Professional Documents
Culture Documents
Planning of Major Fixed Links....
Planning of Major Fixed Links....
Planning of Major
Fixed Links
4.1 Introduction.........................................................................................77
Characteristics of Fixed Links • Cost-Benefit Evaluations • Project
Procurement • Technical Development • Fixed Link Examples
4.2 Feasibility..............................................................................................80
Political Aspects • Benefits • Impacts • Constraints and Legal
Requirements • Decision Making
4.3 Procurement.........................................................................................86
Financing and Ownership • Procurement Strategy • Contract
Packaging • Examples of Procurement Conditions
4.4 Technical Development......................................................................89
4.5 Basic Conditions..................................................................................89
Introduction • General Requirements • Site Conditions
4.6 Design Development and Technical Follow-Up.............................96
Screening Studies • Feasibility and Concept Study • Tender
Erik Yding Design • Detailed Design • Follow-Up during Construction
Andersen 4.7 Tendering and Contracting..............................................................100
Tender Evaluation
cowi a/s
4.8 Construction and Commissioning................................................. 101
Lars Hauge 4.9 Operation, Maintenance, and Transfer.......................................... 101
cowi a/s Very Long Fixed Links
4.10 Fixed Link Examples.........................................................................102
Dietrich L. Hommel Great Belt Link • Øresund Link • Fehmarn Belt Link
cowi a/s References....................................................................................................... 111
4.1 Introduction
4.1.1 Characteristics of Fixed Links
Within the infrastructure of land transportation, “fixed links” are defined as permanently installed
structures allowing for uninterrupted passage of a certain volume and composition of traffic with ade-
quate safety, efficiency, and comfort. The fixed links often cross large stretches of water, but may also
comprise significant land works, for example, when circumventing congested city areas.
77
78 Bridge Engineering Handbook, Second Edition: Fundamentals
of a fixed link usually have a strong, positive impact on the industrial and economic development of the
areas to be served by the link. The beneficial effects shall be assessed against costs, impacts, and con-
straints given for the project, as described further in Section 4.2, in order to reach decisions for project
development. This is a task that shall be managed directly by the responsible authority, though some of
the practical work may be left to independent entities.
FIGURE 4.1 Rendering of the proposed multi-span suspension bridge connecting Yemen and Djibouti. (Courtesy
of Dissing+Weitling architecture.)
Planning of Major Fixed Links 79
4.2 Feasibility
Major fixed links represent important investments for the society and have considerable influence on
the development potentials of the areas they serve.
Common to major infrastructure projects is that the responsible authority or political entity for
infrastructure development must rank the items in the portfolio of potential projects. And often the
task also comprises a ranking between alternatives for the individual projects. The ranking process is
based upon cost-benefit assessments with content as lined out in Table 4.2.
In order to carry out the feasibility studies comprising the elements in Table 4.2, it is necessary to have a
description of the project in question, that is the design must be developed in parallel—to a detailing level
depending on the progression of the project discussions—as described separately in Sections 4.4 through 4.9.
4.2.2 Benefits
4.2.2.1 Improved Traffic Capacity
In order to assess the beneficial impact of a new fixed link the demand for the improved traffic capac-
ity must be assessed and used to model the future traffic patterns and volumes. In case a tolled link is
considered the willingness to pay for use of the link must be included in the assessments. Such traffic
analyses may be performed at an early stage where the design development of the link is at a sketch level
only. The results will be crucial to the evaluations of the beneficial socio-economic effects.
FIGURE 4.2 Fehmarnbelt conceptual design for cable-stayed bridge for road and rail. Example of project with
landmark quality. (Courtesy of Dissing+Weitling architecture.)
4.2.3 Impacts
4.2.3.1 Costs
The estimated cost is decisive for the decision on undertaking the construction of the link, for selection
of solution models, and for the selection of concepts for tendering. The cost estimate may also be impor-
tant for decisions of detailed design items on the bridge.
The uncertainty is in principle to be defined for each single input to the cost model. The uncertainty
is taken as the Bayesian understanding of the contribution, in which the variations because of lack of
knowledge is allowed to be included. Especially, early in the planning, unsettled basis for the design may
be part of the uncertainty.
The risks for construction cost add-ons can in principle be taken from a construction risk analysis.
Furthermore, it shall be noted that only the part of the construction risk that has impact on the con-
struction cost shall be included. The risk for operational cost add-ons can in principle be taken from an
operational risk analysis.
