You are on page 1of 87

PT VALE INDONESIA

Mine – Ferrari Tunnel Bridge Road Junction

TECHNICAL SPECIFICATION

Doc. No. 3866-TS-001


Rev. A
April, 2018

Prepared by :

PT BITA ENARCON ENGINEERING


Engineers • Architects • Consultant
BITA
TABLE OF CONTENTS

1. DIVISION 1 GENERAL REQUIREMENTS

01320 Surveying Services


01400 Concrete Test

2. DIVISION 2 SITE CONSTRUCTION

02200 Site Preparation and Grading


02230 Site Clearing
02315 Excavation, Backfilling and Compaction
02330 Embankment
02335 Subgrade Preparation
02371 Gabions
02459 Precast Prestressed Concrete Piles
02645 Corrugated Metal Pipes
02721 Subbase
02722 Base Course
02740 Asphaltic Concrete Pavement
02765 Traffic Markings
02845 Guardrails
02890 Traffic Signage

3. DIVISION 3 CONCRETE

03210 Reinforcing Steel


03300 Cast-in-Place Concrete
03600 Grout

D:\RPU\Project\2017\17-3866\Spec\TOC.doc Page 1 of 1
DIVISION 1
GENERAL REQUIREMENTS
BITA

SPECIFICATION

01320

SURVEYING SERVICES

1.0 DESCRIPTION OF WORK

This work shall cover the limits and extent of the survey works of lines and elevations for site
preparation and other works as specified in the Drawings and/or as determined by the
Engineer and shall include technical personnel and precise scientific surveying instruments
which shall be in accordance to this Specification.

2.0 REFERENCE STANDARDS

None

3.0 GENERAL PROCEDURES

3.1. Basic Survey Data

Basic survey data based on fixed triangulation polygon points and Bench Marks (BM)
shall be provided by the Principle and shall be at the disposal of the Contractor and
shall serve as a base for the surveying and setting out which he has to carry out.
Should the Contractor have any objections to this basic survey and the relevant
drawings, he shall inform the Engineer in writing within one (1) week after the submittal
of the basic survey data.

3.2. General Survey Requirements

The Contractor shall perform all surveying calculations and setting out necessary to
establish the accurate location of the position in accordance with the drawings and
shall be approved by the Engineer. Horizontal and vertical control shall be by closed
loop traverses.
Maximum permissible errors of closure shall be:

a. Horizontal Traverses:
- Angular error = 10  N
- Relative error < 1/1000
(N = number of stations)

b. Vertical Traverses:
- Elevation difference error = 10  D Km (mm)
(D = total shortest distance)

All slope distance shall be reduced to level distances.

PROJECT NO. : 17.3866 DIVISION : GENERAL REQUIREMENTS SPEC. NO. : 01320


REVISION :A DATE : April 2018 PAGE : 1 of 3
BITA

3.3. Bench Marks (BM)

3.3.1. The Contractor shall protect, preserve and keep accessible the BM of the
basic survey and those provided by the Contractor.

3.3.2. BM’s shall not be removed or disturbed by the Contractor or other persons.
Any damage or disturbance of the BM, accidental or otherwise shall be
reported to the Engineer. The Contractor at all times shall be responsible for
timely replacement or repair of the damaged BM's. The costs of rebuilding
BM's shall be the Contractor's responsibility without additional compensation.

3.3.3. BM's shall be made of mild steel or cast iron encased in an appropriate size of
concrete block as described below:

c
f

d
b
a

Plain Concrete

Stone Bedding
10

e Compacted Subgrade
90-95% Soil Density

a b c d e f
Soft Soil : 100 90 15 20 45 2.5 cm
Hard Soil : 70 50 15 15 15 2.5 cm

Cost of BM’s construction shall be the Contractor’s responsibility.

3.3.4. The inscriptions shall be clearly legible and durable.


Underground BM's shall be protected by concrete pipes and other acceptable
structures and shall be kept free from water and earth.

3.3.5. Horizontal traverse pegs shall be wood pegs, 50mm x 50mm by 300mm long,
firmly driven into the ground, protruding 20mm above the ground surface with
nails at the center to mark the point.

3.4. Survey Personnel and Equipment

The Contractor shall recruit only qualified surveyors, who prior to the engagement in
the project area shall be approved by the Engineer, and they are directly responsible
and bound to supply the Engineer with any required information on questions relating
to the survey. The Contractor shall use a sufficient number of reliable, accurate and
certified scientific instruments for survey purposes. The Contractor’s proposed survey
equipment shall be approved by the Engineer prior to commencement of survey
works.

PROJECT NO. : 17.3866 DIVISION : GENERAL REQUIREMENTS SPEC. NO. : 01320


REVISION :A DATE : April 2018 PAGE : 2 of 3
BITA

4.0 MATERIALS

None

5.0 CONSTRUCTION REQUIREMENTS

5.1. Survey Record and Computations

Complete records shall be maintained of all field surveys in a neat and orderly format.
Survey shall be clearly identified by project, location, dates, and names. Bound books
shall be used for permanent records.
Separate field records shall be kept for each of the following categories:

- Control traverse and secondary traverses.


- BM levels.
- Location surveys.
- Construction surveys.
- Cross-sections.

Coordinates of all BM's, control points, traverse stations, center-line alignments and
points of intersections shall be calculated prior to surveying.
Sketches shall be prepared for each BM control point and reference point that shows
distances and azimuths to each reference point.
Profile and topographic elevation shots shall be recorded in the field book.
All records and computation shall be made a permanent record, maintained in a safe
place. Permanent storage of inactive field records will be maintained by the Engineer.

5.2. Verification of Accuracy

All the survey elements, controls and setting out shall be checked by the Engineer at
irregular intervals during the execution of this project. The Contractor shall give timely
assistance to the Engineer during the field survey verification.
The following computations shall be used in reviewing the original field notes:
Traverse angular error e1 = 1'  n
Traverse linear error e2 =  (L² + D²)

L = difference between North latitude and South latitude.


D = difference between East departures and West departures.

e
Precision = ---------------
Perimeter

Any improper survey done by the Contractor shall be corrected and reworked upon
discovery without any extra compensation.
The Contractor shall keep all marks and line of sights clear which are required during
the verification. Any control made by the Engineer shall not relieve the Contractor of
his entire responsibility for the minute accuracy of the alignment, elevations, slopes,
dimensions and positions of any structure or facilities.

PROJECT NO. : 17.3866 DIVISION : GENERAL REQUIREMENTS SPEC. NO. : 01320


REVISION :A DATE : April 2018 PAGE : 3 of 3
BITA

SPECIFICATION

01400

CONCRETE TEST

1.0 DESCRIPTION OF WORK

This specification shall cover the procedure for making concrete test of all concrete works as
indicated in the Drawings.
The work shall include but not be limited to the following:

- Laboratory tools and equipment needed.


- Storage provision.
- Mixing platform near storage area.
- Non-absorptive moulds with base.
- Steel tamping-rod bullet pointed at the bottom, the dimensions shall be 16mm (5/8")
diameter by 600mm (2') long.
- Slump cone.
- Air content test.
- Shovel and hand-scoop.
- Boxes for shipping the specimens.

2.0 REFERENCE STANDARDS

2.1. Standar Nasional Indonesia (SNI):

- SNI 03-1972-2008 - Metode Pengujian Slump.


- SNI 1974-2011 - Cara uji kuat tekan beton dengan benda uji silinder.
- SNI 2458-2008 - Tata cara pengambilan contoh uji beton segar.
- SNI 03-2492-2002 - Metode pengambilan dan pengujian beton inti
- SNI 2493-2011 - Tata cara pembuatan dan perawatan benda uji beton di
laboratorium.
- SNI 03-3403-1994 - Metode pengujian kuat tekan beton inti pemboran
- SNI 03-4810-1998 - Metode pembuatan dan perawatan benda uji beton di
lapangan.

2.2. American Society of Testing and Materials (ASTM):

- ASTM C31 - Test Method of Making and Curing Concrete Test Specimens in the
Field.
- ASTM C39 - Test Method for Compressive Strength of Cylindrical Concrete
Specimens.
- ASTM C42 - Test Method for Obtaining and Testing Drilled Cores and Sawed
Beams of Concrete.
- ASTM C143 - Test Method for Slump of Hydraulic Cement Concrete.
- ASTM C172 - Standard Practice for Sampling Freshly Mixed Concrete.
- ASTM C192 - Standard Practice for Making and Curing Concrete Test Specimens
in the Laboratory
- ASTM C231 - Test Method for Air Content of Freshly Mixed Concrete by the
Pressure Method.

PROJECT NO. : 17.3866 DIVISION : GENERAL REQUIREMENTS SPEC. NO. : 01400


REVISION :A DATE : April 2018 PAGE : 1 of 5
BITA

2.3. American Concrete Institute (ACI):

- ACI 308 - Standard Practice for Curing Concrete.

2.4. Specification 03300 - Cast-in-Place Concrete.

3.0 GENERAL PROCEDURES

3.1. Concrete samples shall be taken in accordance with ASTM C172 and/or SNI 03-2458-
2008 or as specified below.

3.2. The specimens shall be representative of the batch and shall consist of portions from
different points in the batch.

3.3. The specimens shall be taken in three (3) or more regular increments throughout the
discharge of the entire batch except at the beginning or end, and placed in a metal
container such as a boggie or wheelborrow.
3
The specimens for compressive test shall be taken for every 30m or less of concrete
placing.
The rate of discharge of the batch shall be regulated by the rate of revolution of the
drum and not by the size of the gate opening. Sampling shall be worked out by
passing a receptacle repeatedly through the entire discharge stream or diverting the
entire stream into the container. Care shall be observed not to restrict the flow in such
a manner not to cause segregation of concrete.

3.4. Sample shall be mixed thoroughly with a shovel to ensure uniformity. The slump test
and the test specimens shall be made immediately.

4.0 MATERIALS

Refer to section 5.0 Construction Requirements of this Specification.

5.0 CONSTRUCTION REQUIREMENTS

5.1. Content of Chloric Ion

Amount contents of chloric ion in the structural concrete from cement, aggregates,
3
water and admixtures shall not exceed 0.30kg/m . Content test of chloric ion shall be
performed at a concrete plant and site prior to concrete placing, and the result shall be
submitted to the Engineer for approval.

5.2. Slump Test

A slump test shall be taken for each set of specimen taken. The method shall conform
to SNI 03-1972-2008 and/or ASTM C143, or as describe below:

- Properly clean and wet the slump-cone.


- Fill the slump-cone in three (3) nearly equal layers.
- Puddle each layer with twenty five (25) strokes of the tamping-rod. Distribute the
strokes evenly over the cross-section of the slump-cone.
- Strike off the top smoothly so the slump-cone is exactly filled.
- Clean off all concrete that may have spilled around the base of the cone.

PROJECT NO. : 17.3866 DIVISION : GENERAL REQUIREMENTS SPEC. NO. : 01400


REVISION :A DATE : April 2018 PAGE : 2 of 5
BITA

- Remove the slump-cone from the concrete in approximately five (5) seconds,
being careful to raise it in a vertical direction only.
- Measure the slump immediately. This is the difference between the height of the
slump-cone and the height of the concrete specimen.

Slump shall not be less than 50mm but not more than 125mm as specified in SNI 03-
1972-2008 or as determined by the Engineer.

5.3. Molding

The method of molding shall conform to SNI 03-4810-1998 and or ASTM C31
standard. The specimens shall be made as close to the point of delivery as possible.
If the material is to be transported a distance from the source, the concrete shall be re-
mixed with a shovel before making the molds.
The procedure as follows:

- Place the molds on a heavy base plate, preferably metal.


- Fill the mold in three (3) nearly equal layers.
- Puddle each layer with twenty five (25) strokes of the tamping rod. Take care not
to dent the bottom of the container in rodding the bottom layer.
- Strike off the top smoothly and cover with a glass or metal plate to prevent
evaporation. Never use a piece of wood.

5.4. Laboratory-Cured Specimens

5.4.1. Cubics for strength test shall be molded and laboratory-cured and tested in
accordance with SNI 2493-2011.

5.4.2. Cylinder for strength tests shall be molded and laboratory-cured and tested in
accordance with SNI 1974-2011, SNI 2493-2011 and or ASTM C39.

5.5. Handling and Storage

5.5.1. The curing of the specimens shall conform to ACI 308 and ASTM C31.

5.5.2. The first 24 hours after molding are important. The specimens should be
moved only from the place of molding to the storage designated place, taking
care to keep them in an upright position and avoiding vibration and jarring.
Specimens maybe stored in tightly-constructed, firmly-braced wooden boxes,
damp sand pits, or temporary buildings as long as the temperature adjacent to
the specimens can be maintained between 15.6C and 26.7C and loss of
moisture from the specimens can be prevented.

5.5.3. At the age of one (1) day each set of specimens should be sent/ analyzed to a
recognized laboratory for proper curing and testing. Pack the specimens in a
sturdy box for shipment, leaving the specimens in the containers. The space
between the specimens and the box should be filled with wet sand or sawdust.
Each set of specimens should be accompanied by the data recorded at the
time of making the specimens.

5.5.4. If it is impossible to ship the specimens at the age of one (1) day, it should be
stored in thoroughly damp sand at the end of the initial 24 hour period, and
shall be maintained in a moist condition at 21C - 24.5C until shipment is
made. The specimens shall be shipped as soon as possible and at least
several days before the seven (7) days period is up, as the laboratory must
have the specimens a day or so before the seven (7) days test.

PROJECT NO. : 17.3866 DIVISION : GENERAL REQUIREMENTS SPEC. NO. : 01400


REVISION :A DATE : April 2018 PAGE : 3 of 5
BITA

5.5.5. The Contractor shall provide a shed and an insulated locked box of sufficient
size to store equipment and specimens at the site, and whatever labour is
required in the preparation of specimens.

5.6. Testing

5.6.1. Inspection and testing will be performed by a firm engaged by the Contractor.
Tests of cement and aggregates may be performed to ensure conformance
with specified requirements in Specification 03300.

5.6.2. Test for air content each time a set of specimens is prepared for compression
testing. Test shall be in accordance with ASTM C231.

5.6.3. The Contractor shall cooperate with the Testing Laboratory to facilitate their
work. The Contractor shall notify the Testing Laboratory and the Engineer at
least 24 hours in advance of placing concrete for inspection and testing of
concrete at the plant and at the field, and for inspection of formwork and
reinforcement. The Contractor shall provide a shed and an insulated locked
box of sufficient size to store equipment and specimens at the Project site,
and whatever labor is required in the preparation of specimens.

5.6.4. The actual making, handling, transporting, and curing of specimens shall be
done by the staff of Testing Laboratory only.

5.6.5. Plant tests and inspections shall include the following minimum requirements:

- Sampling and testing concrete ingredients.


- Reviewing and checking Contractor's proposed design mixes.
- Inspecting plant and equipment for measuring, mixing and delivering
concrete.
- Inspecting batching and mixing operations.
- Inspecting concrete mix.

5.6.6. Field tests and inspections shall include the following minimum requirements:

- Checking truck number and/or delivery tickets of plant mixed concrete.


- Checking amount of water added to concrete mix, if permitted, in field.
- Making samples and test for air-content in concrete.
- Making slump tests according to SNI 03-1972-2008 and or ASTM C143.
- Making specimens for laboratory testing of compressive strength.
- Taking temperatures of as-mixed concrete, of as-deposited concrete, and
of concrete during curing period.
- Taking air temperatures during placing and curing of concrete.
- Checking concrete placing and curing procedures.
3
The field test shall be made for each 30m or for each arrival of truck.

5.6.7. Laboratory tests and inspection shall include the following minimum
requirement:

- Compressive strength tests in accordance with ASTM C39 and or SNI


1974-2011:

· Three (3) pieces of specimens cured at laboratory for seven (7) days
strength.

PROJECT NO. : 17.3866 DIVISION : GENERAL REQUIREMENTS SPEC. NO. : 01400


REVISION :A DATE : April 2018 PAGE : 4 of 5
BITA

· Three (3) pieces of specimens cured at laboratory for twenty eight (28)
days strength.
· Three (3) pieces of specimens cured at site for seven (7) days
strength.
· Three (3) pieces of specimens cured at site for twenty eight (28) days
strength.
· Other strength as occasion demands.
· Three (3) pieces of specimens cured at laboratory and site for three
(3) days strength and the expected day which the strength have
reached specified strength, if hardening acceleration is used.

- Weighing of all specimens.

5.6.8. Core tests of hardened concrete shall be as follows:

- Core test shall be performed in case compressive strength tests of


laboratory are not satisfactory or detection of failure in placed concrete.
- The Engineer reserves the right to direct that samples be cored from any
portion of works for the purpose of examination and testing. The cutting
equipment and method of coring shall be approved by the Engineer.
Specimens shall be taken and tested in accordance with SNI 2493-2011,
SNI 03-3403-1994 and or ASTM C42. The cored portion of the work shall
be made good to the satisfaction of the Engineer.
- The Contractor shall bear the costs for the core tests if they are required
because of test specimen failure, or if the core test fails.

5.6.9. If the tests and reports indicate that the placed concrete does not meet the
specified strength, the Engineer will notify the Contractor in writing. Additional
curing as specified by the Engineer may be required and modifications may be
required in the concrete mix design for the remaining concrete work; or the
concrete may be required to be removed and replaced; in either case at the
expense of the Contractor.

5.7. Environmental Conditions

Do not pour concrete during rain or when rain is expected unless the work can be
protected from rain and/or flowing surface water.

PROJECT NO. : 17.3866 DIVISION : GENERAL REQUIREMENTS SPEC. NO. : 01400


REVISION :A DATE : April 2018 PAGE : 5 of 5
DIVISION 2
SITE CONSTRUCTION
BITA

SPECIFICATION

02200

SITE PREPARATION AND GRADING

1.0 DESCRIPTION OF WORK

This work shall include but not be limited to the following:

- The Contractor shall furnish adequate equipment, accessories and enough manpower.
- Subgrade preparation, road pavement, open ditch, culvert, utility lines and others as shown in
the Drawings.
- Clearing, grading, sloping, compaction of ground surface, spreading and compaction of sand
layer and/or sand gravel according to the Drawings.

