Professional Documents
Culture Documents
02
SCR House
User Manual
Customer References
Customer: ONGC Baroda
Rig / Hull: F-3050-2
Tag Number: NA
www.nov.com
REVISION HISTORY
CHANGE DESCRIPTION
www.nov.com
Table of Contents
This manual may consist of several volumes, chapters and sections and is housed in a number of
different binders as necessary to adequately document the equipment presented.
www.nov.com
www.nov.com
FINAL DOCUMENTATION
SCR System
Chapter 1
Installation, Operation &
Maintenance
www.nov.com
FINAL DOCUMENTATION
SCR System
Section 1.1
Operation & Maintenance
www.nov.com
10877884-IDX 01
www.nov.com
www.nov.com
Technical Manual
www.nov.com
REVISION HISTORY
TABLE OF CONTENTS
1 SYSTEM INFORMATION
1.1 Description
The SCR Drive System provides electrical power conversion and control for the DC motors
on a drilling rig. The system regulates AC power from engine-generator sets and delivers
continuously variable DC power to traction motors which are coupled to functions such as
Drawworks, Rotary Table, Top Drive, Cement Pumps and Mud Pumps (see Figure 1-1).
1.2 Specifications
The drive system conforms to IEEE-45 standards for electrical switchgear. For offshore
systems, certification can be obtained from American Bureau of Shipping (ABS), United
States Coast Guard (USCG), and Det Norske Veritas. See Table 1-1 for system
specifications.
ELECTRICAL
AC Input Three phase, 60 Hz, 600 VAC
MECHANICAL
Temperature Range -22F to 105F
(-30C to 40C)
Figure 1-2 shows a typical one-line diagram. Observe that power from the engine-
generator sets is collected on a common AC bus.
AC to DC rectification occurs in SCR bridges. The output of the SCR bridge is applied to
the DC traction motors via contactors. Contactor logic is set at the Control Console being
used. Note that circuit breakers isolate each generator set and SCR Unit from the Main AC
Bus.
2. Start the engine and run it at idle speed until it is warmed up.
1. Turn the SYNC switch to the number of generator about to be brought on line. The
PUSH TO CLOSE pushbutton on the appropriate generator cubicle door should
illuminate.
2. Set the SPEED ADJUST control knob so the FREQUENCY meter indicates 60 Hz.
3. Adjust the VOLTAGE ADJUST control knob so the VOLTS meter indicates 600
Volts.
4. Charge the circuit breaker (if necessary) by pushing the CHARGE pushbutton for
electrically charged circuit breakers, or by cranking the circuit breaker handle for
manually charged breakers.
5. Close the circuit breaker by pushing the illuminated PUSH TO CLOSE pushbutton
on the appropriate generator cubicle door.
1. (Models 1200, 1201, 1500) Turn the SYNCHRONIZING switch (Item 9 on Figure 1-
3, Item 11 on Figure 1-4) to SYNC.
OR
1. (Model 1400) Turn the SYNCRONIZING switch (Item 15 on Figure 1-5) to the
number of generator about to be brought on line.
OR
2. Position the VOLTS ADJUST knob (Item 13 on Figure 1-3 and 1-4, Item 10 on
Figure 1-5, Item 17 on Figure 1-6) so the AC VOLTMETER (Item 5 on Figures 1-3
and 1-4, Item 18 on Figure 1-5, Item 7 on Figure 1-6) indicates 600 Volts.
3. Adjust the SPEED ADJUST knob (Item 12 on Figures 1-3 and 1-4, Item 9 on Figure
1-5, Item 18 on Figure 1-6) until the SYNCROSCOPE needle (Item 20 on Figures 1-
3 and 1-4, Item 17 on Figure 1-5, Item 22 on Figure 1-6) moves clockwise (the
engine/generator speed is faster than desired) and the two SYNCHRONIZING
LIGHTS (Items 21 on Figure 1-3, Items 19 on Figures 1-4 and 1-5, Items 23 on
Figure 1-6) brighten/dim.
Item Description
1. GEN Circuit Breaker
2. AC Kilowatts Meter
3. AC Kilovars Meter
4. AC Ammeter
5. AC Voltmeter
6. Generator Run Light
7. Generator On Line Light
8. Engine Control Switch
9. Synchronizing Switch
10. Ammeter Select Switch
11. Voltmeter Select Switch
12. Speed Adjust Knob
13. Volts Adjust Knob
14. % AC Ground Ammeter
15. % DC Ground Ammeter
16. Ground Fault Indicator Lamps
17. Ground Detector Test Button
18. Power Limit Light
19. Hertz (Frequency) Meter
20. Synchroscope
21. Synchronizing Lights
Figure 1-3. Controls and Indicators for Models 1200 and 1500
Item Description
1. GEN Circuit Breaker
2. AC Kilowatts Meter
3. AC Ammeter
4. AC Kilovars Meter
5. AC Voltmeter
6. Generator Run Light
7. Generator On Line Light
8. Ammeter Select Switch
9. Voltmeter Select Switch
10. Engine Control Switch
11. Synchronizing Switch
12. Speed Adjust Knob
13. Volts Adjust Knob
14. % AC Ground Ammeter
15. % DC Ground Ammeter
16. Ground Fault Indicator Lights
17. Ground Detector Test Push Button
18. Power Limit Light
19. Synchronizing Lights
20. Synchroscope
21. Hertz (Frequency) Meter
Item Description
1. GEN Circuit Breaker
2. AC Kilowatts Meter
3. Kilovars Meter
4. AC Ammeter
5. Engine Control Run/Off/Idle Switch
6. GEN Run Light
7. GEN On Line Light
8. Push to Close Lighted Pushbutton
9. Speed Adjust Knob
10. Volts Adjust Knob
11. % AC Ground Fault
12. % DC Ground Fault
13. Ground Fault Indicator Lights
14. Ground Detector Test Push Button
15. Generator Synchronization
Select Switch
16. Frequency (Hertz) Meter
17. Synchroscope
18. AC Voltmeter
19. Synchronizing Lights
20. Power Limit Light
21. Hour Meter
4. Crank the handle of the GEN CIRCUIT BREAKER (Item 1 on Figures 1-3, 1-4, and
1-5, Item 24 on Figure 1-6) once to charge the GEN CIRCUIT BREAKER.
5. Close the GEN CIRCUIT BREAKER when the needle of the SYNCROSCOPE
points straight up, the SYNCHRONIZING LIGHTS go out, and the PUSH TO
CLOSE pushbutton on the GEN CIRCUIT BREAKER is illuminated.
6. Position the VOLTAGE ADJUST knob so the KVAR meter gives the same reading
as the other generator(s) on line.
1. Open the circuit breaker by pushing the circuit breaker OFF pushbutton.
3. If the GOVERNOR CONTROL switch has an OFF position, go to the OFF position
only after engine has cooled down.
1. Check the Driller's Console to insure assignment for this SCR is turned off (the 12
o'clock position de-assigns all SCRs).
2. Charge the circuit breaker (if necessary), by pushing the CHARGE pushbutton (for
electrically-charged circuit breakers) (refer to Figures 1-3 through 1-6) or by cranking
the circuit breaker handle (for manually-charged circuit breakers). Some systems
have molded-case circuit breakers. These do not require charging.
3. Close the SCR circuit breaker by pushing the PUSH TO CLOSE pushbutton (this
may be mounted remotely or directly on the circuit breaker). Crank the circuit
breaker handle once to close molded-case circuit breakers.
1. Close the feeder circuit breaker to feed AC supply to the distribution transformers
and the MCC.
2. Close the circuit breakers corresponding to each of the blowers and auxiliaries. Set
the HAND/OFF/AUTO switch to AUTO (if applicable).
3. If the motors are shunt wound, switch on the appropriate field power supplies. Each
motor's field current should be 50 Amps (or per the motor nameplate rating).
Adjust the VOLTS ADJUST knobs so all generator units KVAR meters are the same.
2.7.2 KW Sharing
A master/slave circuit automatically balances the Kilowatts (Horsepower) among all on-line
engines (the load is shared equally).
The master generator is the lowest- numbered unit connected to the Main AC Bus. The
remaining generators are slaved to the master. For example, if Generator 1, 2, and 4 are
connected to the Main AC Bus, Generator 1 is the master.
In systems using Auto Share (Auto Sync) AC Control Modules, master/slave floats. No AC
Control Module can be the dedicated master in an Auto Share system.
The magnetic coupling that exists between paralleled generators insures that all engine
generator sets connected to the Main AC Bus at the same time will run at the same speed.
The SPEED ADJUST knob on the master generator has total control of the Main AC Bus
frequency. The slave units SPEED ADJUST controls are disabled.
The combination of KW (Real Power) and KVAR (Reactive Power) sharing between engine
generator sets should cause all generator AMMETERS to read about the same value. Any
imbalance in the readings of the various KVAR meters can be adjusted by using the
VOLTAGE ADJUST knob of the generator that has the lowest KVAR meter reading.
Bring additional generators on line to increase the total power available. To increase the
total DC power available, increase the total power by putting more generators on line. AC
power is usually a small fraction of the DC power. To increase power for a specific DC
function, it also helps to reduce the power consumed by the other DC functions.
Due to the Main AC Bus feature and the Power Limit circuit, it is possible to connect as few
generators to the Main AC Bus as are necessary to do the work. For economy and
efficiency, match the total available power to the total load.
The GEN ON LINE and SCR ON lights will illuminate when the respective units are
connected to the Main AC Bus. The lights go out when that unit is tripped off-line
(disconnected from the Main AC Bus). If a generator\SCR unit becomes inoperative,
continue the system operation on other units.
If the SYNCHROSCOPE is inoperative, use the SYNC lights to parallel the generators. If
both the SYNCHROSCOPE and the SYNC lights fail, use a Multimeter.
Switch the Multimeter to a 600 VAC scale. Connect it across the generator circuit breaker
from the top to the bottom of any one phase. The voltage will swing from minimum to 600
VAC just as the SYNC lights should change from dim to bright. Adjust the SPEED ADJUST
knob for the oncoming generator until the swing slows. Close the circuit breaker when the
Multimeter voltage reading is minimum.
The green SURGE SUPPRESSION light will extinguish if a problem blows the Surge
Suppression Circuit incoming line fuses.
The SPROCKET SLIP light illuminates when Mud Pump assignment contactors trip. This is
caused by a sprocket slip, chain failure, or belt slippage on a dual motor mud pump. After
the chain drive is repaired, push the SPROCKET SLIP RESET button to extinguish the
SPROCKET SLIP light and to allow the contactors to close.
The three GROUND DETECTOR lights and the % AC GROUND and % DC GROUND
meters indicate ground faults.
These are only indicators and the fault must be located and corrected.
AC ground faults can occur anywhere along the AC power network (generator to AC bus
cables, feeder distribution to the AC motors, and the generator control bus in the cubicle
itself). The GROUND DETECTOR lights will isolate the fault to one of the phases, and the
% AC GROUND meter will indicate the degree of the fault.
DC ground faults may occur anywhere along the DC network from the DC (+) and DC (-)
buses in the SCR cubicles to the motor cables. Isolate the fault to one motor by observing
the % DC GROUND meter. The % DC GROUND meter needle will fluctuate as the faulty
motor speed is changed.
1. Turn off the SCR unit by tripping the SCR circuit breaker. The SCR ON light will
extinguish.
2. Disconnect the generator from the Main AC Bus by tripping the Generator circuit
breaker. The GEN ON LINE light will extinguish.
3. Push the engine IDLE pushbutton. Cool the engine per the engine manufacturer.
4. After the engine cool-down period is over, turn the Generator Control cubicle
OFF/IDLE/RUN switch to OFF to stop the engine. Shut down the fuel rack if there is
no OFF button.
2.10 Capabilities
Figure 1-7 shows an SCR bridge Current versus Voltage response curve. Figure 1-8
shows DC series and shunt motors Speed versus Torque curves. These are for a specific
brand and model motor. Other brands and models will be different.
Figure 1-7. SCR Bridge Current versus Voltage Curve
3 MAINTENANCE
This chapter contains information to assure proper operation of the system through periodic
functional tests and preventive maintenance.
If the system fails to perform as indicated in the functional test instructions, consult the
troubleshooting guidelines listed in this manual.
If the house is not ordered, the equipment should be handled with care to prevent
excessive mechanical shock, and protected from possible damage due to moisture and dirt
during rig-up. See Figures 1-11 and 1-12 for cubicle lifting procedure.
3.2 Installation
If an SCR house was not ordered, refer to the following instructions for installation of the
SCR Cubicles. Figure 1-14 shows a typical SCR Drive Cubicle lineup.
3.3 Cubicles
Door Clearance
The SCR room must be large enough to allow the doors to be opened 90 degrees. The
doors cover the full height of the cubicles. The height of the room must have clearance for
the cable tray, piping, and ducting.
The room air must be changed twice per minute when the cubicles are enclosed in a room.
Ducting in the front and rear of the room should force the air to flow the full length of room.
Heat Loss
Heat loss for a SCR system housed in a room fully insulated on walls, floor and ceiling, and
containing no distribution transformers, is approximately 2.5 tons for each 1,000 HP of DC
load.
Vibration Pads
If the cubicles are mounted in a high vibration area, such as the region close to the engine
skid, the cubicles should be mounted on vibration insulating pads. The vibration frequency
should be within 30 Hz, and the amplitude should not exceed 0.02 cM. Korfund spring-type
vibration isolators are recommended.
Location
Lift the cubicle with a crane into the general installation area. Use four lifting points per
cubicle. Refer to Figures 1-11 and 1-12 for the lifting procedure.
Use hydraulic hand trolleys (Rol-A-Lift or equivalent) to move the cubicles into the exact
location. Two trolleys may be required for wide cubicles such as the Motor Control Center.
Cover the vertical rest beams of the trolleys with carpeting to protect the finish of the
cubicle panels.
Slide the trolley horizontal forks all the way underneath the cubicle.
Jack up the cubicle approximately 6" (15 cm) above the floor.
Push the cubicle carefully into the location, jack down, and remove the trolley horizontal
forks.
Mounting
Bolt the cubicles together at the top and bottom using 3/8" bolts.
Install the AC bus splices to connect the bus together from cubicle to cubicle.
Cable Installation
Refer to the cabling diagrams in the SCR job book. Cables between the cubicles are
furnished by the customer unless the SCR drive system is installed in a Power Control
Building.
All power terminations are made through the cubicle top unless otherwise designed.
If the SCR system is supplied inside a Power Control Building, power and control cable
terminations are at one end of the building.
The terminations are copper stubs with a one-inch diameter bolt hole. The customer
should furnish plated-copper, crimp-type lugs. Avoid screw-type pressure connectors.
If multiple single conductor cables are used to feed the system, transposing of the cables
must be considered to ensure current sharing between conductors.
Control Consoles
The Driller's Console is typically mounted on top of the Drawworks pneumatic control
console. The Mud Pump and Cement Pump consoles are provided with tabs. Each tab has
a bolt hole for wall installation. Refer to the respective console drawings for detailed
installation instructions.
Control cable terminations are made from the bottom with plug-in-type Pyle National
connectors or screw-type terminal blocks fed through stuffing tubes.
3.4 Testing
This section contains information to test the proper functioning of the SCR Drive System.
Perform the test daily. If the system fails any part of the test, use the Troubleshooting
section to locate the malfunction.
Team Work
Personal Wear
Live Circuit
Tools
All electric tools should be grounded. Handles on the tools should be insulated. Do not
leave tools in the cubicles after the work is completed.
Fuses
Close a fuse by pushing on the plastic cover. Do not place a finger underneath the cover.
Fire
Remove power to the unit under fire. Read the label on the fire extinguisher to be sure it
can put out an electrical fire. Water may be used, but be very certain that all power is
removed including the power on the main bus.
Perform the following checks to assure the proper functioning of the drive system.
2. Check Ground Detector indicators. All three lamps should glow a dim orange. The
Ground Fault Percentage meters should read close to Zero.
3. Check field current supply of all shunt motors.
4. Ensure that KWs and KVARs are shared between all the generators on line.
5. During tripping, listen for switching action of the DW Dynamic Brake contactor.
Perform the "Mechanical Overspeed Trip" and "Reverse Power Trip" Functional tests,
located in Table 2-4 (see Section 2).
1. Check waveshape of SCR Amps at the test pins on the DC Control Module. See the
SCR Unit section for further details.
When working in conditions of low humidity, wipe off meter lenses with a
damp cloth or use anti-static spray.
3.5 Servicing
Servicing consists of cleaning the system components and replacing those which have
become defective or worn out. Periodic servicing will make the SCR Drive System more
reliable and last longer. A reliable system is less likely to suffer sudden failures or
deteriorate below the performance specifications.
The system components are vulnerable to three factors: inferior quality, harsh operation
and severe environment.
3.6 Quality
Efforts to eliminate this source of failure are made at our manufacturing and testing facility.
The system is rigorously tested through every phase of operation. The electronic modules
are placed in ovens at 165°F (75°C) for 96 hours to simulate numerous hours of operation
at normal temperature. Thus, components which are likely to fail during the first hours of
operation are replaced before shipment.
The drive system should be operated within its capabilities. Operation above the ratings
subjects the system to severe strains. The controls should be handled with care. A harsh
switching action can generate a damaging transient overload.
3.8 Environment
3.8.1 Heat
Components can fail suddenly due to overheating. Even though the drive system is rated
between -22°F (-30°C) through 104°F (40°C), the system operation is more reliable at
normal temperatures. Components age faster at temperature extremes.
The blowers in each SCR cubicle remove the heat from the electrical assemblies. As a
further precaution, vital units such as the SCR bridges and electronic modules have heat
sinks for faster cooling. Inspect the assemblies frequently for indications of overheating
such as charring or burned insulation due to loose connections. Replace the damaged
components even thought they may not have failed completely.
3.8.2 Vibration
The drive system units do not generate vibrations. However, vibrations from rotating
machinery such as the generator set cause mechanical stress that can loosen connections
and crack insulation.
3.8.3 Dust
Dust is attracted to high voltage switchgear surfaces because of the static electricity
charge. As a result, circuit discontinuities, or even shorts can occur.
3.8.4 Moisture
Moisture aggravates problems caused by dust. The contaminants cake on the components
and conductivity is increased. Further, corrosion can occur.
3.8.5 Cleaning
Wipe clean the cubicle and component surfaces with a lint-free cloth moistened with a mild
cleaning solvent. Be sure to leave the surfaces dry.
