You are on page 1of 2

duration of work

No. Stages of Work M1 M2 M3 M4 M5 M6


W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4
A. Masterplan Planning and Design
1 Urban Context
a Target User Research and Study
b
Carrying capacity reserch and study
c analysis of institutional structures
d business, economic, social, and
cultural pre-feasibility studies
2 Site Survey and Report
a Site measurement
b vegetation identification
c
identification of potential and physical
constraints on existing site
d Soil test
e MEP, drainage (inlet-outlet), Water
Source, environment quality, wind,
sun light
Pra - Report
duration of work
No. Stages of Work M1 M2 M3 M4 M5 M6
W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4
3 Planning and Design Analysis (on-
site)
a Mission and Vision
b topography analysis
c the existence of the area with its
surroundings
d disaster analysis and mitigation
measures
e access and circulation
f calculation of space area
g Infrastructure and Facility analysis
h MEP Study and Analysis
i Structure Study and Analysis
j calculation of area and plot area
Mid- Report
4 Concept and DED Phase
a Concept Diagram
b Concept Zoning

c Architectural Concept
d Landscape Concept
e MEP and Structure Concept
Draft - Final Report
5 Budget / Cost Estimation
Final Report