2.0 REFERENCE STANDARDS

2.1. American Association of State Highway and Transportation Officials (AASHTO).

2.2. American Society for Testing and Materials (ASTM).

2.3. All applicable local rules and codes, the highest or most stringent value to apply.

2.4. Specification 02315 - Excavation, Backfilling and Compaction.

3.0 GENERAL PROCEDURES

3.1. General

3.1.1. The Contractor shall submit samples of materials for all of the works to the
Engineer for testing and approval.

3.1.2. The Contractor shall also submit Shop Drawings as requested by the
Engineer.

3.1.3. The Contractor shall strictly study and follow all the details/sections, elevation,
profiles, dimensions and alignments shown in Drawings.

3.1.4. Should the Contractor have any absolute doubt of the dimensions that may not
be readable, the Engineer must be consulted prior to execution of the work.
Any errors or omissions by the Contractor shall be his own expense.

3.1.5. The Contractor shall advise the Engineer in writing duly signed by his
authorized/designated representative, where and when to start any portion of
the work and this shall be approved by the Engineer.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02200


REVISION :A DATE : April 2018 PAGE : 1 of 4
BITA

3.1.6. The Contractor shall submit to the Engineer, his work schedule every two (2)
weeks and which includes the following:

- equipment list,
- manpower list,
- volume to be accomplished.
Such schedule shall be approved by the Engineer, before any work will be
started.

3.1.7. The Contractor shall not be permitted to transfer any equipment or manpower
assigned to the portion of work which was mentioned in the work schedule
already approved unless otherwise reconsideration is made prior to the shifting
and approved by the Engineer.

3.1.8. The Contractor shall obtain all government permits and other requirements for
such operation.

3.1.9. Delay of work due to untimely acquisition of the permits from government
authorities shall not be considered for requested extension of the time to
complete work as stipulated in the contract.

3.1.10. During bad weather and/or occurrence of rain or if the ground to be worked on
is wet, the Contractor shall not be permitted to operate unless otherwise
determined by the Engineer.

3.1.11. Night shift operation will not be permitted, unless approved by the Engineer.

3.2. Inspection and Testing

- Standby survey team must be on site during the course of the operation.
- Testing shall be conducted with following steps:

 before work starts,


 before work stops daily.

- All equipment and survey instruments that shall be used in this particular job must
be inspected and tested before permitted to work.

3.3. Clearing and Grubbing

The area above natural ground shall be cleared of all vegetable growth, such as trees, logs,
upturned stumps, roots of downed trees, brush, grass, weeds and all other objectionable
material, within the limits designated in the Drawings or as directed by the Engineer.
Within the limits of clearing, the areas below natural ground surface shall be grubbed to a
depth necessary to remove all stumps, large roots, buried logs and other objectionable
material.

4.0 MATERIALS

Refer to section 5.0 Construction Requirements of this Specification.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02200


REVISION :A DATE : April 2018 PAGE : 2 of 4
BITA

5.0 CONSTRUCTION REQUIREMENTS

5.1. General

5.1.1. Finished levels of embankments that are finished sub-grade levels shall not be
more than 100mm higher nor 100mm lower than the required grade and shall
allow free run-off surface water.

5.1.2. Side slopes shall be neatly trimmed to the lines and inclinations shown in the
Drawings.

5.1.3. The Contractor shall be responsible for the stability of all embankments and
replace any portions that have been damaged or displaced due to
carelessness or neglect on the part of Contractor or to such natural causes as
storms.

5.1.4. All unnecessary structures such as trees, drains, culverts and temporary
structures not specified to remain in place shall be demolished and removed
to a depth of 900mm below the finished grade and the holes shall be backfilled
and tamped immediately.

5.1.5. All construction materials shall not be stored in the prepared site until the
grading and site preparation works are completely turned over and accepted
by the Engineer.

5.1.6. Prior to site preparation and grading, all top soil, clearing and grubbing shall
have been done and accepted by the Engineer.

5.1.7. Equipment used for site preparation and grading shall be approved tools, road
graders or compactors suitable for such soil condition of the site.

5.1.8. Any complete portion of the work area found to be unstable or below grade
and not acceptable shall be repaired and re-graded by the Contractor with no
additional compensation.

5.1.9. All benchmarks designated in place shall stay and must never be altered in
any manner.

5.1.10. After the work is completed, all stakes or vertical controls destroyed or
damaged shall be re-established to the points chosen by the Engineer.

5.1.11. During the final grading, only expert grader operators shall be allowed to
conduct the operation in order to maintain the requirements of this
specification, except on areas to be done by hand tamping.

5.1.12. At the end the day's work, all holes must be sealed or filled and areas
composed of loose soil fragment must be leveled off and compacted.

5.1.13. Any excavation, backfilling or compacting needed in this work shall be carried
out in accordance with the requirements of Specification 02315.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02200


REVISION :A DATE : April 2018 PAGE : 3 of 4
BITA

5.2. Clearing and Grubbing

The limits of clearing and grubbing shall be as defined and shown in the Drawings or as
directed by the Engineer. Generally clearing and grubbing shall be in all the construction
areas of buildings, structures, roadways, embankments, material sites located on the Site,
areas through which ditches and channels are to be excavated and such other areas as
may be specified. Clearing and grubbing shall be performed in advance of grading
operations.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02200


REVISION :A DATE : April 2018 PAGE : 4 of 4
BITA

SPECIFICATION

02230

SITE CLEARING

1.0 DESCRIPTION OF WORK

This work shall consist of all necessary topsoil stripping and stockpiling in accordance with the
location, height and spacing as shown on the Drawings or as determined by the Engineer.
It includes but is not limited to the following:

- Furnishing of all the required equipment and accessories.


- Supply of the experienced operators, skilled workers and labourers and foreman with an
adequate background in earthworks.
- Loading, hauling and dumping of the stockpiled soil to places designated by the Engineer.

2.0 REFERENCE STANDARDS

Any applicable standards and codes, the most stringent values to apply.

3.0 GENERAL PROCEDURES

3.1. Topsoil shall consist of organic soils reasonably free of admixture of subsoil, refuse,
stumps, roots, rocks, brush, weeds or vegetative growth.
Stripping of topsoil shall comprise the excavation of suitable material from the natural
ground cover on those portions of the site designated on the plans or as directed by
the Engineer.
Topsoil shall be segregated and stockpiled in designated locations for subsequent use
in landscaping and/or reclamation.

3.2. The Engineer shall establish the points for all the areas intended to be worked on, and
the Contractor shall place his reference stakes from these permanent points.

3.3. After the stake out, the actual area shall be estimated together with the Engineer and
Contractor and shall be issued by the Engineer for execution. However, the issuance
of such calculation will not relieve the Contractor's responsibility of any errors and
omissions.

3.4. The Contractor shall plan and locate the stockpile at every 50meters distance on
centres and such shall be placed at the road side for easy hauling.

3.5. All the excavated materials to be disposed shall be transported to the areas
designated by the Engineer.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02230


REVISION :A DATE : April 2018 PAGE : 1 of 2
BITA

3.6. The Contractor shall allow 50 to 70mm depth of soil to remain uncut as the Engineer
may direct for the purpose of compaction and the balance shall be totally or evenly cut
as shown on drawings. Any excess in cutting shall be repaired.

3.7. Where particular locations of low depression occur as considered by the Engineer,
these shall be filled from the excavated soil and compacted to the necessary
maximum soil density requirements.

4.0 MATERIALS

Refer to section 5.0 of this Specification.

5.0 CONSTRUCTION REQUIREMENTS

5.1. Top soil stripping depths shall be 200mm, unless otherwise specified by the Engineer.
Minimum stripping distance shall be 50meters radius or as determined by the
Engineer.

5.2. No objectionable materials such as branches or roots and boulders or stones shall be
mixed in the stockpile. If there are any unsuitable materials, these must be segregated
and disposed of at the site designated by the Engineer.

5.3. Good and functional temporary drainage system shall be provided around the
stockpile area to prevent erosion of stockpile.

5.4. Only light weight dozer or motor scraper shall be applied in the stripping operation.
Substitution of equipment shall be allowable as approved by the Engineer.

5.5. Prior to conclusion of the day’s work activities, all holes and loose earth shall be filled
or sealed, pulverized and levelled off to the ground elevation. Temporary grading and
drainage necessary to keep the work area free of ponding water shall be constructed
and maintained by the Contractor.

5.6. Topsoil storage piles shall be provided with erosion control and shall be seeded as
directed by the Engineer.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02230


REVISION :A DATE : April 2018 PAGE : 2 of 2
BITA

SPECIFICATION

02315

EXCAVATION, BACKFILLING AND COMPACTION

1.0 DESCRIPTION OF WORK

This work shall include, but not be limited to the following:

- Furnishing adequate equipment and tools, materials, enough manpower to finish all the work
including temporary retaining wall, if required.
- Excavation, backfilling and compaction all the works that require excavation and/or backfilling
such as foundation, ditches, culverts, utility lines and others as shown in the Drawings.
- Removing all unsuitable backfill material to disposal place as determined.
- Excavation and hauling backfill material from an excavation place.
- To complete the work as required in this Specification.

2.0 REFERENCE STANDARDS

2.1. American Society for Testing and Materials (ASTM)

2.2. Any applicable local codes and standards, the highest or most stringent to apply

3.0 GENERAL PROCEDURES

3.1. Excavation

3.1.1. Excavation shall be done in accordance with the lines and depth indicated on
the plans or as established by the Engineer. The width of excavation shall be
made wide enough to give easy movement in doing the work.

3.1.2. Elevation as shown in the Drawings is approximate only and the Engineer can
instruct any change if necessary.

3.1.3. After each excavation is completed, the Contractor shall notify the Engineer to
that effect, and no follow up operation shall be executed until the Engineer has
approved the depth of excavation and the soil layer character of the
excavation bottom.

3.1.4. All hard layers or other hard surfaces to be excavated shall be free from loose
materials, clean and to be cut horizontally or incline according to the Drawings
or as directed by the Engineer prior to compacting backfill material.

3.1.5. Where unsuitable material is exposed at the elevations of planned excavation,


the Contractor will be required to perform additional excavation, as directed by
the Engineer, to depths where suitable bearing is reached.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02315


REVISION :A DATE : April 2018 PAGE : 1 of 6
BITA

3.1.6. For soft layers, final surface of the excavation shall not be finalized before the
next work is ready to be done, so that the rain water or other surface water
cannot damage the excavation surface.

3.1.7. To excavate the soft soil, Contractor shall install temporary retaining wall to
avoid the soil falling into the excavation hole.

3.1.8. Contractor shall protect the excavation hole from water or rain water by
providing temporary drain or pump, or approved dewatering.

3.1.9. Materials excavated below required elevations, through Contractor error or


carelessness shall be corrected as directed by the Engineer at no cost to the
Principle.
It is assumed that materials at the job site can be excavated with normal
equipment such as power shovel or bulldozer.
If rock is encountered, the Contractor shall notify the Engineer who will render
a decision before further excavation can be proceeded.
After the end of each excavation, the Contractor shall notify the Engineer, and
the work can be proceed after the Engineer approves the depth and the type
of the soil layer at the bottom of the excavation.

3.2. Backfilling and Embankment

3.2.1. Backfilling and embankment can only be started when backfill material and
location of the work have been approved by the Engineer.

3.2.2. Contractor shall not proceed the backfilling work before the Engineer approves
the former work.

3.2.3. Excavated material suitable for use as backfill and embankment material may
be deposited by the Contractor in storage piles at points convenient for re-
handling of the material during the backfilling and embankment operations.
The location of storage piles shall however, be subject to the approval of the
Engineer.

3.2.4. Backfilling of concrete work shall only be carried out when the age of the
concrete work is 14 days minimum, and when the masonry work is 7 days
minimum, or after the approval from the Engineer.

3.3. Compaction

The Contractor shall furnish satisfactory power-operated or power driven hand operated
compactor wherever possible to compact fill, as well as cut areas. For the compaction of
cohesive soils, self-propelled tamping rollers or towed sheep foot rollers shall be used.
Smooth steel wheel vibratory rollers shall be used to compact granular fill materials.
Compaction by flooding or jetting shall not be permitted.
If the fill or degree of compaction is unsatisfactory, necessary adjustment shall be made
until the appropriate compaction requirements are met. Material placed over layers not
satisfactorily compacted shall be removed and unsatisfactory areas re-compacted as
directed by the Engineer.

4.0 MATERIALS

Refer to section 5.0 Construction Requirements of this Specification.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02315


REVISION :A DATE : April 2018 PAGE : 2 of 6
BITA

5.0 CONSTRUCTION REQUIREMENTS

5.1. Excavations

5.1.1. Excavation work is final when the bottom of the excavation has reached the
required elevation as shown in the Drawings or has been approved by the
Engineer.

5.1.2. All excavated material shall be deposited and / or stockpiled at designated


place as determined by the Engineer. Subject to the approval of the Engineer,
such material may be used for backfilling or otherwise shall be disposed of
offsite.

5.1.3. Over excavated outside the required lines and grades as shown in the
Drawings or as directed by the Engineer through Contractor error or
carelessness, the over-excavated material will not be paid and the Contractor
shall correct the work according to the Drawings at his expense.

5.1.4. Excavation shall be carried out in a manner so as not to damage the


benchmark or other finished works. All damages caused by this work shall be
the Contractor's responsibility and shall be corrected by the Contractor without
any additional cost and time.

5.1.5. The Contractor shall remove any rock encountered in areas of final elevation
to a depth of at least 150mm below the planned final elevation. Rock shall be
defined as stone or hard shale in its original ledge, and boulders over half (0.5)
cubic meter in volume or over one (1.0) meter in greatest dimension, which
will require removal by special equipment and/or explosives.

5.2. Backfilling and Embankment

5.2.1. Backfill Material

- The approved material used in backfilling shall be free of any appreciable


amount of gravel or stone particles more than 37.5mm in greatest dimension
and of such gradation as to permit thorough compaction.
- When, in the opinion of the Engineer, such material is not readily available, the
use of rock or gravel mixed with earth will be permitted, in which case no
particles larger than 100mm in greatest dimension and 37.5mm in least
dimension may be used, and the percentage of fines shall be sufficient to fill
any void and ensure a uniform and thoroughly compacted mass of proper
density.
- All excavated material except earth shall not be used as backfill material
except approved by the Engineer as mentioned in point 5.1.2 of this
Specification.
- Backfill material that is deposited near the working place for more than 12
hours shall be protected with polyethylene sheet so as not to damage the
material which has been approved by the Engineer.
- Each layer of backfill material, if dry, shall be wetted uniformly to the moisture
content required to obtain the specified density.
- Backfill material for culvert shall have minimum CBR value of 25%, from
Reject Dryer, Mining Quarry, and Blue Zone Rock Quarry.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02315


REVISION :A DATE : April 2018 PAGE : 3 of 6
BITA

5.2.2. Preparation

Prior to placing of backfill material, the following works shall have been carried
out in advance:

- Clearing the location and/or excavating in accordance with the Drawings or as


directed by the Engineer.
- The Contractor shall notify the Engineer prior to placing of backfill material and
the Engineer will examine the condition of the location that is being prepared
for the purpose.
- Location that is being covered by backfill/embankment material shall be dried
from surface water by using pump or other equipment approved by the
Engineer.

5.2.3. Placing of Backfill Material

- Backfill material shall not be spread out or compacted during or prior to


imminent rain events.
- Backfill within or not within embankment area shall be placed layer by layer
with maximum loose fill thickness of 250mm and shall be compacted to level.
- Backfill material for culvert shall be placed simultaneously on both sides in
loose fill layer not more than 250mm.
- Backfill not within the embankment area shall be compacted to a density
comparable with the adjacent, undisturbed material or as stipulated in section
5.3 of this Specification.
- Backfill within embankment areas shall be compacted in accordance with
density as stipulated in section 5.3 of this Specification.
- Unless otherwise provided by the plans or special provisions, hand tamping
will not be accepted as an alternate for mechanical compaction.
- The Contractor shall not place new layer of backfill material until the former
layer has been approved by the Engineer.
- No backfilling shall be done without the approval of the Engineer.

5.3. Compaction

5.3.1. General

- When necessary, each layer before being compacted shall be processed as


required to bring the moisture content sufficiently close to optimum to make
possible its compaction to the required density. The material shall have
uniform moisture content through the entire layer of material to be compacted.
- Each layer of material shall be compacted uniformly by use of pneumatic tire
rollers, grid rollers, three-wheeled power rollers, vibratory, sheep foot or
tamping rollers or other approved type compactors.
- Backfill material between culverts shall be compacted uniformly by using baby
roller, tamper or hand compactor until minimum height of embankment as
shown in the Drawings.
- The rolling shall be done in a longitudinal direction along the embankment and
shall generally begin at the outer edges and progress towards the centre in
such a manner that each section receives equal compaction effort.
3
- At least one roller shall be operated continuously for each 600m , or fraction
thereof, of material placed per hour. When several small embankments, each
of small area, are so isolated from each other that one roller cannot compact
them satisfactorily, additional rollers shall be provided.
- Hauling equipment shall be operated over the full width of each layer insofar
as practicable.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02315


REVISION :A DATE : April 2018 PAGE : 4 of 6
BITA

5.3.2. Maximum Dry Density and Optimum Moisture Content

Maximum dry density and optimum moisture content of soils shall be


determined by one of the methods described in ASTM D1557 (AASHTO T180)
commonly known as the Modified Proctor Test.

5.3.3. Moisture Control

At the time of compacting areas where high density is required, fill material
and the surface on which it is placed shall be within the specified range of
moisture content. The Contractor shall not compact-fill until it is within the
range required for moisture content. He shall add an accurately determined
and carefully measured amount of water to materials or surfaces that are too
dry.
The Contractor shall pile or spread out to dry, material which is too wet, and if
necessary, disk, harrow or pulverize it by hand or mechanical means.

5.3.4. Proof-rolling

- The Contractor shall proof roll stripped and cut areas under Engineer's
direction, to determine if soft spots exist in the area. He shall use a loaded
dump truck, compaction roller, or similar approved compacting equipment.
The type, size and weight of the equipment to be used shall be as directed by
the Engineer.
- The Contractor shall place and compact fill material in low spots. If wet or
spongy areas are revealed, he shall notify the Engineer so that corrective
measures may be determined. Areas that support structures shall be inspected
during proof rolling and approved by the Engineer before further earthwork
operations are performed.