TURN OFF THE MAIN POWER TO THE SYSTEM BEFORE CLEANING. TEST
THE CLEANING SOLVENT ON A SMALL SURFACE TO MAKE SURE IT
DOES NOT DAMAGE THE PLASTIC PARTS OR INSULATION, OR REMOVE
PAINT.
3.8.6 Inspection
Check all components for overheating and corrosion. Replace damaged components even
if not completely failed. Inspect cables and wires for broken or burned insulation. Tighten
all connections and check switches, knobs, and buttons for easy movement.
Operating conditions dictate the servicing period. Adhere to the following schedule during
the initial period and adjust it according to need.
3.8.7 Connections
Experience has shown that many problems with electrical equipment are the result of loose
connections. Periodic checks for tightness can be helpful.
2. Check Driller's console and Foot Throttle for air pressure. If there is moisture inside
the compartments, the dryer in the air line may be clogged.
3. Check assignment contactors. Inspect the coils for signs of overheating such as
discoloration or charred insulation. Check contacts for corrosion or pitting. Inspect
the freewheeling diodes; also inspect auctioneering diodes in the system.
4. Clean tachometer pickup plugs. Do not screw pick up in too far. Flywheel will
damage coil upon starting diesel.
Clean and inspect the system components as indicated in Weekly Servicing. In addition,
tighten the bus bar bolts.
2. It is important to keep the SCR house interior dry while stacked. Install covers on all
external connectors on the plug panels. Place corrosion inhibitors in consoles and
cabinets.
5. Apply power to generator and traction motor heaters if possible. Heaters in electrical
equipment areas are helpful.
1. Inspect bus bars for debris. Inspect and clean throughout cubicles, consoles, MCC
cans and underneath the main and switchgear line-ups.
3. Manually operate all motor starters and contactors before powering up.
6. Open all fuses in the system and high-resistance check the main three phase bus
bars before applying power.
7. Remove covers and inspect SCR bridges. Clean as necessary.
8. Reconnect HOC batteries. If good, they will fully recharge within 24 hours.
9. Clean all potentiometer windings (speed adjust, voltage adjust, hand throttles, foot
throttle).
15. Check resistance of all magnetic pickup circuits and all actuator circuits.
18. Check current and voltage feedback for all SCR bridges.
19. Perform emergency-off and reverse power trip tests for all engines.
21. If equipment has been idle for more than one year, all electrolytic capacitors should
be replaced.
4 TROUBLESHOOTING
4.1 Overview
It consists of first looking at the broad possibilities of failure, and then breaking down the
likely possibility into successively smaller trouble spots.
Examine the whole system as it is situated between the generators and the loads. Then
narrow the search to a cubicle or console, then to an internal assembly, and finally to a
component. The malfunction can be quickly located by seeking out signs of trouble, such
as extreme readings on the meters, tripped circuit breakers, and smoking components.
Troubleshooting is easier and faster if the nature of the malfunction is pinned down.
Sometimes, the faulty behavior of the system may be caused by operator error. For
example, the Driller may forget to turn on the lockout switch, open the throttle, and assume
that the SCR unit is defective.
The faulty behavior of a motor or generator may be blamed on the SCR system. Make
sure the fault is not outside the system before making extensive repairs such as replacing a
SCR cell.
If the malfunction occurs off and on, it may be useful to keep a log of the system
parameters with a strip chart recorder.
Many malfunctions can be located by analyzing the meters and lights on the front panel.
Warning lights on the cubicle panels flag ground faults, AC surge, sprocket slip, and
reverse power conditions. Operational lights indicate whether a SCR or a Generator is on
the bus. Even voltmeters and ammeters provide valuable troubleshooting information. For
example, a stalled motor is indicated by high current, and low voltage. Low current and
high voltage is an indication of an unloaded motor.
Think of the system as being made up of interrelated blocks or units. Ignore the contents of
the unit, and simply consider the inputs and outputs. Refer to Figure 1-15.
D R IL L E R 'S
G E N E R AT O R
CO N SO LE
DC
C IR C U IT
E L E C T R O N IC
BREAKER
M O DULE
G AT E F IR IN G
A C S U P P LY
PULSES
S C R B R ID G E
0 - 7 5 0 V D C S U P P LY
POW ER
C O N TR O L
A malfunctioning unit does not provide the correct outputs. The fault may be due to
incorrect inputs. If not, some of the assemblies within the unit may be defective.
To troubleshoot, the system, first isolate the faulty unit by examining the outputs of the
suspected units. Then examine the inputs to the faulty unit. If one of the inputs is
incorrect, trace the signal from the incorrect input to its source unit. If, however, the inputs
are correct and the outputs are incorrect, troubleshoot the defective unit. Isolate the fault to
any one of the unit assemblies by a similar system analysis.
Inputs to many of the SCR Drive System units are of two forms: power and control. For
example, a SCR cell must receive the AC supply and the control firing pulse at the gate. If
both the inputs to the SCR cell are correct and the output of the SCR cell is incorrect, the
cell is defective.
The defective unit can be easily located by tracing signals associated with the malfunction.
G E N E R AT O R 1 C IR C U IT SCR 1 C O N TA C T O R
BR E AK ER
G E N E R AT O R 2 C IR C U IT SCR 2 C O N TA C T O R M OTOR
BR E AK ER
The motor can be operated on any one of the two power lines (refer to Figure 1-16). If it
fails to run, the fault can be in the motor, the assignment switch, or the power lines.
The power line can be checked out by simply switching the motor to one of the other lines.
If the motor runs, then obviously, the first power line is defective.
Each power line is made up of components in series. If the power line circuit is defective,
all the components and the wiring must be suspected. The defective component can be
located by tracing the power supply from the motor back to the generator.
Begin the signal tracing at the motor. If power is present at the motor and the motor is not
running, the motor is defective.
If power is absent at the motor, check for its presence on both sides of the contactor. If
power exists on the SCR side, but not on the motor side, the contactor is open.
Signal tracing should continue back toward the Generator until the defective component is
located. In extremely long series circuits, it may be convenient to divide the circuit in half.
Begin the probe in the middle. If the signal is missing, trace back toward the generator until
the signal is regained. If the signal is present, trace away from the generator until the signal
is lost.
The following instruments are needed to troubleshoot the SCR Drive System.
4.5.1 Multimeter
The Simpson Model 250 (or equivalent) is recommended to measure voltage and
resistance values. The meter should be insulated, rugged and possess:
Digital multimeters may be used to measure voltage and current signals in the SCR drive
but you should be aware that some digital meters are overly sensitive to the high electrical
noise typical of that found in any switching high power supply. Digital meters that are not
designed with proper filtering and measuring techniques and can give inaccurate readings.
This meter is used to safely measure high currents. The Columbia Model 1000A is
recommended.
4.5.3 Oscilloscope
The oscilloscope is used to check the SCR gate pulses and ripple on various DC voltages.
The Tektronix Model 305 (or equivalent) is recommended. The unit chosen should have >3
Inch diagonal viewing screen and two channels for comparing two signals.
1. Disconnect power cables from the bus stubs located at the top of the cubicle.
2. Remove bus links which connect the AC bus from cubicle to cubicle.
3. Remove the bolts which join the cubicles at the top and bottom.
4. Slide the fork of a hydraulic hand trolley underneath the cubicle and jack it up
approximately 6" above the floor.
5. Pull out the cubicle carefully, taking care not to bump the adjoining cubicles.
Repair of the SCR Drive System normally consists of repairing an assembly within a
system unit. A system unit is not replaced unless it is damaged beyond repair. When a unit
is replaced, perform a functional test on it before operating the system. Refer to the
respective unit manual for test instructions.
If an AC Control Module is malfunctioning, replace it with the spare AC Control Module and
return the faulty unit to us.
To remove and replace the AC Control Module perform the following steps.
1. Unscrew the Deutsch fastener at the top of the module and swing open the cover.
2. Release the wiring harness by removing each wire from the terminal board.
3. Unscrew the four Deutsch fasteners which hold the module to the cubicle wall.
4. During new module installation, ensure you match the wire number to pin number.
5. Reconnect the module to the cubicle wall with the four Deutsch fasteners.
6. Reconnect the wiring harness by replacing each wire on the terminal board. Ensure
that each wire is correctly placed and that the retaining screw is tightened.
7. Swing the cover closed and fasten it in place with the Deutsch fastener on top.
Technical Manual
Generator Unit
www.nov.com
REVISION HISTORY
TABLE OF CONTENTS
1 OPERATION ..................................................................................................................... 4
1.1 Description .............................................................................................................. 4
1.2 Specifications.......................................................................................................... 6
2 MAINTENANCE ................................................................................................................ 9
2.1 Testing .................................................................................................................... 9
2.2 Servicing ................................................................................................................. 9
2.3 Theory of Operation .............................................................................................. 24
2.4 Troubleshooting .................................................................................................... 49
3 HI-LINE OPERATION ..................................................................................................... 55
4 REMOVAL & REPAIR .................................................................................................... 58
4.1 Model 1000 ........................................................................................................... 58
4.2 Model 1400 ........................................................................................................... 59
4.3 Model 1861 ........................................................................................................... 60
1 OPERATION
1.1 Description
The Generator Unit controls the engine/ generator set to develop a constant AC supply.
The output of several generators are fed to a common AC bus (refer to Figure 2-1).
Each Generator Unit's AC Control Module has an electronic engine governor, a voltage
regulator and a circuit breaker (refer to Figure 2-2). The circuit breaker is interlocked with a
Protection circuit which automatically trips the breaker for malfunctions such as
overcurrent, overvoltage, under/overfrequency and reverse power. In addition, a
Synchronization Panel is provided with each system to match individual generator equency
and voltage to the bus frequency and voltage.
1.2 Specifications
1.2.1 Electrical
1.2.2 Mechanical
They are mounted in a sheet steel cubicle. Dimensions vary from model to model. A
typical Generator Cubicle is 90" H. x 36" D. x 24" W. and weighs 2,000 pounds.
ELECTRICAL POWER
AC Supply Three phase, 60 Hz., 600 VAC.
Overfrequency 67 - 68 Hz.
Underfrequency 50 Hz.
ENGINE GOVERNOR
Regulation 0.5 Hz, steady state.
Many of the electronic circuits associated with generator control are housed in the AC
Control Module. The AC Control Module is constructed from 14-gauge steel, and has its
own heatsink.
2 MAINTENANCE
This section contains testing and servicing information to assure proper operation of the
Generator Unit. TROUBLESHOOTING (later in this chapter) has an explanation of the
various Generator Unit circuits. REMOVAL AND REPAIR (also later in this chapter)
identifies the various generator assemblies.
2.1 Testing
Perform the functional tests given in Tables 2-2 through 2-6 after repairing/replacing any
assembly. Perform the Reverse Power Trip and Engine Mechanical Overspeed tests listed
in Table 2-4 once a month.
The TEST switch allows a quick check of the systems vital signals. The TEST switch and
the TEST METER are color-coded. For example, if the TEST switch is set to the yellow
BREAKER TRIP VOLTAGE position, normal condition is indicated by the TEST METER
needle deflecting to the yellow.
2.2 Servicing
Servicing consists of oil change and calibration procedure of the throttle actuator terminal
shaft.
The Woodward EG-3P and EG-10P Actuators receive oil from the engine oil supply, so
regular engine oil change intervals are sufficient.
The Woodward EG-B 10P Actuator has it's own oil supply. Change it every six months
under favorable operating conditions. The oil sump holds one U.S. Quart. Refer to the
following and the manufacturer's literature.
The main difference between these models: the EG-B has a Ball Speed
governor and self-contained oil supply.
1. To drain the oil, unscrew the Drain Cock located in the lower left-hand corner of the
front panel.
To flush the actuator, add one quart of diesel fuel or kerosene through the Oil Cup located
on the top. Run the engine speed up and down by switching the Engine Control switch
between IDLE and RUN. After a few minutes, shut the engine off and drain the fluid.
Repeat flushing until the Drain Cock fluid is clean.
2. Drain all the fluid and screw in the Drain Cock. Fill the actuator with one quart of the
recommended lubricating oil. Woodward recommends Mobil 1.
Calibrate all engine actuators if KW load sharing at full load exceeds 10% (see Table 2-5).
ACTION RESULTS
PRELIMINARY
A. Open all the Generator unit fuses, with A. There are no measurable results from
the engine shut down. this step.
THROTTLE CHECK
A. Disconnect Throttle(+) (TB11-1) and A. There are no measurable results from
Throttle(-) (TB11-2)(this is TB4 or TB9 this step.
in older systems).
Refer to your system prints to
determine the terminal strip
connections for the Throttle and
Exciter.
B. Measure the resistance between the B. The resistance should be 30 to 36 .
leads to the Throttle to check for open
or short circuit conditions.
C. Measure the resistance between each C. The reading should be an open circuit
throttle actuator lead and ground. reading () unless the cable is
grounded.
D. Reconnect the throttle leads. D. There are no measurable results from
this step.
EXCITER CHECK
A. Disconnect the Exciter(+) wire from A. There are no measurable results from
TB11-7 and the Exciter(-) wire from this step.
TB11-8 (this is TB4 or TB9 in older
systems).
Refer to your system prints to
determine the terminal strip
connections for the Throttle and
Exciter.
B. Measure the resistance between the B. The resistance should be 3 to 20 (this
leads to the Generator Exciter to check depends on generator model).
for open or short circuit conditions.
C. The resistance should be after
C. Check the resistance from each exciter TB11-8 in the generator switchgear is
lead to ground. disconnected.
D. Reconnect the Exciter leads. D. There are no measurable results from
this step.
D. Close fuses F30, F31, F32, F35, F36, and D. There are no measurable results from this
F37 on the input of the AC Regulator step.
Transformer.
A. A.Disconnect wires Gate A+ (Pin 504) A. There are no measurable results from this
and Gate A- (Pin 505). step.
B. Close the Exciter fuses. B. There are no measurable results from this
step.
Exciter fuse numbers depend on
model of system (check your
generator control schematic in your
drawing package). The Exciter fuses
for the 1400 system are F39 & F40.
C. Observe the generator VOLTMETER. C. The voltage should rise to 200 VAC, and fall
cyclically as K1 (the build-up relay) picks up
and drops out.
D. Monitor the signals at Pins 512 through D. These signals should also rise and drop.
517.
E. If the results indicated in Steps C and D E. There are no measurable results from this
occur, reconnect the Gate A+ and Gate A- step.
wires.
A. Determine the model of your Throttle Actuator. If A. There are no measurable results from this step.
it is a Woodward Model EG-B 10P, perform
Steps B through F set the various
Steps B through D. If it is a Woodward Model
controls of the Throttle Actuator.
EG-3P or EG-10P, skip to Step E.
Woodward Models EG-3P and EG-10P do
not have these controls and, therefore,
do not require these steps to be
performed.
A. Connect one engine/generator to the Main AC A. There are no measurable results from this step.
Bus.
GENERATOR CIRCUIT BREAKERS
This test only needs to be performed if WILL NOT CLOSE UNTIL
components in the synchronizing circuit SYNCHRONIZED WITH THE MAIN AC
have been changed or if a problem is BUS. DO NOT CLOSE ANOTHER
encountered in synchronization. GENERATOR’S CIRCUIT BREAKER
UNTIL THE SYNCHROSCOPE AND
SYNC LIGHTS HAVE BEEN CHECKED
FOR PROPER OPERATION.
B. Proceed to a second/subsequent generator, and B. The pointer of the SYNCHROSCOPE will turn
following the steps indicated in the previous counterclockwise. The SYNC LIGHTS will be
sections of the test, adjust its controls to develop dimly illuminated.
600 VAC at 58 Hz.
C. Connect an AC Voltmeter, switched to read 600 C. There are no measurable results from this step.
VAC, between the oncoming generator's stab A
phase and the Main AC Bus stab A phase.
D. Adjust the generator’s frequency to 60 Hz, so D. The pointer of the SYNCHROSCOPE will turn
that it slowly goes in and out of synchronization clockwise or counterclockwise. The SYNC
with the Main AC Bus. Observe the Voltmeter, LIGHTS will alternately dim and brighten.
the SYNCHROSCOPE, and SYNC LIGHTS.
E. Close the oncoming generator’s circuit breaker E. The generator’s circuit breaker will not close if
when sync occurs. proper synchronization has not been achieved.
The KVAR meters of all generators on line
Synchronization between the Main AC should each read the same value.
Bus and the oncoming generator has
occurred when the needle of the
SYNCHROSCOPE points vertically, the
SYNC LIGHTS are off, and a Simpson
Model 250 (or equivalent) Volt Ohm Meter
(VOM) connected to the top and bottom
of the Main AC Circuit Breaker indicates
minimum voltage.
ACTION RESULTS
KW Sharing Test
A. Connect all engine/generator sets to the A. There are no measurable results from this
Main AC Bus. step.
B. Make assignments to provide 60% KW B. The KW METERS of all engine/generators
Load. should read the same and track together as
the KW Load varies.
Master/Slave Sharing Test
A. Connect all the system generators to the A. Observe that only the master generator
Main AC Bus. The KW and KVAR reading SPEED ADJUST dial has an effect on the
of each connected engine/generator set speed of all the engines on the lines. Verify
should be about the same. that the lowest numbered online generator
controls all other online generators.
B. Disconnect Generator 1 from the Main AC B. Verify that with Generator 1 off the Main AC
Bus. bus, Generator 2 controls all other
connected generators
C. Disconnect Generator 2 from the Main AC C. Verify that with Generators 1 and 2 off the
Bus. Main AC bus, Generator 3 controls all other
connected generators.
D. Reconnect all generators to the Main AC D. There are no measurable results from this
Bus. step.
ACTION RESULTS
LOAD DISTRIBUTION TEST (Concluded)
A. Start an engine/generator set and run it A. There are no measurable results from this
at IDLE. Follow the recommended warm step.
up time specified by the
engine/generator set manufacturer.
B. Put the ENGINE CONTROL switch to B. The generator voltage and frequency
RUN and adjust the SPEED ADJUST should increase as the engine goes from
potentiometer to 60 Hz. IDLE to RUN speed.
C. Put the ENGINE CONTROL switch to C. The generator voltage and frequency
IDLE. should decrease to the idle value.
D. Put the ENGINE CONTROL switch to D. The generator frequency should stabilize
RUN. at 60 Hz. within two overshoots.
A. After performing the Engine/Generator A. There are no measurable results from this
Idle-Run test, connect the step.
engine/generator to the Main AC Bus.