The risk estimation will result in a best estimate of the contribution from risk items to the cost, the so-called
risk add-on, and this value will be associated with uncertainty. The other uncertainties may also influence
the best estimate of the cost, but their main purpose is to illustrate the distribution of the cost estimate.
investigations and assessments shall take place early in the project period—and may occasionally be on
the critical path of fast track projects.
4.2.3.2.1 CO2 Footprint
The carbon dioxide footprint of infrastructure projects attracts increasing focus in the climate debate
and it is expected that a CO2 account will be required for all major infrastructure projects in order for
the public to assess the climatic impact of the project. The list of contributors to the CO2 account is long;
however, the dominating contributors are expected to be from production of the constituent materials
of an infrastructure project, which is mainly steel and concrete.
It may be valuable just to document that attention has been given to the CO2 footprint, for example,
by specifying work methods and design solutions with a small or minimum contribution.
of alternatives may be pursued. The selection of parameters for which it is most appropriate to make
more detailed analyses can be made on the basis of a sensitivity analysis of the parameters with respect
to the utility. Risks may be regarded as uncertain events with adverse consequences. Of particular inter-
est are the different risk pictures of the alternatives. These risk pictures shall be quantified by the use of
preferences so that they can be part of the comparison.
At a later phase, decisions will have to be made on which models to select for tender design, and later
in the tender evaluation, to which tenderer to award the contract. In these comparisons the basis and the
input shall be well established, as the comparison here shall be able to select the single best solution with
sufficient accuracy. A weighting of criteria is necessary. A strictly rational weighting and conversion of
these criteria directly into terms of economical units may not be possible. It is normally regarded suf-
ficient, if the weighting and selection process are indicated to the tenderers before the tender.
4.3 Procurement
4.3.1 Financing and Ownership
The responsible authority for infrastructure will be the long-term owner of the infrastructure projects.
However—provided sufficient revenue can be generated from operation of the new infrastructure to
finance the construction and operation in a certain period—the authority will have the option either
to maintain ownership himself or to give a concession to a third party who will then finance, establish,
own, and operate in a concession period until final transfer of the ownership to the responsible authority.
The following attempts to provide a short overview of various concepts that are to be considered in
the definition of the procurement strategy for a fixed link project.
Basically the contract is a DB contract for which two very detailed illustrative designs had been devel-
oped for tendering. After floating the tender, the owner carried through a Competitive Dialogue Process
with the two tendering groups in which all significant design issues were raised and discussed between
the owner and the contractor (but not disclosed to the competing group). The owner could reject solu-
tions he would not accept and in certain cases adjust the employers’ requirements in order to reach a full
clarification. Such changes in the employers’ requirements would be revealed to the competing group
immediately. In this way the owner assured a close interaction with the tenderers in their development
of the designs to his satisfaction. The final bid received from the tenderers would hence be fully compli-
ant as all reservations should be clarified in advance. The Competitive Dialogue Process will of course
require resources and time, but it may overall be cost efficient for the owner—even if he pays a signifi-
cant amount for the tenderers’ bid design development.
may change during the process). The Scandinavian projects—Great Belt, Øresund and Fehmarn—are
described in more detail in Section 4.10.
TABLE 4.4 Components of Technical Development and the Related Time Phases (Not to Scale)
Functional Requirements/Site Data/Codes and Standards/
Basic Conditions Constraints
Design development and technical follow-up Alignment → concept → basic → detailed → execution →
follow-up → supervision
Tendering and contracting Tendering → bidding → evaluation → contract award →
final pricing
Construction and commissioning Selection → mobilization → construction →
commissioning
Training, operation, and maintenance Planning → training → operation and emergency
Planning → training → inspection and maintenance
90 Bridge Engineering Handbook, Second Edition: Fundamentals
way, that is included in the basis together with the technical and economical aspects. Risks are often
studied separately according to the consequences of concern, for example:
• Economical risk (rate of interest, inflation, budget overrun, and changed traffic pattern)
• Operational risk (accidents, loss of lives, impact to environment, disruption of the traffic, loss of
assets, and loss of income)
• Construction risks (failure to meet time schedule or quality standards, unexpected ground condi-
tions, and accidents)
Economical risks in the project may be important for decisions on whether to initiate the project at
all. The construction risk may have important implications on the selection of the structural concept
and construction methods.