5.3.5. Density for Cohesive Soils

For soil having 30% or more, by weight, of particles passing a No. 200 sieve,
required relative compaction, as determined by one of the method described
in ASTM D1557 (AASHTO T180), and expressed as a percentage of
maximum dry density, and moisture content, at the time of compaction shall
be as follows:

Relative Moisture
Fill Areas Compaction Range
(%) (%)*

General Fill, including culvert backfill 95 -3 W o +3


Main Roads and Heavy Vehicle Parking 95 -4 W o +2
(Top Meter)
Connecting Roads and Light Vehicle 95 -4 W o +3
Parking (Top Half Meter)
Warehouse and Workshop Floors (Top Half 95 -4 W o +2
Meter)
Trench Backfill (Except where superseded 90 -3 W o +3
by higher compaction requirement)

*W o = Optimum Moisture Content.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02315


REVISION :A DATE : April 2018 PAGE : 5 of 6
BITA

5.3.6. Density for Cohesionless Soils

Soil having less than 30% by weight, of particles passing a No. 200 sieve,
required relative compaction as determined by one of the methods described
ASTM D1557 (AASHTO T180), and expressed as a percentage of maximum
dry density as follows:

Relative Compaction
Fill Areas
(%)
Drainage blanket beneath No requirement. Compact with light buldozer (eg.
embankment D-6) traffic
Cushion fill beneath floor slabs 95
May be inspected by protruding, at Engineer’s
option
Road base and culvert backfill 95
Trench backfill 92
Trench or chimney drains No requirement

5.3.7. Disposal of Excavation Material

All suitable excavated material as approved by the Engineer shall be used for
backfill. Material that is not needed or not suitable for backfill shall be
disposed off at designated areas.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02315


REVISION :A DATE : April 2018 PAGE : 6 of 6
BITA

SPECIFICATION

02330

EMBANKMENT

1.0 DESCRIPTION OF WORK

This work shall consist of the construction of embankment by placing and compacting all
borrow materials of acceptable quality obtained from the site and access road preparation
excavation in accordance with these Specifications and to the lines, grades and cross-sections
shown in the Drawings and as directed by the Engineer.

2.0 REFERENCE STANDARDS

2.1. American Association of State Highway and Transportation Officials (AASHTO).

2.2. American Society for Testing and Materials (ASTM).

2.3. Specifications:

- 02200 - Site Preparation and Grading.


- 02315 - Excavation, Backfilling and Compaction.

3.0 GENERAL PROCEDURES

3.1. General

3.1.1. A report describing the soil conditions encountered during investigation of the
site may be inspected at the office of the Engineer. The accuracy of this report
cannot be guaranteed as present conditions since those found in other
locations of the site may vary from those discussed. The Contractor shall be
fully responsible for all on-site soil conditions whether or not furnished in
above-mentioned report.

3.1.2. Stripping, cutting, proof rolling, filling and compacting procedures shall be
approved by the Engineer.
Any work found unsatisfactory shall be corrected in a manner approved by the
Engineer at no additional cost to the Owner.

3.2. Embankment

Embankments and/or fill areas shall be constructed using only the material obtained
from stockpiles of cut material which is approved by the Engineer. The material shall
be free of debris, organic material, rocks over 150mm in maximum dimension and
excessive moisture or dryness.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02330


REVISION :A DATE : April 2018 PAGE : 1 of 4
BITA

3.3. Compaction

The Contractor shall furnish satisfactory power-operated or power driven hand


operated compactor wherever possible to compact fill, as well as cut areas. For the
compaction of cohesive soils, self-propelled tamping rollers or towed sheeps foot
rollers shall be used. Smooth steel wheel vibratory rollers shall be used to compact
granular fill materials. Compaction by flooding or jetting shall not be permitted.

3.4. Inspection

3.4.1. All materials and each part or detail of the work shall be subject to inspection
by the Engineer.
The Engineer shall be provided with access to all parts of the work and shall
be furnished with such information and assistance by the Contractor as is
required to make a complete and detailed inspection.

3.4.2. Earth-work and compaction shall be suspended within the particular area
during field density testing as required by the Engineer.

3.4.3. The Engineer may direct the Contractor to remove or uncover portions of the
work. After examination, the Contractor shall restore said portions of the work
to the standard requirements of this Specification.

3.4.4. The Contractor shall not proceed to execute the work until the lines, grades
and/or structure locations have been established. Any work done by the
Contractor contrary to the Drawings, Specifications or instructions of the
Engineer, or any extra work done without authorization of the Engineer, may
be ordered to be removed or replaced at the Contractor's expense.

4.0 MATERIALS

4.1. Embankment Material

Materials for embankment and/or backfills shall be from Reject Dryer, Mining Quarry,
and Blue Zone Rock Quarry. with minimum CBR≥25%, and shall contain no muck,
roots, sod or other deleterious material, as specified in Specification 02315.

4.2. Change of Soil Material

The soil replacement shall be reddish clay material, and shall be placed layer by layer
to the designated area up to the thickness as shown in the Drawings and as directed
by the Engineer.
Prior to delivery on site, source and sample of the soil material shall be approved by
the Engineer.

5.0 CONSTRUCTION REQUIREMENTS

5.1. General

5.1.1. The Contractor shall proof roll to the required soil density those areas that
have been stripped, prior to placing fill material. He shall remove undesirable
material and replace it with approved material. Fill material shall be deposited
in horizontal layers to a maximum loose depth of 200mm and each layer shall
be properly compacted.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02330


REVISION :A DATE : April 2018 PAGE : 2 of 4
BITA

The Engineer may alter maximum depth of the layer if, because of equipment,
material, or other conditions, he deems it necessary to assure the required
degree of compaction. All fill shall be placed in level lifts. Where fill is to be
placed over a sloping subgrade, the subgrade shall be benched so a sloping
subgrade or fill interface is avoided.

5.1.2. Fill surfaces shall be sloped to drain at all times. Grades shall slope away from
fill crests to minimize fill face erosion.

5.1.3. The subgrade or fill interface net inclination shall be 1.5 (horizontal) to 1
(vertical) or flatter.

5.2. Preparation of Foundation for Embankment

5.2.1. Prior to placing any embankment to any area, all clearing and grubbing
operations shall have been completed in accordance with Specification 02200.
All sod, grass, and decayed vegetable matter shall be removed from the upper
portion of the ground surface, and the top 150mm shall be compacted to 90%
of the maximum dry density determined by AASHTO Method T180 (ASTM
D1557).

5.2.2. When embankments are to be constructed on hillsides or slopes, the existing


slopes other than rock shall be loosened by scarifying or plowing to a depth of
not less than 100mm to ensure a good bond between the embankment and
the existing embankment foundation.
The material which has been loosened shall be recommended simultaneously
with the first layer of embankment material placed.

5.2.3. Where existing embankments are to be widened or included in new


embankment, the slopes of the existing embankment shall be plowed or
scarified to a depth of not less than 100mm, or when this is impracticable,
steps in horizontal and vertical faces shall be cut in the existing slope to a
depth not more than 200mm and the embankment built up in successive
layers, as hereinafter specified, to the level of the old foundation bed before its
height is increased.

5.2.4. Unless otherwise shown in the plans, where existing subgrades are to be
covered with less than 300mm of fill, the top of the old subgrade shall be
scarified and re-compacted with the next layer of the new embankment. The
total depth of the scarified and added material shall not exceed the
permissible depth of layer, compact to at least 95% of the maximum dry
density as determined by AASHTO T180 (ASTM D1557).

5.3. Placing Embankment

5.3.1. General

Unless otherwise specified, all embankments shall be constructed in layers


approximately parallel to the finished grade of subgrade or roadbed. During
construction of embankment, a smooth grade having an adequate crown shall
be maintained at all times to provide drainage. Embankments shall be
constructed in accordance with grades and the general shape of typical
sections shown in the Drawings. After completion of the embankment, it shall
be continuously maintained to its finished section and grade until the project is
accepted.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02330


REVISION :A DATE : April 2018 PAGE : 3 of 4
BITA

5.3.2. Earth Embankments

Earth embankments shall be defined as those composed principally of


material other than rock, and shall be constructed of accepted material from
designated or approved sources.
Except as specified for embankment in swamps, earth embankment shall be
constructed in successive layers, for the full width of the cross section and in
such length as are suited to the sprinkling and compaction methods utilized.
Prior to compaction, the layers shall not exceed 150mm where pneumatic tire
rolling is to be used and shall not exceed 200mm in depth for rolling with other
approved types of rollers.

5.3.3. Placing Over Ground with Shallow Groundwater

Embankments in rice fields or where water is present shall be constructed as


indicated in the Drawings and/or as specified herein.

5.3.4. Fill Adjacent to Culverts

Embankments adjacent to culverts which cannot be compacted by using of the


blading and rolling equipment used in compacting the adjoining sections of
embankment shall be compacted in the manner prescribed under
Specification 02315.
Material placed adjacent to any portion of any structure and in the first two
layers above the top of any culvert or similar structures, shall be material free
of any appreciable amount of gravel or stone particles more than 100mm in
greatest dimension and of such gradation as to permit thorough compaction.

5.4. Compaction

Compaction shall be done to a density comparable with adjacent, undisturbed material


or as stipulated in Specification 02315.
If the fill or degree of compaction is unsatisfactory, necessary adjustment shall be
made until the appropriate compaction requirements are met. Material placed over
layers not satisfactorily compacted shall be removed and unsatisfactory areas re-
compacted as directed by the Engineer.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02330


REVISION :A DATE : April 2018 PAGE : 4 of 4
BITA

SPECIFICATION

02335

SUBGRADE PREPARATION

1.0 DESCRIPTION OF WORK

This work shall cover support of the gravel and sand base course. It shall extend to the entire
area including walkways, roads, park areas or aprons as shown in the Drawings.

2.0 REFERENCE STANDARDS

2.1. American Association of State Highway and Transportation Officials (AASHTO).

2.2. All applicable local standards, regulation and codes, the most stringent values to
apply.

3.0 GENERAL PROCEDURES

3.1. Protection of completed work as described in the Drawings.

3.2. Prepared subgrade shall be protected against drying out and cracking. Any damage
resulting from the negligence thereof shall be repaired at Contractor's own expense.

4.0 MATERIALS

Refer to Section 5.0 of this Specification.

5.0 CONSTRUCTION REQUIREMENTS

5.1. General

5.1.1. The areas covered by the subgrade shall be carefully cleaned so that no
objectionable material is incorporated in the next item to be worked out.

5.1.2. The subgrade shall be made to conform to the prescribed lines, grades and
slopes, and compacted to 90% - 95% proctor density at the Engineer's
satisfaction so that base or bedding material, when placed and compacted will
give the same formation of the grades and lines of the subgrade.

5.1.3. All materials to a depth of 150mm below the subgrade level in cut and to a
depth of 300mm in embankment shall be fully compacted to at least 90% -
95% of the dry density requirements of AASHTO T99 with minimum CBR
value of 5% as noted in the Drawings.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02335


REVISION :A DATE : April 2018 PAGE : 1 of 2
BITA

5.2. Subgrade in Earth Cut

5.2.1. When the subgrade is in earth cut, it shall be formed to the correct traverse
and longitudinal profiles.

5.2.2. The soil shall be compacted with approved tamping rollers. Prior to
compaction, the soil moisture content shall be adjusted by wetting with
approved sprinkler trucks or by drying out, as may be required, in order to
attain the desired degree of compaction.

5.2.3. If soil property is such as to make it impossible to obtain the minimum CBR
required by the project, the unsuitable soil shall be removed upon written
notice from the Engineer.

5.2.4. The removal and disposal of unsuitable soil in earth cuts shall be classified as
common excavation. At the subgrade level, the Contractor shall fill the holes
caused from removal of stumps, roots and boulders with suitable and
approved fill material. Such work shall be covered by the contract price and
shall not be chargeable to the Owner.

5.3. Subgrade in Fill/Embankment

When a subgrade shall fall on fill areas, the following procedures must be strictly
observed:

- Prior to filling, the area shall be compacted and rolled in accordance with the
requirements and/or satisfaction of the Engineer.
- The approved backfill material shall be spread evenly to a maximum thickness of
300mm per layer with a road grader and rolled continuously. The required travel
rate of the road roller will be at 5km/hr and this speed shall be maintained
throughout until completed. During compaction or rolling, the desired soil moisture
content must be carefully controlled. The passes shall be six (6) times minimum to
eight (8) times maximum and/or as determined by the Engineer.
- Compaction or rolling operation will proceed with the same procedure above and
until the backfilling work is satisfactorily completed and accepted by the Engineer.

5.4. Subgrade in Rock Cut

If the subgrade falls on rock cut, the rock shall be neatly excavated to the correct
traverse and longitudinal profiles. The Contractor shall remove all loose materials and
bring the grade up to the correct level by addition of approved granular fill material
compacted and shaped to requirements as shown in the Drawings. No rock cut shall
project above the grade level. There shall be no extra payment for excavation below
the correct grade elevation.

5.5. Protection of Completed Work

Any portion of the subgrade that has been completed and accepted by the Engineer
shall be protected against drying out and cracking. Any damage from default of the
Contractor will be repaired as directed by the Engineer without additional payment.

5.6. Subgrade Tolerance

The completed surface shall vary not more than 10mm higher nor 10mm lower than
the required grade and shall allow free run-off surface water.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02335


REVISION :A DATE : April 2018 PAGE : 2 of 2
BITA

SPECIFICATION

02371

GABIONS

1.0 DESCRIPTION OF WORK

The work shall include transportation, labourer, equipment, materials and installation of
gabions at places as indicated in the Drawings.

2.0 REFERENCE STANDARDS

2.1. Standar Nasional Indonesia (SNI):

- SNI 03-3046-1992 - Kawat Bronjong dan Bronjong Berlapis PVC (Polivinil Klorida).

2.2. Specification 02315 - Excavation, Backfilling and Compaction.

3.0 GENERAL PROCEDURES

3.1. Sample

Sample of stone and wire shall be submitted to the Engineer for approval prior to
delivery to the site.

3.2. Shop Drawings

Prior to fabrication, Contractor shall prepare Shop Drawings covering dimensions,


plan/shape of gabions, openings, size of wire, wire woven, joint or connection, other
required details, for Engineer’s approval.

3.3. Work Schedule

The Contractor shall submit to the Engineer, a work schedule every two (2) weeks in
advance, and which includes the following:

- work plan.
- equipment list.
- manpower list.
- Safety preparation.
- volume to be accomplished.
- procedure/method of work.
- resources.

Such schedule shall be approved by the Engineer, before any work will be started.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02371


REVISION :A DATE : April 2018 PAGE : 1 of 3
BITA

4.0 MATERIALS

4.1. General

Gabions shall have high flexibility and shall be made of hot dip heavy galvanized steel
wire with PVC coating that is mechanically woven with woven machine, with specified
opening width and size according to requirements specified below. Each gabion shall
be divided by diaphragms.
All gabions shall conform to SNI 03-3046-1992, such as manufactured by PT
Maccaferri Gabions of Indonesia or approved equal.

4.2. Gabions
2
4.2.1. Wire for gabions shall have minimum tensile strength of 41kg/mm with
minimum diameter of wire according to the table below and covered with PVC:

Wire Diameter (mm) Tolerance

Woven wire 2,7 ± 0,08


Side wire (stiffener) 3,4 ± 0,10
Tying wire 2,2 ± 0,06

4.2.2. Mesh shall consist of 2 wires that are tightly twisted in three-half-turns to make
hexagonal shape having opening size of 80mm x 120mm.

4.2.3. PVC coating shall be green in colour with minimum thickness of 0.4mm and
from the type that is capable of resisting deleterious effects of natural weather
exposure, immersion in salt water and shall not show any material difference
in its initial compound properties.

4.3. River Stone

Stone for filling the gabions shall be river stone having sizes between 200mm up to
500mm.
River stone shall be sound, durable, tough, and dense and shall have minimum 3
contact surface.

5.0 CONSTRUCTION REQUIREMENTS

5.1. General

5.1.1. Gabions shall be installed after all excavation and backfilling works have been
inspected and approved by the Engineer.
Excavation and backfilling works shall be carried out in accordance with the
requirements of Specification 02315.

5.1.2. Gabions installation shall be executed according to the Shop Drawings and
location condition where gabions are to be placed with slope and elevation as
indicated in the Drawings.

5.1.3. Alignment, elevation and dimension shall be inspected prior to fabrication of


gabions.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02371


REVISION :A DATE : April 2018 PAGE : 2 of 3
BITA

5.2. Installation

5.2.1. Gabions shall be installed at places as indicated in the Drawings.

5.2.2. The ground on which gabions to be built shall be levelled at elevation


according to the requirements as shown in the Drawings or as directed by the
Engineer.

5.2.3. Stones for filling the gabions shall have uniform dimension especially for part
of gabions that are exposed.
Stones shall be filled into the gabions in a manner so that they are neat and fill
up the gabions.
Then the cover shall be tightly sketched over the stones until selvedge wires
meet.

5.2.4. Filling gabions through mesh opening that can make stones easily come out
from the gabions is not allowed.
3
5.2.5. Filled gabions shall have a minimum density of 1,3ton/m , with voids that are
evenly distributed and shall not exceed the 40% maximum.

5.2.6. All sides of gabions including panels and diaphragms shall be tightly and
securely fastened mechanically along the length of the selvedge to avoid the
mesh from loosening, especially at the cover when the gabions are already
filled with stones.

5.2.7. Gabions shall be tightly fastened to the adjacent ones before the cages are
filled.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02371


REVISION :A DATE : April 2018 PAGE : 3 of 3
BITA

SPECIFICATION

02459

PRECAST PRESTRESSED CONCRETE PILES

1.0 DESCRIPTION OF WORK

This work shall consist of providing materials, labour, tools, equipment, transportation and piling
precast prestressed concrete piles and furnishing them in accordance with this Specification and in
close conformity to the requirements stipulated in the Drawings.

2.0 REFERENCE STANDARDS

2.1. American Welding Society (AWS).

2.2. American Society for Testing and Materials (ASTM).

2.3. Standar Nasional Indonesia (SNI).

2.4. Japanese Industrial Standard (JIS).

2.5. Standard of the Manufacturer

3.0 GENERAL PROCEDURES

3.1. Technical Data and Mill Certificate

Prior to supplying and transportation, the Contractor shall submit a brochure or technical
data complete with mill certificate certifying the precast prestressed concrete piles meet the
specified requirement, for approval of the Engineer.

3.2. Work Method

The Contractor shall, before the commencement of any piling work, submit his proposal of
the work method for the Engineer's approval, including transportation, storing, handling,
driving of piles, driving equipment, crews, and also the detail of pile extension.