ACTION RESULTS
PRELIMINARY
A. Inspect the AC Control Module wiring A. Fix any incorrect or loose connections.
harness for incorrect and/or loose
connections.
B. Turn on the Generator unit. B. The Generator RUN light and the AC
Control Module front panel POWER ON
light will illuminate.
ACTION RESULTS
FREQUENCY DEMODULATOR TEST
(CONCLUDED)
20601-22 Rev. A
A. Check the following parameters at the given A. Since there is no current flow, the measured
location: voltages will be:
PARAMETER LOCATION
A. At run speed, rotate the VOLTS ADJUST control A. There are no measurable results from this step.
knob to its center position.
B. Monitor Test Point 12. B. The voltage should be -92 VDC @ 600 VAC.
C. Monitor the VOLTAGE REFERENCE signal at C. The voltage should be +4 to 6 VDC.
AC Control Module Pin 551.
ACTION RESULTS
VOLTAGE REGULATOR TEST
(CONCLUDED)
D. Monitor the EXCITER FIELD SUPPLY D. The EXCITER FIELD SUPPLY FIRING
FIRING PULSE at AC Control Module Pin PULSE waveform should look like the one
504 (GATE A+). in Figure 2-8.
20601-23 Rev. A
ACTION RESULTS
B. Disconnect TACH SIGNAL lead at AC B. The Generator Circuit Breaker will trip off
Control Module Pin 526. line, the engine will die, and the
Generator ON LINE light will extinguish.
C. Test all remaining engine/generator sets C. Results will be as shown in Steps A and
by repeating Steps A and B. B.
A. Connect a generator to the Main AC Bus. A. There are no measurable results from
this step.
B. Connect a jumper between AC Control B. The Generator Circuit Breaker
Module Pins 533 and 545 (this is the corresponding to the generator will trip off
Throttle Output). line in eight to 10 Seconds.
C. Once the Generator Circuit Breaker trips C. The engine will return to RUN speed and
off line, remove the jumper between Pins the Generator Circuit Breaker will be in
533 and 545. the OFF position.
Table 2-5. Calibration Procedure for Woodward EG-3P and EG-10P Actuators
ACTION RESULTS
SETUP
A. Connect an Ammeter in series with one of the A. There are no measurable results from this step.
throttle leads which are connected to the
Actuator receptacle.
B. Set the Ammeter scale to 100 mA. B. There are no measurable results from this step.
C. Open the Generator Circuit Breaker. C. There are no measurable results from this step.
D. Start the engine, and bring it up to RUN. D. There are no measurable results from this step.
THREADED
ROD
REASSEMBLY
A. Stop the engine. A. There are no measurable results from this step.
B. Disconnect the Ammeter and reconnect the B. There are no measurable results from this step.
throttle lead.
Table 2-6. Calibration Procedure for Woodward EG-B 10P Actuators Used on EMD
Engines
ACTION RESULTS
ACTUATOR CURRENT CHECK This calibration procedure is to ensure
that all of the actuators will work together.
In most cases, if the actuator currents of
all the actuators are within 10mA between
the highest and lowest reading, they will
perform properly.
A. Remove the top cover plate by unscrewing the A. A 1/8" Allen Head adjustable Spring Seat will be
four corner screws. visible in the middle of the actuator about 1"
(2.54 cM) below the top. The seat is held tight by
a 5/16" lock nut.
B. Connect an Ammeter, set to read 100 mA, in B. There are no measurable results from this step.
series with one of the throttle leads which are
connected to the terminal strip located in the Engine
Control Cabinet, which is adjacent to the engine.
D. Compare the actuator currents of all units. D. Determine which (if any) of the actuators require
adjustment. If any do require adjustment,
perform the following Terminal Shaft Adjustment
procedure on the identified unit(s).
TERMINAL SHAFT ADJUSTMENT
A. Loosen the Spring Seat lock nut. Rotate the A. Note that the actuator current changes.
Spring Seat 1/4 turn or less in either direction.
B. Adjust the Spring Seat until the Ammeter reads B. All actuators should draw 30 to 60 mA when the
the same as other recorder actuator currents. engines are at RUN RPM, Off-line, and at normal
operating temperature.
C. Tighten the Spring Seat lock nut. C. There are no measurable results from this step.
The Generator Unit controls the engine/generator set to deliver a constant AC supply to the
Main AC Bus (refer to Figures 2-10 and Figure 2-11). Note that the AC Control Module
contains the electronic Engine Governor, Voltage Regulator, Protection and Master/Slave
circuits.
The HOC consists of a battery charging circuit connected to two 12 Volt batteries. Phases
A and B of the Main AC Bus are tapped, fused, and then rectified in a diode bridge to
obtain the battery charging current. The batteries supply power for the Engine Starting
circuit and the Pulse Pickup circuit in the AC Control Module (refer to Figures 2-11 and 2-
12).
The Generator Circuit Breaker isolates the Main AC Bus from the generator. It has a
magnetic trip unit which trips the circuit breaker if current exceeds a preset value. The
circuit breaker has a UV (Under Voltage) coil which is interlocked with a AC Control Module
Protection circuit. This circuit trips the circuit breaker for various abnormal conditions such
as reverse power, under/overfrequency and overvoltage.
When the Main AC Bus is energized and another generator supply is to be connected to
the Main AC Bus, it is essential to match their voltage and frequencies before closing the
Generator Circuit Breaker. This is accomplished by comparing the two frequencies by
means of the Synchronization Box (shown in Figure 2-11).
When the front panel SYNC switch is in the OFF position, the Sync panel VOLT meter
indicates the Main AC Bus voltage. The needle of the SYNCHROSCOPE and the SYNC
LIGHTS compare the frequencies of the Main AC Bus and the on-coming generator. The
needle of the SYNCHROSCOPE rotates and the SYNC LIGHTS illuminate brightly when
the two frequencies are out of phase. When the frequencies and phases are identical,
there is no potential across the scope and the lights. As a result, the SYNCHROSCOPE
needle remains stationary in the vertical position and both SYNC LIGHTS extinguish.
The electronic Engine Governor controls the engine speed and horsepower, and thereby
regulate the generator frequency (refer to Figures 2-13 and 2-14). Located in the AC
Control Module, the Engine Governor is a feedback control circuit. See the Unique
Devices section of this manual for a general description of the feedback control circuit.
The governor output is connected to a Throttle Control Actuator (this controls the engine
fuel line valve). The Throttle Control Actuator opens the valve in direct proportion to the
current applied by the governor through its coil. The coil signal can be monitored at the AC
Control Module across Pin 533 (Throttle+) and Pin 545 (Throttle-).
G EN . B US
D EM O D U L ATO R
S PE ED FE ED B A C K
RE A L FEE D B A C K
TH R O T TL E L IM IT
G EN .
P UL S E
P IC K U P
EN G IN E
Z8 Z9 Q4
TH R O T TL E
S PE ED R EFE RE N C E
EN G IN E C O N TR O L R A M P C K T.
S W ITC H
M A S TER S L A VE
M S L O G IC TO O TH E R
AC M ODU LE G EN . UN ITS
S L AV E M A S TER /S L A V E
M /S
LO G IC
S L AV E S W ITC H
M A S TER
S L AV E
C U R RE N T C O N TRO L L O O P
S PE ED C O N TRO L L O O P
The engine governor employs two feedback control loops. The Outer Speed Control Loop
matches the actual generator frequency to the applied speed command. The Inner Current
Control Loop matches the horsepower (KW) output of all engines on line.
Op Amp Z8 issues a speed command which is proportional to the difference between the
Speed Command and the Composite Speed Feedback. Speed Command is the Speed
Reference signal as modified by the Engine Control switch ramp circuit and the
Master/Slave Logic signal. Composite Speed Feedback is the sum of the Speed Feedback
and Throttle Limit signals.
Speed Reference
This signal is set by the operator on the front panel SPEED ADJUST knob. The SPEED
ADJUST knob is linked to a potentiometer which outputs a Zero to +11 VDC signal (pin
551). This corresponds to 56 to 64 Hz generator frequency.
When the ENGINE CONTROL switch is moved from IDLE to RUN, the ramp circuit
generates an ascending ramp. This steadily increases the gain of Op Amp Z8. The ramp
circuit generates a descending ramp when the switch is moved from RUN to IDLE.
Changeovers in engine speed are thus accomplished smoothly over a 10 Second time
span.
Master/Slave Logic
A signal from the Master/Slave Logic circuit disables the Speed Reference signal when the
Generator Unit is in the Slave mode.
Speed Feedback
A magnetic pickup device is mounted near the flywheel of the engine. The magnetic
Pickup device emits a pulse each time a flywheel tooth passes by. These pulses are
applied to the Pulse Pickup circuit in the AC Control Module as Tach+ (pin 526) and Tach-
(pin 527). The pulse signal is processed to derive the Speed Feedback signal. The
magnetic pickup device generates it's own voltage and must produce ±2 VRMS. The Pulse
Pickup also activates the HOC circuit (refer to Figure 2-12). This allows the HOC batteries
to power the AC Control Module during the time that the generator voltage is building up.
Generator phase voltages out of AC Regulator transformer T10 are processed through a
Demodulator circuit in the AC Control Module. The Demodulator output is inverted via Op
Amp Z5 to obtain a negative Speed Feedback signal.
The AC Control module is equipped with a circuit that permits the tachometer circuit to
provide a speed feedback signal until the generator voltage is >200 VAC. When this
occurs, the Speed Feedback Switch operates to connect the Frequency Demodulator
Circuit output to the Frequency Regulator as the speed feedback signal.
Op Amp Z9 issues a Throttle Current Command which is proportional to the error in signal
levels between the Speed Command from Op Amp Z8 and the IREAL (KW) feedback. The
output of Op Amp Z9 output is amplified through transistor Q4 and then applied to the
Throttle Actuator Coil via Throttle+ (Pin 533) and Throttle- (Pin 545).
Master/Slave Logic
The Master/Slave circuit decides which current command Z9 should receive. If the
generator is a Master, the Generator Cubicle M/S switch selects the Z8 output. If, however,
the generator is a Slave, the Generator Cubicle M/S switch selects the Master/Slave signal
(pin 543). This signal is the Master generator Z8 output.
The Master/Slave Logic circuit detects whether the generator is the Master or Slave. The
Master/Slave Logic circuit receives the M/S Logic signal from the Generator Circuit Breaker
(pin 544) and Slave signals which are the M/S Logic signals of the other generators (pins
537 through 542). Table 2-7 is the Master/Slave Truth Table.
Figure 2-15 shows the Master/Slave circuit. The Master/Slave Logic switches from 10
VDC (this voltage is approximate since it is partially dropped through a resistor) to -16 VDC
when the circuit breaker is closed to connect the generator to the Main AC Bus. The
Master/Slave Logic of each generator is connected to the Slave inputs of the following
higher-numbered generators. As a result, the Master generator is always the one with the
lowest number. Generator 1 is never a Slave unit since it doesn't receive any Slave inputs.
If Generator 1 is off, the lowest-numbered generator connected to the Main AC Bus
becomes the master.
IREAL Feedback
IREAL is a low-level DC analog of the real current produced by the generator (IREAL x E =
KW). Generator phase voltages out of transformer T10 and line currents out of CT1, CT2,
and CT3 are processed in the AC Control Module through a current demodulator to
develop ITOTAL, I REAL and IREACTIVE signals (refer to Figure 2-10).
This controls the generator's exciter current through the exciter power supply to regulate
the generator voltage (refer to Figures 2-11, 2-13, 2-16, and 2-17).
The Voltage Regulator output can be monitored across Generator EX+ (TB11-7) and
Generator EX- (TB11-8). It should be +10 VDC during IDLE and +70 VDC during RUN for
a nominal 100 VDC exciter.
The Voltage Regulator employs two Feedback Control Loops (Inner and Outer). The Outer
provides overall regulation by matching the generator voltage to the Voltage Reference.
The Inner regulates the Exciter Field Supply. Op Amp Z1 issues the Exciter Current
Command. It is proportional to the error difference between the Voltage Reference and
Voltage Feedback signals.
-1 6 V D C -1 6 V D C -1 6 V D C
P IN N O . P IN N O . P IN N O .
M S L O G IC 5 44 5 44 5 44
M A S TE R S L AV E 5 43 5 43 5 43
S LAV E 5 42 5 42 5 42
S LAV E 5 41 5 41 5 41
S LAV E 5 40 5 40 5 40
A C M O D U LE A C M O D U LE A C M O D U LE
GEN. 1 GEN. 2 GEN. 3
Exciter Current Command. It is proportional to the error difference between the Voltage
Reference and Voltage Feedback signals.
Voltage Reference
This is set by the operator on the front panel VOLTS ADJUST knob. The knob is linked to a
potentiometer which outputs a Zero to +11 VDC signal (Pin 551). This +11 VDC
corresponds to maximum voltage.
Voltage Feedback
V O LTA G E FE E D BA C K
E XC ITE R C U R R EN T FE ED B A C K
V O LT. SCR GE N.
R E FE R .
Z1 Z2 F IR IN G
BU S
C IR C U IT
AC
M TR
R E A C TIV E
E X C ITE R
UN D ER F RE QU EN C Y E XC ITE R
G E N E RA TO R
C UT BAC K FIEL D
AC M ODU LE S U P PLY
E XC ITE R C U R R EN T C O N TR O L L O O P
V O LTA G E C O N T RO L LO O P
The voltage feedback and current feedback signals are processed in the AC Control
Module to derive the IREACTIVE signal.
The IREACTIVE signal is negligible during startup when the circuit breaker is open since
minimal current flows out of the generator. Voltage Reference is the only effective signal.
The VOLTS ADJUST knob can be adjusted to set the generator voltage to the operating
level. When several generators are connected to the Main AC Bus, the terminal voltage is
held fixed by other generators. The VOLTS ADJUST knob can now be adjusted to bias
the IREACTIVE signal so as to distribute the reactive current (KVARs) equally among all
generators.
The Underfrequency Cutback Signal is developed from the frequency feedback. It applies
a negative bias to the summing junction of voltage regulator Op Amp Z1 to cutback the
generator voltage when frequency drops below 50 Hz. At IDLE, when the frequency is 35
to 45 Hz, the voltage is between 300 VAC to 450 VAC.
Op Amp Z2 controls the SCR firing circuit firing angle so that the exciter field current
matches the Op Amp Z1 current command.
The generator output (refer to Figure 2-17) is stepped down and rectified to produce the
exciter current. Two rectifier circuits are used: a diode bridge made up of DB1 and DB2
during startup. Thereafter, a half- controlled bridge made up of two diodes (DB2) and two
SCRs (SCR1, SCR2). During startup, generator residual voltage is rectified through the
diode bridge and applied to the Exciter. The Metal Oxide Varistor (MOV) clamps bridge
voltage to +250 VDC. Through positive feedback, the Exciter voltage, and in turn, the
generator voltage quickly builds up. When the voltage is sufficient to energize the AC
Control Module, build-up relay K1 energizes to switch the transformer output to the half-
controlled bridge. The Exciter current feedback to the Op Amp Z2 summing junction (I EX +
and IEX -) is +0.33 VDC per 1.0 Amp of Exciter current (or as adjusted by the connection of
current-sensing resistors).
This circuit (refer to Figures 2-13 and 2-18) compares the generator supply parameters
against their respective preset limits.
The Protection switch, made up of transistor Q3 and relay K2, deenergizes the Under
Voltage (UV) coil to trip the Generator Circuit Breaker. In some systems, the Generator
Circuit Breaker has a Shunt Trip coil and a UV coil. In these systems, the Shunt Trip coil is
wired to a switch on the Generator Cubicle. Closing this switch will energize the Shunt Trip
coil, thus causing the Generator circuit breaker to trip.
G EN. BU S AC BUS
AC
N O P U LS E C IR C U IT
BREAKER
I REAL REVERSE
POWER
D E T E C TO R
Z 6, Q 1 , K 1
P R O T E C TIO N
FREQ UENC Y U N D E R /O V E R S W ITC H CB
Q 3, K2 UV
FEEDBAC K FREQ UENC Y T R IP
D E T E C TO R
Z 7, Z 14
REVERSE
P O W E R LIG H T
U N D E R F R E Q.
CUTBACK
V O LTA G E
O V E R V O LTA G E
FEEDBAC K D E T E C TO R
Q6
A C M O D U LE
When an engine is running normally, it supplies power to the Main AC Bus. This power is
measured in terms of KWs. The front panel KW METER will display a normal positive
value (> zero). However, when fuel to the engine is cut off due to overtemperature, oil
pressure or because of a clogged fuel filter, the corresponding KW meter will display a
negative reading (below zero). This is because power flows from the bus into the
generator of the faulty engine. The generator functions as a synchronous motor which
keeps the faulty engine running.
This is termed the reverse power phenomenon. Normally-running engines will force a
faulty-running engine to run at the same speed because of the magnetic coupling linking
the generators by way of the Main AC Bus.
Comparator Z7 in the Protection circuit monitors the IREAL (Kilowatts) feedback signal to
trigger the Protection switch when the signal exceeds the preset limit. The time delay
before tripping of the circuit breaker is a function of the level of the reverse KW. For
example, if reverse power is 7%, the Circuit Breaker will trip in eight to 12 Seconds.
Comparator Z6 triggers the Protection switch if the frequency feedback signal indicates that
the frequency is below 50 Hz. Z6 also applies the Underfrequency Cutback signal to the
Voltage Regulator circuit to reduce generator voltage.
Comparator Z14 triggers the Protection switch if frequency feedback signal says that the
frequency is 67 to 68 Hz.
The Voltage Feedback signal is applied to a voltage divider circuit made of resistors R90
and R96. The output of the voltage divider will trigger Q6 if the line voltage >1.16 x normal
bus voltage.
The No Pulse signal will switch from +16 VDC to -16 VDC when the Pulse Pickup circuit
does not receive pulses from the Magnetic Pickup device (this is located near the engine
flywheel).
The Protection switch operates 100 mS after loss of magnetic pulses from the engine. This
will prevent nuisance tripping of the circuit breaker.
The Power Limit Circuit prevents the load from exceeding the capacity of engines on line.
The circuit monitors IREAL (KWs) and ITOTAL (KVAs) of all the generators to keep the SCR
bridges on line from demanding more of either KWs or KVAs that would exceed preset
limits. This action distributes the available power equally among the SCR bridges. The
power limit is normally set at 95% of the engine's horsepower rating and 100% of the
generator's KVA rating.