System definition
Hazard identification
Risk estimation:
Frequency Consequence
Risk-acceptance Risk-reducing
analysis analysis
criteria measures
Risk picture
Risk Unacceptable
evaluation
Acceptable
Final system
to develop and maintain an accurate accounting system for the risks and to plan to update the risk
assessment in pace with the project development. It should be noted that any risk evaluation implies an
inherent or direct assessment of preferences.
In the following, three common risk evaluation methods are discussed: fixed limits, cost efficiency,
and ALARP.
Fixed limits are the classical form of acceptance criteria. Fixed limits are also known from legislation
and it may easily be determined whether a determined risk is acceptable or not. However the determina-
tion of limits, which can ensure an optimal risk level, may be difficult.
With pure cost efficiency consideration an upper limit is not defined; but all cost efficient risk reduc-
ing measures are introduced. For this cost-benefit consideration, it is necessary to establish direct quan-
tification of the consequences in units comparable to costs.
The ALARP method—As Low As Reasonably Practicable—applies a cost-benefit consideration in
which it, however, is stated that the risk shall be reduced until the cost of the reduction measures is
in disproportion with the risk reducing effect. This will result in a lower risk level than the pure cost
efficiency. In ALARP a constraint of the acceptable risk is further introduced as an upper limit beyond
which the risk is unconditionally unacceptable. This constraint will not be coincident with the upper
limit in the fixed limit methodology.
Often it is claimed that society regards 1 accident with 100 fatalities as worse than 100 accidents
with each 1 fatality. Such risk aversion attitude can be introduced in the risk policy and the risk accep-
tance criteria. The aversion against large accidents can also be modeled with aversion factors that are
multiplied on the consequences of accidents with many fatalities; the more fatalities the higher the
factor.
The sensitivity of the evaluations of risk should be considered by a due representation of the uncer-
tainty of the information in the models.
acquired with a few minutes interval access to the data will provide extremely valuable information
about sailing patterns, tonnages, and so on for use in a ship collision analysis.
to a desired level of safety. The following wind climatic data should be available for a particular site for
design of wind sensitive bridge structures.
Mean wind
• Maximum 10 minutes average wind speed corresponding to the design lifetime of the structure
• Vertical wind speed profile
• Maximum short duration wind speed (3 seconds gust wind speed)
Turbulence properties (along-wind, cross wind lateral, and cross-wind vertical):
• Intensity
• Spectral distribution
• Spatial coherence
The magnitude of the mean wind will govern the steady state wind load to be carried by the bridge
structure and be determinant for the development of aeroelastic instability phenomena. The turbulence
properties will govern the narrow band random oscillatory buffeting response of the structure, which is
similar to the sway of trees and bushes in storm winds.
and standards typically do not cover important lifeline structures such as a fixed link, but they may be
used for inspiration for the development of a design basis. A site-specific seismic hazard analysis is usu-
ally carried out for a major bridge project and corresponding design criteria are developed.
shall be developed in a preliminary design and described through drawings and text. It is recommended
to start an architectural study of the solutions in the feasibility studies. The feasibility study shall further
include the definitions and constraints for operation and maintenance, and present the major construc-
tion stages.
Mechanical and electrical installations as well as utilities and access facilities have to be considered as
early in the project phases as possible. These elements often have influence on the geometric layout and
provide other constraints for the project. For instance is proper access, for example, through elevators in
towers and inspection vehicles, vital for later operation and maintenance. The extent of these elements
varies from project to project depending on the traffic modes and on the length of the link. Specific
reference to these elements is not made in the following sections.
The feasibility study phase is concluded by a comparison analysis that provides the technical ranking
of all solutions.
It is important that accidental loads, for instance vessel collision, train derailment, cable rupture,
earthquake, and ice are considered in the tender design phase as they are often governing for the design.
Durability, operation, and maintenance aspects should be considered in the tender design. Experience
from operation and maintenance of similar bridges is an advantage, because it allows a proper service
life tender design to be carried out based on past experience. It is at the early design stages that the con-
structions methods are chosen that have a significant effect on further O&M costs.
It is not unusual that a tender design is prepared for more than one solution to arrive at the optimal
solution. It could for instance be two solutions with different materials (concrete and steel) as for the
Great Belt, East Bridge, two solutions with traffic arranged differently (one level versus two levels) as
for the Øresund Link. Different structural layouts, such as cable-stayed or suspension bridge versus
immersed or bored tunnel, could be relevant to investigate under certain conditions, such as for the
Fehmarn Belt Fixed Link. After the designs have been prepared to a certain level, a selection can be car-
ried out based on a preliminary pricing. Depending on the situation and owners preferences, only one
solution or more solutions may be brought all the way to tender.
