MAJLIS AMANAH RAKYAT

(MARA)

RINGKASAN TUNTUTAN BAYARAN

CADANGAN KERJA PENINGKATAN IMEJ SERTA KERJA ELEKTRIKAL TERMASUK KERJA -KERJA YANG BERKAITAN DI
PEJABAT DAN BENGKEL KENDERAAN BAS MARA (KBM) SIK, KEDAH.

BIL BUTIR - BUTIR SENARAI KERJA JUMLAH (RM) JUMLAH SEBENAR(RM)

1 PRELIM 13,350.00 13,350.00

CIVIL WORKS 287,740.00 290,205.00


2.0 KERJA - KERJA UBAHSUAI
3.0 PEMBINAAN SETOR BENGKEL
4.0 BUMBUNG TAMBAHAN BENGKEL "AWNING"
5.0 DINDING PENGADANG TEMPIAS "HOARDING"
6.0 UBAHSUAI TANDAS DAN BILIK MANDI
7.0 LUBANG PIT
8.0 MENGECAT BANGUNAN DAN PAGAR (Luar Dan Dalam)
9.0 LAPISAN EPOXY LANTAI RUANG SELENGGARAAN
10.0 PONDOK PENGAWAL
11.0 PINTU PAGAR
12.0 PAPAN TANDA
13.0 PAIP "AIR COMPRESSOR"
14.0 TEMPAT LETAK KERETA & MOTOSIKAL
15.0 TEMPAT PENGUMPULAN MINYAK TERPAKAI
16.0 TIANG BENDERA
17.0 TEMBOK PENAHAN "GABION" TEBING SUNGAI
18.0 UBAHSUAI SETOR LAMA
19.0 PEMBINAAN RAK
20.0 ALUMINIUM LOUVERS & SIGNAGE

3 ELECTRICAL 59,020.00 56,620.00


SUB TOTAL 360,110.00 360,175.00
GST 0% -
TOTAL 360,110.00 360,175.00
ADD
90% material on site
Variation Order

TOTAL 360,175.00