Note that IREAL and ITOTAL signals are generated in the AC Control Module and auctioneered
together so that only the signal from the most highly loaded engine/ generator goes to the
power limit circuit (see Figures 2-11, 2-14, 2-19 and 2-20).
The IREAL and ITOTAL signals are low-level DC analog signals representing the real and total
currents developed by the generator. Generator line currents are stepped down through
current transformers CT1, CT2 and CT3. The resulting low level AC signals are rectified
and processed in a current demodulator in the AC Control Module with the generator phase
voltages and rectified to derive IREAL and ITOTAL. The IREAL and ITOTAL signals of all
generators connected to the Main AC Bus are auctioneered to select the signals with the
highest positive values. The Power Limit signal (Op Amp Z1-6) goes positive as the load
increases. It is +0.25 to +0.5 VDC measured at Pin 12 of the Power Limit Board at power
limit. When the load exceeds the power limit, the Power Limit signal positively biases the
negative Firing Reference signals to all SCR bridges on line. Op Amp Z2 ramps input
signal to Z1 from 75% of Power Limit to allow the prime mover to handle a large change
demand for power. Transistor Q1 turns on at power limit to turn on the Driller's Console
POWER LIMIT light. In some systems, Op Amp Z4 output is used to drive the Driller's
Console POWER LIMIT meter.
This circuit (refer to Figure 2-11) consists of three lights. One side of each light connects to
a phase of the Main AC Bus. The light's other side is grounded. If an AC phase becomes
grounded, the light corresponding to that phase is extinguished. The other two lights
become more brightly illuminated. A small C.T. drives a meter to indicate the percent of
the AC ground. This manual's SCR Unit section describes the DC Ground Fault Detection
circuit.
2.4 Troubleshooting
Table 2-8 gives troubleshooting information for engine malfunctions. Table 2-9 gives
troubleshooting information for Generator malfunctions. Table 2-10 gives troubleshooting
information for the AC Control Module.
3 HI-LINE OPERATION
Hi-Line operation allows you to replace or supplement the electrical power obtained from
your engine/generators with electrical power obtained from a commercial power company.
If this source of power is available at your site, the cost savings of utilizing Hi-Line
operation can be considerable.
The Hi-Line operation is primarily performed by a step-down transformer and two circuit
breakers (refer to Figure 2-21). There are other circuit components that allow control or
monitoring of Hi-Line operation. These other components are shown in Figure 2-22.
1 3,8 00 V (or H ig he r)
3 00 0 K VA
6 00 VA C
M CB1 M CB2
1 60 0A F 1 60 0A F /AT
BUS
L O C AT E D IN
H I-L IN E C U B IC L E
The values for the step-down transformer and circuit breakers shown in Figure 2-21 are
given for illustration purposes. The values selected for your particular system may differ.
In Figure 2-21, either or both of the circuit breakers will supply voltage from the step-down
transformer to the system's AC Bus. If only one circuit breaker is closed, the power
delivered to the system's AC Bus will be limited to the rating of the connected circuit
breaker (typically 50% of the step-down transformer's rating). Figure 2-22 shows the
lineup of a typical SCR system containing a Hi-Line Incomer Cubicle.
The two circuit breakers in Figure 2-21 labeled MCB1 and MCB2 are the same
as the Items 31(Hi-Line Incomer Circuit Breaker) in Figure 2-22.
In the following item descriptions, all references are to items shown in Figure
2-22.
REVERSE POWER TRIP RESET Lighted Push Button (LPB) switch (Item 40).
The remainder of the items on the Hi-Line Incomer Cubicle are indicator lights or meters.
The AC AMMETER (Item 32) displays the total current being supplied by the Hi-Line's
step-down transformer. The KILOWATT METER (Item 33) displays the total real power
being supplied by the Hi-Line Incomer Cubicle. The KVAR METER (Item 34) displays the
total reactive power being supplied by the Hi-Line Incomer Cubicle. The AC
VOLTMETER displays the AC voltage being supplied by the Hi-Line Incomer Cubicle to
the Main AC Bus.
The UTILITY OK (Item 35) lamp illuminates if there is no problem with the incoming
commercial power. The REVERSE PHASE ROTATION lamp (Item 36) illuminates if the
incoming commercial power has been connected out of phase with the Main AC Bus. The
PHASE LOSS lamp (Item 37) illuminates if there is a phase loss of the incoming
commercial power. The MCB1 CLOSED lamp (Item 41) illuminates if Main Circuit Breaker
1 is closed. The MCB2 CLOSED lamp (Item 42) illuminates if Main Circuit Breaker 2 is
closed.
In the Model 1000, the Generator Unit assemblies (refer to Figure 2-23) are mounted inside
the Generator Cubicle on the door and side panels.
In the Model 1400, the Generator Unit assemblies (refer to Figure 2-24) are mounted inside
the Generator Cubicle on the door and side panels.
In the Model 1861, the Generator Unit assemblies (refer to Figure 2-25) are mounted inside
the Generator Cubicle on the door and side panels.
Technical Manual
60 HZ SCR Unit
www.nov.com
REVISION HISTORY
TABLE OF CONTENTS
1 OPERATION ..................................................................................................................... 4
1.1 Specifications ......................................................................................................... 4
1.2 Mechanical ............................................................................................................. 6
2 MAINTENANCE ................................................................................................................ 8
3 TROUBLESHOOTING .................................................................................................... 16
3.1 Theory of Operation .............................................................................................. 16
3.2 DC Control Module ............................................................................................... 31
4 TROUBLESHOOTING GUIDE ....................................................................................... 43
5 REMOVAL AND REPAIR ............................................................................................... 51
5.1 Double Access (1200, 1500) ................................................................................ 51
6 REMOVAL & REPAIR .................................................................................................... 62
6.1 Front Access (1400) ............................................................................................. 62
1 OPERATION
The SCR Unit rectifies the three-phase AC supply to provide continuously variable DC
power to the traction motors. The SCR bridge, which performs the rectification, is isolated
by a circuit breaker from the Main AC Bus. The bridge output is assigned to one of the
motors via contactors. The contactors are closed in pairs (DC+ and DC-)(refer to Figure 3-
1).
The contactor logic and the DC voltage level are controlled from the DRILLER'S
CONSOLE (refer to Section 4 of this manual). Electronic circuits in the DC Control Module
regulate the voltage and current within preset limits.
All SCR Units are identical. If one unit is not working, another is usually available to
maintain power to the motor. Similarly, the electronic DC Control Modules and SCR cells of
the bridge are interchangeable.
1.1 Specifications
Electrical
Current
Current Limits
Different limits are selected to allow maximum horsepower and torque to be obtained from
the Rig Equipment without exceeding the Manufacturers ratings. Refer to the label on top
of each DC Control Module to verify current limit settings.
SCR 1 SCR 2
AC BUS AC BUS
MOTOR
The circuit breaker connecting the SCR bridge to the Main AC Bus may be
replaced by a molded case switch.
On older units, the circuit breaker has an overcurrent magnetic trip circuit. Newer units use
ceramic fuses mounted on the vertical bridge for overcurrent protection. There is also an
undervoltage (UV) or shunt trip circuit which is triggered for fuse failure and SCR
overtemperature.
Current Rating
Overtemperature Rating
The overtemperature switch, associated with each SCR is set for 165F (74C) on older
units. Newer units are set for 190F (88C).
1.2 Mechanical
Cubicle
The assemblies are mounted within the SCR Cubicle, on the side and door panels and a
slide pan located below the blowers.
DC Control Module
Many of the SCR rectification and control electronic circuits are assembled on one printed
circuit (PC) card. The PC card One Line Diagram shown in Figure 1-2 (refer to Section 1)
are housed in a module constructed from 14-gauge steel. The module has its own heat
sink.
Size: 4" (10 cM) Wide by 12" (30 cM) Deep by 12" (30 cM) High.
Weight: 21 Pounds (9.5 KG).
Forced-Ventilation System
The ventilation system consists of either two or six air blowers located below the SCR
bridge.
Each bridge requires either one or three motors to power the blowers. Each motor turns
two blowers. One is connected at either end of the motor’s shaft.
Filters are mounted on the ventilation openings. They consist of expanded aluminum gauze
enclosed in a metal frame. They have an MBS (Master Bureau of Standards) rating of 12 to
15% (sufficient to trap common dust particles).
SCR Enclosure
The SCR is mounted within a set of enclosures designed to provide insulation and heat
transfer, and to dampen mechanical vibration. The entire assembly is called the SCR
Enclosure. The innermost assembly consists of the SCR enclosed on either side by
aluminum heatsinks. A two- bolt clamp is tightened to press the heatsinks into the SCR.
Pressure exerted on the SCR is indicated by a gauge located on the top side of the
enclosure.
2 MAINTENANCE
This Section contains specific functional tests to assure proper operation of the SCR unit.
There are two separate tests: one for SCRs and one for SCR Bridges.
Perform the appropriate test(s) after repairing or replacing any of the unit assemblies.
If the unit under test fails to perform as indicated, refer to troubleshooting later in this
section to locate the malfunction.
Refer to Troubleshooting for an explanation of the various SCR Unit circuits, and Removal
and Repair (found at the end of this section) for identification of the components.
See Figure 3-2 for a front panel view of the DC Control Module.
The POWER ON LIGHT (Item 1 on Figure 3-2) illuminates when power is applied to the
DC Control Module.
The TEST SELECT SWITCH (Item 3 on Figure 3-2) permits the operator to check the
Contactor (CONT) and Throttle Reference (REF) signals received from the SCR Control
Cubicle. The TEST SELECT SWITCH and TEST VOLTMETER (Item 2 on Figure 3-2) are
color coded. For example, if the TEST SELECT SWITCH is set to one of the yellow CONT
positions, the TEST VOLTMETER needle will deflect to the yellow band to indicate a
normal condition.
The SCR bridge can be phased up for testing by setting the MANUAL VOLTAGE SWITCH
(Item 5 on Figure 3-2) to ON and rotating the MANUAL VOLTAGE KNOB (Item 4 on
Figure 3-2) clockwise. In the ON position, the MANUAL VOLTAGE SWITCH opens all of
the assignment contactors so that power is not applied to the DC traction motor.
Bridge voltage can be monitored at the SCR VOLTS TEST PINS (Item 7 on Figure 3-2).
The voltage ratio is 16:1, such that the SCR VOLTS TEST PINS (Item 7 on Figure 3-2) will
represent a bridge voltage of 750 VDC when the SCR VOLTS TEST PINS register 46.8
VDC.
Item Description
1. Power ON light
2. Test Voltmeter
3. Test Select Switch
4. Manual Voltage Knob
5. Manual Voltage Switch
6. Zero Throttle Interlock Light
7. SCR Volts Test Pins
8. SCR Amps Test Pins
An indication of Bridge current can be monitored at the SCR AMPS TEST PINS (Item 8 on
Figure 3-2). The current/voltage ratio is 376:1, such that the SCR AMPS TEST PINS
represent 1,000 Amps of bridge current for each 2.66 VDC present on the SCR AMPS
TEST PINS.
The ZERO THROTTLE INTERLOCK LIGHT (Item 6 on Figure 3-2) indicates the
operational status of the module circuit which suppresses the SCR bridge Firing Reference.
When the ZERO THROTTLE INTERLOCK LIGHT is illuminated, the bridge voltage will be
ZERO. It is illuminated under the two following conditions:
2. SCR Unit is assigned to a function before the throttles are set to ZERO.
The light is not illuminated when the throttles are set to ZERO and assigned contactors
PULL IN.
ACTION RESULT
PRELIMINARY
A. Ensure that SCR Unit to be tested will not be A. This step is performed for safety purposes.
assigned from the Driller's Console.
B. Remove the wire from Terminal 134 of the DC B. This opens the contactors.
Control Module.
C. Energize the AC bus, if required. C. On DC Control Module, POWER ON and ZERO
THROTTLE INTERLOCK lights will illuminate (the
ZERO THROTTLE light will extinguish if a DC motor is
assigned AND the REFERENCE SIGNAL was zero at
that time).
D. Close the SCR circuit breaker. D. SCR ON light will illuminate and blowers will switch ON.
SCR BRIDGE CHECK
A. Set the DC Control Module MANUAL VOLTS A. There are no measurable results from this step.
SWITCH to ON.
Rotate the DC Control Module MANUAL VOLTS Observe the reading on the DC Voltmeter mounted on
KNOB slowly clockwise to MAXIMUM and counter- the DC Control Module. The unloaded bridge will
clockwise to MINIMUM. This should cause the initially read a negative voltage and then go positive to
bridge voltage to go from zero to 800 VDC. When 800 VDC.
the SCR bridge is not loaded, the capacitors in the Voltage Feedback from the Voltage Feedback Board
bridge circuitry tend to raise the maximum bridge can be monitored at the DC VOLTS terminals located
voltage. on the front of the DC Control Module. Voltage
Feedback should be 46.8 VDC @ 750 VAC.
The bridge voltage will initially go negative.
ACTION RESULT
CONTACTOR AND THROTTLE CHECK
A. Trip the SCR Circuit Breaker. A. This step is performed for safety purposes.
B. Reconnect the wire to DC Control Module B. This closes the contactors.
Terminal 134.
C. Jumper the Circuit Breaker auxiliary contacts C. This closes the ASSIGNMENT CONTACTORS
TB8-4 to TB8-5. without applying power to the motors.
D. Set the Driller's Console ASSIGNMENT D. Example: Suppose RT is assigned to the SCR Unit
SWITCH to various positions. In each position, in 1 o'clock position. Then RT CONT (pin 129) and
check the Driller's Console contactor (CONT) RT REF 1 (pin 130) can be checked.
and Throttle Reference (REF) signals.
E. Remove the AUXILIARY CONTACT JUMPER E. There are no measurable results from this step.
when all CONT and REF signals are checked
out.
ACTION RESULT
MODULE POWER SUPPLY CHECK
A. Power the Main AC Bus (if necessary). A. There are no measurable results from this step.
B. Check the voltage present at the following B. The voltage at each pins should be as follows:
DC Control Module pins:
Pin(s) Voltage
103 through 108 12 VAC
153 +14 VDC
154 -14 VDC
FIRING PULSE CHECK
GOOD
BAD
BAD
ACTION RESULT
ISOLATE FAULTY SCR This is accomplished by comparing the Current
Feedback ripple and SCR firing pulses on a
dual-trace Oscilloscope while the SCR Unit is
driving a load. During each 60 Hz cycle, there
are six peaks in the ripple. Each of the six SCRs
in the bridge contributes a peak. If one of the
SCRs does not fire, a peak will be missing. If
the SCR misfires, one of the peaks will be
distorted.
A. To check the six SCRs, connect Channel 2 of the A. The waveform will look like the one shown in Figure
Oscilloscope to the DC Control Module SCR 3-5. The firing pulse that is in sync with the missing or
AMPS TEST PINS and connect Channel 1 of the distorted peak is the one going to the faulty SCR
Oscilloscope to the DC Control Module Test (refer to Figure 3-6). In Figure 3-6, the B+ firing pulse
Points listed below: lines up with the distorted peak, indicating that the B+
SCR is misfiring.
DC Control Module SCR
Test Point
TP1 A+
Ch. 1 on
TP2 A- Test Point
TP3 B+ 4 (B-)
TP4 B-
TP5 C+
TP6 C-
Ch. 2 on
SCR Amps
Test Pins
ACTION RESULT
SCR RESISTANCE TEST
A. Trip the SCR Circuit Breaker. A. There are no measurable results from this step.
B. Switch Multimeter polarity to + and the scale to R B. There are no measurable results from this step.
x 10,000.
C. Test the Multimeter by connecting the + (red) and C. The meter needle will swing to indicate Zero
– (black) leads. Ohms.
D. Measure resistance across the SCR by touching D. The resistance measured should be in the >10 KΩ
one Multimeter lead to the AC bus bar and the range. The SCR is leaking if the measured
other Multimeter lead to the DC bus bar. resistance is less. The charging action of snubber
capacitor that is across SCR will be observed (the
resistance will not instantaneously be in the >10
KΩ range, but will instead rise over a period of
seconds). Let the Multimeter needle stabilize
before taking final reading.
E. Measure resistance across the SCR in the E. Again, the resistance should be >10 KΩ.
reverse direction by swapping the Multimeter
leads.
AC LEAKAGE TEST
A. Reactivate an SCR bridge, but do not assign it. A. There are no measurable results from this step.
B. Use a Multimeter to check for AC from each leg B. A reading of >50 VAC indicates excess AC
of the DC Bus to ground. leakage. Most likely a snubber network has
opened.
C. If excess AC leakage was detected in either Step C. Repair/replace any defective components.
B or C, remove power to the SCR Bridge and
check all components in the snubber networks.
3 TROUBLESHOOTING
Figures 3-7 and 3-8 are the schematic diagrams of two different SCR Units. The circuits in
the units can be grouped as follows:
A. SCR Bridge
B. Surge Suppression Circuit
C. Ground Detection Circuit
D. Contactor Control Logic
E. DC Control Module
F. Sprocket Slip Circuit
See Figure 3-7 or 3-8. Three-phase AC from the Main AC Bus is applied to the SCR bridge
through a circuit breaker. Each AC phase is connected to two SCRs. One SCR feeds the
positive AC portion to the +DC Bus and the other SCR feeds the negative AC portion to the
-DC Bus. For example, Phase A is connected to the A+ and A- SCRs. The A+ SCR feeds
the +DC bus while the A- SCR feeds the -DC bus.
The +DC and -DC buses are connected to traction motors via assignment contactors. The
SCRs are switched on and off to vary the DC level through firing pulses applied across the
GATE and CATHODE terminals of each SCR. The firing pulses are generated in the DC
Control Module (refer to Figures 3-7, 3-8, and 3-9).
Refer to the Unique Devices section of this manual for a general description of an SCR.
It has a UV Trip coil and is tripped open automatically if 24 VDC power to the coil is
interrupted. The positive terminal of the coil is permanently connected to +14 VDC power.
The negative terminal is connected to -14 VDC power through various normally-closed
switches which signal the following hazardous conditions:
SCR Overtemperature
There are two temperature sensors. One is mounted on the top of each heat sink column.
The sensor contact is designed to open when the heatsink temperature exceeds 195F
(91C).
Fuse protection for the SCR consists of two 600 Amp fuses mounted in parallel. The UV
Trip circuit is wired through blown-fuse indicator microswitches.