3.3. Fabrication of Piles

All piles shall be fabricated to dimension, length and with material of thickness as shown in
the Drawings.
All piles which have passed the test at factory shall be marked with the following data in a
manner not to be easily destroyed or erased.

- Grade of pile.
- Dimensions.
- Production number.
- Name of manufacturer.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02459


REVISION :A DATE : April 2018 PAGE : 1 of 6
BITA

3.4. Storage and Handling

3.4.1. All piles shall be stored and handled in such manners as will not inflict any
damages thereupon.

3.4.2. The piles shall not be stacked more than 3 (three) tiers high.

3.5. Driving Equipment

3.5.1. Prior to mobilization of driving equipment, the Contractor shall submit a detailed
working plan of driving operation. Failure to do so the Engineer has the rights to
reject such equipment and the Contractor shall bear all the cost associated with
such action.

3.5.2. The Contractor shall consider the type of the soil with its boulder when choosing
the driving equipment.

3.5.3. The Contractor shall propose the hammer type and the driving equipment so that
the piles can be driven to the specified depth or the desired bearing value indicated
by final set is attained, without any damage to the piles due to overstress caused
by driving.

4.0 MATERIALS

4.1. General

4.1.1. The precast prestressed concrete piles shall be manufactured and constructed in
accordance with the details shown in the Drawings and to any other requirements,
as far as applicable, stipulated in the reference standards.

4.1.2. The length of precast prestressed concrete pile for the permanent work to be
fabricated and driven shall be determined by the load test results which shall be
carried out in advance to the permanent piling work in accordance with the
specification stated hereinafter and/or all the soil investigation results.

4.2. Precast Prestressed Concrete Piles

4.2.1. Type of Piles

- The type of piles shall be the spun piles as shown in the Drawings, hereinafter
referred to as the PC Piles, from Wika Beton, Hume Concrete Indonesia or
acceptable equivalent.
- The size and length of piles shall be as shown in the Drawings.
- Unless otherwise shown in the Drawings, Portland cement to be used shall be
type I complying with SNI 2049:2015.
2
- The pile concrete shall have a minimum compressive strength of 600kg/cm .
- The standard spiral reinforcement shall comply with the requirements of JIS A
3532 - SWMA with a nominal diameter according to the manufacturer’s
standard or as shown in the Drawings.
- The standard prestressing steel shall conform to the requirements of ASTM
A416-87a or SNI 1154:2011 or JIS G 3536.
- The cross sectional dimensions of the pile shall be within the tolerance of ±
5mm.
- Pile bending moment capacity shall be as shown in the Drawings.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02459


REVISION :A DATE : April 2018 PAGE : 2 of 6
BITA

4.2.2. Pile Tip

The tip of precast prestressed concrete pile shall be shaped and reinforced in
accordance with the Drawings.
The steel pile shoe shall be made in a standardized form as shown in the
Drawings.

4.2.3. Concrete Cover

The standard concrete cover shall be as follows:

- Normal exposure minimum 50mm.


- Marine exposure minimum 75mm.

4.3. Splices

The pile splices or joints are necessarily required in the case of segmental PC Piles.
The splices shall be made of steel plates with a minimum tensile strength of 37kgf/mm²
conforming to requirements of SNI 07-0722-1989, and shall be formed and shaped as
shown in the Drawings.
The piles splices are designed to resist any kind of forces that may be applied to the piles
section as to ensure the integrity of the pile.
Welding materials to be used shall conform to the requirements of AWS E 6013 or equal.

5.0 CONSTRUCTION REQUIREMENTS

5.1. Pile Testing

5.1.1. General

- The Contractor shall conduct a program of Dynamic Load Test according to


ASTM D4945 to demonstrate the suitability of the proposed pile driving system
and to ascertain the capacity of the installed piles.
- All operations shall be constantly supervised by a qualified Engineer of the
Contractor and personnel employed must have the required ability and
training. Complete testing data shall be recorded.
- Test piles shall be driven in advance of other piles for the project and load
tested in order to determine the load-carrying capacity of the pile. The
Engineer will advise to the Contractor of the maximum acceptable "set" of the
pile at final driving.
- Test piles shall not be driven nor tested without the presence of the Engineer.
- If the working load test pile is satisfactory it may be incorporated into the
structure. If the test pile is found unsatisfactory or mislocated, the pile shall be
removed or abandoned.

5.1.2. Preparation

The Contractor shall provide all the equipment, materials, labours and temporary
works to execute the pile load test.
The work method shall be submitted by the Contractor for the approval of the
Engineer, which includes anchoring and reaction systems, testing equipment
details, testing procedure, pile head treatment and others related.
The pile to be tested shall be driven down in the same manner as the Contractor
intends to execute the piling work subsequently.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02459


REVISION :A DATE : April 2018 PAGE : 3 of 6
BITA

5.1.3. Position

The positions of piles to be tested shall be designated by the Engineer, when the
time comes.

5.2. Driving

5.2.1. Preparation Works

The Contractor shall carry out all the necessary preparation works such as
setting out, marking on piles, temporary staging and other works related, prior
to the commencement of pile driving works.

5.2.2. Location of Piles

Piles shall be driven in the position as indicated in the Drawings. The


Contractor shall be responsible for the true and proper setting out of piles, and
for the correctness of the position, levels, dimensions and alignment of all
parts of the works. The setting out shall be carried out by a qualified surveyor
engaged by the Contractor before commencement and on completion of the
piling work.

5.2.3. Equipment

– All the equipment such as driving rigs, hammers, leaders cushions,


helmets and others and workmanship shall be of first class and be suitable
to the driving work at the site.
– The Contractor shall provide all others, if necessary to execute the work
such as temporary staging, guide, follower and others related.

5.2.4. Driving Procedure and Redrive Checks

- Except for retaining wall, the holes shall be drilled to the specified
elevations or to the depth of the compacted layers as shown in the
Drawings.
- The heads of all piles shall be protected by caps of approved design
having a suitable cushion next to the pile head and fitted into a casting
which in turn supports a timber shock block.
- Each pile shall be driven continuously until the top of the pile shall be at a
depth so that the pile and pile cap connection can be constructed as
shown in the Drawings. The depth of the pile head driven shall be
approved by the Engineer.
- The Contractor may use pile follower to drive the pile to the specified
depth. The Contractor shall propose pile follower and driving equipment so
that the piles can be driven to the specified depth or the desired bearing
value indicated by final driving is attained. The use of the pile follower in
combination with the driving equipment shall not damage the piles and
pile splices.
- The Contractor shall inform the Engineer without delay if an unexpected
change in driving characteristics is noted. A detailed record of the driving
resistance over the full length of the next nearest available pile shall be
taken if required.
- At the start of work and in a new area or section sets shall be taken at
intervals during the last 300cm of the driving to establish the behaviour of
the piles.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02459


REVISION :A DATE : April 2018 PAGE : 4 of 6
BITA

- The Contractor shall give adequate notice and provide all facilities to
enable the Engineer to check driving resistances. A set shall be taken only
in the presence of the Engineer unless otherwise approved.
- Redrive checks, if required, shall be carried out to an approved procedure.

5.2.5. Termination of Pile Driving

The pile driving shall be terminated if any of the following criteria is fulfilled:

- The driven pile is reaching the sufficient depth of 18m from final ground
elevation.
- The final set is reaching 1inch/10 blows.
- The blow count is reaching 2000 blows.

5.2.6. Extension

- Whenever possible, pile splicing shall not be used. In case piles without
splicing are unavoidable, the location of the pile splicing shall be at least
10m below the ground level.
- If the pile has not reached the required penetration rate per blow and if the
top of the pile is approximately 300mm above the ground level, it shall be
stopped for splicing and driven to a depth sufficient to develop the
required penetration rate per blow as directed and approved by the
Engineer.
Splicing work refer to section 5.2.7.

5.2.7. Splicing

- Where required length is greater than the length of pile, the extension of
such pile shall be extended by welding a pile of the same section.
- Piles shall be spliced in accordance with the manufacturer's instruction.
The equipment, materials and method for splicing the pile and the timing
of splicing the pile in connection with the overall pile driving operation
from setting out to cut-off shall be subject to the Engineer's approval.
- The joint part shall be equipped with guide ring and edges of piles shall be
in the shape as shown in the Drawings. The edges to be welded shall be
carefully matched and the root opening shall be kept precisely even with
the use of spacers and stoppers.
- Welding works shall be continuous along the entire area of joint plate
using low-hydrogen welding electrodes, and in accordance with the
requirement of AWS.
- All welding shall be carried out by welders holding certificates or
corresponding grades issued by the approved organizations.
- In order to avoid breaking the weld on the joint during driving, the driving
can only be continued after the welding has cooled sufficiently.

5.2.8. Uplifted Piles

The driven piles shall be observed. If the driven piles are indicating
experiencing heaving, there shall be more pre-boring to be carried out up to
900cm from the ground surface.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02459


REVISION :A DATE : April 2018 PAGE : 5 of 6
BITA

5.2.9. Damaged Piles

Any pile damaged by reason of improper driving or driven out of its proper
location or driven below the elevation fixed by the Drawings or by the
Engineer shall be corrected at the Contractor's expense by one of the
following methods approved by the Engineer for the pile in question:

- The pile shall be withdrawn and replaced by a new and if necessary longer
pile. Any hole from which piles are withdrawn shall be packed with
approved non-plastic material before redriving takes place.
- A second pile shall be driven adjacent to the defective or low pile.

5.3. Record

The Contractor shall submit a complete pile driving report of each pile to the Engineer
daily, which shall include, but not be limited to, the pile number, location, position, the
date of fabrication and driving, hammer details, elevations, and blow counts, rebound.

5.4. Tolerance

5.4.1. The piles shall be installed in their exact positions and to the plumb within a
tolerance of 100mm in any direction from the true position and 1 : 100 from
the true vertical axis of the pile.

5.4.2. Should the piles be out of the tolerances, these piles shall be extracted for
replacement by the new piles or the superstructure of the pile caps and beams
shall be enlarged to accommodate the pile deviated, which however shall be
entirely to the Engineer's direction and that no additional costs shall be due to
the Contractor.

5.5. Pile-Head Treatment

5.5.1. The pile heads shall, after driven down completely to the requirement, be cut-
off, trimmed and treated properly in accordance with the Drawings.

5.5.2. Cut-off lengths of piles shall become the property of the Contractor, and shall
be disposed off to the satisfaction of the Engineer.

5.5.3. After the piles are completely driven to the specified depth and prior to
construction of pile cap, any gap between the piles and the soil shall be filled
with sand material approved by the Engineer.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02459


REVISION :A DATE : April 2018 PAGE : 6 of 6
BITA

SPECIFICATION

02645

CORRUGATED METAL PIPES

1.0. DESCRIPTION OF WORK

This item of work shall consist of furnishing and installing corrugated metal pipes of the size
and length required at the locations shown in the Drawings and in accordance with the
requirements in the Drawings and this Specification.

2.0. REFERENCE STANDARDS

2.1. Standar Nasional Indonesia (SNI):

– SNI 6719:2015 - Pipa-baja-bergelombang.

2.2. American Society for Testing and Materials (ASTM).

2.3. American Association of State Highway and Transportation Official (AASHTO).

2.4. Japanese Industrial Standard (JIS).

2.5. Australian Standard (AS).

2.6. Specifications:

– 02315 - Excavation, Backfilling and Compaction.


– 02330 - Embankment.
– 02335 - Subgrade Preparation.
– 02721 - Subbase.

3.0. GENERAL PROCEDURES

3.1. Product Data

3.1.1. Contractor shall submit product data complete with mill certificate of corrugated
metal pipe to the Engineer for review and approval.

3.1.2. Prior to delivery, list of all materials to be used shall be prepared by the
Contractor, and submit it to the Engineer for approval.
Approval given will not relieve the Contractor of responsibility for correctness of the
order list.
If the submittals differ from the requirements, the Contractor will not be
relieved of the responsibility for executing the work in accordance with the
Contract Drawings at his expense.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02645


REVISION :A DATE : April 2018 PAGE : 1 of 5
BITA

3.2. Shop Drawings

The Contractor shall prepare and submit detailed Shop Drawings to the Engineer for
review and approval.
Shop Drawings shall show details, dimensions, placing diagram, method of installation
and notes on material and finish.

3.3. Inspection

Contractor shall provide information and access for inspection. Rejected material shall
be removed promptly and replaced with material acceptable to the Engineer.

3.4. Match Marking

Adequate match-marking shall be provided by the Contractor where required to


maintain uniformly of installation.

3.5. Delivery and Handling

3.5.1. All materials shall be delivered complete in one shipment. This shall include
necessary bolts, fasteners and couplings.

3.5.2. Contractor shall be responsible for the repair or replacement of any items
damage in shipment.

3.5.3. Storage of materials shall be in accordance with the manufacturer’s


instructions and recommendations.

4.0. MATERIALS

4.1. General

All corrugated metal pipes and accessories shall be new, free from any defects and
shall come from a proven manufacturer.

4.2. Corrugated Metal Pipes

4.2.1. Corrugated metal pipes shall be manufactured from steel material of grade SS
2
400 according to JIS G 3101, having hot dipped galvanized coat of 610gr/mm
complying with ASTM A123 or AS 1650 or AASHTO M 167, and complying
with the requirements of SNI 6719:2015, such as manufactured by Bakrie
Metal Industries, Kencana Cakra Buana or acceptable equivalent.

4.2.2. Thickness steel material shall be according to the internal diameter of


corrugated metal pipes to be used and the depth of embankment or maximum
cover and as recommended by the corrugated metal pipe manufacturer.

4.2.3. Type to be used shall be Multi Plate Pipe in diameter according to the
Drawings.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02645


REVISION :A DATE : April 2018 PAGE : 2 of 5
BITA

4.3. Connections and Fasteners

Connections and or fasteners of bolts shall comply with the requirements of AS 1252
and nuts of AS 1112 grade 4.6.
Bolts and nuts shall come from the manufacturer of the corrugated metal pipe to be
used.

5.0. CONSTRUCTION REQUIREMENTS

5.1. Preparation

5.1.1. Excavation

– Dimension and shape of trenches for laying corrugated metal pipes shall
have width sufficient to allow for proper jointing of corrugated metal pipe
and thorough compaction of the bedding and backfill material under and
around the pipes. Excavation shall be form with sides as nearly vertical as
practical.
– Where corrugated metal pipes are to be installed in new embankment, the
embankment shall first be constructed to the height shown in the Drawings
after which the trench shall be excavated.
– Excavation shall be carried out in accordance with the Specification
02315.

5.1.2. Bedding

– Before any pipe is placed, the subgrade shall be so prepared as to provide


a firm and uniform bearing through its entire length, thoroughly
compacted, free from stones and true to line and grade.
Subgrade shall be prepared according to the requirements of Specification
02235.
– Bedding material for corrugated metal pipe shall comply with the
requirements of Specification 02721 and as shown in the Drawings.
 Placement of bedding material shall be made suitable with the site
condition and as directed by the Engineer, and as recommended by the
manufacturer of corrugated metal pipes.

5.2. Installation

5.2.1. No corrugated metal pipe shall be placed until the bedding and trench have
been approved by the Engineer. Corrugated metal pipe shall not be placed in
cuts until the rough grading has been completed.

5.2.2. Where two or more pipes are to be laid adjacent to each other, they shall be
separated by a distance equal to at least ½ diameter of the pipe, with a
minimum distance of ± 500mm.

5.2.3. Corrugated metal pipe shall be laid that flow is over the lap of the sheets. Field
joints shall be made by butting the ends of pipe together and joining the
sections with a band bolted firmly in place.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02645


REVISION :A DATE : April 2018 PAGE : 3 of 5
BITA

Pipes of diameter of 1200mm or more shall, when specified by the Drawings,


be strutted and/or elongated vertically 5% before placement of fill. Elongation
of the vertical diameter may be accomplished by jacking in the field or
prefabrication. If field jacking is used, the method shall be subject to the
approved of the Engineer. A tolerance of 25% above or below the specified
elongation will be allowed. Where performed elliptical pipe is used and
strutting is specified, further distortion shall not be required, but the struts shall
be wedged tightly in place.

5.2.4. Strutting shall be carried uniformly from end to end of pipes where head walls
are not used. When head walls are used, the amount of jacking and the length
of struts may be reduced gradually under the side slopes of the embankment
so that ends of pipe at the head walls are circular.

5.2.5. Struts shall be left in place until the embankment is complete and compacted,
unless otherwise directed by the Engineer.

5.2.6. All pipes shall be laid true to the designated line, grade and camber. They
shall be shop fitted and match marked so that, when laid, they will form a
smooth and uniform invert.

5.2.7. All possible care shall be used in fitting sections of pipes together so that the
joint openings will not unnecessarily large.

5.2.8. The pipes shall be so lowered as to avoid unnecessary handling in the trench.
Care shall be taken to not permanently deform the pipe while it is being
handled. Dropping pipe will not be permitted.

5.3. Field Coating Repair and Protective Coating

5.3.1. After assembling and laying pipe or pipe arch, damaged galvanized coating
and bolts shall be thoroughly wire brushed and coated with the specified cold
galvanizing compound.

5.3.2. Unless otherwise shown, all outside surface of corrugated metal pipes and fittings
which shall be buried underground shall be coated with a minimum of 40microns
asphalt as a rust protective coating.

5.4. Backfilling and Embankment

5.4.1. Excavations in which corrugated metal pipe has been installed shall be
backfilled with suitable material placed in successive layers.
Backfill material and backfilling work shall comply with the requirements of
Specification 02315.

5.4.2. Embankment shall be carried out in accordance with the requirement of


Specification 02330.

5.5. Placing Apron Endwalls

The bed for the apron endwall shall be excavated to the required width and grade. For
metal aprons with toe plates, a trench shall be excavated for the toe plate in a manner
to permit the toe plate being against the inner face of the trench when the apron is in
its final position. After the apron has been properly secured to the pipe, this trench
shall be backfilled and firmly compacted in accordance with Specification 02315.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02645


REVISION :A DATE : April 2018 PAGE : 4 of 5
BITA

5.6. Inspection

Corrugated metal pipe shall be bedded, placed or backfilled, only with the Engineer’s
approval.