Tender documents to follow the drawings have to be prepared. The tender documents typically com-
prise bill of quantities, special specifications, and so on.
The operation and maintenance objectives in the detailed design have to be implemented in a way that
• Give an overall cost-effective operation and maintenance
• Cause a minimum of traffic restrictions because of O&M works
• Provide optimal personnel safety
• Protect the environment
• Allow for an easy documentation of maintenance needs and results
In addition, the contractor has to provide a forecast schedule for the replacement of major equipment
during the lifetime of the bridge.
1. Preparation
2. Compilation and checking of tenders
3. Evaluation of tenders
4. Preparation for contract negotiations
5. Negotiation and award of contract
The preparation phase covers activities up to and including the receipt of tenders. The main activities
are as follows:
• Define tender opening procedures and tender opening committee.
• Quantify the differences in present value because of function, operation, maintenance, and own-
er’s risk for each of the tendered projects, using the owner’s cost estimate.
After receipt of tenders a summary report, as a result of compilation and checking of tenders, should
be prepared to summarize tender sums. The objective of this report is to collect the information sup-
plied in different tenders into a single summarizing document and to present a recommendation of
tenders for detailed review.
Typical activities among others are as follows:
• Check completeness of compliance of all tenders, including arithmetical correctness and errors
or omissions.
• Identify possible qualifications and reservations.
• Identify parts of tenders where clarification is needed or more detailed examination required.
• Prepare a preliminary list of questions for clarification by the tenderers.
• Review compliance with requirements for alternative designs.
• Upgrade alternative tender design and pricing to the design basis requirements for tender design.
The evaluation of tenders in addition to activities already carried out among others, includes:
• Tender clarification by initial submission of questionnaires to tenderers, followed by clarification
meetings and subsequent receipt of tenderers’ written clarification answers
• Adjustment of tender prices to a comparable basis taking account of revised quantities because of
modified tender design effects of combined tenders, alternatives, options, reservations, and dif-
ferences in present value
• Appraisement of the financial components of the tenders
• Appraisement of owner’s risk
• Technical review of alternatives and their effect on interfaces
• Appraisement of the proposed tender time schedule
• Appraisement of proposed subcontractors, suppliers, consultants, testing institutes, and so on
• Review of method statements and similar information
• Establishment of list of total project cost
The objective of evaluating owner’s risk should be to assess possible overruns in cost and time. An
evaluation of the split of economical consequences between contractor and owner should be carried out.
Risk and uncertainty are inherent in all construction works, and especially in works of exceptional size.
Planning of Major Fixed Links 101
Preparation for contract negotiations should be performed as late as possible allowing all aspects for
the actual project type that can be taken into account. Typical activities should include the following:
• Modify tender design to take account of current status of the project development so as to estab-
lish an accurate contract basis.
• Modify tender design to accommodate alternatives.
• Liaise with third parties regarding contractual interfaces.
• Liaise with interfacing authorities.
• Establish strategies and recommendations for contract negotiations.
The probable extent and nature of the negotiations will become apparent from the tender evaluation.
Typical activities during negotiations and award of contract are as follows:
• Preparation of draft contract documents
• Clarification of technical, economical, and legal matters
• Finalizing contract documents
4.7.1.2 Design-Build
The main goal is shared with the DBB approach to award a contract for construction of a fixed link.
Many of the elements mentioned in the Section 4.7.1.1 will hence also be part of the tendering process
for a DB contract. The approach selected by owners for carrying through the tendering process for a DB
contract cannot be described quite as schematic as the sequence of DBB tender evaluation activities.
Common to all approaches is that the owner wishes to open up for the contractors’ participation in
and response for the design process in order to gain benefits from the special skills and qualifications
of the individual contractor. Hence a common characteristic of tender documents for a DB contract is
that functional and geometrical requirements are very well described, the design basis is extensive, and
eventually great effort has been placed on definition of the work process to follow until a contract is
awarded and the rules of this game condensed into the employers’ requirements.
Situations may arise where users need to turn around and return to the origin of the fixed link.
Facilities for such situations should be evaluated.