Emergency Off
The UV Trip circuit is also activated by the normally closed EMERGENCY OFF pushbutton
on the DRILLER'S CONSOLE.
Three Current Transformers (CT1, CT2 and CT3) are used to sense current flowing into the
SCR bridge. On PC1 board, the CT signals are rectified and the resulting DC output
divided through a resistor circuit. One signal is used to drive the front panel DC
AMMETER. The other signal is applied to the DC Control Module as SCR Amps (Pin 131).
The SCR Amps signal is 2.66 Volts per 1,000 Amps out of the SCR bridge.
3.1.4 RC Filter
A ferrite core is used for each SCR to reduce the rate of change of current (dI/dT) through
the SCR. The RC filter (a resistor and capacitor) is designed to reduce the rate of change
of voltage (dV/dT) across the SCR. Excessive dV/dT or dI/dT can cause the SCR to misfire or
fail.
A pulse transformer isolates SCR voltages from control module firing circuits. The current
pulse rises very quickly to 1 Amp to HARD FIRE the SCR. It then descends to a 0.5 Amp
BACKPORCH (refer to Figure 3-9) to force more and more of the SCR to turn on through a
regenerative process.
There are two pulses, Main and Backup, which are 60 apart. The Main turns on one SCR.
The Backup keeps an opposite-polarity SCR turned on. The previous opposite-polarity
SCR allowing conduction was turned on 60 before the SCR turned on by the Main pulse.
The Main pulse has a minimum duration of 300 mS. The Backup has a minimum duration
of 200 mS. Main and Backup pulses are separated by 2.77 mS. Main and Backup pulses
reoccur every 16.66 mS for each device.
The +DC and -DC buses are tapped to develop a 16:1 ratio analog of the SCR bridge volts.
DC+ and DC- signals from the DC buses dropped through a set of 3.9 K resistors are
used to drive the front panel SCR Voltmeter. The other is a differential voltage signal (+Vbr)
- (-Vbr). This is applied to the DC Control Module (Pins 101-102) for use in the DC
Regulator circuit. When the SCR bridge voltage is 750 VDC, the differential voltage signal
is 46.8 VDC.
Transformer T5 (see Figures 3-7 or 3-8) supplies three-phase 46 VAC, to the PC1 board.
On PC1, the 46 VAC is rectified to 60 VDC for contactor power supply.
The star winding of transformer T4 supplies six 12 VAC three-phase voltages to the module
(VCA, VCB, VAB, VBA, VBC, and VAC to pins 103 through 108). These signals are used to
synchronize firing pulses for the six SCRs and derive ±14 VDC power supplies.
This is an RC circuit which filters transient spikes on the AC bus. Circuit loss does not
disable the drive system but does increase the likelihood of damage to the SCR cells (refer
to Figure 3-10).
The line input is fused and then rectified through a diode bridge. DC output from the bridge
charges a capacitor bank to 1,000 VDC. A 25, 225 W resistor limits the charging current
to 35 Amps. About 30 mS after power is turned on, relay K1 closes to short out the resistor.
The excess charge caused by a spike is discharged through the resistor bank. When power
is turned OFF, the capacitors are also discharged through the resistor bank.
The front panel SURGE SUPPRESSION LIGHT is normally illuminated. It will extinguish if
any of the lines fuses are blown. The line indicator-type fuses are linked via indicator fuse
switches (F4, F5, and F6) to a microswitch (S1) whose normally closed contacts are in
series with the SURGE SUPPRESSION LIGHT circuit. When a line fuse blows, it’s
indicator button opens the indicator switch, thus turning off the SURGE SUPPRESSION
LIGHT.
There are a number of operating conditions and problems that may lead to the generation
of voltage transients. The energization of a transformer primary, a fuse that blows during a
power fault, and switch arcing will all cause voltage transients. These voltage transients
can be responsible for damage to circuit components. Most semiconductor devices are not
able to withstand voltage transients in excess of their voltage ratings.
The MOV-Type Surge Suppression Panel has been made possible due to the improved
devices in the varistor family. The varistor combines the desired characteristics of the ideal
voltage clamp provided by solid-state diode devices with the superior energy-absorbing
ability of a metal oxide element. This MOV-Type Surge Suppression Panel is made of MOV
devices connected line-to-line on the 600 VAC bus in each SCR bridge.
The varistors are fused with 60 Amp indicating fuses. A blown fuse is indicated when the
green SURGE SUPPRESSION LAMP is extinguished.
This circuit (refer to Figure 3-12) consists of three lights. Each light is connected on one
side to a phase of the AC bus and grounded on the other. A series-connected meter
indicates the percentage of the fault.
The lights will dimly illuminate during normal operation. If there is a DC ground fault, it will
complete the circuit through all the phases of the Main AC Bus, so all the three lights will
brightly illuminate. A deflection reading on the %DC GROUND METER indicates a ground
on one of the DC buses.
The bridge output is assigned to one of several traction motors by closing the appropriate
contactors. The contactor logic is set through the DRILLER'S CONSOLE ASSIGNMENT
SWITCH.
Single-pole contactors are used to assign motors which turn in only one direction. For
reversing motors, the outputs of the single-pole contactors are applied to the motor
armature via a double-pole contactor. The double-pole contactor reverses the armature
leads to reverse the motor direction.
The power contactor coils require 74 VDC to energize. The positive terminal of all coils is
connected to +60 VDC. -14 VDC is connected to the negative terminals of the coils by a
number of wired-in-series contacts. These monitor and ensure that all conditions are
satisfactory to power the assigned motor. If any of the contacts in this control logic open,
the power contactors trip and the SCR bridge is phased down.
During the following discussion, refer to Figure 3-13 (a typical Rotary Table Control circuit).
1. The Rotary Table is assigned to SCR 3 at the DRILLER'S CONSOLE
ASSIGNMENT SWITCH.
2. The Rotary Table FORWARD/REVERSE SWITCH is set to REVERSE.
The Rotary Table motor connections are at the bottom-left corner of the schematic. SCR 3
bridge is connected to the Rotary Table motor through single-pole contactors K1 and K6
and reversing contactor K5.
The coil connections for K1, K5 and K6 are shown in the middle of the circuit. The positive
terminals of all the coils are connected to +60 VDC.
Trace the -14 VDC control signal. The -14 VDC power supply in the DC Control Module is
first passed through the normally-closed MANUAL VOLTAGE SWITCH. This switch is
placed in the TEST position to phase up the SCR bridge without applying power to the
traction motors.
The signal emerges from Pin 134 of the DC Control Module as CONT PS. It is routed
through a normally-open auxiliary contact of the SCR 3 circuit breaker. This normally-open
auxiliary contact closes when the circuit breaker is closed, thereby assuring that the SCR
Unit is turned on.
The control signal is then sent to the DRILLER'S CONSOLE where it turns on the SCR 3
ON light. The control signal is also connected to one side of the DRILLER'S CONSOLE
ASSIGNMENT SWITCH. The control signal emerges on the other side at the 3 o'clock
contact since the DRILLER'S CONSOLE ASSIGNMENT SWITCH is set to the 3 o'clock
position.
The contactor signal now passes through the contacts of the RT vane switch relay RL2. A
vane switch was not installed in the Rotary Table equipment; therefore, a jumper was
installed so that RL2 will always be energized. If a vane switch is installed in the Rotary
Table sometime in the future, the jumper can be removed.
The signal next passes through REV contact of the ROTARY TABLE LOCKOUT SWITCH
energizing the coil of contactor K5.
The control signal is then routed through all the normally-closed auxiliary contacts of the
power contactors in the SCR 3 Unit other than K1, K5 and K6. This assures that the bridge
output is not connected to two motors at one time.
At this point in time, the coils of K1 and K6 are energized. To ensure that their contacts
have closed, the control signal is passed through the normally-open auxiliary contacts of
K1 and K6.
The control signal is then returned to the DC Control Module as RT CONT (Pin 129). In the
DC Control Module, the reference for the SCR firing circuits is disabled as long as all the
CONT signals (RT CONT, MP1 CONT, etc.) are not -14 VDC.
The Rotary Table reference and Current Limit signals which originate in the DRILLER'S
CONSOLE are also shown in Figure 3-13.
The DC Control Module (refer to Figure 3-14) contains electronic circuits for the SCR Unit.
These can be grouped into three assemblies:
1. DC Regulator
2. SCR Firing Circuits
3. DW Dynamic Brake
Figure 3-14 shows the DC Control Module block diagram and pin designations.
3.2.1 DC Regulator
The DC REGULATOR is a feedback control circuit which automatically matches the motor
speed and torque to the throttle command from the Control Console in command (Mud
Pump or Driller’s). The DC REGULATOR circuit is shown in Figure 3-14.
The DC REGULATOR output is a FIRING REFERENCE (TP7) to the SCR firing circuits.
Inputs to the circuit consist primarily of the SPEED REFERENCE, SPEED FEEDBACK,
and CURRENT FEEDBACK. The regulator consists of two control loops, an outer
VOLTAGE LOOP (Speed) and an inner CURRENT LOOP (Torque). The SPEED
REFERENCE signal from the Control Console is summed with the SPEED FEEDBACK to
derive a CURRENT COMMAND signal which, in turn, is summed with the CURRENT
FEEDBACK signal to derive the FIRING REFERENCE signal.
The Drawworks has a Foot Throttle to allow quick response to the SCR bridge during
tripping (refer to Figure 3-14). The DW Foot Throttle reference signal (pin 114) is applied
directly to the Current Limit Summing Junction, thus skipping the Speed Feedback
Junction. It, therefore, it acts as a Current Command. When the Driller presses the Foot
Throttle, current to the Drawworks motors rises quickly and the voltage follows.
The DW Speed Reference from the Driller's Console Hand Throttle (pin 117) and the DW
Foot Throttle Reference are auctioneered through D10 and D59 to select the greater value
(more negative) throttle command. When the Driller begins a tripping operation, he first
sets the Drawworks to cathead speed by slightly cracking (moving) the Driller’s Console
Hand Throttle. At this time, the Speed Reference and Foot Throttle are enabled. When the
Driller presses the Foot Throttle to lift a heavy load, the Foot Throttle Reference quickly
supersedes the DW Speed Reference. The Foot Throttle Reference goes to Zero when the
Driller removes pressure from the Foot Throttle.
As a result, the DW Speed Reference is enabled, and the motor speed and torque return to
cathead values.
During testing, it would often be convenient if it were possible to phase up the SCR bridge
without applying power to the motor. A Manual Operation circuit makes this feasible.
When the MANUAL VOLTS switch (S1) is set to the ON position, the -14 VDC CONT
Power Supply to the ASSIGNMENT CONTACTOR logic is disconnected and the MANUAL
VOLTAGE rheostat is connected into the regulator circuit. The bridge can now be phased
up by rotating the MANUAL VOLTAGE rheostat knob clockwise. Power is not applied to
the traction motors since the ASSIGNMENT CONTACTORS remain open.
These circuits generate firing pulses for the SCR bridge (refer to Figure 3-14).
This is an analog of motor torque (torque is directly proportional to the armature current).
This signal originates in the Control Console in command (Mud Pump or Driller’s). These
consoles are equipped with handwheels which the operator rotates to control the traction
motor speed. Each handwheel is linked to a rheostat which outputs a Zero to -8 VDC
Speed Reference signal for Zero (zero speed) to -8 VDC (maximum speed).
The regulator may receive the Speed Reference signal from more than one location.
These circuits generate firing pulses for the SCR bridge (refer to Figure 3-14).
There are six identical firing circuits, one for each SCR. The Firing Pulse waveform actually
consists of two pulses, a main pulse followed by a backup pulse. The backup pulse is
essential for refiring the SCR at low DC output when current is not continuous. The time
difference between the main and backup pulses is constant.
The main pulse is synchronized with one of the six phase signals from the AC bus (VAB,
VBC, etc.) and Firing Reference from the DC Regulator. The backup pulse is synchronized
with a main pulse signal from one of the remaining firing circuits.
This is an analog of the motor speed. It’s range is zero (no feedback) to +5 VDC (maximum
feedback) at 1,000 RPM.
In a shunt motor, the speed is directly proportional to the armature voltage. Therefore, the
differential voltage feedback signals (VBR+) - (VBR-) are simply compared to Op Amp Z701
to derive the single level 'N' (refer to Figure 3-10).
In a series motor, speed is a function of the armature voltage divided by the magnetic flux.
The flux, in turn, is a function of the armature current. N (the symbol for speed
inconventional motor speed equations) for a series motor is obtained by dividing the
Voltage Feedback signal by the shaped Current Feedback signal in Z703.
There are several Contactor Interlock circuits (i.e., Drawworks, Mud Pump, etc.). Each is
completely separate. When all the interlocks on a particular Contactor
Interlock circuit is closed, the selected function (i.e., Drawworks, Mus Pump, etc.) will be
able to run.
This circuit protects the SCR bridge and the traction motor from unintended starts. It
disables the Firing Reference if the CONT signal switches to -14 VDC while the
corresponding Speed Reference is also great (negative). Thus, the Driller must set the
throttle to ZERO before switching the assignment.
This signal prevents the Speed Reference signal from demanding excess current. It is
simply a negative current flow produced by applying -10 VDC across a selected resistor. To
lower the Current Limit, the negative current flow is decreased by selecting a resistor with
higher value. If the current limit desired is 1,000 Amps, the resistor selected will be 390
K.
This signal prevents the Speed Reference from demanding excess speed. It is particularly
useful for series motors. In shunt motors, an adequate field current prevents overspeeding.
This signal prevents the Current Command from demanding excessive power, and thus
overloading the engines. It is effective at about 90% to 95% of the engine-generator
capacity on line. In other assemblies, the Power Limit signal is derived by processing the
KVA Feedback and KW Feedback from all generators connected to the Main AC Bus.
It’s Gate terminal is FIRED with a current pulse. This pulse is just that, a pulse - it is not
a constant voltage which remains applied to the Gate terminal.
If the Gate terminal is fired as soon as the SCR is forward biased, the SCR is working just
like an ordinary diode.
The SCR Gate terminal firing is delayed to vary the DC output. In this SCR firing circuit:
The six-phase Reference will indicate when the SCR is forward biased.
The Firing Reference will indicate when the SCR should be fired to achieve the desired
DC output level.
Before discussing a three-phase diode bridge rectifier, let us review several simple one-
phase rectifiers.
The most basic is a single-phase half-wave rectifier (refer to Figure 3-15). This consists of
a diode mounted in-line with a one phase AC input. The output is a pulsating DC voltage
that varies between zero and maximum voltage. The diode conducts for 180. For 180
(when the diode is not conducting), the output will be zero. During the other 180, the
output will rise from zero to maximum and then back to zero.
A single-phase diode full-wave rectifier bridge (refer to Figure 3-15) has four diodes. Each
of the AC input lines has two diodes connected to it. Each of these diodes is connected to a
different DC output line. The diodes turn on and off automatically as the bias changes. This
process is called commutation.
The left-most part of Figure 3-16 shows a three-phase diode bridge rectifier and several
input waveforms.
Compare the circuit of the single-phase full-wave bridge rectifier to the three-
phase bridge rectifier. The only major difference is the addition of the two
diodes for the C phase and the C phase winding. If these are disregarded and
the A and B phase voltages are summed, the two rectifier bridges are (for all intents
and purposes) the same.
In a three-phase diode bridge rectifier, things get a little more interesting. Even though the
diode is capable of conducting for 180, it will only do so for 120. This is because the
diode connected to a second AC phase becomes more positively biased than the diode
connected to the first phase. At this time, the diode connected to the first phase stops
conducting and the diode connected to second phase starts conducting. This process
happens on both output voltage legs of the rectifier. The only difference is that the events
on the two output voltage legs occur 60 apart.
Look at the top waveforms (VA, VB, and VC). Anytime VA is +VAC, the A+ diode may
conduct. Anytime VA is -VAC, the A- diode may conduct. However, the diode will not
conduct until 60 after it can start conducting because a diode connected to another phase
has a larger potential voltage. Once the + diode starts conducting, it will be paired with a -
diode on the output DC voltage leg for 60. At that point, a - diode on another phase will
start conducting and the first - diode will stop. VL will thus be the output of diodes A+ and B-
for 60, then diodes A+ and C- for 60, then diodes B+ and C- for 60, etc. Note that each
diode conducts for 120.
The six-diode bridge waveform shows the commutation process through a single 60 Hz
three-phase cycle. The 360 cycle is divided into vertically-divided 30 sections (refer to
waveform A in Figure 3-16). Observe that between 30 to 150, the A+ diode is more
positively biased than either B+ or C+ and is therefore conducting. Similarly, the C- diode is
more negatively biased than either A- or B- during 90 to 210 and is therefore conducting.
Each diode conducts for 120 and is turned off for 240. Table 3-4 gives the commutation
sequence.
90 C- B-
150 B+ A+
210 A- C-
270 C+ B+
330 B- A-
Figure 3-16 also shows a three-phase six-SCR rectifier bridge. In an SCR rectifier bridge,
commutation does not occur automatically. It must be forced through firing pulses.
Observe that SCR A+ is forward biased between 30 and 150. All the SCRs are forward
biased for current flow during 120 of each AC cycle. The SCR can be fired (conduction
started) anytime during this 120 period. This 120 period is defined as the range of the
firing angle ().
DIODE BRIDGE
A. DIODE BRIDGE
SCR BRIDGE
When = 0 (waveform B in Figure 3-16), the SCRs are fired as soon as they are forward
biased. The SCR bridge output is maximum. In this case, the SCR bridge is functioning just
like a Diode Bridge. This gives maximum average VDC (we can call it our reference VDC
or 1).
If is 60 (waveform C in Figure 3-16), the SCRs are not fired until 60 after they are
forward biased. In this case, the average VDC is 0.5.
If is 90 (waveform D in Figure 3-16), the SCRs are not fired until 90 after they are
forward biased. In this case, the average VDC is Zero.
This circuit provides overspeed protection for two series motors that are driven in parallel
from a single SCR bridge. Such an arrangement is normally used for Mud Pumps.
If either one of the motors exceeds a preset speed limit, due to a malfunction in the chain
or belt drive, the circuit cuts off power to both motors by tripping the ASSIGNMENT
CONTACTORS and turning on the front panel SPROCKET SLIP LIGHT.
In the system, overspeed protection for shunt motors is achieved through a FIELD LOSS
RELAY.
The FIELD LOSS RELAY monitors the field current. It opens to trip the assignment
contactors of the motor if the current is <50% of the motor rated value.