5.7. Protection After Laying

The Contractor shall be responsible for the protection of all corrugated metal pipes
until final acceptance of the work. Any pipe which is damaged, either through
Contractor’s operations or due to failure to properly protect the same, shall be replaced
in kind at the Contractor’s expense.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02645


REVISION :A DATE : April 2018 PAGE : 5 of 5
BITA

SPECIFICATION

02721

SUBBASE

1.0 DESCRIPTION OF WORK

The work shall consist of furnishing, hauling, placing and compacting subbase materials on the
prepared subgrade in accordance with lines, grades, dimensions and cross sections as shown and
as directed by the Engineer.

2.0 REFERENCE STANDARDS

2.1. American Society for Testing and Materials (ASTM)

2.2. Any applicable local codes and standards, the highest or most stringent to apply

2.3. Specification 02315 - Excavation, Backfilling and Compaction

3.0 GENERAL PROCEDURES

3.1. General

Subbase construction shall not be worked out unless the subgrade has been properly
prepared in strict compliance with the lines, grades and profiles as shown and as directed
by the Engineer.

3.2. Testing

The density of compacted material shall be determined by ASTM D1557. The test shall be
made to the full depth of the layer at locations determined by the Engineer, which shall be
not more than 200m apart.
Test holes shall be backfilled and compacted by the Contractor without any delay.

4.0 MATERIALS

Material for subbase shall be a natural or artificial mixture of hard durable particles of mineral
aggregates selected from an approved borrow pit source. It shall be free from clay lumps, vegetable
matter, and organic soil and shall not easily break under prevailing climate and cycles of moisture
change.
Any material which is surplus to backfilling of work under Specification 02315 may be used in the
preparation of subbase, provided it meets the above requirements and is approved by the Engineer.
If the thickness of required subbase exceeds 200mm, it shall be divided into a layer of upper
subbase of 150mm thick and a layer of lower subbase to a minimum of 50mm thick.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02721


REVISION :A DATE : April 2018 PAGE : 1 of 2
BITA

The grading of material for upper subbase shall comply with the following requirements:

Sieve Designations Percentage by


Weight passing
Standard (mm) Alternative (inch)

50 2 in 100
25 1 in 60 – 100
9.5 3/8 in 30 – 100
4.75 No. 4 15 – 100
2.00 No. 10 10 – 70
0.425 No. 40 5 – 40
0.075 No. 200 2 – 25

5.0 CONSTRUCTION REQUIREMENTS

5.1. Subbase Preparation

Subgrade and all drainage works shall be completed in accordance with this
Specification for at least 50meters ahead of the placing of the subbase material.
Subbase may be spread and shaped by any acceptable methods which shall not cause
the segregation of the fine and coarse aggregate. The material shall be brought to
correct moisture content in achieving the specified degree of compaction by sprinkling
a controlled amount of water and thoroughly mixing with a road grader until the
moisture content is uniform.

5.2. Rolling and Compaction

Immediately after proper mixing and shaping, each layer of 200mm maximum shall be
evenly compacted with suitable compacting equipment approved by the Engineer.
Rolling operation shall start along the sides or edges and progress toward the area
center line.
The rolling shall continue until roller marks are slightly visible and uniformly
compacted to a hard dense surface. Speed of compacting equipment shall be constant
rate of 5km/hr. Dry density shall be 90-95% as determined by ASTM D1557 with
minimum CBR as indicated in the Drawings.

5.3. Subbase Tolerance

The completed surface shall vary not more than 15mm above or below the design
grade at any point, and the minimum thickness of subbase shall not be less than
15mm below the required thickness at any point.
Subbase which does not conform to these tolerances shall be corrected by loosening,
reshaping and re-compacting to the satisfaction of the Engineer.

5.4. Compaction Standard

All of the subbase shall be compacted to not less than 93% of the maximum dry
density as determined by the methods set out in Specification 02315.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02721


REVISION :A DATE : April 2018 PAGE : 2 of 2
BITA

SPECIFICATION

02722

BASE COURSE

1.0. DESCRIPTION OF WORK

This work shall consist of furnishing, hauling, spreading, watering, rolling and compaction of graded
aggregate material on a completed and accepted subgrade in accordance with the established lines,
grades and cross sections as shown in the Drawings.
It shall include but not be limited to supplying of labour, equipment, plants or rock crushers equipped
with the required screens and other accessories necessary to satisfactorily complete this work.

2.0. REFERENCE STANDARDS

2.1. Standar Nasional Indonesia (SNI).

2.2. American Association of State Highway and Transportation Officials (AASHTO).

2.3. Any applicable local codes and standards, the highest or most stringent values to apply.

3.0. GENERAL PROCEDURES

Refer to section 5.0 Construction Requirements of this Specification.

4.0. MATERIALS

4.1. Aggregate base material shall be selected from an approved source. The coarse aggregate
retained on the 4.75mm sieve shall consist of hard durable particles or fragments of rock
and gravel. Gravel which splits when alternately wetted and dried shall be avoided. The
gravel shall be of approximately uniform gradation and must be screened and washed.
Fine aggregate passing 4.75mm (no. 4) sieve shall consist of natural or crushed aggregate
and fine mineral particles.

4.2. All aggregate shall be free from vegetable matter, lumps of clay and other deleterious
substances and the gradation of the aggregates need to be proposed to achieve level
of CBR of ≥ 80% or as indicated in the Drawings.

5.0. CONSTRUCTION REQUIREMENTS

5.1. Preparation of Base Formation

5.1.1. Where aggregate is required to be laid on a prepared formation in either as


base course or other construction, such formation shall be completed and
accepted for at least 100meters or so many square meters ahead of the
placing of the base material. However, any earlier approval of prepared
formation and any damaged to or deterioration in the formation shall be made
good at the Contractor's expense before aggregate base is placed.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02722


REVISION :A DATE : April 2018 PAGE : 1 of 3
BITA

5.1.2. Where aggregate base is required to be laid directly on the existing pavement,
the surface of the pavement shall first be slightly scarified or roughened
sufficiently to be made permeable and re-compacted.

5.1.3. Re-compaction shall be performed after the addition of aggregate base,


provided that the total depth of scarified and added material does not exceed
the permissible depth of loose layers.

5.1.4. Any lumps larger than 50mm resulting from scarifying shall be picked out or
broken before the addition of aggregate base. Mixing of the existing scarified
pavement with the new aggregate base should be avoided.

5.1.5. No separate payment shall be made for scarifying or roughening and


compaction, as this work shall be considered incidentals for the aggregate
base preparation.

5.2. Spreading

Aggregate base shall be evenly spread over the full width of the road bed in layers
with un-compacted thickness not exceeding 250mm and be subject to the Engineer's
approval. The layers, if more than one (1), shall be as nearly equal in thickness as
possible. The material maybe spread and shaped by any approved method that shall
not cause segregation of the fine and coarse aggregates. Any portion of segregated
coarse or fine material shall be corrected or removed and replaced with graded
material. Material shall contain the correct moisture content to achieve the specified
degree of compaction by sprinkling with the right quantity of water. Mixing shall be by
motor grader until moisture content of material is almost uniform throughout.

5.3. Rolling and Compaction

5.3.1. Immediately after the final mixing and shaping is completed, each layer of
200mm minimum thickness shall be compacted with suitable and approved
equipment. Rolling shall start along the sides and then progress towards the
road centerline in a controlled speed of 5km/hr.

5.3.2. The rolling direction shall overlap each other in a longitudinal manner. On
super-elevated sections, rolling shall start at the low grade and progress
towards the high side. Rolling operation shall continue until the surface is
uniformly compacted, hard, and dense and roller marks are no longer visible.

5.3.3. If aggregate base is too wet or too dry to be compacted to the required
density, it shall be dried out or sprinkled with water, prior to or during
compaction.

5.3.4. No additional payments shall be made for adding water or drying of the
material.

5.3.5. Any surface irregularities that may develop after the construction shall be
corrected by removing the irregular portion and replaced with good material as
required. Each layer of aggregate base shall be compacted to at least 95% of
the maximum modified dry density as determined by SNI 03-1743-1989 or
Method D of AASHTO Test T180.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02722


REVISION :A DATE : April 2018 PAGE : 2 of 3
BITA

5.4. Surface and Thickness Tolerances

The completed surface or finished profile shall vary not more than 10mm above or
below the design elevation at any point.
Any deviation in excess of 10mm tolerance shall be corrected by loosening, adding or
removal of material, reshaping and re-compaction. Such expenses shall be the
Contractor's responsibility.
Where aggregate base is laid in place with variable thickness on the existing
pavement, such thickness shall be within the allowable limits shown in the Drawings.
Likewise, proper corrections and/or adjustments shall be done to the profile grade
upon written approval of the Engineer, in order to meet the allowable tolerance as
stated in this specification.

5.5. Inspection and Testing

The density of compacted material shall be determined by SNI 03-1743-1989 or ASTM


D 1557 or AASHTO T 180. The test shall be executed to the full depth of the layers at
location or points determined by the Engineer, which shall not be more than 200meters
apart. Test holes shall be backfilled with the same material and compacted by the
Contractor without delay.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02722


REVISION :A DATE : April 2018 PAGE : 3 of 3
BITA

SPECIFICATION

02740

ASPHALTIC CONCRETE PAVEMENT

1.0 DESCRIPTION OF WORK

The work shall include but not be limited to the following:

- The preparation of skilled labour, technicians, engineers, as well as an unskilled labour.


- The supply of materials and appropriate equipment, machinery, Asphalt Mixing Plant and any
other necessary equipment/machinery for these works.
- Stripping of grading layer, levelling, overlay, and laying and compaction of the gravel and/or
crushed stone layer, as stipulated by the Drawings and this Specification.
- Laying of asphaltic concrete as overlay, with appropriate equipment, in correct thickness and
location as stipulated in the Drawings.

2.0 REFERENCE STANDARDS

2.1. American Association of State Highway and Transportation Officials (AASHTO).

2.2. American Society for Testing and Materials (ASTM).

2.3. Standar Nasional Indonesia (SNI):

- SNI 03-1737-1991 - Tata Cara Pelaksanaan Lapis Aspal Beton (LASTON) untuk
Jalan Raya.

2.4. Specifications:

- 02315 - Excavation, Backfilling and Compaction.


- 02335 - Subgrade Preparation.
- 02721 - Subbase.
- 02722 - Base Course.

3.0 GENERAL PROCEDURES

3.1. Samples

The sample materials proposed for use on the entire work must be given to the Engineer as
soon as practicable, for testing and acceptance.

3.2. Stage of Work

3.2.1. The Contractor shall inform the Engineer, no later than 3 days before the work is
scheduled to begin, of the initial stages of the work scheduled for commencement.
If the Contractor implements the work without prior approval from the Engineer,
then all damages and faults that occur as a result of this shall be the responsibility
of the Contractor.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02740


REVISION :A DATE : April 2018 PAGE : 1 of 5
BITA

3.2.2. When each stage of the work is completed, the Contractor shall contact the
Engineer for an analysis before the subsequent stages of the work shall begin.

3.2.3. The Contractor shall submit the equipment list to be used, complete with totals and
its capacities, to determine its suitability and to obtain approval form the Engineer.

4.0 MATERIALS

4.1. Backfilling for Subgrade Preparation

Backfilling material for preparing subgrade shall comply with the requirements of
Specification 02315.

4.2. Materials for Subbase Layer

Material for sub-base layer shall comply with the requirements stated in the Specification
02721.

4.3. Base Course Materials

Base-course material shall be selected from the approved sources. Aggregate material
shall be free from dirt and other impurities and the grading shall comply with the
requirements of Specification 02722.

4.4. Materials for Asphaltic Concrete Work

4.4.1. General

All materials for asphaltic concrete work such as:

- Coarse aggregate,
- Fine aggregate,
- Filler,
- Solid asphalt,
- Emulsified liquid asphalt,

shall comply with the requirements of SNI 03-1737-1991.

4.4.2. Asphalt Concrete

Asphalt Concrete (AC) of MS 744 in minimum thickness of 70mm shall be used as


wearing course (top layer).

4.5. Equipment

4.5.1. Field Equipment

- Compaction equipment:
· Vibrator Roller
· Tandem Roller 4-6ton
· Tandem Roller 8-10ton
· Pneumatic Tyre Roller 10-12ton
- Grader.
- Dump Truck.
- Asphalt Sprayer and Asphalt Finisher.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02740


REVISION :A DATE : April 2018 PAGE : 2 of 5
BITA

- Compressor.
- Water Tank.
- Shovels, rakes, brooms, wooden beams, wheel barrows and other support
equipment.
- Hand Compactor.

4.5.2. Asphalt Mixing Equipment

- Asphalt Mixing Plant.


- Shovel Loader.
- Shovels, chisels and other support equipment.

5.0 CONSTRUCTION REQUIREMENTS

5.1. Subgrade Preparation

The subgrade preparation shall be implemented as stipulated by Specification 02335.

5.2. Subbase Preparation

The subbase preparation shall be carried out in accordance with the requirements of
Specification 02721.

5.3. Base Course Preparation

The base course preparation shall be carried out in accordance with the requirements of
Specification 02722.

5.4. Asphaltic Concrete Work

5.4.1. Mixture Plan

The mixing plant shall be supervised to obtain correct asphaltic concrete mixes.
The data that shall be obtained are as follows:

- Type of aggregate,
- Aggregate gradation,
- Quality of aggregate,
- Type of solid asphalt,
- Planned layer thickness,
- Type of filler.

The percentage of asphalt (by weight) to be added to the dry aggregate shall be
determined from the results of laboratory mix design.
The optimal quality of the asphalt shall be determined using the Marshall test, and
these results shall comply with the requirements of SNI 03-1737-1991.

5.4.2. Sampling at Asphalt Mixing Location

Sampling of the asphalt mix shall be carried out at least once every production
day, unless otherwise instructed by the Engineer.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02740


REVISION :A DATE : April 2018 PAGE : 3 of 5
BITA

5.4.3. Mix Production

The mix’s proportion of materials shall be done correctly according to the approved
design.
Mixing shall be done as thorough as possible in order to obtain homogeneous mix.
The aggregate shall be heated to 175C. The asphalt's temperature shall be lower
than that of the aggregate, with the maximal difference of 15C.
The mixing temperature is reached by various asphalt types being used, the
requirement are as follows:

- for penetration 60 130C - 165C,


- for penetration 80 124C - 162C.

5.4.4. Field Preparations

Before laying of the mix, the surface upon which asphaltic concrete shall be laid
shall comply with the following requirements:

- The surface shape, both longitudinal and transversal, shall be prepared as


stipulated by the Drawings.
- The surface shall be free from undesirable materials, such as dust and other
detachable objects.
- A surface without using tack coat shall be moisted sufficiently (not too dry).
- A surface using tack coat shall be dry.
- The surface shall have less than 0.5l/m² of tack coat applied to it.
- To surfaces which do not use tack coat, prime coat shall be applied, as much
as 0.6 -1.5l/m².

5.4.5. Transportation

- Transportation shall be with a dump truck with a large, metal trailer, and this
shall be clean and sprayed with detergent, petrol or soluble lime before being
used, so as to prevent the asphalt from sticking to the truck.
- During transportation, the asphalt mix shall be covered with a tarpaulin to
protect the mix from the effects of the weather.

5.4.6. Spreading

- Spreading is done for leveling and overlay, or as indicated in the Drawings.


- Spreading shall begin at the farthest point from the Asphalt Mixing Plant
(AMP) and end up at the point closest to the AMP.
- The thickness of each layer shall be according to the Drawings.
- Asphalt mix shall be spread at a temperature of at least 115C.
- Spreading will be done by using an approved spreader machine, except
otherwise specified.

5.4.7. Compaction

- Compaction is the final stage of the work in the process of road construction
which must be supervised continuously, and it has the following sequence of
work:

· Initial compaction shall be done at a minimum temperature of 110C,


using a Tandem Roller 4 - 6ton, and from two to four tracks, with a speed
of 3-4km/hour.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02740


REVISION :A DATE : April 2018 PAGE : 4 of 5
BITA

· Immediately after the first compaction is finished, a 10 -12ton Pneumatic


Roller shall be used for compaction in between, with air pressure 70-80psi
and speed 5-10km/hour.
· Compaction is finished with an 8 - 10ton Tandem Roller immediately after
the compaction in between is ended, and this final stage shall be deemed
completely when the traces of the compactor's wheel are no longer visible,
with the Tandem Roller speed of 5 - 8km/hr.
The temperature of the asphalt shall be 60C or at least a little bit higher
than asphalt's melt point, at the completion of this stage.

- The method of compaction shall be as follows:

· For a straight road, the compaction shall begin from the outside edge of
the road and shall always move parallel directly with the road centerline
towards the center of the pavement.
· For a super-elevated curves, the compaction shall begin from the low side
of the road and progress directly towards the higher side of the road.
· For an ascending and descending road, the compaction shall begin at the
lowest point and move towards the highest part of the road, parallel to the
road's axis.
· To prevent the asphalt mix from sticking to the Tandem Roller, it is
necessary to moist the wheel of the Tandem Roller with water previously.
· The activator wheel of the Tandem Roller shall initially face the track,
which is to be rolled.

5.4.8. Continuation

The spreading and compaction shall be done according the method described
above, and shall not have too many continuations in the road.
If continuation shall be made, the Contractor shall ensure that the setting of the
road is done perfectly and that the thickness is the same.
Where the asphalt mix layer which has already been rolled is to be connected with
the new asphalt mix, the edge of the previous asphalt mix shall be made vertical
by cutting, and this aforementioned vertical edge shall be given a tack coat to
obtain greater strength at the connection face.

5.4.9. Supervision of Laying

The supervision of laying shall be done according to the following sequences:

- Analysis of the quantity and level's uniformity of the tack coat.


- Analysis of level's uniformity, the gradient, the continuations, the spread's
thickness and its temperature before compaction.
- Analysis of temperature at every compaction, method of compaction and
results of the compaction.
The asphalt concrete road may be open for slow speed traffic after the last
compaction is finished and the asphalt's temperature is low enough (according
to the type of asphalt), or after approximately 2 (two) hours. The road can be
open for full traffic after 4 (four) hours.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02740


REVISION :A DATE : April 2018 PAGE : 5 of 5
BITA

SPECIFICATION

02765

TRAFFIC MARKINGS

1.0 DESCRIPTION OF WORK

This work shall consist of the provision and application of all traffic markings on roadways for
the purpose of guiding traffic of vehicles as indicated in the Drawings.
This work shall include but will not be restricted to supply of labour, materials, tools and
equipment to be used for preparation of surfaces, application of paint, making good any defect
and cleaning of any splashes to other work. All coating shall be as required in this Specification
or determined by the Engineer.