The situation is of special importance in case of emergencies where time is critical, as it would be
detrimental to injured traffic victims if rescue vehicles should run the whole length of the fixed link.
Facilities for turn around for emergency vehicles should be considered as well as the option to approach
an emergency area opposite the normal traffic flow—provided pertinent traffic control systems are in
place. Also helicopter-pads for efficient transport of injured persons should be considered.
Sweden
Denmark
Copen-
hagen
Great Øresund
Belt Link Link
Fehmarn
Belt Link
Germany
FIGURE 4.4 Denmark with the national Great Belt Link, the Øresund Link to Sweden and the Fehmarn Belt Link
to Germany. (Courtesy of COWI A/S.)
Planning of Major Fixed Links 103
4.10.1.1 Organization
The company A/S Storebæltsforbindelsen was established January 23, 1987 on the basis of an agreement
of June 12, 1986 between political parties, forming a majority in the Danish Parliament. The company
was registered as a limited company with the Danish State as sole shareholder. The purpose of the com-
pany was to plan, design, implement, and operate the fixed link.
The management of the company was organized in accordance with the Danish Company Act and
consisted of a supervisory board, appointed by the shareholder, and management, appointed by the
supervisory board. The management consisted of three directors: the managing director, the technical
director, and the finance director.
The line organization consisted of a number of project organizations, each headed by a project direc-
tor who was responsible to the management for planning, design, and construction of his specific part
of the link.
FIGURE 4.5 The Great Belt Fixed Link. Combined road and rail low-level West Bridge in foreground, East Bridge
suspension road bridge, and ramp to the East Tunnel for railway. (Courtesy of Sund & Bælt Holding A/S.)
104 Bridge Engineering Handbook, Second Edition: Fundamentals
The project is financed by government guaranteed commercial loans to be paid back via user tolls.
The pay-back period for the highway part is estimated to 15 years, whereas the railway crossing is to be
paid by the Danish State Railways over 30 years in fixed installments per year.
From 1989 to 1990 outline design, tender design, and tender documents were
prepared with the main focus on navigation safety and environmental
considerations. Comparative studies of four alternative main bridge concepts
were carried out to thoroughly evaluate the technical, economical, and
environmental effects of the range of main spans:
Cable-stayed bridge 916 m main span
Cable-stayed bridge 1204 m main span
Suspension bridge 1448 m main span
Suspension bridge 1688 m main span
Navigation risk studies found only the 1688 m main span adequate to cross the existing navigation
route without affecting the navigation conditions negatively.
A 1624 m main span suspension bridge with side spans of 535 m across a 78° relocated navigation
route was chosen for tender and construction.
The pylons were tendered in both steel and concrete. For the approach bridges’ superstructure, 124 m
long concrete spans and 168 m long steel spans as well as composite steel/concrete concepts were devel-
oped. Although an equally competitive economy was found, it was decided to limit the tender designs to
concrete and steel spans. However, the tenderers were free to propose hybrid solutions.
The tender documents were subdivided into four packages to be priced by the contractors; super-
structure and substructure inclusive pylons for the suspension bridge, and superstructures and sub-
structures for the approach bridges. The tender documents were released to prequalified contractors and
consortia in June 1990.
In December 1990 the tenders were received. Eight consortia submitted 32 tenders, and four alterna-
tives to the basic tender design.
In October 1991 construction contracts were signed with two international consortia; a German,
Dutch, and Danish joint venture for the substructures, inclusive concrete pylons, and an Italian contrac-
tor for an alternative superstructure tender where high strength steel where applied to a more or less
unchanged basic cross section, thereby increasing the span length for the approach bridges from 168 to
193 m (see Figure 4.6).
The suspension span is designed with a main cable sag corresponding to 1/9 x span length. The steel
bridge girder hangs from 80 cm diameter main cables in hangers each 24 m.
The girder is continuous over the full cable-supported length of 2.7 km between the two anchor
blocks. The traditional expansion joints at the tower positions are thus avoided. Expansions joints
are arranged in four positions only—at the anchor blocks and at the abutments of the approach
bridges.
Planning of Major Fixed Links 105
FIGURE 4.6 Great Belt, East Bridge, Denmark. (Courtesy of Sund & Bælt Holding A/S.)
The concrete pylons rise 254 m above sea level. They are founded on caissons placed directly on
crushed stone beds.