Overspeed protection for series motors is normally provided through the OVERSPEED
CIRCUIT in the DC Control Module.
The OVERSPEED CIRCUIT works for all configurations of series motors except where two
motors are driven in parallel from a single SCR bridge (refer to Figure 3-17).
Suppose MP1A breaks its chain drive. The unloaded motor will overspeed. It will draw full
voltage, but little current. Most of the current will flow into MP1B. The OVERSPEED
CIRCUIT will not detect the overspeed because the Current Feedback signal indicates the
total current drawn by the two motors.
The SPROCKET SLIP circuit measures the DC current drawn by each motor through Hall
Effect Devices (HED) and compares them to the voltage to detect overspeed.
Figure 3-18 is the installation diagram of the HEDs. HED1, mounted on the -DC cable,
measures current to the MP1A motor. HED2, mounted on the +DC cable, measures
current to the MP1B motor.
Refer to Figure 3-18, the Sprocket Slip circuit. Differential voltage signals from HED1 and
HED2 are compared on Op Amps Z1 and Z2 to obtain I1A, and I1B respectively. The
currents are auctioneered via D1 and D10 to select the current with the lower value. Since
the motors have equal armature voltage, the motor with the lower current has the higher
speed.
The motor with the lower current is slipping (not doing work). The motor with the higher
current is actually driving the sprocket.
The normally-open contacts of K1 are mounted in the assignment logic of both mud pump
motors. These contacts of K1 open to trip the main assignment contactors, thereby cutting
off power to the motors. When K1 deenergizes the K1 contacts connected between Pins
16 and 19, and between Pins 17 and 18 opens. These contacts are in the Mud Pump
Contactor lines (refer to the Mud Pump Contactor schematic in your drawing package).
The normally-closed contact of K1 closes to turn on the front panel SPROCKET SLIP
LIGHT. The SPROCKET SLIP LIGHT can be switched off by pushing the adjacent RESET
pushbutton. Depressing the RESET pushbutton disconnects +20 VDC, thus allowing the
coil of K1 to reenergize.
4 TROUBLESHOOTING GUIDE
This signal will only be present on the SCR Units driving the
Drawworks.
C. Drawworks Speed Reference C. Monitor the voltage at Pin 117 (DW SPD REF) of the DC Control Module
Signal not present. while moving the Drawworks Hand Throttle from stop to stop. The voltage at
the Pin should vary between Zero VDC (MINIMUM) and -8 VDC
(MAXIMUM). If the voltage is absent, trace the signal from the Drawworks
HAND THROTTLE rheostat.
The Propulsion Control Console ASSIGNMENT SWITCH must be
set to DRILLING (if applicable).
This signal will only be present on the SCR Units driving the
Drawworks.
DRILLER’S CONSOLE
A. Contactor Signal is missing. A. When SCR Circuit Breaker is closed, and DW is selected on the Driller’s
Console, the signal on Pin 116 (DW) of the DC Control Module should be -
14 VDC.
B. Hand Throttle On Driller’s Console B. With the SCR Bridge on, measure the voltage across Pins 101 (VBR+) and
is extremely sensitive. 102 (VBR-) of the DC Control Module. The voltage across the Pins should be
1/16 of the voltage on the SCR Bridge. When the SCR Bridge is +750 VDC,
the voltage between Pins 101 and 102 should be +46.8 VDC. Polarity of Pin
101 is + for series motors, – for shunt motors. Absence of the voltage will
cause this problem.
The MP1 CONT and MP2 CONT signals are only present on
SCR Units which are driving Mud Pumps.
The rig’s Mud Pump 2 may be driven from the DC Control
Module MP1 inputs. The Driller’s Console MP1/2 labels will
match the rig’s MP1/2 labels.
D. Mud Pump #1 Hand Throttle D. Monitor the voltage at Pin 125 (MP1 REF DC) and Pin 126 (MP1 REF
Reference Signal not present. MPC) of the DC Control Module while moving the Driller’s Console
Mud Pump #1 Hand Throttle from stop to stop. The voltage at each of
the pins should vary between Zero VDC (MINIMUM) and -8 VDC
(MAXIMUM). If the voltage at either of the pins is absent, trace the
signal to the MP rheostat on the Driller’s Console.
DYNAMIC BRAKE
A. Dynamic Brake Logic Signal DB A. Monitor the voltage at Pin 127 (DB FIELD) of the DC Control Module.
FIELD missing. The voltage should be Zero VAC with the SCR Circuit Breaker open,
120 VAC during the braking cycle with the SCR Circuit Breaker closed.
MP1 REF DC
MP2 REF DC
PROP CONT
P REF WHC
MP1 CONT
MP2 CONT
SCR AMPS
DB FIELD
DB CONT
RT CONT
RT REF 2
RT REF 1
CNT -14
RT CL
SLV 2
SLV 1
DB
138
137
136
135
134
133
132
131
130
129
128
127
126
125
124
123
122
121
120
119
See Figure 3-20 for a overall front view of the assemblies in the SCR cubicle.
Figure 3-20. Typical Model 1200 or 1500 Generator/SCR Cubicle - Double Access
To remove an SCR cell, simply disconnect the incoming wires to the terminal board on the
components plate, and remove the bus stubs from the bus bars. Each stub is attached to
the bus bar with two 3/8 Inch bolts.
The trigger fuse lead on the spare SCR cell is left unhooked. If it is to be a + cell (located at
the front of the cubicle), connect the lead to the left stub, which is attached to the +DC bus
bar. If it is to be a - cell (located at the rear of the cubicle), connect lead to the right stub,
which is attached to the -DC bus bar (the wire should always be attached to the SCR cell
bus bar that supports the fuse).
5.1.3 SCR Removal and Reassembly Procedure for Front and Rear Access, Horizontal
Bridge
1. Trip the SCR Circuit Breaker before touching any part of the SCR Enclosure.
10 11
3
4
1
6
7 13 9
11 14
10 12 8 7
Item Description
1. Pulse Transformer
2. 1 F Capacitor
3. Fuse
4. Microswitch
5. TB1
6. TB2
7. Heat Sink
8. 25, 55W Resistor
9. Clamp
10. Bus Stub
11. GEN Stub
12. SCR
13. Overtemperature Switch
14. Pressure Gauge
Figure 3-21. SCR Cell Mechanical View - Double Access
2. Tools needed: screwdriver, 7/16" box end wrench, socket wrench handle and
extension, 3/8" socket, and ½" socket.
4. Replace the trigger fuse if its plunger has tripped the microswitch.
8. Remove the 1/4” bolts at the back of the enclosure and disconnect the Gate (G) and
Cathode (K) leads. Once these things have been accomplished, extract the Gate (G)
and Cathode (K) leads through the hole in the Glastic box.
9. Disconnect the capacitor and trigger fuse leads and lift out the Glastic box.
10. Loosen the two 3/8" bolt clamp and lift out the SCR.
11. Separate the heatsink connections and lift out the SCR.
12. Replace the SCR and reassemble in reverse order. Braid the SCR leads.
13. Tighten both clamp bolts equally until the gauge reads recommended value.
14. Reinstall the Glastic box and connect the capacitor and trigger fuse leads.
15. Insert the leads through the Glastic box hole and reinstall the 1/4" bolts.
17. Replace the SCR enclosure and tighten the attaching bolts.
18. Connect the wires leading into the enclosure at the terminal board.
19. Account for all your tools before closing the SCR Circuit Breaker
See Figure 3-22 for a front view of the assemblies in the SCR cubicle.
See Figure 3-23 for a mechanical layout drawing of the SCR Bridge Cell.
SCR Replacement
Figure 3-23. Layout of Front Access Vertical Bridge Model 1400 SCR Cubicle
6.1.1 SCR Removal and Reassembly Procedure for Front Access, Vertical Model 1400 SCR
Bridge
1. Trip the SCR Circuit Breaker before touching any part of the SCR enclosure.
2. Tools needed: screwdriver, 7/16" box-end wrench, and ½" combination wrench.
3. Remove fuse assembly to access SCR assembly. Unfasten Trip Indicator leads.
5. Disconnect the Gate (G) and Cathode (K) leads and pull through the stuffing tube.
6. Pull out the clip lead which connects the resistor to the heatsink.
7. Using the 7/16" box-end wrench, disconnect the bus from the heatsink.
8. Use the ½" wrench to remove the heatsink bolts clamping the SCR.
10. Lift out the defective SCR and put in new one. Braid the SCR leads.
11. Carefully slide reinstall the front heatsink and SCR assembly.
12. Tighten the SCR clamping bolts until the pressure gauge reads 2,500 lb.
13. Using the 7/16" box-end wrench, reconnect the bus to the heatsink.
14. Reconnect the clip lead which connects the resistor to the heatsink.
15. Pull the SCR leads through the stuffing tube and reconnect them.
17. Fasten the Trip Indicator leads and replace the fuse assembly.
18. Count your tools before closing the SCR Circuit Breaker.
Technical Manual
Driller’s Console
www.nov.com
REVISION HISTORY
TABLE OF CONTENTS
1 OPERATION ..................................................................................................................... 4
1.1 Description .............................................................................................................. 4
1.2 Indicators and Controls ........................................................................................... 6
1.3 Operating Instructions............................................................................................. 9
2 MAINTENANCE .............................................................................................................. 12
2.1 Installation ............................................................................................................ 12
2.2 Testing .................................................................................................................. 13
2.3 Servicing ............................................................................................................... 16
3 TROUBLESHOOTING .................................................................................................... 18
3.1 Theory of Operation .............................................................................................. 20
4 REMOVAL & REPAIR .................................................................................................... 35
4.1 Driller's Console .................................................................................................... 35
4.2 DW Foot Throttle .................................................................................................. 35
4.3 Canadian Standards Association (CSA) ............................................................... 39
1 OPERATION
1.1 Description
The Driller's Console is the primary control for the rig DC functions. It is installed on the
drill floor near the Drawworks and contains an Assignment switch to apply power to various
combinations of functions suitable for tripping or drilling. In addition, the Driller's Console
houses a lockout switch and throttle for each function. Lights on the Driller's Console panel
indicate the on-line status of the generators, SCR units, and auxiliary AC devices such as
blowers, chain oilers, etc.
1.1.1 Specifications
The Driller's Console is pressurized. The customer should provide a dry air
bleed at 75 to 150 PSI.
MECHANICAL
Mechanical Console
The console is fabricated from
14-gauge stainless steel. The Speed
Control handles are also stainless
steel. The meters and lights are
mounted behind reinforced glass.
The assembly is watertight.
Size: 18 to 30" High x 36" Wide x 12"
Deep
(46 to 74 cM High x 92 cM Wide x
31 cM Deep).
Weight: 130 to 200 Pounds (60 to 92 KG).
DW Foot Throttle
The DW Foot Throttle is fabricated
from No. 303 stainless steel plate.
The Foot Throttle pedal is
corrugated to provide a skid-proof
footing. The assembly is watertight.
Size: 12.75" High x 12.75" Wide x 11"
Deep
(32 cM High x 32 cM Wide x 28 cM
Deep) maximum.
Weight: 30 Pounds (14 KG).
Figure 4-1 shows the various types of indicators and controls on a typical console. The
numbers shown with parentheses in the following description indicate items on Figure 4-1.
The GEN and SCR Status Lights (Items 3 and 4) illuminate when the corresponding units
are connected to the Main AC Bus.
The positions of the ASSIGNMENT Switch (Item 1) are arranged as the hours on a clock,
with the vertical (12 O'clock) position being OFF.
3
4
5
6
DETAIL A
11
8 8 9 10 10
12
Item Description
1. ASSIGNMENT switch
2. POWER LIMIT meter 13
3. GEN Status lights
4. SCR Status lights
5. BLWR Status lights
6. POWER LIM light
7. ROTARY TABLE ammeter
8. ON-OFF switch
9. EMERGENCY OFF switch
10. FWD-OFF-REV switch
11. RT LIMIT switch
12. Hand Throttle hand wheel
13. Drawworks Foot Throttle
Positions on the left side of the ASSIGNMENT Switch (positions 7 through 11) are
designed for tripping and those on the right side (positions 1 through 5) are intended for
drilling. The Driller, however, is free to choose whichever is needed at any time. For each
of these positions of the ASSIGNMENT Switch, the number in the blocks refer to the SCR
units. The function it drives is listed below the number in the block.
In DRILLING positions, DWA and DWB motors are connected in series (DWS). This
provides full lifting capability, but only half the hoisting speed. On one SCR bridge in
TRIPPING positions, the motors are connected to separate SCR bridges, giving full
hoisting speed.
The BLOWER Status lights (Item 5) are associated with auxiliary AC devices of the
corresponding DC functions. For example, the DW BLOWER light illuminates when all
auxiliary devices of both the Drawworks motors such as blowers and chain oilers are
switched on.
There are LOCKOUT Switches (Items 8 and 10) for each DC function. Once turned ON,
the corresponding Hand Throttle wheel (Item 12 - there are four) is rotated clockwise to
turn it from Zero to maximum speed.
1.2.1 Mechanical
The Drawworks Foot Throttle pedal (Item 13) is pressed to operate the Drawworks once
the DW Hand Throttle (Items 12) is rotated out of the OFF position.
The RT ammeter (Item 7) indicates current drawn by the Rotary Table motor. This is an
indication of developed torque. The RT LIMIT knob (Item 11) is rotated clockwise to
increase the torque limit on the Rotary Table motor from 0 to 10.
The POWER LIMIT meter (Item 2) indicates percentage of available total power capability
of the generators and SCRs on line being consumed by the load. The POWER LIMIT light
(Item 6) illuminates when the generators connected to the Main AC Bus approach (≈90%)
their maximum capability.
The EMERGENCY OFF button (Item 9) is pressed to disconnect power to all DC functions
in case of an emergency.
3. Check the Generator Cubicle GEN RUN and ON LINE status lights to ensure there
are sufficient generators connected to the Main AC Bus to fill the load requirement.
4. Check the SCR status lights to make sure the SCR units to be used are connected
to the Main AC Bus.
5. On Propulsion or Winch systems, ensure that the SCR units to be used have been
assigned to DRILLING at the Control Room Console.
If all auxiliary motor starters are not closed, the BLOWER Status Light will not
illuminate.
9. Rotate the desired HAND THROTTLE (Items 12) clockwise to achieve the desired
speed.
10. The POWER LIMIT Meter (Item 2) will indicate percentage of power consumed out
of the total available from the generators connected to the Main AC Bus. The
POWER LIMIT Light (Item 6) will illuminate when power consumption reaches
≈90%. In the interest of fuel economy, operate the rig between 90 to 95% of full
power (as long as all functions are operating at desired speeds). Power Limit can
be released by connecting additional generators to the Main AC Bus. If all available
generators are connected to the Main AC Bus and the POWER LIMIT Light
illuminates, all the equipment will still run, though at reduced speed. Speed
reduction is performed automatically by a Power Limit circuit to prevent overloading
of the engine/generator sets.
1.3.2 Drawworks
3. After the tripping operation, slow the Drawworks to the HAND THROTTLE setting by
removing pressure on the FOOT THROTTLE.
2. Observe the RT AMMETER periodically to check the current drawn by the motor.
The torque limit will not be exceeded if the RT LIMIT knob is set to match the pre-
determined current limit even if pipe torque forces the Rotary Table to stall.
3. If the Rotary Table stalls, but more torque is required, the torque limit can be raised
by rotating the RT LIMIT Knob clockwise.
1. To turn on the Mud or Cement Pump, perform the preceding General Instructions.
2. For any maintenance activity, the pumps can be operated from the Mud or Cement
Pump Console. The Driller's Console LOCKOUT switch must be switched on before
either Pump Console can be operated.
The Mud and Cement Pump Console Hand Throttles can provide a maximum
of only half speed.
2 MAINTENANCE
Refer to Section 3 (SCR Unit) for general information regarding maintenance and testing of
the SCR Unit. The following part of this section provides installation, testing, and servicing
instructions specific to the Driller's Console.
2.1 Installation
The Driller's Console is normally mounted on top of the pneumatic Drawworks Console.
Cables to the Driller's Console are brought in underneath via connectors or stuffing tubes
(refer to figure 4-1).
TO DW FOOT THROTTLE
TO ROTARY TORQUE INDICATOR
DRY AIR BLEED
Place the Driller's Console on top of the pneumatic Drawworks Console and weld it around
the edges. An alternate method is to bolt it down. If the bolt-it-down method is used,
washers must be placed on the bolts so as to achieve an airtight seal.
The Foot Throttle is flush mounted on the Drill Floor close to the Driller's Console. The
cable from the Driller's Console should be strung below the Drill Floor.
Refer to Figure 4-3. Cutout a 9.75" (25 cM) square section and drill four 0.562" (1.5 cM)
clearance holes. Insert the ½-13 bolts (length of bolt is dependent on deck material) in the
pedal place holes, then place the lower assembly in the cutout and fasten in place with the
½-13 bolts.
2.2 Testing
Perform the functional test after repairing or replacing any of the console assemblies. If the
unit fails to perform as indicated, refer to Troubleshooting later in this section to locate the
malfunction.
To test the Driller's Console, simply observe the operating instructions to run the motors in
each Assignment switch position. Make sure the Blower lights turn on as indicated and the
motor performance follows the throttle command.
If it is not feasible to run the motors, observe the instructions listed in Table 4-2.
4.88
5.38
4.88
5.38
1.00 1.00
12.75
10.75 MOUNTING CENTERS
ACTION RESULT
1. Open all SCR Circuit Breakers. 1. This prevents SCR Bridge phase up
The Circuit Breaker may be a switch. when the assignment contactors are
closed.
2. Jumper the auxiliary contacts of the SCR #1 2. This enables assignment contactors to
switch (CB). Place the jumper between TB8-4 be closed in SCR #1 for the function
to TB8-5 in the SCR #1 Cubicle. being tested. The green SCR ON lamp
on the Drillers console will illuminate.
3. On the ASSIGNMENT Switch, select a 3. In the example, the MP1 contactors will
function to be tested (for example, MP1 may pick up, the blowers on Mud Pump
be run on SCR #1 in the ASSIGNMENT motors of MP1 will run, the auxiliary
switch’s 2 o’clock position by rotating the functions (Rod Oiler, Chain Oiler, etc.)
ASSIGNMENT switch to the 2 O’CLOCK will operate and the MP1 BLOWER ON
position and turning the MP1 OFF-ON switch lamp on the Drillers Console will
to ON. illuminate.