2.0 REFERENCE STANDARDS

2.1. American Association of State Highway and Transportation Officials (AASHTO):

– AASHTO M 249 - Standard Specification for White and Yellow Reflective


Thermoplastic Striping Material

2.2. Standard of the Manufacturer.

2.3. Peraturan Menteri Perhubungan No. PM 34/2014 tentang Marka Jalan.

3.0 GENERAL PROCEDURES

3.1. Product Detail

3.1.1. Details of proposed products/materials and manufacturers shall be submitted


before construction. Failure to do so may lead to rejection of materials on site
and failure to meet program requirements.
All materials shall be of such quality as to produce first class and durable
finishes and to be at least equal requirements of the relevant standards.

3.1.2. Contractor shall also submit a certification by traffic marking manufacturer that
is complied with local regulation.

3.2. Sample Panels and Test Areas

3.2.1. Before coating with a particular system commences, the Contractor shall paint
test areas or sample panels to demonstrate that the specified thickness and
finish to the paint film is being obtained all shall be approved by the Engineer.

3.2.2. The paints, equipment and method of application used for test areas or
sample panels shall be representative of those to be used for the work.
Test areas or sample panels shall be retained and shall form the standard for
all subsequent work.

3.2.3. Contractor shall be responsible in providing samples and sample panels.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02765


REVISION :A DATE : April 2018 PAGE : 1 of 4
BITA

3.3. Delivery and Storage

All coating shall be fresh stock and be of new and first quality, delivered at job site in
unopened original manufacturer's containers, and stored in the dry, watertight,
lockable enclosure.
All coating materials shall be in sealed containers and labeled so as to plainly show
the designated name, formula or specification number, batch number, colour, date of
manufacture and manufacturer's directions

3.4. Inspection and Testing

The Engineer shall have free access to all work locations, and warehousing facilities
and the right to inspect the preparation of all surfaces and the application of all
paintings.

3.5. Non Conformity

3.5.1. Before any deviation from this Specification, the Engineer shall be consulted.
Failure to do so will in no way relieve the Contractor of his responsibility for
satisfactory compliance with standards and procedures set forth in this
Specification.

3.5.2. The Engineer shall have the right to reject any work which is not carried out in
accordance with this or any other applicable Specifications. All expense
incurred by the correction of rejected work shall be borne by the Contractor.
Causes for rejection of work or portions shall include but not be limited to the
following:

- Surface preparation considered unsatisfactory by the Engineer for any


reason.
- Failure of Contractor to apply the minimum number of coats of the
appropriate thickness.
- Failure of Contractor to allow minimum specified drying time between
coats.

3.6. Warranty

Submit written warranty signed by traffic coating manufacturer and installer agreeing
to repair or replace traffic coatings that do not meet requirements or that deteriorate as
defined in this Specification within the warranty period of 5 years after date of
substantial completion. Warranty does not include deterioration or failure of traffic
coating due to unusual weather phenomena, failure of prepared and treated substrate,
formation of new cracks in excess of 1.5mm wide, fire, vandalism, or abuse by truck
traffic, or maintenance equipment.

4.0 MATERIALS

4.1. General

4.1.1. All coating materials shall conform to the Specifications shown herein and to
the requirements hereinafter specified.

4.1.2. All coats to be used in this work shall be provided by the same designated
manufacturer, and shall not be mixed with paint from other sources or of
dissimilar compositions.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02765


REVISION :A DATE : April 2018 PAGE : 2 of 4
BITA

4.2. Paint

Traffic markings paint shall be made from waterbased acrylic suitable for marking
interior and exterior curbing and lanes on driveways, sidewalks, factory floors, parking
lots and other areas where zone markings are required.
It shall meet the following requirements:

– Excellent adhesion on concrete, asphalt or brick masonry surfaces that required


quick dry and frequent recoating,
– Fast drying
– High visibility
– Abrasion resistant
– Glass beads can be added for making reflective markings
– Environmentally friendly,

such as Traffikote TFK - 108 WB by Propan Raya or acceptable equivalent.

4.3. Colours

Colour of traffic lines and markings shall be white, unless otherwise as indicated in the
Drawings.

4.4. Type of Markings

Unless otherwise indicated in the Drawings, type of markings includes but is not limited
to:

- Longitudinal lines (broken and unbroken lines).


- Transverse lines (stop lines, holding lines and pedestrian crossing).
- Diagonal lines.
- Sign of symbol.

4.5. Size of Markings

The size, spacing and pattern of longitudinal lines, tranverse lines and other markings
shall be as stated in Peraturan Menteri Perhubungan No. PM 34/2014 or other
applicable local standard, and as shown in the Drawings.

4.6. Equipment

Equipment for application of traffic markings shall be according to the manufacturer’s


standard.

5.0 CONSTRUCTION REQUIREMENTS

5.1. Preliminary, Preparation and Treatment

5.1.1. General

- All paints shall be used in accordance with the manufacturer's application


instructions.
- Surfaces to be painted shall be cleaned and dry prior to application of
paint or surface treatments. Existing painted surfaces designated for re-
painting shall be cleaned in a manner that shall leave the surface so
treated, as possible to new condition.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02765


REVISION :A DATE : April 2018 PAGE : 3 of 4
BITA

- Oil and grease shall be removed with clean cloths and cleaning solvents
that have low toxicity and flash-point in excess of 38C.

5.1.2. Pre-Marking

Measure and position marking line by using rope and make dots with chalk or
white paint that easily cleaned.

5.2. Paint Application

5.2.1. Paint application shall be according to the written installation instruction of the
paint manufacturer, with paint thickness in dry condition as follows:

– Two (2) coats of waterbased acrylic paint (@200microns or 2m²/kg, if


using roll or brush), or
– One (1) coat of waterbased acrylic paint (200microns or 2m²/kg, if using
spray).

5.2.2. Lines of traffic markings shall be uniform straight edges and shall made in
width and length as indicated in the Drawings.

5.3. Atmospheric Conditions

Do not apply traffic markings in rain, fog or mist, or when such weather conditions are
imminent during the application and curing period.

5.4. Protection and Cleaning

Protect the newly traffic markings from damage and wear during 10 to 15minutes after
application before ready for traffic.
Clean traffic markings just before final inspections. Use cleaning materials and
procedures recommended by the manufacturer.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02765


REVISION :A DATE : April 2018 PAGE : 4 of 4
BITA

SPECIFICATION

02845

GUARDRAILS

1.0 DESCRIPTION OF WORK

The work shall cover the transportation, furnishing of man power, equipment and materials,
and installation of guardrails at location as shown in the Drawings or as directed by the
Engineer.

2.0 REFERENCE STANDARDS

2.1. American Association of State Highway and Transportation Officials (AASHTO).

2.2. American Society for Testing and Materials (ASTM).

2.3. Standard of the Manufacturer.

3.0 GENERAL PROCEDURES

3.1. Technical Data

Contractor shall submit technical data of the required material to the Engineer for
review and approval prior to delivery to the site.

3.2. Shop Drawings

Prior to starting the work, Contractor shall prepare and submit Shop Drawings describing
dimensions, lay-outs, connections and other necessary details for installation for Engineer’s
review and approval.

3.3. Delivery

The Engineer will inspect the fabrication at the time the materials were to be delivered
at the site designated by the Engineer. The material shall be considered inspected if
there is an acceptance and approval from the Engineer. The Contractor shall be
responsible for the delivery of guardrails, posts and other parts to the agreed delivery
place.

3.4. Shipping Instruction

Prior to the shipment, all materials shall be galvanized in accordance with the
manufacturer's specification and shall be approved by the Engineer.
All loose items such as bolts, nuts, washers, fasteners and connectors shall be
packaged, labeled and properly sealed. Bigger items such as guardrails and posts
shall be piece marked and its corresponding weight shall be indicated.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02845


REVISION :A DATE : April 2018 PAGE : 1 of 3
BITA

4.0 MATERIALS

4.1. Guardrails

4.1.1. All guardrails and accessories shall be new and made of hot dip galvanized
steel beams which are neither too rigid nor too elastic, but which are able to
absorb impact.

4.1.2. Guardrails shall have characteristics as follows:

- Rail in ± 4330mm with 2.7mm thick and weight of ± 45kg,


2,
- Having maximum tensile strength of 5600kg/m
- Strength of beam including connection of 680kg and deflection of 50mm if
tested on a clear span along 365cm using load through flat plate of 80mm
width at the centre,
- Connections having capability to withstand side pull of 2200kg,
- Complying with AASHTO M180,

such as manufactured by Bakrie Metal Industries, Kencana Cakra Buana,


Bumi Kaya or acceptable equivalent.

4.2. Accessories

Guardrails shall be completed with accessories manufactured by the same


manufacturer as the guardrails and consisting of the following:

- Supporting post length of ± 1800mm in 6mm thick and weight of 26kg.


- Block piece length of ± 350mm in 6mm thick and weight of 5kg.
- Terminal end length of ± 725mm in 2.7mm thick and weight of 8kg.
- High tensile hexagon bolts and nuts according to ASTM A 325.

4.3. Concrete

Concrete for foundation of posts shall comply with the requirements as shown in the
Drawings.

5.0 CONSTRUCTION REQUIREMENTS

5.1. General

5.1.1. The guardrails shall be installed in accordance with the manufacturer's


installation instructions.

5.1.2. Where shown to use guardrails in curve shape with radius between 2000mm
or more, this curve shape shall be bended at the manufacturer’s factory.

5.2. Installation

5.2.1. Posts

Post shall be set plumb, by hand or mechanically dug holes. Driving of post
shall avoid shaterring, battering, brooming or distorting of the top of butt. Post
shall be set on steel anchored concrete and shall be as shown in the Drawings.
Concrete work shall be in accordance with the approved Shop Drawings.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02845


REVISION :A DATE : April 2018 PAGE : 2 of 3
BITA

5.2.2. Anchorage

End anchorage if required shall be constructed according to the details shown


by the manufacturer.

5.2.3. Bolts

Post bolt shall be located at the centre corrugation of rail beam as


recommended by the manufacturer.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02845


REVISION :A DATE : April 2018 PAGE : 3 of 3
BITA

SPECIFICATION

02890

TRAFFIC SIGNAGE

1.0 DESCRIPTION OF WORK

This work shall include but not be limited to the following:

- Furnishing all labour, materials, tools, equipment, services for all exterior site signage as
indicated in the Drawings, as specified herein and/or as directed by the Engineer.
- Coordinating with work of all other trades.
- Furnishing and installing all supplementary or miscellaneous items, appurtenance and devices
incidental to or necessary for sound, secure and complete installation.

2.0 REFERENCE STANDARDS

2.1. Peraturan Menteri Perhubungan No. PM 13/2014 - Rambu Lalu Lintas.

2.2. American Society for Testing and Materials (ASTM):

- ASTM A36/A36M - Specification for Structural Steel.


- ASTM A307 - Specification for Carbon Steel Externally Threaded Standard
Fasteners.
- ASTM A123 - Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel
Products.
- ASTM B221M - Specification for Aluminium-Alloy Extruded Bars, Rods, Wire,
Shapes and Tubes.

2.3. Related Specifications:

- 02315 - Excavation, Backfilling and Compaction.


- 03300 - Cast-in-Place Concrete.

3.0 GENERAL PROCEDURES

3.1. Samples

The Contractor shall submit prototype samples, colour match samples, complete alphabet,
numerals, punctuation and graphics for review prior to start of fabrication. If more than one
foundry’s cut will be used, submit each cut for review.

3.2. Shop Drawings

3.2.1. The Contractor shall submit Shop Drawings indicating construction details, finishes,
anchorage details, quantities and graphic layouts for each sign type.

3.2.2. Sign schedule as a Shop Drawing shall be submitted for final review approval.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02890


REVISION :A DATE : April 2018 PAGE : 1 of 5
BITA

3.2.3. The Contractor shall also submit proofs of artwork, map art, symbols for final
review approval.

3.3. Delivery

The materials shall be delivered/ packaged separately or in like groups of names, labelled
as to names enclosed. Delivery shall also include installation template, hardware or
adhesive for mounting and installation instructions.
All loose or small items shall be piece marked.

3.4. Inspection and Testing

Quality of workmanship shall be satisfactory. Deviation from what is required in this


Specification shall be rejected and shall be changed with no additional cost to the Owner.

4.0 MATERIALS

4.1. Acceptable Manufacturers

Only manufacturers who have been in the business of making signs for a minimum of five
(5) years will be eligible to supply traffic signage. Provide list of completed project and
owners name and address.

4.2. General

4.2.1. Signs and sign elements shall conform to the layout and proportions as
indicated in the Drawings.

4.2.2. Symbols, typography and colour shall be as follows:

- Copy on Drawings is for layout purpose only. Actual copy for signs is in the
Drawings.
- Stated dimensions in the Drawings shall take precedence over scale
dimensions. If the Drawing is not scaled, a notation “not to scale” occurs in
the Drawing.
- The graphic configuration of signs is ultimately governed by original art for
each sign provided by the successful contractor for architectural approval.
- Original art shall conform to the dimensions and general configurations
shown on sign type drawings/diagrams. If the conflict between original art
and drawings is apparent, the Engineer shall be notified immediately and
for resolution of the conflict. If such a conflict is not brought to the
attention of the Engineer, the original art shall govern.
- Colours shall be in accordance with manual of uniform traffic control
devices.
- The sign schedule is a consolidated reference which gives the sign copy,
sign type, and information which is not conductive to exclusive
categorization. Sign contractor is responsible for verifying exact copy upon
signs with the Engineer.
- Letterforms shall be Helvetica regular in sizes shown and/for scheduled.
- Letterforms shall be aligned to maintain a base line parallel to the sign
format.
- Edges of letterforms shall be sharp and clean with no edge build-up or
bleeding. Surfaces of letterforms shall be without pinholes.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02890


REVISION :A DATE : April 2018 PAGE : 2 of 5
BITA

- Letter height shall be identified as “cap” letter height.


- Directional arrow shall be type indicated for each sign type.

4.2.3. Materials shall be new stock, free from defects impairing strength, durability
and appurtenances:

- Signs and components shall be complete and free from visual and
structural/mechanical flaws.
- No fabrication materials or procedures shall be used that that will change
the visual quality or have an adverse effect on existing materials and
surface in the complex.

4.3. Metals

4.3.1. Aluminium

– Sheet aluminium shall meet the requirements of ASTM B-209 alloy 606a-
T6 with a minimum thickness as indicated in the Drawings.
– Structural or extruded aluminium shapes shall meet the requirements of
ASTM B-221, alloy 6063-T6 with a minimum thickness of 3.18mm.

4.3.2. Steels

Steel structural steel sections, channels, tubing, and angles shall meet the
requirements of ASTM A36, with prime paint coating of minimum thickness
0.05mm.

4.4. Concrete

Concrete shall conform to the requirements of Specification 03300.

4.5. Hardware, Fasteners and Anchors

4.5.1. Shall be non-corrosive type and shall be non-conductive and/or insulated


when joining non-compatible material. Paint for shop coating and field touch-
up of dissimilar metal connecting members, including anchors and clips, shall
be alkali-resistant, bituminous paint.

4.5.2. Vandal-resistant fasteners shall be used whenever possible.

4.6. Ink and Paint

4.6.1. Inks and paints required shall be a type made for the surface material on
which it is applied and recommended by the manufacturer of the ink and paint.
Exact identification of ink and paint shall be noted as in the Shop Drawings,
together with data describing the method of application, if other than “air”
drying.

4.6.2. Use no ink or paint that will fade, discolour or delaminate as a result of
proximity to a light source or heat.

4.6.3. Inks and paints shall be evenly applied and without pinholes, scratches,
orange peeling application marks and others. Workmanship in connection with
finishes and formation of letters shall conform to the standards of the trade.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02890


REVISION :A DATE : April 2018 PAGE : 3 of 5
BITA

4.6.4. Prime coats or other surface pre-treatments, where recommended by the


manufacturer for inks and paints, shall be included in the work as part of the
finished surface work at no extra cost to the Owner.

4.7. Convex Mirror

Convex mirror for outdoor installation shall have diameter as required by the
Drawings, complete with post for support, and shall meet the following requirements:

– Mirror made of acrylic with minimum thickness of 1mm.


– Back of mirror made of steel with aluminium protector.
– Viewing angle 130º.
– Provided with panel and mirror clamp (knock down).

4.8. Other Materials

Provide other materials as required for a complete project and in accordance with the
requirements of Peraturan Menteri Perhubungan No. PM 13/2014.

5.0 CONSTRUCTION REQUIREMENTS

5.1. Fabrication

5.1.1. Letterforms and graphics die-cut from regular vinyl and reverse cut vinyl shall
be of the best commercial quality available. Die cutting shall be executed such
that the edges and corners of finished letterforms and graphics shall be true
and clean.

5.1.2. Vinyl die cut shall include a pre-coated pressure sensitive adhesive backing
for mounting. Where specified as removable, vinyl die-cut shall remove
without residue or difficulty.

5.2. Sign Types

Refer to the Drawings for sign type identification.

5.3. Colour

Refer to uniform traffic control devices for colour identification.

5.4. Preparation

5.4.1. Prior to work, inspect the completed work of other trades and verify that work
is complete to the point where installation may begin.

5.4.2. In the event of discrepancies, immediately notify the Engineer in writing.

5.5. Installation

5.5.1. Signs and components shall be complete and free from visual and structural
or mechanical flaws.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02890


REVISION :A DATE : April 2018 PAGE : 4 of 5
BITA

5.5.2. No fabrication or installation materials or procedures shall be used that will


change the visual quality or have an adverse effect on the existing materials
and surfaces on the structures.

5.5.3. Install in accordance with manufacturer’s printed instructions, according to


code requirements, and as detailed. Units shall be rigidly attached, mounted
plumb and level.

5.5.4. Special care shall be taken during installation to assure that signs are not
damaged or scratched. Signs showing damage shall be repaired or replaced.

5.5.5. Where a special remark on the signage location plan occurs regarding a
specific sign placement, the remark shall take precedence over the above
stated placement rule.

5.5.6. Installation shall conform to the code requirements pertaining to signage


installation including requirements set forth by the uniform traffic control
devices, adopted by Local Authorities.

5.5.7. No fabrication or installation materials or procedures shall be used that will


change the visual quality or have an adverse effect on the existing materials
and surfaces on the structure.