The anchor blocks shall resist cable forces of 600,000 tons. They are founded on caissons placed on
wedge-shaped foundation bases suitable for large horizontal loading. An anchor block caisson covers
an area of 6100 m2.
The caissons for the pylons, the anchor blocks, and the approach spans as well as the approach span
pier shafts have been constructed at a prefabrication site established by the contractor 30 nautical miles
from the bridge site. The larger caissons have been cast in two dry docks, and the smaller caissons and
the pier shafts for the approach bridges on a quay area, established for this purpose.
A pylon caisson weighed 32,000 tons and an anchor block caisson 36,000 tons when they were towed
from the dry dock by tug boats to their final position in the bridge alignment.
The two approach bridges, 2530 m and 1538 m, respectively, are continuous from the abutments to
the anchor blocks.
Both the suspension bridge girder and the approach bridge girders are designed as closed steel boxes
and constructed of few basic elements: flat panels with trough stiffeners and transverse bulkhead trusses.
The suspension bridge girder is 31.0 m wide and 4.0 m deep; the girder for the approach bridges is 6.7 m
deep. They are fabricated in sections, starting in Italy. In Portugal, on their way by barge to Denmark,
a major preassembly yard was established for girder sections to be assembled, before they were finally
joined to full span girders in Denmark.
The East Bridge was inaugurated on June 14, 1998.
Tender evaluation resulted in selecting an alternative design: two haunched concrete box girders with a
typical span length of 110.4 m reduced to 81.75 m at the abutments and the expansion joints. The total
length was subdivided into six continuous girders, requiring seven expansion joints.
Altogether 324 elements, comprising 62 caissons, 124 pier shafts, and 138 girders have been cast
in five production lines at a reclaimed area close to the bridge site. All the elements were cast, moved,
stored, and loaded out on piled production lines without use of heavy gantry cranes or dry-docks. The
maximum weight of an element was 7400 tons. The further transportation and installation was carried
out by The Swan, a large purpose-built catamaran crane vessel (see Figure 4.7).
By this concept, which was originally presented in the tender design, but further developed in the con-
tractor’s design, the entire prefabrication system was optimized in regard to resources, quality, and time.
The bridge was handed over January 26, 1994.
FIGURE 4.7 Great Belt, West Bridge, Denmark. (Courtesy of Sund & Bælt Holding A/S.)
Planning of Major Fixed Links 107
FIGURE 4.8 Great Belt, East Tunnel, Denmark. (Courtesy of Sund & Bælt Holding A/S.)
4.10.2.1 Organization
The Øresund Link’s Owner is Øresundskonsortiet, established as a consortium between the Danish
company A/S Øresundsforbindelsen and the Swedish company Svensk–Danska Broförbindelsen in
January 27, 1992. The two parties each own 50% of the consortium.
The purpose of the consortium is to own, plan, design, finance, construct, and operate the fixed link
across Øresund.
The management of the consortium is similar to the Storebælt organization with a supervisory board
that has appointed a managing director, a technical director, and a finance director.
The project is financed by commercial loans, guaranteed jointly and severally between the Danish
and the Swedish governments. The highway part will be paid by user tolls, whereas the two countries’
railway companies will pay fixed installments per year. The pay-back period is estimated to 24 years.
The revenue also has to cover the construction work expenses for the Danish and Swedish land-based
connections.
top deck and the two-track railway on the lower deck; secondary a one-level bridge. Both concepts were
based on cable-stayed main bridges.
Five consortia were prequalified to participate in the competition for the high-level bridge, and six
consortia for the approach bridges.
In June 1995, the bids for the Øresund Bridge were delivered. Although all four consortia had elabo-
rated tenders for the two-level bridge, only two tenders were received for the one-level bridge, and only
one consortium suggested to built the approach bridges in one level. The two-level concept was clearly
the economically most favorable solution.
In November 1995 the contract for the entire bridge was awarded to a Danish–Swedish–German
consortium (see Figure 4.9).
The 7,8 km bridge includes a 1090 m cable-stayed bridge with a main span of 490 m. The 3013 m and
3739 m approach bridges have spans of 141 m. The entire superstructure is a composite structure with
steel truss girders between the four-lane motorway on the upper concrete deck and the dual track rail-
way on the lower deck.
Fabrication of the steel trusses as well as casting of the concrete deck was carried out in Spain. The
complete 140 m long girder sections, weighing up to 7000 tons, were tugged on flat barges to the bridge
site and lifted into position on the piers.
