in respect of, for example, rigidity and resistance to
3.9.2 Mastic asphalt point loading. The choice of material should be made
after considering the manufacturer’s
Mastic asphalt should be laid in accordance with the recommendations.
recommendations of BS 8204-5. Where it is being
used as a combined underlay and damp-proof This type of smoothing underlayment is normally
membrane, care should be taken to provide only used on rigid, uncontaminated sand/cement
continuity with the damp-proof course in the walls. screeds or concrete bases. Some materials contain
protein protected with antimicrobial and/or
3.9.3 Cementitious fungicidal additives.
3.9.3.1 Natural rubber latex/cement (aggregate 3.10.4 Epoxy and other resin compounds
filled)
Proprietary underlayments based on epoxy and
This type provides a general purpose underlay other resin compounds are available for specific
which should be used where foot and light wheeled applications. They should be used in accordance
traffic only is anticipated. These materials contain with the manufacturer’s recommendations.
protein protected with antimicrobial and/or
fungicidal additives.

10 © BSI 2009
Section 3 BS 8203:2001+A1:2009
Bought by MR MARK SPINDLEY,Resdev Ltd,on 07/11/2012 08:38 Latest version. Not to be distributed/networked. For multi-user access www.bsigroup.com/license © BSI

3.11 Protection against heat 3.12 Fire hazard


Underfloor heating systems in the United Kingdom The fire properties of floor surfaces are not
have traditionally been run at temperatures up controlled by any of the national building
to 27 °C and the floor coverings covered by this regulations but local regulations may restrict their
British Standard have given satisfactory service at use in primary escape routes and certain
these temperatures provided an appropriate grade construction and transport regulations may restrict
of adhesive is used. Floor coverings conforming their use in vehicles.
to BS EN 650, BS EN 651, BS EN 1816 and It is normal good practice (described in BS 5588-5
BS EN 12104 will reduce the response of underfloor and Approved Document B to the Building
heating because of their thermal insulation Regulations for England and Wales [1]) to use a floor
properties. covering with good slip resistance in wet conditions
Where hot water pipes are laid below the floor for floors and stairs in escape routes.
covering for purposes other than heating, they
should be laid as follows to prevent possible failure 3.13 Skirtings and covings
of the adhesive or damage to the floor covering. The A variety of skirtings and covings may be used with
laying of conduits or pipes in a screed should be the floor coverings covered by this British Standard.
avoided, if possible, as cracks may occur over them. Extruded sections are available in a number of
To minimize the effects of shrinkage cracking where different profiles and should be affixed to the wall
it is essential that conduits and pipes are using a suitable adhesive. Some types may
incorporated, a minimum of 25 mm thickness of additionally be seam welded to the floor covering to
screed containing reinforcement should be placed give continuity of surface.
over the conduit or pipe. The reinforcement should
be placed centrally in the depth of the screed over In-situ coving can be formed from materials such as
the conduit or pipe and extend for 250 mm on each flexible polyvinyl chloride floor coverings, linoleum
side. and rubber using a suitable cove former. Such
covings should be constant in radius and care should
Where ducts or trunking more than 75 mm wide are be taken to ensure that they are straight and
to be incorporated in the screed they should regular to minimize the formation of voids beneath
preferably be laid with their top surface flush with the floor covering.
the screed surface.
Alternatively, where such ducts or trunking have to
be buried in the screed below finished screed level, 3.14 Edging and dividing strips
the surface should be brought to screed level with a Edging and dividing strips are available in wood,
material strong and resilient enough to carry the metal and plastics. These may be used between
imposed loads. dissimilar types, thicknesses or colours of floor
The significant increase in depth of a bonded screed covering, at door openings or to act as a finish to a
required to accommodate pipes and trunking within floor edge.
its thickness may lead to increased risk of
3.15 Stairs
hollowness.
Attention is drawn to the possibility of damage to or The floor covering materials covered by this British
softening of floor coverings situated in close Standard are suitable for stair treads and risers,
proximity to stoves, cookers or heating appliances. providing that they are used with a slip-resistant
nosing which may be preformed. The treads should
High surface temperatures may be caused by direct be levelled and prepared to receive the floor covering
sunlight falling on the floor covering, when in the same manner as the main body of the floor.
buildings have large windows with southerly
NOTE Nosings of internal stairs for public buildings should be
aspects. Adhesives capable of withstanding these of a contrasting colour for the benefit of people with impaired
temperatures should be used. vision.

