Professional Documents
Culture Documents
ASEM ELGAWHARY
JANUARY 2018
PESCO
JANUARY 2018
1.0 INTRODUCTION
However any Build, Own & Operate (BOO) project involves risks including
country risks, commercial risks, and force majeure risks. The developer carries
a risk as it provides 25-30 percent of the project’s capital, while the larger
burden falls on the lender who finances 70-75 percent of the project.
Finally, to ensure the smooth progress of the program and using BOO projects
as a tool for economic growth the following points should be taken in
consideration:
The BOO model offers several benefits to the host country as well as to private
companies. Some of the major advantages are:
PESCO
2 JANUARY 2018
I. Power Energy Users: the most important participant in any BOO
scheme is to secure the appropriate Energy Users for the projects.
These users must be fully committed to the project, which must enter into
multiple of Power Purchase Agreement (PPA) with the Project Company.
This is intern will facilitate the project financing. The Egyptian Electricity
Transmission Company (EETC) can play an important role as user for
part of the project generated Energy based on previous approved tariff
and through a banking instrument as shown in attachments 1 of 2.
PESCO
3 JANUARY 2018
possible future improvements and repairs, measurements of
performance efficiency and maintenance requirements.
D. Lenders: The sponsors contribute a sizable equity to the project
and the remaining required funds come mainly from commercial
banks, international financial institutions, and private international
and national investors.
The price of the electricity purchased from a private power producer is known
as the tariff, and is separated into capacity and energy components. These are
defined as the costs of constructing and operating the power and desalination
plant respectively. The tariff structure is a two-part tariff which includes a
capacity charge and an energy charge (defined below and should yield mutual
benefits to the project developer and the power purchaser). With the provision
of the purchaser’s right to dispatch the plant, the purchaser will be held
responsible to provide a capacity payment to the producer in case the plant is
not called upon to provide energy. In case the plant is called on the purchaser
will pay for the energy provided in addition to the capacity payment. The
combined tariff should cover all the development costs in addition to providing
a satisfactory profit to the electricity producer.
Capacity charges are set to cover he fixed costs, project’s capital and investor
returns incurred by the project regardless of whether the plant is called on to
provide energy or not. The capacity purchase price will vary annually to the
level of plant reliability.
PESCO
4 JANUARY 2018
Project Capital Costs:
These include project development and construction costs including pre-
feasibility, engineering, legal and auditing services.
Fixed operating and maintenance costs:
These include maintenance activities, spare parts costs, overhauls,
management fees salaries and any other operating costs.
Financing costs:
Group the costs of servicing the debt interest and principal payments or
the total borrowing in addition to any extra financial fees such as letter of
credit charges, project monitoring costs, interest and exchange rate
hedging costs.
Insurance costs:
Cover costs incurred for possible risks such as fire, theft, workers’
compensation, insurance, political risks and force majeure threats.
Equity shareholder returns:
Comprise costs incurred to provide for returns to investors on their paid in
capital in the construction and operating phases. The return sought by
investors will vary according to their perceived risks.
The energy charge is set to provide enough revenue to cover fuel costs and
variable operating and maintenance expenses. It will vary depending on the
amount of energy that is actually delivered to the power purchaser. This price
will only be paid in case the plant is called on to provide energy. A typical
energy charge will include the following elements:
Fuel costs:
Refer to the costs incurred to obtain the fuel required to generate
electricity. Lower fuel costs can be achieved if the power purchaser is
responsible for ensuring quantity and the price was optimally set on the
basis of competitive supply.
Variable operating and maintenance costs:
The costs incurred to generate electricity per unit running hour. They
can be forecasted on the basis of the expected level of output as
derived from the country’s least cost expansion plan. Other extra
costs might be incurred and charged as stated in the power
purchase agreement or as agreed upon informally.
As mentioned above, the obligations of the parties under this agreement will
be in effect only if the Fuel Supply Agreement is in effect. The company
cannot sell electric energy produced by the complex to any other entity other
than the identified parties by host government. Also under the terms of this
contract, the end users acknowledge that the project company may contract
PESCO
5 JANUARY 2018
with another Construction Contractor and also with a specified Operations
and Maintenance Contractor.
PESCO
6 JANUARY 2018
PESCO
7 JANUARY 2018