this chapter:
1. The shortest time necessary to complete all of the activities in a network is called the:
A. Activity duration length
B. Critical path
C. Maximum slack path
D. Compression path
2. Which of the following cannot be identified after performing a forward and backward pass?
A. Dummy activities
B. Slack time
C. Critical path activities
D. How much overtime is scheduled
3. Which of the following is not a commonly used technique for schedule compression?
A. Resource reduction
B. Reducing scope
C. Fast-tracking activities
D. U se of overtime
4. A network-based schedule has four paths, namely 7, 8, 9, and 10 weeks. If the 10-week path
is compressed to 8 weeks, then:
A. We now have two critical paths.
B. The 9-week path is now the critical path.
C. Only the 7-week path has slack.
D. Not enough information is provided to make a determination.
5. The major disadvantage of using bar charts to manage a project is that bar charts:
A. Do not show dependencies between activities
B. Are ineffective for projects under one year in length
C. Are ineffective for projects under $1 million in size
D. Do not identify start and end dates of a schedule
7. Reducing the peaks and valleys in manpower assignments in order to obtain a relatively
smooth manpower curve is called:
A. Manpower allocation
B. Manpower leveling
C. Resource allocation
D. Resource commitment planning
9. Optimistic, pessimistic, and most likely activity times are associated with:
A. PERT
B. GERT
C. PDM
D. ADM
10. The most common “constraint” or relationship in a precedence network is:
A. Start-to-start
B. Start-to-finish
C. Finish-to-start
D. Finish-to-finish
11. A network-based technique that allows for branching and looping is:
A. PERT
B. GERT
C. PDM
D. ADM
12. If an activity on the critical path takes longer than anticipated, then:
A. Activities not on the critical path have additional slack.
B. Activities not on the critical path have less slack.
C. Additional critical path activities will appear.
D. None of the above
13. Which of the following is not one of the three types of dependencies?
A. Mandatory
B. Discretionary
C. Internal
D. External
14. You have an activity where the early start is week 6, the early finish is week 10, the latest
start is week 14, and the latest finish is week 18. The slack in this activity is:
A. 4 weeks
B. 6 weeks
C. 8 weeks
D. 18 weeks