© BSI 2009 11
Bought by MR MARK SPINDLEY,Resdev Ltd,on 07/11/2012 08:38 Latest version. Not to be distributed/networked. For multi-user access www.bsigroup.com/license © BSI

12
blank
BS 8203:2001+A1:2009
Bought by MR MARK SPINDLEY,Resdev Ltd,on 07/11/2012 08:38 Latest version. Not to be distributed/networked. For multi-user access www.bsigroup.com/license © BSI

Section 4. Installation 4

4.1 Liaison and workmanship All wood based panels used as underlays should
be loosely stacked in the room where they are to
4.1.1 Liaison be laid in order to condition as close to in-use
The liaison previously established with the main conditions as possible before laying. Hardboard
contractor and other trades (see 1.4) should be should be pre-conditioned by sponging with water
maintained during the work. For example, the work on the mesh side with approximately 1 l per panel
should be scheduled so that: (1 200 mm × 2 400 mm). The panels should then
a) any concrete base and screed are allowed be stacked for at least 24 h and preferably 48 h
sufficient time to dry; before fixing. Hardboards should be installed and
fixed whilst slightly expanded, but allowed to fully
b) the building is watertight with appropriate dry after fixing to avoid the risk of buckling after
heating, lighting and ventilation; the cover is applied.
c) operations which could damage the floor
covering are completed before the floor covering is In order to obtain the best results the underlay
installed. should be laid across the line of the boards of the
sub-floor, with no gaps between the joints of the
Other operations which require access to the same sheets or any step between each sheet. A gap
area should not be scheduled during the installation should be provided around the perimeter of a floor
of the floor covering and the curing period for the to upstands or abutting construction and at door
adhesive. The floor covering should be protected thresholds to allow for possible expansion of the
before these operations take place, and until
underlay. This should be a minimum of 10 mm at
completion.
each stage or 2 mm per metre run of board, or as
4.1.2 Workmanship specified by the manufacturer. The gap should be
Care should be taken to ensure good workmanship left open and covered by a skirting board, or filled
and efficient supervision. Operatives with the with a compressible strip such as cork. Joint lines
necessary skill and knowledge should be employed. should be staggered and joints in the sheet and
the timber base should not coincide.
4.2 Storage Fabricated underlays should be fixed using screw
Floor covering materials should be stored in a nails, ring shank nails, screws or divergent staples
secure, clean, warm, dry, well-ventilated place which should be finished flush with the surface.
(see 4.4 for treatment of materials before and The length of the fixings should be at least 2.5
during laying). times the thickness of the underlay sheet, but no
Special storage conditions are required by law for longer than would allow the fixing to protrude
flammable and highly flammable liquids including below the sub-floor."
some adhesives. Many products are subject to the
various regulations and may require a licence to !Text deleted"
store.
4.3 Underlays
4.3.1 Fabricated underlays
!Any hollows in the base should be levelled by
sanding, planing or patch-filling with a suitable
underlayment.

© BSI 2009 13
BS 8203:2001+A1:2009 Section 4
Bought by MR MARK SPINDLEY,Resdev Ltd,on 07/11/2012 08:38 Latest version. Not to be distributed/networked. For multi-user access www.bsigroup.com/license © BSI

4.3.2 In situ underlays Underfloor heating should be switched off 48 h prior


to laying the floor coverings. Since most adhesives
Mastic asphalt should be laid in accordance
with BS 8204-5. Where it is used as a combined which are used for floor laying do not achieve
maximum bond strength immediately, the heating
underlay and damp-proof membrane, care should be
should not be turned on until at least 48 h after
taken to provide continuity with the damp-proof
course in the walls. To provide an absorbent base for laying and peak temperature should be avoided for
a further 7 days.
the application of adhesives, the asphalt should be
skimmed with a minimum of 3 mm thickness of a If a priming coat is used, the manufacturer’s
suitable proprietary smoothing underlayment. instructions should be followed.
In these cases, the asphalt surface should be A number of floor covering manufacturers have
prepared by sand rubbing, or by the application of extensive and detailed laying instructions which are
proprietary adhesion primers. relevant to their materials and these should be
Cementitious underlays should be applied in consulted.
accordance with the manufacturer’s instructions. 4.4.2 Product conditioning
4.3.3 Smoothing underlayments 4.4.2.1 Cork tiles
Smoothing underlayments should be mixed and laid It is essential that cork tiles be in a dimensionally
in accordance with the manufacturer’s instructions. stable condition when laid. To achieve this the tiles
should be removed from the carton, and any other
4.4 Laying wrapping, at least 48 h before laying commences. If
4.4.1 General site conditions allow, the tiles should be distributed
in the room in which they are to be laid to allow
Before starting to lay any floor coverings ensure them to acclimatize to the conditions likely to
that any conflicting overhead work has been prevail in occupation, otherwise they should be
completed. The presence of underfloor heating and distributed in an area where the humidity and
security systems should be checked and all temperature conditions are similar to those likely to
preliminary work, such as the fixing of floor sockets prevail in occupation.
for service plugs, should be completed. The base
should be sound, smooth, clean and dry before Some proprietary cork tiles with special surface
laying commences. treatments are supplied preconditioned and with
these the manufacturer’s instructions should be
It is essential that the laying area should be at followed.
a steady temperature between 18 °C and 27 °C
for at least 48 h prior to, during and for at 4.4.2.2 Other resilient floor coverings and
least 24 h after completion. adhesives
Provision should also be made for adequate Prior to installation, the flooring materials should
ventilation throughout and after installation. be allowed to become acclimatized to the site
conditions in the laying area. Rolls should be stored
Existing floor coverings and sufficient residual securely in an upright position for at least 24 h in
adhesive should be removed (see 3.5). Where it is the laying area. Boxes of tiles should be removed
difficult to establish whether or not these materials from the delivery pallet and stored not more than
contain asbestos they should be removed using a five boxes high in the laying area for at least 24 h.
wet method without generating dust.
The conditioning time should be extended to at
NOTE Attention is drawn to Asbestos and man-made mineral
fibres in buildings: practical guidance published by DETR [2] least 48 h if the floor covering has been stored or
that gives advice on the precautions to be taken when removing transported at temperatures less than 10 °C
existing flooring containing asbestos. immediately prior to delivery. Extremes of
Floor coverings should not be installed to cover temperature should be protected against, especially
expansion joints. A proprietary joint should be day and night temperatures. Where the ambient
inserted and the floor covering terminated either room temperature exceeds 27 °C and the high
side of this joint. temperatures are caused by sunlight, shading
should be used to limit the temperature increase.
The subfloor should be prepared to receive the floor
covering by the use of a fabricated underlay on The material manufacturer should be contacted for
timber bases or a suitable underlayment on screeds, guidance on specific instances of uncertainty.
concrete or other solid bases.
Worn areas of concrete bases or cement-sand
screeds should be made good with a smoothing
underlayment. In no circumstances should floor
hardening solutions be used.