On the cable-stayed bridge the girder was erected in 140 m sections on temporary supports before
being suspended by the stays. This method is unusual for a cable-stayed bridge, but it is attractive
because of the availability of the heavy lift vessel, and it reduces the construction time and limits vessel
traffic disturbance.
The cable system consists of two vertical cable planes with parallel stays, the so-called harp shaped
cable system. In combination with the flexural rigid truss girder and an efficient pier support in the side
spans, a high stiffness is achieved.
The module of the truss remains 20 m both in the approach and in the main spans. This results in stay
cable forces of up to 16,000 tons, which is beyond the range of most suppliers of prefabricated cables.
Four prefabricated strands in a square configuration have therefore been adopted for each stay cable.
FIGURE 4.9 Øresund Link, cable-stayed bridge, Denmark–Sweden. (Courtesy of Søren Madsen/Øresundsbron.)
Planning of Major Fixed Links 109
The concrete pylons are 203.5 m high and founded on limestone. Caissons, prefabricated on the
Swedish side of Øresund, have been placed in 15 m water depth, and the cast-in-place of the pylon shafts
is progressing. Artificial islands have been established around the pylons and near-by piers to protect
against vessel impact.
All caissons, piers, and pier shafts are being prefabricated on shore to be assembled offshore.
The bridge was opened for traffic in July 2000.
The final concept designs of the competing link structures (status November 2010) encompass the
following:
1. Cable-stayed main bridge with 2 main spans of 724 m each and a total length of 2414 m, two
approach bridges with lengths of 5748 m and 9412 m, respectively consisting of 200 m spans typi-
cally, and reclaimed peninsulas to connect to the shorelines. The superstructure carries road and
rail in 2 levels and uses a steel cross section for the main bridge and a composite section for the
approach spans. Land works to connect to the road and rail on land are part of the project, too.
2. Immersed tunnel with total length of approximately 18 km with large reclaimed areas in
front of the shore lines. The tunnel comprises in one section 2 roadway tubes, a central gallery
between the roadway tubes, and 2 railway tubes. Standard elements of 217 m length are planned
and special elements of 42 m length are arranged where technical equipment will be placed.
These special elements are deeper (2 stories) than the normal ones and 10 of these elements
will be used. Land works to connect to the road and rail on land are part of the project too (see
Figure 4.10).
Femern A/S has, on the basis of the completed concept designs and an initial environmental evalu-
ation, found that the tunnel offers slight advantages with respect to the marine environment and thus
recommended in November 2010 to develop the immersed tunnel as the preferred solution in the future.
This recommendation was confirmed by the Danish Transport Minister in February 2011 and consti-
tutes the present working basis. The final decision between the 2 solutions has to await the conclusion
from the ongoing EIA (Environmental Impact Analysis) or VVM (Danish equivalent to EIA) studies.
Here it shall be noted that Femern A/S’s published cost evaluation has derived at construction costs
of 3800 MEURO for both technical solutions—a quite unusual result.
Alternatives to the 2 main solutions are studied and evaluated too, and they cover a suspension bridge
with a large, single span and a bored tunnel solution with 3 bored tubes.
The future steps in the project development are confirmation of the preferred solution by final EIA/
VVM, submission for plan approval in Germany and Denmark, start of the tendering procedures, and
ending up in a construction act to be passed by the Danish Parliament. The actual construction start is
envisaged in 2014 and the opening of the link planned for 2020.
FIGURE 4.10 Fehmarnbelt Link, concept bridge design, Denmark–Germany. (Courtesy of Dissing+Weitling
architecture.)
Planning of Major Fixed Links 111
References
AASHTO. 2012. LRFD Bridge Design Specifications. 6th Edition, American Association of State Highway
and Transportation Officials, Washington, DC.
Euro Codes. 2011. Basis of Structural Design. European Committee for Standardization, Brussels, Eurocode
EN 1990, Related Design volumes EN 1991—EN 1999.
Larsen, O. D. 1993. Ship Collision with Bridges. The Interaction between Vessel Traffic and Bridge Structures.
Structural Engineering Document no. 4. IABSE Green Book, ISBN 3-85748-079-3, International
Association for Bridge and Structural Engineering, Zürich, Switzerland.
Strait Crossing Bridge. 2011. Homepage for the Confederation Bridge by Strait Crossing Bridge Ltd
(http://www.confederationbridge.com/en/).