5.5.8. Exterior aspects adversely altered or damage by sign installation shall be


restored to original condition and appearance by this Specification to the
satisfaction of the Engineer.

PROJECT NO. : 17.3866 DIVISION : SITE CONSTRUCTION SPEC. NO. : 02890


REVISION :A DATE : April 2018 PAGE : 5 of 5
DIVISION 3
CONCRETE
BITA

SPECIFICATION

03210

REINFORCING STEEL

1.0 DESCRIPTION OF WORK

This work shall consist of furnishing concrete reinforcement in conformity with the Drawings. The
work shall include all machinery, equipment, manpower and the required workmanship and
performance to the satisfaction of the Engineer.
This Specification shall govern over the Drawings in the event of any conflicting details that may
arise.

2.0 REFERENCE STANDARDS

2.1. Standar Nasional Indonesia (SNI):

- SNI 2052:2014 - Baja Tulangan Beton.


- SNI 03-6816-2002 - Tata Cara Pendetailan Penulangan Beton.
- SNI 1729:2015 - Spesifikasi untuk bangunan gedung baja struktural.

2.2. American Society for Testing and Materials (ASTM):

- ASTM A615/A615M - Standard Specification for Deformed and Plain Carbon-Steel


Bars for Concrete Reinforcement.

2.3. American Concrete Institute (ACI):

- ACI 315 - Details and Detailing of Concrete Reinforcement.


- ACI 318 - Building Code Requirements for Reinforced Concrete.

2.4. Specification 03300 - Cast-in-Place Concrete.

3.0 GENERAL PROCEDURES

3.1. Sample and Mill Certificate

3.1.1. The Contractor shall submit to the Engineer samples and the manufacturer's
certificate of compliance with the concrete reinforcement requirements for
approval.

3.1.2. Prior to ordering of material, all the order lists and cutting schedules shall be
properly prepared by the Contractor and submitted to the Engineer for approval.
However, such approval shall in no way relieve the Contractor of his responsibility
for ascertaining the accuracy of such order lists and cutting schedules.
Any revision of the approved material lists and schedules of the concrete
reinforcement shall be the full risk and expense of the Contractor.

PROJECT NO. : !7.3866 DIVISION : CONCRETE SPEC. NO. : 03210


REVISION :A DATE : April 2018 PAGE : 1 of 3
BITA

3.2. Shop Drawings

3.2.1. Shop Drawings shall be submitted by Contractor for Engineer's approval and shall
include of the following:

- Concrete reinforcement cutting schedule showing dimensions, locations,


bends, hooks sizes, anchor and laps, and others which shall conform to ACI
315 and SNI 03-6816-2002.
- Bar spacing, concrete cover allowances and spacers, dowels and metal chairs.

3.2.2. The Contractor may be permitted to substitute the designed sizes of the concrete
reinforcement as shown in the Drawings provided that the substitution is carefully
analyzed and he has checked that the required strength is still maintained. Such
substitution shall be approved by the Engineer prior to work execution.

3.2.3. Details of concrete reinforcement and accessories not shown in the Drawings shall
be in accordance with the Engineer requirements.

3.3. Handling and Storage

Concrete reinforcement shall be protected at all times from damage and shall be stored in a
location (and on blocks) where the potential for rusting is minimized and is not in contact
with oil, grease, mud and other objectionable materials.

4.0 MATERIALS

4.1. Reinforcing Steel

4.1.1. Reinforcing steel of plain type with diameter of < 10mm shall be of grade BjTP-24
material with yield strength of 2400kg/cm² and shall comply with SNI 2052:2014
or ASTM A615/A615M.

4.1.2. Reinforcing steel of deformed type with diameter of  10mm shall be of grade
BjTS-40 material with yield strength of 4000kg/cm² and shall comply with SNI
2052:2014 or ASTM A615/A615M.

4.2. Accessories

4.2.1. Metal chairs, spacers and other shall be sized and shaped to adequately support
reinforcing.

4.2.2. Accessories in exposed concrete shall be made of galvanized steel. Steel


material shall conform to the requirements of SNI 1729:2015.

5.0 CONSTRUCTION REQUIREMENTS

5.1. Hooks/Bends

Reinforcing steel shall be provided with hook/bend minimum as in indicated in the Drawings
or as specified in SNI 03-6816-2002 or as determined by the Engineer.

PROJECT NO. : !7.3866 DIVISION : CONCRETE SPEC. NO. : 03210


REVISION :A DATE : April 2018 PAGE : 2 of 3
BITA

5.2. Cutting

Length in excess required in the Drawings (apart from overlaps), shall be done by steel
cutting or any cutting tools approved by the Engineer.
In areas where block outs are made for machineries, equipment and other utilities, the mild
steel bar shall be cut to suit the opening or size of the block out.

5.3. Dowel Bars

Unless otherwise shown in the Drawings, for the designed slabs up to 150mm thickness,
use 12mm diameter round dowel bars, 600mm long, spaced at 250mm on centers.
For slabs 160mm to 500mm thickness, use 16mm diameter round dowel bars, 800mm
long, spaced at 200mm on centers.

5.4. Placing and Fastening of Reinforcing steel

5.4.1. Before placing, the reinforcing steel shall be free from loose, rust, loose scales, oil,
paint and any other objectionable substances.

5.4.2. All reinforcing steels shall be accurately placed in conformance with the grade,
dimension and location as shown in the Drawings. Metal chairs or inserts shall be
spaced at one meter square or as determined by the Engineer. Stones, bricks or
wood blocks are not allowed as chairs or insert. All laps shall be tied with no. 16
AWG or 1.62mm diameter tie wire or equal. Spot welding may be applicable in
mild steel reinforcement only in lap work as approved by the Engineer.

5.5. Concrete Pouring

Concrete pouring shall be carried out in accordance with Specification 03300.

PROJECT NO. : !7.3866 DIVISION : CONCRETE SPEC. NO. : 03210


REVISION :A DATE : April 2018 PAGE : 3 of 3
BITA

SPECIFICATION

03300

CAST- IN- PLACE CONCRETE

1.0 DESCRIPTION OF WORK

This work shall include cast-in-place concrete structures, constructed in close conformity with the
lines, grade and dimensions shown in the Drawings.
All work, material and performance related to cast-in-place concrete shall conform to this
Specification and related Specifications and standards.

2.0 REFERENCE STANDARDS

2.1. Standar Nasional Indonesia (SNI):

- SNI 2049:2015 - Semen Portland


- SNI 2847:2013 - Persyaratan Beton Struktural untuk Bangunan Gedung.

2.2. American Concrete Institute (ACI):

- ACI 211.1 - Standard Practice for Selecting Proportions for Normal, Heavyweight,
and Mass Concrete - Procedure for Mix Design.
- ACI 318 - Building Code Requirements for Reinforced Concrete
- ACI 347 - Formwork for Concrete.

2.3. American Association of State Highway and Transportation Officials (AASHTO):

- AASHTO M6 - Standard Specification for Concrete Aggregates.


- AASHTO M153 - Preformed Sponge Rubber and Cork Expansion Joint Fillers for
Concrete Paving and Structural Construction.
- AASHTO T11 - Amount of Material Finer than 0.075mm (No. 200) Sieve in
Aggregate.
- AASHTO T 26 - Quality of Water
- AASHTO T27 - Sieve Analysis of Fine and Coarse Aggregate.
- AASHTO T112 - Clay Lumps and Friable Particles in Aggregate.
- AASHTO T113 - Lightweight Pieces in Aggregate.

2.4. American Society for Testing and Materials (ASTM):

- ASTM C33 - Specification for Concrete Aggregate.


- ASTM C150 - Specification for Portland Cement.
- ASTM C260 - Standard Specification for Air-Entraining Admixtures for Concrete.
- ASTM C494 - Standard Specification for Chemical Admixtures for Concrete.
- ASTM C685 - Specification for Concrete Made by Volumetric Batching and
Continuous Mixing.

PROJECT NO. : 17.3866 DIVISION : CONCRETE SPEC. NO. : 03300


REVISION :A DATE : April 2018 PAGE : 1 of 12
BITA

2.5. Related Specifications:

- 01400 - Concrete Test.


- 02315 - Excavation, Backfilling and Compaction.
- 03200 - Concrete Reinforcement..

3.0 GENERAL PROCEDURES

3.1. Shop Drawings

The following Shop Drawings shall be submitted by Contractor for Engineer's approval:

- Reinforcing steel cutting schedule showing bends, hooks sizes, laps, anchors and
others as specified in Specification 03200.
- Shop Drawings of form works shall show structural members, spacing, sizes, joints,
inserts and other related work in form works, and shall be approved by the Engineer.
- Scheme of concrete pouring including mix design, manpower, equipment and tools.

3.2. Field Inspection, Sampling and Testing

3.2.1. Field Inspection

- Prior to the commencement of the cast-in-place concrete work the following


preliminary test shall be performed by the Laboratory at the Contractor's
expense. Additional tests shall be performed if necessary.
- The Contractor is obligated to follow the results of the trial mixes and
estimates he intends to use in the work described herein.
- The Contractor shall furnish assistance to the Engineer in sampling and testing
works. The preliminary tests shall include the determination of:

· Durability.
· Characteristics and distribution of aggregates.
· Cement type and quality.
· Selection and dosage of admixtures.
· Proportioning of aggregates classes in the mix.
· Cement strength, type.
· Water cement ratio.
· Slump test.
· Characteristic of different fresh concrete mixes.
· Compressive strength.
· Water tightness.
· Resistance to weathering.
· Resistance to adverse chemical reactions.

- These tests shall be carried out until concrete mixes have been obtained in
conformance with this Specification.

3.2.2. Sampling and Testing

All testing and sampling shall be accomplished by the Contractor without additional
cost. This work shall continue during actual concrete placing.

PROJECT NO. : 17.3866 DIVISION : CONCRETE SPEC. NO. : 03300


REVISION :A DATE : April 2018 PAGE : 2 of 12
BITA

Samples and testing shall be taken by the approval of the Engineer, as described
below:

a. Cement

Cement shall have the certificate obtained from the factory of origin, showing
weight per bag of three (3) to six (6) ply rating.

b. Aggregates

Aggregate shall conform to and be tested according to ASTM C 33


Specification. Test shall start thirty (30) days prior to the start of the concrete
work.

c. Concrete

At least thirty (30) days before concreting starts, the Contractor will make trial
mixes for testing, materials to be used, and methods which are introduced in
the works.
Trial mixes shall be as specified in section 3.3 of this Specification.

d. Admixtures

All admixtures for concrete shall be tested according to the relevant ASTM C
260 and ASTM C 494 at least thirty (30) days prior to the start of the concrete
works.
Admixtures shall not be used without approval of the Engineer.

3.2.3. Test Mixing/Trial Mixes

- The Contractor shall conduct test mixing of concrete, each types and
strength applied, prior to placement of concrete.
- Mixing design shall meet the requirements of ACI 211.1.
- Mixing design shall indicate water-cement ratio, water content, admixture
content, cement content, aggregate content, aggregate gradations, slump, air
content and strength.
- Maximum water cement ratio shall not be more than 0.4.
- The design slump shall be in the range 60mm to 100mm.
- The aggregates shall be batched from no less than two size grading, coarse
and fine (sand). Coral sand shall not be used for works under this Contract.
- The Contractor shall submit the grading curves to the Engineer for approval.
The aggregate sources and the size grading shall not then be changed from
the approved aggregates.
- Trial mixes shall be carried out by the Contractor before the mix design is
approved by the Engineer. Proportions may be determined by weigh batching
or volume batching. In the case of volume batching, two (2) volume boxes
shall be made, one being for sand and the other for coarse aggregate.
- Cement content shall be assessed by the number of 50kg bags of cement type
I used in each cubic meter of concrete, in this case being not less than seven
(7). Water content shall be assessed by water meter or the number of buckets
of known volume of water. There shall be no casual addition of water to the
mix by hose or bucket. The Contractor may include concrete additives to the
mix with the Engineer’s approval.

PROJECT NO. : 17.3866 DIVISION : CONCRETE SPEC. NO. : 03300


REVISION :A DATE : April 2018 PAGE : 3 of 12
BITA

- Make test mixing to that when test specimens are cured and tested under
laboratory conditions, their compressive strength will exceed the adequate
strength required. For each test mixing, make four (4) specimens at 7 days
and 28 days strength.
The 7 days test strength shall be at least 65% of the 28 days strength required
for the test mixing.
Concrete test shall be as stipulated in Specification 01400.
- The test result report shall be submitted to the Engineer for approval. The
Contractor shall not commence construction of concrete works until the
Engineer has approved the Contractor’s Concrete Mix Design. Once
approved, the Contractor shall not vary the trial mix proportions or component
materials without the written approval of the Engineer.
- Prior to using any water reducing agents or high early strength promoting
admixtures, the Contractor shall submit details of the products technical data
to the Engineer for review. The Contractor shall prepare a series of four (4)
concrete test cubes specimens trial mix using the approved Concrete Mix
Design with the proposed concrete admixture. Testing of the specimens shall
be carried out by a test laboratory approved by the Engineer. Two (2) of the
specimens shall be tested at 7 days and the remaining two (2) tested at 28
days. The results of the trial mix testing (incorporating the admixture) shall be
submitted to the Engineer for review and approval following each series of
testing.

4.0 MATERIALS

4.1. Concrete

4.1.1. Composition of concrete, either by weight or by volume, shall be as determined by


the Engineer and shall comply with the following conditions:

- Slump shall be as specified in Specification 01400.


- Alternative mixes shall be used with the approval of the Engineer.
- Excluding surface water aggregates.

4.1.2. Unless otherwise shown in the Drawings, concrete are grouped in different
classes, according to the following requirements:

- f'c = 28MPa concrete for pile cap, pile head treatment, pedestal, tie beam,
wingwall and others as shown in the Drawings.
- f’c= 25MPa concrete for U ditches, manholes and others as shown in the
Drawings.
- f’c= 20MPa concrete for concrete surface drain or spoon drain as shown in the
Drawings.
- f’c= 10.4MPa concrete for lean concrete bedding for foundation and filling.

4.1.3. All ready mixed concrete shall comply with the requirements of ASTM C 94.

4.2. Cement

Cement shall be portland cement type I complying with SNI 2049:2015, ASTM C 150.
Cement shall come from one brand, from Holcim, Gresik, Indocement or acceptable
equivalent.

PROJECT NO. : 17.3866 DIVISION : CONCRETE SPEC. NO. : 03300


REVISION :A DATE : April 2018 PAGE : 4 of 12
BITA

4.3. Water

Water for mixing, curing or other designated applications shall be clean and free from
harmful and deleterious substances such as alkali, acids, salt and other inorganic matters.
However, as the case may happen, all water except what as mentioned herein shall be
tested and shall meet the requirement of AASHTO T26 and/or approved by the Engineer.

4.4. Fine Aggregates

4.4.1. The fine aggregate for concrete consisting of natural hard sand shall meet ASTM
C33 requirements, and shall be approved by the Engineer for concreting works.
Fine aggregate shall also meet the requirements of the following:

DESCRIPTION AASHTO TEST METHOD % BY WEIGHT


Clay Lump T 112 0.5%
Coal and Ignite T 113 0.5%
Material Passing No. 200 Sieve T 11 3 %

4.4.2. Fine aggregate shall not contain inorganic materials, acids, alkalis and other
substances. Fine aggregates shall be uniformly graded and shall meet the
following grading requirements:

SIEVE DESIGNATION % WEIGHT PASSING SIEVE (AASHTO T 27)

3/8” (9,5mm) 100


No. 4 (4,75mm) 95 – 100
No. 16 (1,18mm) 45 – 80
No. 50 (0,300mm) 10 – 30
No. 100 (0,150mm) 2 – 10

4.5. Coarse Aggregates

4.5.1. The coarse aggregates for construction shall consist of crushed granular
stones, crushed stone, blast furnace slag or other approved inert material of
similar characteristics which are hard, durable and free from deleterious
substances.

4.5.2. Coarse aggregates shall not contain deleterious substances in excess of the
percentages:

DESCRIPTION AASHTO TEST METHOD % BY WEIGHT

Clay Lumps T 112 0.25%


Materials passing No.200 sieve T 11 1%
Thin or elongated pieces - 10%
(length greater than 5 x max.
thickness

Other deleterious substances shall not exceed the percentage limits set forth-
in this Specification and/or approved by the Engineer.

PROJECT NO. : 17.3866 DIVISION : CONCRETE SPEC. NO. : 03300


REVISION :A DATE : April 2018 PAGE : 5 of 12
BITA

4.5.3. Coarse aggregate grading requirements shall be as specified in ASTM A33:

MAXIMUM SIZE
OF COARSE % BY WEIGHT PASSING SIEVES
AGGREGATE SIEVE DESIGNATION
(CM) 5.08 2.54 1.905 1.27 0.952 4 8 16
3.81 95-100 - - - 10-13 0-5 - -
1.905 - 100 90-100 - 20-55 0-10 0-5 -
0.952 - - - 100 85-100 10-30 0-10 0-5

4.5.4. Separate sizes of coarse aggregate shall be combined with other sizes at the
proportions by weight or by volume to produce an aggregate that meets the
grading requirements specified.

4.5.5. A sample of approved coarse aggregate material shall be retained on-site in a


sealed clear plastic container for comparison purposes. Any material brought
to site that differs substantially from the approved sample shall be rejected.

4.6. Curing Materials

Curing materials shall conform to the following requirements:

DESCRIPTION TEST METHOD

Burlap cloth made from jute or kenaf AASHTO M 182


Liquid membrane-forming compounds AASHTO M 148
for curing concrete
White polyethylene sheeting (film) for AASHTO M 171
concrete curing

Other applicable method of curing concrete shall be approved by the Engineer.

4.7. Admixture

4.7.1. Air entraining admixtures shall conform to ASTM C 260 for all exposed
concrete.

4.7.2. Water reducing and retarding admixture for controlling the setting time of
concrete, if required, shall conform to ASTM C 494 type B and D.

4.7.3. Admixture for accelerating the setting time of concrete, if required, shall
conform to ASTM C 494 type C.

4.7.4. Admixture for waterproofing substructure concrete, if required and as shown in


the Drawings or as instructed by the Engineer, shall conform to BS 1881: Part
122 for water absorption or ASTM C 494 type A.

4.7.5. Superplasticiser shall be of the following types:

- Non-retarding type shall conform to ASTM C494 type F,


- Slump-retaining type shall conform to ASTM C494 type G,
- Retarding type shall conform to ASTM C494 type G,

from Sika, BASF, Fosroc or acceptable equivalent.