14 © BSI 2009
Section 4 BS 8203:2001+A1:2009
Bought by MR MARK SPINDLEY,Resdev Ltd,on 07/11/2012 08:38 Latest version. Not to be distributed/networked. For multi-user access www.bsigroup.com/license © BSI

4.4.3 Adhesives Adhesive manufacturers’ instructions will indicate


which of their adhesives can be used in this manner.
4.4.3.1 General
4.4.3.3.2 Laying into dry adhesive
The adhesive manufacturer’s instructions for the
use of the adhesive should be followed. Most flooring This method is normally used when fixing the
adhesives are spread with a notched trowel to various grades of polyvinyl chloride floor coverings
ensure even coverage of the base at the correct with bitumen adhesives and pressure sensitive
thickness. The details of the trowel and the method adhesives. It can also be used when laying floor
of use of the adhesive are normally specified by the coverings directly over non-absorbent bases when it
flooring adhesive manufacturer having regard to is necessary to allow any carrier in the adhesive,
the type and thickness of floor covering being laid, e.g. water or solvent, to evaporate before the floor
the type of base and the adhesive to be used. covering is laid to avoid entrapment. The adhesive
In the absence of such instructions, the should be spread onto the base and allowed to dry
before the floor covering is laid. As the method
manufacturer should be contacted.
requires that the dried adhesive film be sufficiently
4.4.3.2 Application tacky to form an adequate bond with the floor
covering it is essential that adhesives specifically
Adhesives should be applied by one of the following
designed for use by this method are selected.
methods:
a) notched trowel. Details of the trowel to be used 4.4.3.3.3 Laying into contact adhesive
will be given in the instructions of either the Contact adhesives should be applied to both the
adhesive or floor covering manufacturer. The base and the underside of the floor covering and
depth of spacing of the notches should be both films of adhesive should be allowed to dry
maintained throughout the installation; before the floor covering is laid. It is essential that
b) roller. Adhesives applied by roller produce a the floor covering is carefully positioned before it is
flat surface film as is required with pressure actually laid in place as a strong bond is formed on
sensitive adhesives. A pre-wetted short-pile contact. The area spread with adhesive at any time
synthetic roller is usually recommended either on should be such that it can be covered with floor
its own or immediately following the notched covering within the time that the adhesive remains
trowel application. receptive.

4.4.3.3 Methods of use 4.4.3.4 Safe use of adhesives

4.4.3.3.1 Laying into wet adhesive 4.4.3.4.1 General

This method should be used for gum/spirit The Health and Safety at Work etc. Act 1974 [3]
adhesives and for chemically curing adhesives such requires that adhesive suppliers should provide
as epoxy resins and polyurethanes. It is also sufficient information to enable their products to be
commonly used for water-borne adhesives when used safely and without risk to health. This is
applied over absorbent surfaces. The floor covering normally done in the form of Material Safety Data
should be laid whilst the adhesive is still wet. Sheets and users should be fully aware of this
information when carrying out their COSHH
The amount of adhesive applied, the type of assessments.
adhesive, the porosity of the base and the ambient
conditions, including ventilation, are all factors It is the responsibility of users to ensure they are
which may affect the rate of drying or curing and following current legislation.
therefore determine the area which should be 4.4.3.4.2 Solvent borne adhesives
spread with adhesive at any one time.
Adhesives which are labelled “Petroleum mixture
A modification of this method, commonly termed the giving off a heavy inflammable vapour”, “highly
“double drop” method of laying can be used flammable”, “highly inflammable” or “flammable”
especially on non-porous subfloors as it markedly present a potential fire hazard and UK law requires
reduces the danger of trapping water or solvent special use, transportation and storage conditions
from the adhesive. The floor covering is laid into the including, in some cases, a licence. See the various
wet adhesive to obtain good transfer to the back. It petroleum regulations and the Highly Flammable
is then lifted and peeled back to allow the water or Liquid and Liquefied Petroleum Gases
solvent in the two films of adhesive to evaporate Regulations 1972 [4].
leaving tacky films on both floor and floor covering.
The floor covering is then replaced applying
pressure overall.

