Professional Documents
Culture Documents
Tutorial 3
Tutorial 3
1. List down and discuss the various types of certificates an architect is empowered to
issue in a building contract
-Interim Certificate, this certificate issued is to allow the contractor to claim payment of
work done from the client or developer. In the PAM2018 clause 30, the contractor
submitted a payment application for interim claim with the complete details and particulars
as required by the Architect or Consultant Quantity Surveyor. Then, the Architect or CQS/
M&E Engineer will go to the site to ascertain the amount claimed by the contractor. CQS
is to issue a valuation certificate including M&E Enginneer’s recommendation to the
Architect within 7 days and upon receipt of CQS valuation certificate; the Architect must
issues Architect Certificate to the employer within 21 days from receipt of contractor’s
claim. After receipt of the Architect certificate; the employer shall need to pay the amount
certified to the Contractor within the Period of Honoring Certificates.
-Final certificate, this certificate is issued by the Architect signifies that the Contractor has
completed his various obligations under the contract. This certificate shall be issued upon
the issuance of the Certificate of Making Good Defects and the Consultant Quantity
Surveyor must also complete the Final Account within the period as stipulated. Moreover,
the period to complete the final account by CQS is stated in the appendix. If none is stated
it shall be 15 months from the date of Certificate of Practical Completion. The final
payment to Contractor; Architect shall issue a Final Certificate to the Employer.
Additionally, Final certificate shall be issued within 28 days after Certificate of Making
Good Defects has been issued or within 21 days after the period of honoring of certificate
for the payment of the Penultimate Certificate. Final Certificate contains final payment to
Contractor based on the Final Account less all sums certified in previous payment
certificates to Contractor.
-Penultimate certificate
Once the penultimate certificate has been issued, it means that there is no more work
to evaluate and trigger the final progress payment. Only remains the final certificate that
has not been issued by the Architect. This certificate is required to be issued by an
Architect not later than fourteen days after the Certificate of Making Good Defects has
been issued for penultimate payment. The difference between penultimate certificate and
normal certificate for a progress payment is that the half of the retention sum which is 2.5%
has been released. Apart from this, the penultimate payment shall be made by the
Employer within the period of honoring certificate (21days). There will be no further
payments will be made until any of the defects have been rectified and the final certificate
is issued. At this point, the final payment will be made, including the release of the
remaining retention fund.
Discuss the provisions in a building contract on the responsibility of the employer and the
contractual rights of the contractor if the employer defaults in honoring the architect
interim certificate.
A provision is a legal clause that is designed to protect the interests of one or all
of the parties involved in a building contract. As an employer, he/she has the responsibility
of taking one of the important provisions that should be listed on the building contract
which is the contingent payment provisions. The contingent payment provisions had a
common concern among contractors in the construction industry is the risk of non-
payment for work that has been completed. If the provision is clearly expressed as setting
a condition precedent in which the general contractor is not obligated to pay the
subcontractor unless payment is received by the employer, it is considered a pay-if-paid
provision.
Interim Certificates are being used oftenly in the building construction contracts
and it is only to be issued by the architect at regular intervals based on periodic estimates
of the value of works properly executed and materials and goods supplied for the works.
In order to arrive at an amount due in interim certificates, interim valuations are to be
carried out upon receipt of the contractor’s claim with details and particulars.
In addition to issuing the Interim Certificate, the Architect is also required to direct
the Contractor as to the amounts payable to any of the Nominated Sub-Contractors and
Nominated Suppliers under the Interim Certificate. Other than that,the Architect also
informs or notify the relevant Nominated Sub-Contractor and Nominated Supplier as to
the amounts due to them under the Interim Certificate.