4. Rotate the MP1 HAND THROTTLE fully 4. Monitor the throttle voltage variation at
clockwise while observing the throttle voltage MP1 INPUT (pin 125) on the DC Control
variation. Module. Measure it in respect to
ground. It should be Zero VDC when
the MP1 HAND THROTTLE is fully
counter-clockwise (minimum) and
increase to -8 VDC as it is rotated fully
clockwise (maximum).
5. Repeat Steps 2 through 4 of this functional Refer to the control logic diagrams in
test for each SCR and each function powered the SCR System Print Book to
by the SCR system. Remember to move the identify the DC Control Module
jumper for the auxiliary contacts of the SCR numbers for the desired test
switch to TB8-4 and TB8-5 of the SCR being functions.
tested.
6. Verify the Drawworks Foot Throttle operation. 6. Monitor for Drawworks Foot Throttle
Make this check for each SCR. Jumper TB8-4 voltage on the pin 114 of the DC Control
to TB8-5 in only one SCR at a time. Module as the Foot Throttle is slowly
depressed. The voltage will vary from
Zero VDC when the Foot Throttle is not
depressed to -8 VDC as the Foot
Throttle is fully depressed.
7. Remove the jumper from the SCR switch 7. There is no measurable result from this
(CB) auxiliary contacts. Close the SCR switch functional test action.
(CB) to prepare the SCR to become
operational.
2.3 Servicing
2.3.1 Console
2. Rotate the hand wheels and the switches and examine the switch and rheostat
assemblies behind the Driller's Console door panel. Check the switch contacts and
rheostat wiper arms carefully. Test the rheostat linkage for tightness.
Perform the following service on the Foot Throttle every three months under normal
conditions.
1. Remove the Foot Throttle (refer to Figure 4-4) and open the rear dust cover.
2. Check and re-tighten the set screws. Ensure that the Foot Throttle potentiometer
returns to zero.
3. Check that the rheostat wiper does not rub the wires entering the Foot Throttle.
12.75
12.75
TOP VIEW
8.10
3 TROUBLESHOOTING
The Theory of Operation which follows Table 4-3 provides an explanation of the various
circuits in the Driller's Console.
3.1.1 Console
Mechanical
To permit operation in an explosion hazard area, the Driller's Console electrical assemblies
are isolated from the local atmosphere by maintaining a positive pressure within the
Driller's Console enclosure. This prevents an electrical spark from igniting what could be
explosive gas on the drill floor. The Driller's Console is also watertight.
The customer is required to supply dry air at 75 to 150 PSI via a connector located
underneath the Driller's Console. An Air Pressure Sensor triggers an alarm in the Driller's
Console if positive pressure is lost.
Electrical
The following description describes a Drive System with three generators and four SCR
units. Refer to the diagrams in this section as a study aid. The SCR Schematics Manual
has the diagrams appropriate to your rig.
Figure 4-5 shows the Assignment Switch position labeling and the corresponding wiring of
a typical Driller's Console.
The Driller's Console receives the -14 VDC contactor power supply signals from each SCR
unit from which the throttle power supply is generated. It returns those power signals to the
appropriate throttle and contactor signals.
Figure 4-6 indicates the wiring for a typical SCR 2. Note that SCR 2 can operate the RT,
DW A, and MP 1. Contactor and throttle lines for only these functions are wired.
The AC Section provides 115 VAC power and control signals which turn on the GEN
STATUS lights. The MCC provides control signals which turn on the BLOWER STATUS
lights.
ASSIGNMENT SWITCH
OFF
SCR1 SCR2 SCR3 SCR4 SCR1 SCR2 SCR3 SCR4
RT 12 RT
DWB DWA MP2 11 1 DWS MP1 MP2
PS PS
RT RT
MP1 DWB DWA 9 3 MP1 DWA MP2
PS PS
RT
5 DWS PS - MP2
DW FOOT
THROTTLE
ASSIGNMENT SWITCH
OFF
SCR1 SCR2 SCR3 SCR4 SCR1 SCR2 SCR3 SCR4
www.nov.com
RT 12 RT
DWB DWA MP2 11 1 DWS MP1 MP2
PS PS
RT RT
DWB MP1 DWA 10 2 MP1 DWS MP2
TC Number: 10691194-FDD
TD PS
RT RT
MP1 DWB DWA 9 3 MP1 DWA MP2
PS PS
DW SPD REF 117
RT RT DW FT TH 114
DWB MP2 DWA 8 4 MP1 MP2 DWA
PS PS
RT
5 DWS PS - MP2 RT I LIM 128
RT REF 1 130
SCR 2 SCR 2
MP1 REF MPC 126
DC MODULE
MP1 REF DC 125
CP REF 2 110
DRILLER'S
TB2 CP REF 1 113
CONSOLE
RT CONT 129
ASSIGNMENT TB2 MP1 CONT 124
SWITCH -14 VDC
MP2 CONT 121 154
ASSIGNMENT
Printed REV: 01
P CONT 120
CONTACTORS
DW CONT
Page
116
CP CONT 112
CB AUXILIARY
MANUAL SW
ON
CONTACTOR PS 134
OFF
Document number
22
01
SCR 2 PCI
D25RSTD-1200-MAN-009
Latest REV: 01
Printed On: 2014.08.12.07.05.02
Printed By: dalvis Printed On: 2014.08.12.07.05.02
Figure 4-7 shows the circuits which are enabled when the ASSIGNMENT switch is set to
the 10 o'clock position to run Mud Pump 1 on SCR 2. It does not matter which generator is
connected to the Main AC Bus. Further, the Mud Pump 1 ON/OFF switch is set to ON and
the Mud Pump 1 HAND THROTTLE is rotated to provide the desired number of strokes
from the mud pump.
Assignment Logic
Assignment logic enables a -14 VDC signal (see Figure 4-7) which originates in the DC
Control Module at Pin 154. The -14 VDC signal is returned to the SCR Cubicle to close the
appropriate ASSIGNMENT contactors and then sent to the DC Control Module to unlock
the SCR Firing Circuits.
The -14 VDC signal is first passed through the normally closed MANUAL VOLTS switch.
The MANUAL VOLTS switch is turned on for testing purposes to phase up the SCR bridge
without running a motor.
The -14 VDC signal emerges at Pin 134 as Contactor Power Supply (CONT PS). It is a part
of the 74 VDC contactor voltage: -14 VDC at Pin 154 and +60 VDC at PC1-41, see Figure
4-7. The -14 VDC CONT PS is then passed through the normally-open auxiliary contacts of
the SCR switch. The -14 VDC CONT PS is enabled when the SCR switch is closed (this
feeds AC power to the rectifier bridge).
-14 VDC CONT PS is applied to TB6-2 and from there is supplied to the Driller's
Console TB2-2 via a control cable. The SCR 2 -14 VDC CONT PS is applied to
ASSIGNMENT switch contacts C1 and C10.
Mud Pump 1 can be powered by either SCR 1 or SCR 2. Mud Pump 2 can be
powered by either SCR 3 or SCR 4.
-14 VDC CONT PS also causes L7, the green SCR 2 ON lamp located on the Driller's
Console to illuminate.
The ASSIGNMENT switch (refer to Figure 4-8) consists of eight decks. The first
deck is labeled A, the second B, then C, D, E, F, G, and H. They are divided
into four adjacent deck pairs (A and B, C and D, E and F, G and H). Each deck pair
makes a switch having 12 terminals. Contact is made by a roller between the
terminals of the adjacent deck pairs. For instance, if the ASSIGNMENT switch is set
at the 2 O'clock position, A2 contacts B2, C2 contacts D2, etc.
When the ASSIGNMENT switch is set to the 10 O'clock position, the -14 VDC CONT PS is
conducted from ASSIGNMENT switch contact C10 to D10, passing power to the contacts
of S2, the MP1 ON/OFF switch (this switch also controls the blowers on the MP1 traction
motors). From S2, the power travels to TB2-5 and then down the control cable to TB6-5.
The next contacts in the circuit shown in Figure 4-7 are on the Sprocket Slip Card and are
between PC5-16 and PC5-19. These contacts are shown in Figure 4-7 as normally
opened. They, however, are closed when power is applied. The Sprocket Slip Card
prevents traction motor overspeed, should one of the DC motors be unloaded.
On some systems, there are provisions for locking out the Mud Pump. Refer to
your system prints to see if this provision applies to your system.
-14 VDC CONT PS now goes through the normally-closed SAFETY INTERLOCK
CONTACTS (the Draw Works A (K6) and Rotary Table (K4) power contactors). The -14
VDC of CONT PS is now present on the left side of the Mud Pump power contactors K2
and K7. Since there is now 74 VDC across K2 and K7, they will pick up and connect the
traction motors to the SCR bridge.
K2 and K7's normally-open auxiliary contacts are now closed to bring -14 VDC CONT PS
onto Pin 124 of the DC Control Module. At this time, CONT PS is renamed the
CONTACTOR SIGNAL. The -14 VDC CONTACTOR SIGNAL will turn off the Inhibit Circuit
of the DC Module if the Mud Pump 1 Hand Throttle is at it's full CCW position.
In Figure 4-9, the Mud Pump 1 Throttle Assembly consists of two ganged (mechanically
connected) rheostats. The front rheostat's output is supplied to Pin 125 of SCR 1's DC
Control Module. The rear rheostat's output is supplied to Pin 125 of SCR 2's DC Control
Module. The Mud Pump Throttle Reference signal is active when the Mud Pump Throttle is
rotated enough to produce ≈-1 VDC to the DC Control Module.
1. The output of the Mud Pump Throttle does not have to reach Zero Volts for the
motor to stop rotating.
2. It permits the Charging Pump to be started before the Mud Pump begins to run.
Throttle Logic
The Throttle Hand Wheel is linked to a rheostat which outputs a Zero to -8.2 VDC signal.
This corresponds to Zero through maximum throttle.
The -8.2 VDC supply for the rheostat is developed on the Driller's Console PCB (refer to
Figure 4-10) from the -14 VDC from each SCR unit.
The -14 VDC input is dropped through five Watt 82Ω resistors and applied to 8.2 Volt Zener
diodes. The voltage across a Zener diode is constant even though the incoming voltage
may vary. The regulated -8.2 VDC is applied to the hand throttle, foot throttle and RT I
(torque) Limit rheostats.
The Throttle Hand Wheel rheostats for each function are gang-mounted (moving the
throttle hand wheel rotates the wiper of each rheostat the same number of degrees). The
reference signal from each Throttle Hand Wheel rheostat is applied to all the SCR units
that are capable of powering the same motors. This assures that there will be little change
in the motor performance (e.g., if Mud Pump 1 is switched from SCR1 to SCR2).
A micro-switch is linked to each Throttle Hand Wheel. The micro-switch contacts are
closed when the Throttle Hand Wheel is rotated. The micro-switches control the logic for
the auxiliary functions.
There is one blower light associated with each DC function. The light illuminates when all
associated AC functions are switched on.
Refer to figure 4-11. Observe that the MP1 BLOWER light cannot turn on until the MP1A
BLOWER, MP1B BLOWER, the MP1 ROD OILER, and the MP1 CHAIN OILER are
switched on.
The blower lights operate off 115 VAC from the Generator section. The relays which
switch on the AC functions are located in the MCC (Motor Control Center Section). A relay
is energized when ON/OFF switch MP1 is closed. The normally-open contacts of MP1
close to switch on power to the AC functions listed in the previous paragraph.
The Drawworks and Rotary Table blowers are enabled by their respective OFF/ON
switches.
The blower for the Drawworks or Rotary Table may be configured to run for
two to five seconds before the throttle can be raised to start the traction
motor. If this has been done on your equipment, it was to comply with an ABS
(American Bureau of Shipping) rule which requires a drill floor motor to be purged of
existing air before operation.
The alarm will sound if either the positive pressurization within the Driller's Console is lost
OR the blower is not switched on.
The normally-closed air pressure switch stays closed to trigger the alarm if the pressure
drops below two inches of water difference between the pressure inside the Driller's
Console and outside pressure. The alarm is also triggered if the normally-closed blower
contact does not open when motor starter picks up.
The Power Limit Light illuminates to indicate that the generators connected to the Main AC
Bus are close to power limit. Contactor K1 on the Power Limit board closes to feed 115
VAC to the light. Refer to the Power Limit theory of operation in Section 2 of this manual.
DW/RT Interlock
On some rigs, the motor is used to drive either the Drawworks or the Rotary Table through
a chain drive. A gear box is used to shift the chain drive between the two functions.
A normally-closed contact of the Rotary Table relay is part of the DW CONT logic. Thus,
the interlock circuit enables the DW CONT signal and disables the RT CONT signal. This
situation is reversed when the Rotary Table Throttle Hand Wheel is rotated clockwise. The
micro-switch closes and, in turn, energizes the RT relay. Consequently, the DW CONT
signal is disabled and the RT CONT signal is enabled.
Mechanical
Refer back to Figure 4-4 for front and side views of the DW Foot Throttle. The pedal of the
DW Foot Throttle is linked through a spring to a counterweight. Thus, it will return to the un-
depressed position when released.
Electrical
The incoming -8.2 VDC signal is enabled when the Draw Works micro-switch is closed.
Therefore, the DW Foot Throttle becomes operational only after the Drawworks Throttle
Hand Wheel is set beyond the OFF position.
Figure 4-12 depicts the Foot Throttle circuit. The pedal arm of the Foot Throttle is linked to
the rheostat wiper arm. The resulting DW FT TH signal varies from Zero to -8 VDC. This
equates to Zero to maximum throttle.
PC 1 TB9
- 8.2V 10 1
RED
DW-MSW
TB4
(SCR 4) DW FT TH 10 2
WHITE
TB1
(SCR 1) DW FT TH 12
GROUND 20 3
GREEN
3-CONDUCTOR CABLE
To access the Driller's Console assemblies, open the front panel door by unlocking the
latches. Figure 4-13 shows these assemblies.
Release the four ½-16 bolts located in the corners of the Driller's Console Foot Throttle
pedal assembly and lift it out. To access the Foot Throttle rheostat, remove the rear dust
cover by releasing the four corner screws (see Figure 4-14).
A. Door View
B. Compartment View
Figure 4-13. Driller’s Console Assemblies
Table 4-4. Draw Works Foot Throttle Assembly Components (reference 11467-38 Rev. H)
ITEM QTY PART NUMBER DESCRIPTION
Compliance with CSA Approval/Listing of Model 425 Driller's Console for use in Class I,
Division II, Groups C & D Hazardous Atmosphere Locations.
The Air Purge Alarm System must comply with NFPA-496 Rules for Type Z Purging as
interpreted by CSA.
1. Delete the Alarm Silence toggle switch, or replace with a CSA Approved self
resetting Alarm Silence switch.
3. Increase the orifice diameter to 0.161" (#20 Drill Bit) to provide 5.0 SCFM (cubic feet
per minute at specified conditions of temperature and pressure) flow at 50 PSI.
All Driller's Consoles with a CSA label affixed have been manufactured to
comply with CSA requirements.
4.3.2 Implementation
1. Implement for all Driller's Consoles shipped to Canada or for eventual Canadian
use:
2. Implement for all Driller's Consoles shipped after April 15, 1980.
4. Implementation at any location other than the Ross Hill manufacturing plant, 1530
West Belt North, Houston, Texas 77043, violates CSA Agreements.
WARNING
MULTI-POLE CONNECTORS ARE FOR INSTALLA-
TION PURPOSES ONLY. DO NOT DISCONNECT
UNLESS AREA IS KNOWN TO BE NON-HAZAR-
DOUS AND ALL CIRCUITS ARE DE-ENERGIZED.
LR 34415
AVERTISSEMENT
CONNECTEURS MULTIPOLAIRES CONVENANT
UNIQUEMENT POUR L'INSTALLATION. S'ASSUR-
ER QUE L'EMPLACEMENT N'EST PAS DANGER-
EUX ET QUE TOUS LES CIRCUITS SONT
DESAMORCES AVANT DE DEBRANCHER.
0601-4173-01B
Technical Manual
Mud/Cement Pump
www.nov.com
REVISION HISTORY
CHANGE DESCRIPTION
TABLE OF CONTENTS
1 OPERATION ..................................................................................................................... 4
1.1 Description .............................................................................................................. 4
1.2 Specifications.......................................................................................................... 4
1.3 Operating Instructions............................................................................................. 4
2 MAINTENANCE ................................................................................................................ 7
2.1 Installation .............................................................................................................. 7
2.2 Testing .................................................................................................................... 7
3 TROUBLESHOOTING ...................................................................................................... 7
3.1 Theory of Operation ................................................................................................ 7
4 MUD PUMP CONSOLE .................................................................................................. 13
4.1 Specifications........................................................................................................ 13
5 CEMENT PUMP CONSOLE ........................................................................................... 15
5.1 Specifications........................................................................................................ 15
1 OPERATION
1.1 Description
The Mud Pump Console enables control of the pumps for maintenance operations such as
changing liners. The following description is referenced to the Mud Pumps. The same
description applies to Cement Pumps.
The Mud Pump Console is not intended for routine operation of the mud pumps. The
throttle range from the Mud Pump Console is restricted to half the range available from the
Driller's Console. In addition, the Rod Oiler, chain Oiler, and Charging Pump are not
automatically switched on.
The Cement Pump Console can run the cement pumps from zero to full speed (as
needed). Assignment power however is derived from the Driller's Console so the Driller
can maintain control over when the cement pumps can be operated.
1.2 Specifications
Figure 5-1 identifies the controls and indicators of the Mud Pump. The Mud Pump Console
has a dual set of controls, one for Mud Pump 1 and another for Mud Pump 2.
During normal operation of the pumps from the Driller's Console, the OFF/ON switches
should remain switched on. Padlock attachments are available at the SPROCKET SLIP
RESET buttons to prevent unwanted operation. The POWER ON light illuminates when
the Mud Pump is:
assigned.
not locked out.
turned on.
ELECTRICAL
The Mud Pump Console has dual- and sometimes
triple-control circuits, one for Mud Pump 1 and
another for Mud Pump 2. If there is a third circuit, it
would be for Mud Pump 3. Each circuit receives the
following voltages from the SCR units assignable to
Mud Pumps:
1. +14 VDC to turn on a POWER ON light.