© BSI 2009 15
BS 8203:2001+A1:2009 Section 4
Bought by MR MARK SPINDLEY,Resdev Ltd,on 07/11/2012 08:38 Latest version. Not to be distributed/networked. For multi-user access www.bsigroup.com/license © BSI

The vapours from all flammable and highly The adhesive should be spread evenly with the
flammable adhesives will spread for considerable notched trowel provided with the adhesive or with
distances along the ground, down stairways, etc., a notched trowel with dimensions stipulated by the
thus extending the fire hazard beyond the adhesive manufacturer. Spread the adhesive in
immediate vicinity of the work. It is essential that sufficient quantity for laying only a few square
all sources of ignition in the neighbourhood are metres at a time. Do not spread adhesive on areas
eliminated. that will take part tiles until after the part tile has
NOTE Potential sources of ignition include lighted cigarettes, been cut. Each tile should be carefully worked into
pilot lights, gas torches or burners and electrical appliances position, to exclude air beneath the tile and to
including motors and switches. ensure overall contact with the adhesive. Ensure
It is essential that the work area is sufficiently that no adhesive has collected between the tiles so
ventilated when any solvent borne adhesive is being that good, but not too tight, joints are attained.
used to ensure that fresh air is constantly The floor should be rolled laterally and transversely
introduced, thereby minimizing inhalation of with a floor roller weighing approximately 68 kg.
vapours and a build up of a vapour pocket. It is 4.4.5 Linoleum floor coverings
essential that smoking is prohibited in the vicinity
even when non-flammable solvents are used as Sheet material should be cut and fitted. The
some of the vapours decompose to toxic gases in the adhesive should be spread evenly on the subfloor
heat of a lighted cigarette. with a suitably notched trowel. The floor covering
should be laid into the adhesive within the
4.4.3.4.3 Reactive adhesives (e.g. epoxy resin and recommended adhesive open time and should be
polyurethane) well rolled laterally and transversely with a floor
Most adhesives in this class can cause skin roller weighing approximately 68 kg. The floor
irritation, dermatitis or perhaps skin sensitization covering should be re-rolled within 30 min and as
when in direct contact with the skin. Handling necessary to maintain overall contact.
procedures should ensure that uncured materials do Seams may be welded using a linoleum welding
not come into contact with the skin, e.g. by wearing cord 24 h after installation.
gloves. Hands should be washed thoroughly after
For tiles, the main field should be laid into the
using adhesives of this type. Some adhesives may
adhesive working within an area that can be laid
contain materials which could cause irritation of the
skin and/or give off irritant vapours which may within the open time of the adhesive. The perimeter
tiles should be fitted prior to the application of
cause breathing problems. Good ventilation should
adhesive. The floor should be rolled in both
always be provided and approved respirators may
be necessary, especially if the adhesive is being directions with a floor roller weighing
approximately 68 kg and re-rolled within 30 min
spray applied.
and as necessary to maintain overall contact.
4.4.3.4.4 Water borne adhesives
4.4.6 Plastics floor coverings
Water borne adhesives are generally far less
Sheet material should be cut and fitted. The
hazardous than solvent borne or reactive types.
adhesive should be spread evenly on the subfloor
Good ventilation should be provided and skin
contact avoided. using a suitable notched trowel as recommended by
the manufacturer and the notch size should be
4.4.3.4.5 Waste disposal and emptied containers maintained throughout the application. The
material should then be laid into the adhesive
Waste material and the residue in emptied within its recommended open time and, where
containers give rise to the same hazards as the
recommended by the manufacturer, should then be
adhesive itself. Such waste should not be left on
rolled in both directions with a floor roller weighing
sites but should be disposed of safely according to approximately 68 kg. The floor should be re-rolled
the information given in the Material Safety Data
within 30 min and as necessary to maintain overall
Sheet. Users should ensure they comply with the
contact. If a jointless floor is required, the seams
relevant legislation. should be welded. If heat welded then the adhesive
4.4.4 Cork floor tiles should be allowed to dry, normally for 24 h after
installation before the floor covering is welded.
Cork tiles should be fixed with an adhesive
specifically designated as being suitable for the
type, i.e. sanded, ready sealed, polyvinyl chloride
faced etc., and thickness of cork being laid.