PROJECT NO. : 17.3866 DIVISION : CONCRETE SPEC. NO. : 03300


REVISION :A DATE : April 2018 PAGE : 6 of 12
BITA

Type of superplasticiser to be used shall be as recommended by the


admixture manufacturer and as approved by the Engineer.

4.8. Joint Filler and Joint Sealant

4.8.1. Joint filler shall conform to the requirement of AASHTO M 213 and US
Federal Specification HH-F 341a type 1 class B, such as Bitumen
Impregnated Board by Sika, Flexcell or acceptable equivalent.

4.8.2. Joint sealant shall conform to the requirement of BS 4254 and US Federal
Specification SS-S-200 D EA.A. Spec. P.D.-605-2.1F, such as Masterflex 700,
Thioflex 600 or acceptable equivalent.

4.9. Concrete Reinforcement

Concrete reinforcement and dowel bars shall be as specified in Specification 03210.

5.0 CONSTRUCTION REQUIREMENTS

5.1. Falsework and Forms

5.1.1. Falsework shall be built on foundation of sufficient strength to carry the loads
without settlement.

5.1.2. Falsework which cannot be founded on solid footings must be supported and
reinforced by sufficient additional supporting falsework. Prior to placing of
falsework, a representative design to carry the loads for a certain job shall be
submitted to the Engineer for approval.

5.1.3. Forms shall comply with the requirements below:

- All forms shall be provided with adequate clean out openings to permit
inspection and easy cleaning after all the reinforcement is in position.
- Form materials shall be of lumber not less than 20mm thick and plywood
not less than 12mm, metal not less than 0,6mm, or other acceptable
material.
All exposed concrete surfaces shall be cast with a smooth “off-form” finish.
No plastering shall be undertaken without the approval of the Engineer.
Provide timber or plastic chamfer strips (20mm x 20mm) securely nail
fixed on all corners of formwork for exposed concrete members as
indicated in the Drawings.
Wood material used shall be approved by the Engineer, sufficiently dry
and solid enough to receive load, selected straight, sound and free from
loose knot holes, splits and other defects, milled to net shapes and sizes.
The samples of materials, dressed on at least 2 edges and one side for
tight fit, shall be submitted to the Engineer for approval.
- Form, shoring and bracing design and construction shall be the
Contractor's responsibility.
Forms shall be mortar tight and structurally rigid to disallow distortion due
to the pressure of the vibrator and the concrete and other loads.
- Forms shall be constructed carefully and inspected for adequacy of
construction before concrete pour.
- All corner joints shall be rigid in order to prevent opening during
construction progress. The Contractor shall be responsible for the
adequacy of forms and supports.

PROJECT NO. : 17.3866 DIVISION : CONCRETE SPEC. NO. : 03300


REVISION :A DATE : April 2018 PAGE : 7 of 12
BITA

- Metal ties, struts, bolts and rods shall be arranged so that when the forms
are removed, all metal shall not be less than 50mm from the exposed
concrete surface.
- For all weather exposed concrete, metal ties if permitted shall be removed
to a depth of at least 25mm from the concrete face without resulting injury
of the concrete surface.
- Suitable cones shall be provided. The cavities shall be filled with mortar
and the surface left smooth, even and uniform in colour.

5.1.4. Where the bottom of the forms is inaccessible, the lower form boards shall be
left loose, or other provisions made so that extraneous materials may be
removed from the forms easily before concrete placing.

5.2. Form Surface Treatment

All form surfaces shall be-treated with approved form release oil prior to placing of
reinforcing steel, and, wood forms shall be wetted with water before concrete placing.
No treatment compound shall be used which may discolour the finished concrete.

5.3. Placing of Utility Pipes, Conduits and Block Outs

5.3.1. Utility pipes and conduits for power and telecommunication cables that are to
be embedded in the concrete, shall be installed before placing the concrete, at
position as indicated in the Drawings, and in manner as not to reduce the
concrete strength. Those utility pipes and conduits shall be protected/ covered
in order to avoid the concrete entering them during concrete pouring.

5.3.2. Block outs shall be prepared in dimensions to suit the sizes of machineries,
equipment and other utilities to be placed on concrete slabs, as shown in the
Drawings and the approved Shop Drawings.

5.4. Tolerances

The Contractor shall maintain and set the concrete forms to ensure that, after form
removal and prior to patching and finishing work, no portion of the concrete work shall
exceed any of the tolerances specification in the Drawings. Variations of deck levels
shall be measured before removal of shoring and supports.
Tolerances shall conform to ACI 347 and/or be approved by the Engineer.

5.5. Concrete Cover

Unless otherwise specified, minimum thickness of concrete cover shall be made


according to the usage and as shown in the Drawings.

5.6. Proportioning and Mixing of Concrete

5.6.1. Proportioning of materials shall be accomplished by weighing or by volume


batching.

5.6.2. The Contractor shall submit his proposed mixing plant to the Engineer for approval
before use. The plant must be robust and reliable, and be capable of mixing
10cubic meters of concrete in not more than two hours. The mix volume boxes
shall be so sized that they suit the capacity of the mixing bowl of the plant.

PROJECT NO. : 17.3866 DIVISION : CONCRETE SPEC. NO. : 03300


REVISION :A DATE : April 2018 PAGE : 8 of 12
BITA

5.6.3. Mixing of concrete shall not commence without ensuring that the stocks of
components are adequate, with a reasonable safety margin, for the completion
of the particular pour of concrete.

5.6.4. In case of pours which can not be interrupted, the Contractor shall make
provision for adequate standby equipment as approved by the Engineer.

5.6.5. Ready-mixed concrete shall be mixed and delivered in accordance with


requirements of ASTM C685.

5.7. Construction Joints

All construction joints shall be located where shown in the Drawings or determined by
the Engineer.
Construction joints shall be perpendicular to the principal lines of stress and in general
shall be located at points of minimum shear at horizontal construction joints.
Necessary dowels, load transfer devices and bonding devices shall be placed as
shown.

5.8. Open Joints

Open joints shall be constructed where shown by insertion and subsequent removal of
wooden strip, metal plate or other approved material.
The insertion and removal of the template shall be accomplished without chipping on
breakage of edges or corners of the concrete. Reinforcement shall not extend across
an open joint unless otherwise specified.

5.9. Filled Joints

5.9.1. Poured expansion joints shall be constructed similar to open joints. When re-
moulded expansion joints are specified, thickness of filler as installed shall be
as required in the Drawings. The joint filler shall be cut to the same shape and
size as the surface being joined.

5.9.2. It shall be fixed firmly against the surface of the concrete already in place in
such a manner that it will not be displaced when concrete is deposited against
it.

5.9.3. Where it is necessary to use more than 1 (one) piece of filler to cover any
surface, the abutting pieces shall be placed in close contact and the joint
between them shall be covered with a layer of asphalt saturated roofing felt of
not less than 18kg grade, one side of which shall be covered with hot asphalt
to ensure proper retention.
Where joint sealant is indicated, the joint filler shall be set at least 7mm below
or behind the exposed concrete surface.

5.9.4. Immediately after the forms are removed, the expansion joints shall be
inspected carefully.

5.9.5. Any concrete or mortar that has sealed across the joints shall be cut neatly
and removed.
When, during construction, an opening of 3 mm or more appears in any joint
over which any traffic will occur, the opening shall be completely filled with
joint sealant as directed by the Engineer.

PROJECT NO. : 17.3866 DIVISION : CONCRETE SPEC. NO. : 03300


REVISION :A DATE : April 2018 PAGE : 9 of 12
BITA

5.10. Steel Joints

Steel joints and water stop shall be placed as locate at all construction joints which
contact with soil or underground water and elsewhere as indicated in the Drawings and
as directed by the Engineer.

5.11. Placing of Concrete

5.11.1. Concrete shall not be placed until forms, reinforcements, insert, block outs and
others have been approved by the Engineer.
The forms shall be cleaned, free of shakes, splits, notches, debris, and warps
before concrete is poured.

5.11.2. The prepared and approved area for pouring the concrete shall be no larger
2
than 36m per block. In every concrete run, pouring shall be done one (1)
block after the other.
The external surface of concrete shall be properly worked out during the
placing.

5.11.3. Ambient temperature when placing of concrete shall be 30ºC ± 2ºC.


Temperature of concrete shall not exceed than 35ºC.

5.11.4. The difference between temperature of inside of the concrete and its surface
shall not be more than 20ºC.

5.11.5. Thorough vibration of 380-500mm distances shall be maintained in order to


avoid honeycombing and to obtain smooth surfaces.
During the vibration of concrete, the vibrator stick shall be held plumb or
perpendicular to the horizontal surface of the fresh concrete.

5.12. Chutes Pipes and Troughs

5.12.1. Concrete shall be placed so as to prevent segregation of materials and


displacement of reinforcing bars.
Where steep slopes are required, the chutes shall be equipped with baffle
boards which shall be in short lengths that reverse the direction of movement.
All chutes, troughs and pipes shall be maintained and kept free from a
hardened coating of concrete by properly flushing with water after each run.
The flushed water shall be discharged clear of the concrete already in place.

5.12.2. Concrete shall not be dropped in the forms from a height more than 150cm
unless confined by closed chutes or pipes or tremie. After initial setting of
concrete, forms shall not be jarred and no strain shall be placed on the ends of
the reinforcement. Concrete shall be discharged from the mixer and
transported within 1 (one) hour to final positions as approved by the Engineer.
This shall guarantee that the concrete is of the required workability at the point
and time of placing and the Contractor shall maintain a continuous delivery of
concrete.

5.12.3. All the equipment, machinery and tools used for this work shall be clean, and
in good operating condition. If possible a standby unit or spare parts shall be
available in site.

5.12.4. If used, pump lines must be laid so that the flow of concrete is not interrupted.
Sharp bends shall be avoided.

PROJECT NO. : 17.3866 DIVISION : CONCRETE SPEC. NO. : 03300


REVISION :A DATE : April 2018 PAGE : 10 of 12
BITA

5.12.5. Water content and particle size of aggregates shall be carefully watched when
concrete is being pumped to avoid clogging.
The slopes of troughs for conveying the fresh concrete shall be well chosen so
that the concrete with minimum water content flows in a uniform stream
without segregation of cement and aggregate.

5.12.6. When concrete is placed directly on earth or plastic membrane placed on


earth, the bed or base shall be clean and compacted, and free from standing
or running water, and shall be in accordance with the Specified Drawings.
Form surfaces upon where concrete are to be placed shall be properly cleaned
of mud, loose rock, debris and other objectionable materials of coatings.
These procedures shall be subject to the Engineer for the approval.
To prevent surface water entering the concrete, place plastic membrane made
of HDPE sheet on the prepared surface. The installation of HDPE sheet and
its accessories shall be carried out in strict accordance with manufacturer’s
installation instruction
This procedure shall be approved by the Engineer.

5.13. Removal of Forms

Forms and falsework shall not be removed without the approval of the Engineer. The
Engineer's approval shall not relieve the Contractor for the safety of the work. The
schedule for removal shall be approved in advance by the Engineer.

5.14. Patching of Concrete

5.14.1. The Contractor shall request to the Engineer to inspect concrete surfaces
immediately upon removal of forms.

5.14.2. The Contractor shall (at his own expense) replace concrete not conforming to
required lines, details and elevations or having excessive defects. Do not
patch, fill, touch-up, repair, or replace exposed architectural concrete except
upon the express direction of the Engineer.

5.14.3. All general concrete formed surfaces shall have "as-cast" finish using
specified forms.
Tie holes shall be plugged. Exposed surfaces and surfaces to receive paint
shall have repairable defects patched, have joints pointed, have fins and
mortar drippings rubbed smooth, and have form coating films and surface dirt
removed.

5.14.4. Honeycombs, hollows or cold joints shall be repaired only upon the express
direction of the Engineer.
Patching materials shall be cohesive, un-shrinkable and surpass the concrete
in strength.

5.14.5. Remove blemishes, rust, stains or discolouration exposed concrete or


concrete to be painted by:

- Light sand blasting.


- A clean down with a mild solution of detergent and water applied by
scrubbing vigorously with soft bristle brushes, then flushing out with water.
Remove rust stains by applying a paste of oxalic acid, allow to stand and
to remove by rubbing with an approved hone.

PROJECT NO. : 17.3866 DIVISION : CONCRETE SPEC. NO. : 03300


REVISION :A DATE : April 2018 PAGE : 11 of 12
BITA

- A clean down with a solution of muriatic acid containing not less than 2%
or more than 5% acid by volume, applied to surface previously saturated
with clean water. Remove acid. Protect metal and other materials that
would be damaged by acid.
- Lime poultice.
- Honing or grinding.

5.15. Concrete Finishing

Unless otherwise specified, the surface of the concrete shall be finished immediately
after removal and shall be finished to the grades and dimension as shown.

5.16. Backfilling

Backfill shall be placed in layers of 150mm maximum loose fill thickness and tamped
thoroughly as soon as concrete is twenty eight (28) days old or until the cylindrical test
indicates the twenty eight (28) days strength has been achieved.
All backfill material shall be approved by the Engineer prior to the backfilling work, as
specified in Specification 02315.

5.17. Curing and Protection

The following measures shall be taken to protect freshly deposited concrete from the
sun, wind and rain until it has set properly, and to prevent quick drying:

- All forms containing concrete shall be kept moist until they are removed.
- All exposed surfaces of concrete shall be moistened continuously for 7
consecutive days after pouring.
- Special care shall be taken of surfaces of roof-slabs which shall either be covered
with moistened hessian or be protected from drying out by other suitable means.
- It shall not be allowed to store materials on or to transport them over construction,
which, in the opinion of the Engineer, has not been sufficiently hardened.

PROJECT NO. : 17.3866 DIVISION : CONCRETE SPEC. NO. : 03300


REVISION :A DATE : April 2018 PAGE : 12 of 12
BITA

SPECIFICATION

03600

GROUT

1.0 DESCRIPTION OF WORK

The work shall include furnishing of equipment, materials, labour and application of grout at places
as directed by the Engineer.
The work shall include, but not be limited to the following:

- Grouting of anchor bolts and base plates.


- Grouting of posts and structural steel columns.
- Grouting of machinery and equipment.

2.0 REFERENCE STANDARDS

2.1. American Society for Testing and Materials (ASTM).

2.2. British Standard (BS).

2.3. Related Specifications:

- 03300 - Cast-in Place Concrete.


- 05120 - Structural Steel.
- 05500 - Miscellaneous Metals.

3.0 GENERAL PROCEDURES

3.1. Samples and Technical Data

Sample, brochure and/or technical data of the specified material shall be submitted to the
Engineer for approval, prior to delivery to location.

3.2. Handling and Storage

Original pack/bag from the factory shall be tightly closed and shall be kept in storage with
enough ventilation, free from humidity and water, and shall be placed at 30cm above floor.

4.0 MATERIALS

4.1. Grout

Grout shall be made of cement material and shall have minimum characteristics as
follows:

- Premixed product ready to use,

PROJECT NO. : 17.3866 DIVISION : CONCRETE SPEC. NO. : 03600


REVISION :A DATE : April 2018 PAGE : 1 of 3
BITA

- Impact and vibration resistant,


- Non-shrinkage and non-metallic type,
- Complying with ASTM C 1107,
- Having minimum compressive strength of 610kg/cm² at 7days of age, according to
ASTM C 109 or 650kg/cm² according to BS 1881 part 116,
- Low VOC,

such as Sika Grout 214-11, Conbextra GPXtra by Fosroc, Masterflow 810 by BASF or
approved equal.

4.2. Water

Water for mixing shall be clean water complying with the requirements of Specification
03300.

4.3. Moulds/Formworks

Moulds/formworks shall be made of steel plate or plywood from suitable thickness, which
shall be formed in sizes and forms as specified in the Drawings.
Moulds/formworks shall be made in same size for places which shall have same size and
form.

5.0 CONSTRUCTION REQUIREMENTS

5.1. Preparation

5.1.1. Moulds/formworks shall be designed so that the grout is surcharged throughout the
grouting operation. Good access should be provided.

5.1.2. Moulds/formworks shall have been prepared and surfaces/parts to be grouted are
clean, dry and free from oil, grease and other contaminants likely to impair bond.
Dust has to be blown from pockets.

5.1.3. Anchors, fixing bolts and base plates shall have been elevated prior to grouting.

5.2. Weather

The weather at the time of grout application being held shall be in accordance with the
requirements of the grout manufacturer.

5.3. Mixing

The mixing comparison between grout and water shall be in accordance with the
manufacturer instruction.
Mixing is carried out mechanically, by force action mixer or a suitable mixing paddle
attachment to a slow speed drill.

5.4. Application

5.4.1. Grout might be poured or pumped into the mould, or as specified by the
manufacturer's instruction.
Gentle vibration will aid flow.

PROJECT NO. : 17.3866 DIVISION : CONCRETE SPEC. NO. : 03600


REVISION :A DATE : April 2018 PAGE : 2 of 3
BITA

5.4.2. Use of straps or chains will aid flow where distances of over 100cm are involved
(sawing action of the strap or chain promotes sympathetic flow of the grout-the
technique shall be used with discretion to avoid the creation of voids).

5.4.3. Flow of grout shall be maintained until the grout has completely filled the void and
has risen for the full length of the form on the opposite side. Grouting shall take
place from one side only.

PROJECT NO. : 17.3866 DIVISION : CONCRETE SPEC. NO. : 03600


REVISION :A DATE : April 2018 PAGE : 3 of 3
BITA ENARCON ENGINEERING

HEAD OFFICE
Jl. Pahlawan No.74, Bandung – 40124, West Java, Indonesia
Phone : +62 227202748 (Hunt), Fax: +62 22 7202749
Email : bita@bita.co.id

JAKARTA OFFICE
Jl. Prof DR Satrio No.289, 3rd Floor Karet Kuningan, Jakarta – 12930, Indonesia
Phone : +62 21 5790 1030, 7093 1291, Fax: +62 21 5790 1291
Email : bita‐jkt@bita.co.id

YOGYAKARTA OFFICE
Jl. Palagan
Jl P l T t
Tentara P l j No.27, Yogyakarta –
Pelajar N 27 Y k t 55581, Indonesia
55581 I d i
Phone / Fax : +62 274 885370
Email : bita_yogya@bita.co.id

www.bita.id

You might also like