Professional Documents
Culture Documents
In a project one has to deal with numerous contracts. These contracts are awarded depending on
the diversity of activities pertaining to the project, spread of the area involved, availability of
agencies etc. For example, in a typical gauge conversion or laying of new track project of the
railways, there may be a separate contract for each of the major bridges, tunnels, earthwork and
minor bridges. There are contracts for supply and laying of ballast. There are numerous
transportation contracts. There are welding contracts as also several contracts for supply of track
material, signaling equipment, telecom and electrical works. The failure of one of the contracts
could result in delay of the whole project. Hence the number of contracts in a 100 km track-
laying or gauge conversion project of railways could be typically between 60 and 100. Every
contract is typical in its contents.
The popular types of civil engineering works, project contracts are the following:
Under GMC, the parties agree in advance that if the costs exceed a certain
estimated maximum sum, the contractor does not get his percentage on such
excess. Under SSP if there is a saving from the estimated project cost for
execution, the owner and the contactor share such savings at a pre-agreed ratio.
5. Performance-based contracts: Construction + AMC(Annual Maintenance
Contract) for six years. Thus construction is linked to maintenance. During
construction the performance indicators and their weights are defined. Here
surveillance reports certifying performance is essential which guarantee
1
progressive payments. For e.g. for the construction of a road the performance
indicators could be the following:
a) Lane Painting: 15% payment
b) Installation of road signs: 15% payment
c) Street Lighting: 20% payment
d) Road Leveling: 50% payment
Here, if lane painting is not done, 15% payment is cut.
2
often provide a stand-by loan facility for any cost overruns not covered
by the construction contract.
f) Equity investors
g) Other parties: Insurers, equipment suppliers, engineering and design
consultants, project monitoring consultants etc.
7. BOT Contracts: These are Build-Operate-Transfer Projects also known as DBFO
( Design-Build-Finance-Operate) Projects. In this type of project the Sponsor
never owns the assets that are used to provide the project services. However the
Sponsor constructs the project and has the right to earn revenues from the
operations of the project. This structure is used where the public nature of the
project may make it inappropriate for a private-sector sponsor to own the assets –
like in the case of a tunnel or a bridge etc.
8. BOO or Build-Own-Operate Projects: These are projects where the ownership
remains with the private-sector project sponsor throughout the life of the project –
for example a power station in the private sector or a mobile phone network. Here
the sponsor gets the benefit for any residual value of the project.
In the last three types of Projects explained above, the most important contract
entered with the pivotal government agency is that which provides the framework
under which the project obtains its revenues. The two main models for such a project
agreement are:
3
a pre-fixed or a pre-indexed price. This type of contracts may be
entered when the product is a easily saleable one like oil, gas etc..
d) Hedging Contract: This is found mostly in commodity markets such as:
i) A long term forward sale of the commodity at a fixed price.
ii) An agreement on a certain floor level price in case the prices
fall below this level. If the price is above the floor price then
the product could be sold in the open market.
iii) An agreement of both a floor level and a ceiling price. If the
price is below the ceiling or above the floor price, then the
product could be sold in the open market. In this way the
project is assured of a minimum level of income and at the
same time does not benefit additionally when the prices breach
the ceiling.
iv) Contract for Differences (CfD): Under the CfD agreement the
Project Company sells its product only in the market and not to
the offtaker. If however the product price goes below a certain
level, the offtaker pays the difference to the Project Company
and vice-versa.
v) Throughput Contract: This is used, for example in Pipeline
Contracts where the user agrees to carry not less than a certain
volume through the pipeline and pay a minimum price for this.
4
The Tariff structure however leaves any costs of inefficiency on the part of
the Project Company. These could typically be:
1) Project Overrun Costs: If the projects costs more than the agreed sum
and hence perhaps more financing and more interest payments than
were earlier envisaged.
2) Non-Availability: If plant is not available for operation for the
committed time then revenues are lost and perhaps penalties are to be
paid.
3) Higher Operating Costs: If the plant does not operate at the expected
levels of efficiency.
Escalation of Tariff: this provides for tariff escalation clause during the
projected long-term life of the agreement.
The public sector entity with whom the concession agreement is signed could be a
national or a regional government, a municipality, a state entity set up by the state
to grant the concession.
Concession agreements for the above types of services can be divided into two
classes:
1. Service Contracts: This is where the project has to provide a service and the
Contracting Authority will pay for these services. Payments are made for the
availability of the project for the services to be rendered, but a split between the
variable charge and the fixed charges is not as easily defined as in the case of an
5
offtake agreement. Hence, normally one payment is made for the provision of the
facility as a whole.
The main issue that arises in a service contract is how to define the availability of
a service. Availability is relatively easier to measure in case of equipment but
difficult to define in the case of a public building or a hospital. Calculation of
pro-rata share of loss of availability is even more difficult if part of a building is
still available for the service. However some project-specific definitions are
worked out for this purpose and certain quality requirements are also set.
2. Toll Contracts:
i) Real Tolls: Here the concession agreement gives rights to the concessionaire to
collect tolls or fares from the general public. Typically the terms of such a
concession agreement are:
The Project Company (i.e. the Sponsor) is obliged to complete the project
to an agreed specification by an agreed date.
The government body makes available the land and rights of way required
for the concession.
Ownership of project facilities atleast the immovable portion) remains
with the public sector ( BTO/BOT Projects)
The concession is granted for a fixed period of time during which the
government authority agrees not to give competing concessions to another
party.
Operation and Management of the concession is in the hands of the
project company.
A maximum tariff is fixed with indexation for inflation within which the
project company sets the actual tariff.
Minimum service provisions are specified relating to the availability and
quality of service.
Project Companies are liable for heavy penalties for breach of safety
standards.
Although the maximum term for the concession is fixed, if the debts are
repaid and the investors have earned their agreed rates of return, the
concession may be terminated. This takes care of cases where actual
returns from a project are way higher than the projected returns, rather
because of extraneous factors than because of the quality of service
provided by the project company and hence the investors should not earn
excessive profits.
In case the usage level may not be adequate to finance the project a
minimum guarantee clause assures a rate of return good enough to attract
investors.
6
ii) Shadow Tolls: This is resorted to when payment by the contracting authority
directly to the project company becomes necessary due to the following:
Direct levying of tolls is too complex, for example in the case of a road
network.
Traffic flows would be distorted by drivers trying to use alternative routes
where tolls are not paid.
Traffic flows too small.
There is public opposition to payment of tolls.
In such cases the project company is paid according to usage ( say so much per
passenger or car kilometers). The payment formula is often on a diminishing
sliding scale.
7
Each project document will contain an allocation of risks to the contracting parties. For
example, if the construction company’s obligations are simply to design and construct the
infrastructure, with the commissioning obligation lying with the operator, agreement will need to
be reached between the construction company and the operator company as to when each party’s
liabilities commence and finish. If the Operator is liable for liquidated damages, or delays in
commissioning, it will want to ensure that its commissioning period does not commence until
such time that the construction company has satisfied all of its obligations under the construction
contract.
It is therefore critical that all parties carry out a review of all documents and the risk
allocation inherent in them.
**************************