16 © BSI 2009
Section 4 BS 8203:2001+A1:2009
Bought by MR MARK SPINDLEY,Resdev Ltd,on 07/11/2012 08:38 Latest version. Not to be distributed/networked. For multi-user access www.bsigroup.com/license © BSI

For tiles, the main field should be laid into the However, BS EN 1264-2, which is used to design
adhesive working within an area that can be laid underfloor heating systems, allows for a maximum
within the open time of the adhesive. The perimeter floor surface temperature of 29 ºC in occupied
tiles should be fitted prior to the application of areas. In areas where the use of these higher
adhesive. The floor should be rolled in both temperatures is unavoidable then agreement from
directions with a floor roller weighing both the adhesive and flooring manufacturers
approximately 68 kg and re-rolled within 30 min should be obtained.
and as necessary to maintain overall contact.
Some thicker floor coverings, especially those with
4.4.7 Rubber floor coverings foamed backing layers, have a higher thermal
Rubber floor coverings should be conditioned and resistance and this can result in unacceptably
installed as described in 4.4.1 (but at a minimum high interface temperatures in order to achieve
temperature of 15 °C), and 4.4.6. the required surface temperature.
4.5 Initial treatment and maintenance 4.7.2 Design
Prior to handover, the floor should be swept or Heated screeds should include joints across
suction cleaned to remove all dust and debris. All doorways and between areas with separate
traces of adhesives should be removed using the heating control zones. If the underfloor heating
method recommended by the adhesive manufacturer recommends further joints, this
manufacturer. Special care should be taken when a advice should be followed (see BS 8204-7).
bituminous adhesive has been used with a light
coloured floor covering to ensure the surface is not In addition, the recommendation of the screed
stained. manufacturer should be taken on the maximum
bay sizes.
Further treatment and maintenance should be in
accordance with the manufacturer’s instructions 4.7.3 Commissioning
and BS 6263-2.
It is essential that before any floor covering is
installed the heating system is commissioned. This
4.6 Protection has two purposes:
When laying is completed, all the scrap material
a) to ensure that the heating system is
and debris should be removed and the floor swept or
suction cleaned. Allow the adhesive to dry fully, functioning and no leaks or cable breaks
normally for at least 24 h. When the floor has to be require the heat source to be uplifted or
put back into use before handover, all trafficked repaired; and
areas should be protected with hardboard or other b) to ensure that the screed is dry and in a
appropriate sheeting to ensure the surface is not stable state to receive the flooring.
scratched or otherwise damaged prior to handover.
If the protective material has printed information Preheating is prescribed in BS EN 1264-4 and
on it, this should be placed uppermost, away from BS 8204-1:
the decorative face of the floor covering.
1) heat up should not begin for 21 days after
!4.7 Underfloor heating laying cement screeds, or 7 days for
calcium sulfate screeds;
4.7.1 Operating temperatures
2) initial heat up should be carried out in
When used with many flooring materials,
accordance with the recommendation of
underfloor heating can cause problems if the
the screed manufacturer and continued
temperature at the interface between the subfloor
until the screed is dry (see 3.1.2).
and the flooring exceeds 27 °C or is subject to
rapid fluctuations in temperature. In the majority NOTE Where time scales do not allow for adequate drying of
of installations this temperature will not need to the base to occur, liquid applied surface damp proof
be exceeded if the building insulation meets the membranes can be used upon base substrates that include
requirements of Part L of the Building underfloor heated systems; however, the recommendations of
both the surface DPM and the screed manufacturers should be
Regulations [6]. sought prior to the commencement of work. It is also important
to note that the underfloor heating system should be fully
commissioned prior to installation of the surface DPM."

© BSI 2009 17
BS 8203:2001+A1:2009
Bought by MR MARK SPINDLEY,Resdev Ltd,on 07/11/2012 08:38 Latest version. Not to be distributed/networked. For multi-user access www.bsigroup.com/license © BSI

