Professional Documents
Culture Documents
2. The person who may be ultimately responsible for approving the trade-off is the:
A. Project manager
B. Line manager
C. Project sponsor
D. Customer
4. If the start date of a project is delayed but the budget and specifications remain fixed, what
would the project manager most likely trade off first?
A. Scope
B. Time
C. Quality
D. Risk
BAB 18
1. According to learning curve theory, learning takes place at a fixed rate whenever the production
levels:
A. Increase higher than normal
B. Increase, but at a lower than normal rate
C. Double
D. Quadruple
3. On a 90 percent learning curve, the 100th unit required 80 hours. How many hours would
the 200th unit require?
A. 200
B. 180
C. 100
D. 90
2. A written or pictorial document that describes, defines, or specifies the services or items to
be procured is:
A. A specification document
B. A Gantt chart
C. A blueprint
D. A risk management plan
4. In which type of contract arrangement is the contractor least likely to want to control
costs?
A. Cost plus percentage of cost
B. Firm-fixed price
C. Time and materials
D. Purchase order
5. In which type of contract arrangement is the contractor most likely to want to control costs?
A. Cost plus percentage of cost
B. Firm-fixed price
C. Time and materials
D. Fixed-price-incentive-fee
6. In which type of contract arrangement is the contractor at the most risk of absorbing all
cost overruns?
A. Cost plus percentage of cost
B. Firm-fixed price
C. Time and materials
D. Cost-plus-incentive-fee
7. In which type of contract arrangement is the customer at the most risk of absorbing excessive
cost overruns?
A. Cost plus percentage of cost
B. Firm-fixed price
C. Time and materials
D. Fixed-price-incentive-fee
8. What is the primary objective the customer’s project manager focuses on when selecting a
contract type?
A. Transferring all risk to the contractor
B. Creating reasonable contractor risk with provisions for efficient and economical performance
incentives for the contractor
C. Retaining all project risk, thus reducing project contract costs
D. None of the above
9. Which type of contract arrangement is specifically designed to give a contractor relief for
inflation or material/labor cost increases on a long-term contract?
A. Cost plus percentage of cost
B. Firm-fixed price
C. Time and materials
D. Firm-fixed price with economic price adjustment
10. Which of the following is not a factor to consider when selecting a contract type?
A. Type/complexity of the requirement
B. Urgency of the requirement
C. Extent of price competition
D. All are factors to consider.
11. In a fixed-price-incentive-fee contract, the “point of total assumption” refers to the point in
the project cost curve where:
A. The customer assumes responsibility for every additional dollar that is spent in fulfillment
of the contract.
B. The contractor assumes responsibility for every additional dollar that is spent in fulfillment
of the contract.
C. The price ceiling is reached after the contractor recovers the target profit.
D. None of the above
12. A written preliminary contractual instrument prepared prior to the issuance of a definitive
contract that authorizes the contractor to begin work immediately, within certain limitations,
is known as a:
A. Definitive contract
B. Preliminary contract
C. Letter contract/letter of intent
D. Purchase order
13. A contract entered after following normal procedures (i.e., negotiation of terms, conditions,
cost, and schedule) but prior to initiation of performance is known as a:
A. Definitive contract
B. Completed contract
C. Letter contract/letter of intent
D. Pricing arrangement
14. Which of the following is not a function of the contract administration activity?
A. Contract change management
B. Specification interpretation
C. Determination of contract breach
D. Selection of the project manager
15. A fixed-price contract is typically sought by the project manager from the customer’s organization when:
A. The risk and consequences associated with the contracted task are large and the customer
wishes to transfer the risk.
B. The project manager’s company is proficient at dealing with the contracted activities.
C. N either the contractor nor the project manager understand the scope of the task.
D. The project manager’s company has excess production capacity.
16. Which of the following are typical actions a customer would take if the customer received
nonconforming materials or products and the customer did not have the ability to bring the
goods into conformance?
A. R eject the entire shipment but pay the full cost of the contract
B. Accept the entire shipment, no questions asked
C. Accept the shipment on condition that the nonconforming products will be brought
into conformance by the vendor at the vendor’s expense.
D. Accept the shipment and resell it to a competitor
17. If a project manager requires the use of a piece of equipment, what is the breakeven point
where leasing and renting are the same?
Cost Categories Renting Costs Leasing Costs
Annual maintenance $ 0.00 $3,000.00
Daily operation $ 0.00 $ 70.00
Daily rental $100.00 $ 0.00
A. 300 days
B. 30 days
C. 100 days
D. 700 days
18. In which type of incentive contract is there a maximum or minimum value established on
the profits allowed for the contract?
A. Cost-plus-incentive-fee contract
B. Fixed-price-incentive-fee contract
C. Time-and-material-incentive-fee contract
D. Split-pricing-incentive-fee contract
19. In which type of incentive contract is there a maximum or minimum value established on
the final price of the contract?
A. Cost-plus-incentive-fee contract
B. Fixed-price-incentive-fee contract
C. Time-and-material-incentive-fee contract
D. Split-pricing-incentive-fee contract
21. Using the same data from Problem 20, and the same contract type, how much will the contractor
be reimbursed if the cost of performing the work is $85,000?
A. $97,000
B. B. $99,000
C. C. $112,000
D. $114,000
22. Using the same data from Problem 20, and the same contract type, how much will the contractor
be reimbursed if the cost of performing the work is $120,000?
A. $112,000
B. B. $119,000
C. C. $126,000
D. $129,000
24. Using the same data from Problem 23, and the same contract type, how much will the contractor
be reimbursed if the cost of performing the work is $102,000?
A. $104,000
B. B. $107,400
C. C. $109,400
D. $110,000
25. Using the same data from Problem 23, and the same contract type, how much will the contractor
be reimbursed if the cost of performing the work is $105,000?
A. $105,000
B. B. $106,500
C. C. $110,000
D. $111,500