Annex A (normative) Other forms of apparatus may be suitable but the


Dampness testing width of the area should not be less than 150 mm
and it is essential that the principles of thermal
A.1 Basis of test insulation and vapour barrier are followed, so that
an insulated vapour-proof space is created.
The basis of the test is to use a hygrometer or probe
to measure the relative humidity of a pocket of air Suitable vapour barrier materials are sheet metal,
entrapped between an impervious thermally glass, 2 mm thick clear acrylic sheet, or 2 mm thick
insulated housing and the surface of the screed or PVC-U, and the apparatus should have a maximum
concrete base. Sufficient time is allowed for U-value of 1.0 W/(m2 K).
moisture equilibrium to become established A.2.2 Hygrometer or relative humidity (rh) probe, for
between the pocket of air and the base. measuring relative humidity to an accuracy of
Concrete under normal conditions will never be ±3 % rh. This can be a hair, paper or synthetic fibre
completely dry. Those responsible for laying floor hygrometer of the clock type, or an electronic
coverings require to know when the moisture level relative humidity probe.
of the concrete has been reduced to a value where
A.2.3 Preformed butyl sealant tape
flooring can be safely laid. Water in the coarse pores
of concrete is relatively mobile and can lead to A.2.4 Adhesive tape
damage to flooring whereas water in the fine pores
is relatively immobile and harmless. A.2.5 Protective mats (rubber or polyethylene)
When concrete is allowed to dry, the coarse pores A.3 Suitability
become empty first because water in coarse pores The method of test is appropriate for measurement
exerts a higher vapour pressure, and hence
of percentage relative humidity values above porous
evaporates more quickly, than water in fine pores.
surfaces such as screeds and concretes. Low porosity
Because the size of the pores controls the vapour surfaces such as power floated concrete will require
pressure that arises in them, it also controls the
extended testing periods before true readings can be
vapour pressure of a small volume of air entrapped
achieved, and any surface treatment such as
between the concrete surface and an impervious concrete curing compounds or waxes should be
housing (or box). The vapour pressure determines
removed. The method may not be suitable for use on
the relative humidity of that entrapped air so a
proprietary screeds and is not suitable for
hygrometer or probe reading indicates the extent to performance assessment of surface applied
which harmful moisture is still present.
moisture barriers.
Experimental evidence has shown that when the
measured relative humidity falls to 80 % the water A.4 Procedure
has evaporated from the coarse pores and the screed Turn off any artificial aids used for accelerating
is sufficiently dry to allow installation of resilient drying at least 4 days before final readings are
floor coverings. If some allowance is made for errors attempted. Accelerated drying should not be used
in determining the relative humidity, it is for screeds.
reasonable to recommend that the concrete be
considered dry when the relative humidity falls Seal the apparatus firmly to the floor and allow
sufficient time for the entrapped air to reach
to 75 % or less.
moisture equilibrium with the screed or base.
For these reasons the hygrometer or probe method
For an unbonded screed, where the damp-proof
for dampness measurement is recommended over
membrane is placed between the base and screed as
and above invasive methods.
described in 6.4.3b) of BS 8204-1:1999, allow a
A.2 Apparatus period of not less than 4 h before taking the first
reading. Equilibrium can be assumed when two
A.2.1 Insulated impermeable box, which can be consecutive readings taken at 4 h intervals show no
sealed to the floor surface to create an enclosed change.
pocket of air which is isolated from the humidity and
fluctuations in temperature of the outside air.
(Examples of suitable equipment are shown
in Figure 1.)
It is essential that the insulated box is sealed to the
floor using a preformed butyl sealant tape and that
readings can be taken while the apparatus is in
position on the floor without breaking the seal and
releasing the trapped pocket of air.

18 © BSI 2009
Bought by MR MARK SPINDLEY,Resdev Ltd,on 07/11/2012 08:38 Latest version. Not to be distributed/networked. For multi-user access www.bsigroup.com/license © BSI

© BSI 2009
Figure 1 — Typical apparatus

19
BS 8203:2001+A1:2009
BS 8203:2001+A1:2009
Bought by MR MARK SPINDLEY,Resdev Ltd,on 07/11/2012 08:38 Latest version. Not to be distributed/networked. For multi-user access www.bsigroup.com/license © BSI

For very thick constructions, i.e. direct finished base Annex B (normative)
slabs or bonded screeds, i.e. where the damp-proof Assessment of levels and surface
membrane is placed below the base slab as regularity
described in 6.3.2 or 6.4.3a) of BS 8204-1:1999,
allow a period of at least 72 h to elapse before taking Check surface levels against datum using normal
the first reading. Equilibrium can be assumed when surveying methods.
two consecutive readings taken at 24 h intervals
show no change. Constructions with thickness Check surface regularity by using a 3 m long
straightedge laid in contact with the floor surface
greater than 200 mm can take considerably longer
and resting under its own mass. Measure the
than one week before moisture equilibrium is
deviations of the surface from the underside of the
established. To prevent edge effects with these very straightedge by means of a slip gauge or other
thick constructions, the area of 1 m2 surrounding suitable accurate measuring device.
the instrument should be covered with an
impervious sheet material during the test. For local irregularities use a 300 mm straightedge.
To minimize the time required for the instrument to The number of measurements required to check
be in a position on the floor, the following technique levels and surface regularity should be agreed
can be applied. Cover the positions to be measured between the parties concerned, bearing in mind the
with impervious mats (e.g. polyethylene sheet, accuracy required and the likely time and cost
rubber mats) not less than 1 m × 1 m, taped to the involved.
floor at their edges. Leave in position for at least
3 days in the case of screeds and 7 days in the case
of thick constructions. After removing the mat,
immediately seal the instrument to the centre of the
covered area. Experience has shown moisture
equilibrium is usually attained within 2 h to 4 h of
placing the instrument but should be left overnight
for confirmation.
To avoid expensive equipment being left on site the
probe may be removed from the apparatus shown
in Figure 1b) and the hole plugged before the box is
sealed to the subfloor. After allowing time to reach
equilibrium, the plug is removed, the rh probe
inserted promptly, and time is allowed for this to
reach equilibrium before readings are taken.
A number of simultaneous measurements may be
necessary to give a representative survey. This
should take into account the size and layout of the
installation, as well as any variation in the subfloor
construction.
If readings greater than 75 % are obtained the
equipment should be removed and the floor be
allowed to dry before further readings are
attempted.
A.5 Verification of hygrometer or probe
As the accuracy of a hygrometer can drift with time
or in transit it may need to be recalibrated
frequently. The accuracy of the hygrometer or
rh probe at 75 % rh may be checked by sealing it in
a desiccator or humidity cabinet over a saturated
solution of analytical or general purpose reagent
grade sodium chloride, at a constant temperature
of (20 ± 2) °C for a minimum of 12 h.

20 © BSI 2009
BS 8203:2001+A1:2009
Bought by MR MARK SPINDLEY,Resdev Ltd,on 07/11/2012 08:38 Latest version. Not to be distributed/networked. For multi-user access www.bsigroup.com/license © BSI

List of references (see 1.2)


Normative references
BSI standards publications
BRITISH STANDARDS INSTITUTION, London
BS 5442-1, Classification of adhesives for construction — Classification of adhesives for use with flooring
materials.
BS 6100, Glossary of building and civil engineering terms.
BS 6263-2, Care and maintenance of floor surfaces — Code of practice for resilient sheet and tile flooring.
BS 6925:1988, Specification for mastic asphalt for building and civil engineering (limestone aggregate).
BS 7916, Code of practice for the selection and application of particleboard, oriented strand board (OSB),
cement-bonded particleboard and wood fibre boards for specific purposes.
BS 7953, Entrance flooring systems — Selection, installation and maintenance.
BS 8102, Code of practice for protection of buildings against water from the ground.
BS 8201:1987, Code of practice for flooring of timber, timber products and wood based panel products.
BS 8204-1, Screeds, bases and in-situ floorings — !Part 1:" Concrete bases and !cementitious"
levelling screeds to receive floorings — Code of practice.
BS 8204-5:1994, Screeds, bases and in-situ floorings — Code of practice for mastic asphalt underlays and
wearing surfaces.
BS EN 204, Classification of !thermoplastic wood adhesives for non-structural applications".
BS EN 300, Oriented strand boards (OSB) — Definitions, classification and specifications.
!BS EN 312, Particleboards – Specifications."
BS EN 548, Resilient floor coverings — Specification for plain and decorative linoleum.
BS EN 622-2, Fibreboards — Specifications — !Part 2:" Requirements for hardboards.
BS EN 622-4, Fibreboards — Specifications — !Part 4:" Requirements for softboards.
BS EN 622-5, Fibreboards — Specifications — !Part 5:" Requirements for dry process boards (MDF).
BS EN 636, Plywood — Specifications !Text deleted".
BS EN 649, Resilient floor coverings — Homogeneous and heterogeneous polyvinyl chloride floor
coverings — Specification.
BS EN 650, Resilient floor coverings — Polyvinyl chloride floor coverings on jute backing or on polyester felt
backing or on polyester felt with polyvinyl chloride backing — Specification.
BS EN 651, Resilient floor coverings — Polyvinyl chloride floor coverings with foam layer — Specification.
BS EN 652, Resilient floor coverings — Polyvinyl chloride floor coverings with cork-based backing —
Specification.
BS EN 653, Resilient floor coverings — Expanded (cushioned) polyvinyl chloride floor coverings —
Specification.
BS EN 654, Resilient floor coverings — Semi-flexible polyvinyl chloride tiles — Specification.
BS EN 655, Resilient floor coverings — Tiles of agglomerated composition cork with polyvinyl chloride wear
layer — Specification.
!BS EN 685:2007, Resilient, textile and laminate floor coverings — Classification."
BS EN 686, Resilient floor coverings — Specification for plain and decorative linoleum on a foam backing.
BS EN 687, Resilient floor coverings — Specification for plain and decorative linoleum on a corkment
backing.
BS EN 688, Resilient floor coverings — Specification for corklinoleum.
BS EN 1816, Resilient floor coverings — Specification for homogeneous and heterogeneous smooth rubber
floor coverings with foam backing.

© BSI 2009 21
BS 8203:2001+A1:2009
Bought by MR MARK SPINDLEY,Resdev Ltd,on 07/11/2012 08:38 Latest version. Not to be distributed/networked. For multi-user access www.bsigroup.com/license © BSI

BS EN 1817, Resilient floor coverings — Specification for homogeneous and heterogeneous smooth rubber
floor coverings.
BS EN 12199, Resilient floor coverings — Specifications for homogeneous and heterogeneous relief rubber
floor coverings.
BS EN 12104, Resilient floor coverings — Cork floor tiles — Specification.
!BS EN 13986, Wood-based panels for use in construction — Characteristics, evaluation of conformity
and marking."
CP 102, Code of practice for protection of buildings against water from the ground.

Informative references
BSI standards publications
BRITISH STANDARDS INSTITUTION, London
BS 5588-5:1991, Fire precautions in the design, construction and use of buildings — Code of practice for
firefighting stairs and lifts.
!BS 8204-7, Screeds, bases and in situ floorings — Part 7: Pumpable self smoothing screeds — Code
of practice.
BS EN 1264-2, Water based surface embedded heating and cooling systems — Part 2: Floor heating:
Prove methods for the determination of the thermal output using calculation and test methods.
BS EN 1264-4, Floor heating — Systems and components — Part 4: Installation.
BS EN 13810-1, Wood-based panels — Floating floors — Part 1: Performance specifications and
requirements."
Other documents
[1] GREAT BRITAIN. Building Regulations for England and Wales 2000 Approved Document B (Fire
Safety) 2000. London: The Stationery Office.
[2] Asbestos and man-made mineral fibre materials in buildings: practical guidance. 2000. DETR
Publications. http://www.detr.gov.uk/environment/asbestos/guide/index.htm
[3] GREAT BRITAIN. Health and Safety at Work etc. Act 1974. London: The Stationery Office.
[4] GREAT BRITAIN. Highly Flammable Liquid and Liquified Petroleum Gases Regulations. Statutory
Instrument 1972 No. 917. Factories. London: The Stationery Office.
![5] WOOD PANEL INDUSTRIES FEDERATION. IS(WPIF)3/2008, Code of Practice for Particleboard
and Oriented Strand Board (OSB) Floating Floors (WPIF Industry Standard), Lincolnshire: 2008.
[6] NBS/OFFICE OF THE DEPUTY PRIME MINISTER. The Building Regulation for England and
Wales 2000: Approved Document L (Conservation of fuel and power), London. 2006."

22 © BSI 2009
Bought by MR MARK SPINDLEY,Resdev Ltd,on 07/11/2012 08:38 Latest version. Not to be distributed/networked. For multi-user access www.bsigroup.com/license © BSI

blank
BS 8203:2001
+A1:2009
Bought by MR MARK SPINDLEY,Resdev Ltd,on 07/11/2012 08:38 Latest version. Not to be distributed/networked. For multi-user access www.bsigroup.com/license © BSI

BSI — British Standards Institution


BSI is the independent national body responsible for preparing
British Standards. It presents the UK view on standards in Europe and at the
international level. It is incorporated by Royal Charter.

Revisions

British Standards are updated by amendment or revision. Users of


British Standards should make sure that they possess the latest amendments or
editions.

It is the constant aim of BSI to improve the quality of our products and services.
We would be grateful if anyone finding an inaccuracy or ambiguity while using
this British Standard would inform the Secretary of the technical committee
responsible, the identity of which can be found on the inside front cover.
Tel: 020 8996 9000. Fax: 020 8996 7400.

BSI offers members an individual updating service called PLUS which ensures
that subscribers automatically receive the latest editions of standards.

Buying standards

Orders for all BSI, international and foreign standards publications should be
addressed to Customer Services. Tel: 020 8996 9001. Fax: 020 8996 7001.
Standards are also available from the BSI website at http://www.bsi-global.com.

In response to orders for international standards, it is BSI policy to supply the


BSI implementation of those that have been published as British Standards,
unless otherwise requested.

Information on standards

BSI provides a wide range of information on national, European and


international standards through its Library and its Technical Help to Exporters
Service. Various BSI electronic information services are also available which give
details on all its products and services. Contact the Information Centre.
Tel: 020 8996 7111. Fax: 020 8996 7048.

Subscribing members of BSI are kept up to date with standards developments


and receive substantial discounts on the purchase price of standards. For details
of these and other benefits contact Membership Administration.
Tel: 020 8996 7002. Fax: 020 8996 7001. Further information about BSI is
available on the BSI website at http://www.bsi-global.com.

Copyright

Copyright subsists in all BSI publications. BSI also holds the copyright, in the
UK, of the publications of the international standardization bodies. Except as
permitted under the Copyright, Designs and Patents Act 1988 no extract may be
reproduced, stored in a retrieval system or transmitted in any form or by any
means – electronic, photocopying, recording or otherwise – without prior written
permission from BSI.

This does not preclude the free use, in the course of implementing the standard,
of necessary details such as symbols, and size, type or grade designations. If these
details are to be used for any other purpose than implementation then the prior
written permission of BSI must be obtained.

If permission is granted, the terms may include royalty payments or a licensing


agreement. Details and advice can be obtained from the Copyright Manager.
BSI Tel: 020 8996 7070.
389 Chiswick High Road
London
W4 4AL

You might also like