PO WER ON
L IG H T
O F F /O N
S W IT C H
TH ROTTLE H AND W H EE L
To operate a pump from the Mud Pump Console for maintenance activity, perform the
following steps:
1. Set the MP1 (MP2) OFF/ON switch and the corresponding throttle to OFF.
2. At the Driller's Console, set the MP1 (MP2) THROTTLE to OFF. Set the
ASSIGNMENT switch to MP1 (MP2) and turn On the corresponding OFF/ON switch.
3. At the Mud Pump Console, the MP 1 (MP 2) POWER ON light will illuminate.
4. Set the MP 1 (MP 2) OFF/ON switch to ON and rotate the Mud Pump Console
THROTTLE HANDWHEEL to achieve the desired speed.
5. To resume normal operation from the Driller's Console, turn the Mud Pump Console
THROTTLE HANDWHEEL to OFF. Do not turn the Mud Pump Console OFF/ON
switch OFF. Turning the ON/OFF switch OFF at either of the consoles prevents
operation of the pump from either the Mud Pump Console or the Driller's Console.
2 MAINTENANCE
Refer to the Section 3 (SCR Unit) for general instructions regarding shipping,
storage and servicing.
2.1 Installation
Four stabs are welded to the back panel of the console to facilitate bulkhead mounting.
2.2 Testing
Test the affected console after repairing or replacing any of its active components. A
functional test consists of operating the console according to the instructions listed in the
Driller's Console section.
3 TROUBLESHOOTING
Figure 5-2 shows the Mud Pump Console assembly, Figure 5-3 is the Mud Pump Console
circuit, and Figure 5-4 is the Mud Pump Control Logic circuit. Figure 5-4 shows the circuitry
that is activated when MP1 is driven from the Mud Pump Console on SCR 2. Table 5-2 lists
several possible Mud Pump console problems and the troubleshooting to determine the
problem.
L O C K O U T S W IT C H
R H E O S T AT POWER ON
L IG H T
A. DOOR
PC CARD
B . C A B IN E T
The Mud Pump Console (see Figure 5-1) provides local control of the mud pump during
maintenance operations. It is not intended for normal running of the pumps, speed range is
usually restricted to half of the speed available from the Driller's Console.
4.1 Specifications
The enclosure is fabricated from 14 gauge stainless steel and affords a degree of
protection meeting NEMA Standard 4X.
The Mud Pump Console is enclosed in a stainless steel enclosure that has connections for
externally supplied air purging. The Mud Pump Console can be made to be suitable for
Class I Division II operation by providing proper purging air.
The power supplies for the Console are fed from the SCR system. A grounding cable
MUST be run from the Mud Pump Console ground stud to the SCR system ground bus.
The connection must be <1 resistance.
4.1.3 Enclosure
The integrity of the Console and its seals must be maintained and should not be modified in
any manner. All components mounted through the enclosure should be gasketed with RTV
sealant. All screws should be fixed in place with LOCKTITE or similar.
The Mud Pump Console door is held closed by spring catches. These door latches act to
discourage entry by unauthorized personnel. Because of this use, the spring latches should
not be replaced by any other type of securing device.
The mud pump console has an air regulator system the will maintain positive pressure
inside the console as long as there is air supplied by the rig's air supply. The purging
system is built to comply with the National Fire Protection Association's guideline NFPA
496, Purged and Pressurized Enclosures for Electrical Equipment (1989), for type Z
purging. Upon customer request, the equipment can be built to comply with type X purging.
It provides local control of the cement pump during normal or maintenance operations and
is intended for normal running of the cement pumps with control over the full speed range.
Assignment power is only available from the Driller's Console.
5.1 Specifications
The Enclosure Is Fabricated from 14 gauge stainless steel and affords a degree of
protection to NEMA Standard 4X.
It is a stainless steel enclosure having connections for externally-supplied air purging and is
suitable for Class I Division II operation by providing proper purging air.
The power supplies for the Console are fed from the SCR system. A ground cable MUST
be run from the console grounding stud to the SCR system ground bus with <1
resistance.
5.1.3 Enclosure
The integrity of the Cement Pump Console and its seals must be maintained. It should not
be modified in any manner. All components mounted through the Cement Pump Console
enclosure should be gasketed with RTV sealant. All screws should be fixed with LOCKTITE
or similar solution.
The Console door is held closed by spring-loaded latches. These deter accidental entry. Do
not replace with any other type.
The Cement Pump Console has an air regulator system that maintains a positive pressure
inside the Cement Pump Console as long as there is air supplied by the rig's air supply.
The purging system complies with the National Fire Protection Association's guideline
NFPA 496 - Purged and Pressurized Enclosures for Electrical Equipment (1989), for type Z
purging. Upon customer request, the equipment can be built to comply with type X purging.
Technical Manual
Drawworks Braking
www.nov.com
REVISION HISTORY
TABLE OF CONTENTS
1 DW DYNAMIC BRAKE
1.1.1 Description
The DW Dynamic Brake slows the drawworks motors to the HAND THROTTLE speed
setting after the FOOT THROTTLE is released. The DW Dynamic Brake is designed to
function during hoisting. It is not a substitute for the Eddy Current brake commonly
used on the drawworks drum.
The DW Dynamic Brake is automatically applied three seconds after the FOOT
THROTTLE is released (provided the motor speed exceeds the HAND THROTTLE
setting). Typically, the motors require 30 to 40 seconds to coast from full speed to cathead
speed. But with dynamic braking, the time is reduced to 12 to 18 seconds.
1.1.2 Specifications
Electrical
Three 0.16Ω stainless-steel grid resistors are connected in series to provide a 0.48Ω
braking resistance. This resistance is capable of sustaining 300 Amps continuously. On
some offshore SCR drilling systems, the DW Dynamic Brake will have six or more grid
resistors.
In some systems, the grid resistors may be installed outside the SCR house for greater
heat dissipation and control circuit installed in the feeder or dynamic brake cubicle.
Mechanical
The DW Dynamic Brake Cubicle is fabricated from 14 gauge steel and is 90" (230 cM)
high. Refer to your SCR Drawing package for width and depth dimensions. DW Dynamic
Brake Cubicle weight is 2,000 Pounds (960 KG).
Inspect the ventilation grids in the cubicle panels frequently to ensure that they are free of
any debris.
Table 9-1 lists instructions to functionally test the Series Motor Dynamic Brake control
circuit.
The Dynamic Brake slows the drawworks motors to the cathead speed set on the hand
throttle. It is typically used after the Driller hoists a pipe up to the monkey board. When he
throws out the clutch, the motors are free-wheeling at full speed. Recall that when a
separately-excited motor is free-wheeling, it behaves as a generator, sending power back
to the source. This phenomenon is called regeneration. The motor can be effectively
braked by dissipating the regenerated power in a resistor bank.
ACTION RESULT
A. Assign Drawworks and ensure brake is A. Power contactor K2 will be energized. DW DB (DC
off (refer to Figure 9-1). Control Module Pin 138) will be 115 VAC. DW DB CONT
(DC Control Module Pin 135) and DW DB FIELD (DC
Control Module Pin 127) will be Zero Volts.
B. Turn the DW switch ON. B. MS 1 will energize to provide nominal field supply.
C. Release DW FOOT THROTTLE >3 C. Pin 127 of the DC Control Module will switch to 115 VAC.
Seconds. This will energize MS2 and enable full field supply. At the
same time, Pin 135 of the DC Control Module will switch to
115 VAC. This will energize DWDB power contactor K1 and
relay RL1. As a result, the resistor bank will be connected
across DWA motor armature terminals.
D. Depress the foot throttle. D. DC Control Module Pins 127 and 135 will switch back to
Zero Volts. Power contactor K1 and relay RL6 will
deenergize. This will disconnect the resistor bank. Relay
MS2 will deenergize. This will switch the field supply back to
a nominal value. 1.5 Seconds later, DW DB contactor K1
and RL1 will deenergize.
The series motor is not an effective generator unless its field is excited.
The resistor bank (refer to Figure 9-1) is connected across DWA motor armature terminals
when both K1 and K2 power contacts are closed. 115 VAC from transformer T1 keeps
power contactor K2 energized as long as the Overtemperature switch OT1 remains closed.
MS1 will energize when RL5 (the DW Blower contact) is closed. This indicates that the
Drawworks is switched on. 600 VAC is now applied to transformer T2. DW field is kept at
a nominal value by resistors R1, R2 and R3.
The Auxiliary Contacts of Power Contactors K1 and K6 in SCR 1 will close when
Drawworks is assigned to SCR 1. Similarly, when Drawworks is assigned to SCR 2, Power
Contactors K3 and K4 will close. MS2 will energize when the K701 contact in one of the
modules closes. See Figure 3-14 in the SCR Unit section of this manual for the brake
control circuit. Relay K701 and K702 will energize when all the conditions listed below are
fulfilled:
DW CONT (Pin 116) is -14 VDC. This indicates that DRAWWORKS is assigned at the
Driller's Console.
DW FT TH (Pin 114) goes to Zero. This indicates that the FOOT THROTTLE has been
released.
Firing Reference (TP7) is approximately -5 VDC for SCR bridge Zero Volts output.
PROBLEM ACTION
A three second delay is inserted in the circuit to ensure the Driller has not eased up on the
throttle while edging up the pipe. Both K702 in the DC Control Module and K701 in the DC
Control Module energize one second apart (K701 closes first, then K702), indicating that
the Firing Reference is held at -5 VDC. The Firing Reference is inhibited to prevent the
SCR bridge from phasing up while the resistor bank is in the circuit.
When DW Dynamic Brake MS2 energizes, its normally-open contact will close to short-
circuit R1, R2 and R3, letting the DW field go to braking current (200 Amps).
Power contactor K1 and relay RL1 will energize when the DC Control Module K702 closes,
connecting the resistor bank across the DWA armature terminals.
Relays K701 and K702 in the DC Control Module will deenergize if any one of the
conditions listed change.
Normally, the firing Reference increases in the positive direction when DWA motor reaches
cathead speed set by the DW hand throttle.
Figure 9-2 shows a component-side view of the Series Motor DW Dynamic Brake
Assembly.
1.5.1 Description
The Dynamic Brake slows the drawworks motors to the hand throttle speed setting after the
foot throttle is released. The DW Dynamic Brake is designed to function during the hoisting
mode. It is not a substitute for the Eddy Current brake commonly used on the drawworks
drum.
The DW Dynamic Brake is automatically applied three seconds after the FOOT
THROTTLE is released, provided the motor speed exceeds the HAND THROTTLE setting.
Typically, the motors require between 30 and 40 seconds to coast from full speed to
cathead speed. Dynamic braking reduces this to between 12 and 18 seconds.
1.5.2 Specifications
Electrical
Eight 0.16Ω stainless steel grid resistors connected in series provides 1.28Ω braking
resistance. This is capable of sustaining 300 Amps continuously.
Mechanical
The cubicle is fabricated from 14 gauge steel and is 90" (230 cM) high. Refer to your SCR
job book for width and depth dimensions. The weight of the cubicle is 1,500 Pounds (720
KG).
In some systems, the grid resistors may be installed outside the SCR house.
This allows for greater heat dissipation. In this instance, the control circuitry
is installed in the Feeder or Field Supply Cubicles.
The resistor bank becomes hot during the braking operation. Inspect the ventilation grids
in the cubicle panels frequency to make sure they are free of any debris.
Table 9-3 lists instructions to test the DW Dynamic Brake control circuit shown in Figure 9-
3.
The Dynamic Brake slows the drawworks motors to the cathead speed set on the hand
throttle. It is typically used after a pipe is hoisted up to the monkey board. When the clutch
is thrown out, the motors are free-wheeling at full speed. If a separately-excited motor is
free-wheeling, it behaves as a generator, sending power back to the source. This
phenomenon is called REGENERATION. The motor can be effectively braked by
dissipating the regenerated power in a resistor bank.
Figure 9-3 shows the Shunt Motor DW Dynamic Brake circuit. The resistor bank is
connected across the DW A motor armature terminals when both K8 and K9 contacts are
closed.
Figure 3-14 in the SCR Unit section shows the DW Dynamic Brake control circuit. Relay
K701 and K702 will energize when the following conditions are fulfilled:
DW CONT (Pin 116) is -14 VDC. This indicates that DRAWWORKS is assigned at the
Driller's Console.
DW FT TH (Pin 114) goes to Zero. This indicates that the FOOT THROTTLE has been
released.
Firing Reference (TP7) is less than -5 VDC for Zero Volts out of the SCR bridge.
A three to five second delay has been designed into Dynamic Brake electronics. This
prevents the DW Dynamic Brake from engaging whenever the FOOT THROTTLE is
released before the braking has reached the desired level. This gives an immediate
drawworks response if the throttle is activated before the delay is completed and the DW
Dynamic Brake is turned on.
Relays K701 & K702 are both energized, although only the contacts of relay K702 are
utilized. The firing reference will be forced below -5 VDC because the FOOT THROTTLE is
released and the drawworks motors are turning at a high RPM. Anytime the DW Dynamic
Brake is ON, the firing reference is suppressed (inhibited). This prevents the SCR bridge
from phasing up while the resistor bank is connected across the DW A motor armature.
Relay K701 and K702 in the DC Control Module will deenergize when the drawworks
motors speed has decreased to the cathead speed set by the Drawworks Console HAND
THROTTLE. When the DW Dynamic Brake turns OFF, the firing reference will be released
and the SCR bridge will phase up to power the DW A motor.
RL3 picks up before and drops out after K9 so that K8 does not drop out
during the transition. If the contacts of K9 welds closed, K8 cannot pick up.
This will inhibit all braking functions by stopping 115 VAC to DC Control
Module Pin 138.
PROBLEM ACTION
BRAKE DOES NOT SWITCH ON
A. Operational error A. Brake will not switch on if the HAND THROTTLE is set at a
high speed. The HAND THROTTLE should not be rotated
beyond the 10 o'clock position.
B. Overtemperature B. OVERTEMPERATURE switch should be closed.
C. Loss of power supply C. Check for 115 VAC at Pin 138 of the DC Control Module with
DW assigned. If the voltage at Pin 138 is absent, check all
dynamic brake circuit fuses.
D. Control circuit malfunction D. When DW is assigned, K8 should energize. When the FOOT
THROTTLE is released for more than three seconds, Pin 135
of the DC Control Module should switch from Zero to 115
VAC. If it doesn't, replace the DC Control Module in the SCR
Cubicle assigned to DW. When Pin 135 of the DC Control
Module is 115 VAC, K9 and RL3 should power the resistor
bank to DW A motor armature terminals.
BRAKE REMAINS ON
A. Control circuit malfunction A. When the FOOT THROTTLE is depressed again, Pin 135 of
the DC Control Module should switch back to Zero Volts. If it
doesn't, replace the DC Control Module in the SCR cubicle
assigned to DW. When Pin 135 of the DC Control Module
goes to Zero Volts, K9 and RL3 should deenergize. If the DW
Dynamic Brake remains on when the SCR bridge is phased
up, high current will flow through the resistor bank circuit. If
this happens, the overtemperature switch should open and
deenergize K8.
2.1 Operation
2.1.1 Purpose
Regenerative braking is designed to slow the declutched Drawworks (DW) motors. It is not
a supplement or substitute for the Eddy Current Brake which brakes the DW main
drum. The declutched DW motors can take up to 45 seconds to coast downward from full
speed to cathead speed if they are allowed to spin freely, If regenerative braking is utilized,
the DW motors will drop from full speed to cathead speed in twelve to 15 seconds.
2.1.2 Theory
An armature winding.
Mechanical energy.
In a motor, both the armature and field windings have current flowing through them. The
current in each winding generates an electromagnetic field around that winding. The flux
lines of the armature winding electromagnetic field interact with flux lines of the field
winding electromagnetic field to cause a force which tries to push them apart. The field
winding is fixed in place, the armature winding is mounted on a shaft which is free to rotate.
The magnetic interaction causes the armature winding, and thus the shaft on which the
armature winding is mounted, to rotate. This rotation is used to drive pumps or other
mechanical devices. Electrical energy has been changed to mechanical energy.
In a generator, the field winding has current flowing through it which generates an
electromagnetic field. The flux lines of this electromagnetic field are cut by the armature
conductors as the shaft rotates. The rotation is caused by the mechanical energy stored in
the inertia of the motor armature windings and shaft. The field flux cutting the armature
windings generates an Electromotive Force (EMF). The EMF (an impressed potential
voltage) causes a current to flow if a complete circuit is connected to each end of the
armature winding. If the complete circuit contains resistors, the current flow through the
resistors will dissipate the electrical energy as heat. The energy converted to heat is
wasted, since it performs no useful work. This method of slowing down the DW motor is
called Dynamic Braking (refer to Figure 9-5).
It is also possible to connect the power output of the armature windings to the original
electrical power source via the SCR bridge. Returning the converted power (mechanical to
electrical) to the electrical power source is the most efficient way of braking or slowing the
DW motor since energy is not wasted. This way of slowing down the DW motor is called
Regenerative Braking (refer to Figure 9-5).
K2
K1 BRAKE CO N TRO L
S E R IE S R E S IS T O R S IG N A L
M O TO R BANK
A
K1
W H E N K 1 P U LL S IN , E N E R G Y IN T H E F R E E W H E E L IN G
A R M AT U R E D IS S IPAT E S A S H E AT.
These descriptions of Dynamic Braking and Regenerative Braking have been greatly
simplified. We did not explain that:
1. The original power source is AC.
2. The AC is changed to DC by an SCR bridge to power the motor.
3. During Regenerative Braking, the DC output of the motor is changed back to AC by
an SCR bridge.
2.1.3 Technique
Just like a regular diode, SCRs only pass electron flow in one direction. The flow through
the SCR is always from negative to positive as shown by the arrow-headed line shown at
the top of each circuit in Figure 9-5.
( E LE C T R O N F LO W ) ( E LE C T R O N F LO W )
+
- Ia
+
- Ia
F IR IN G O F S C R
+
- M O TO R CEM F -
+
0V
POW ER A A
AC AC
SO U R C E
- SO U R C E
+
M O T O R IN G P O W E R = E a x I a R E G E N E R AT IN G P O W E R = E a x I a
The motor rotates in the same direction in both braking techniques as it does when being
used as a motor. During braking, the armature windings are the power source. The voltage
produced by the armature windings is the opposite of that felt when the motor is functioning
as a motor. The resultant armature winding electron flow is in the same direction. For
electrical power to be returned to the source in Regenerative Braking, the output of the
armature must be switched so the electron flow through the SCRs will continue to flow in
the same direction.
Since the output of the armature winding is DC, the SCR bridge is turned on when the
inverted voltage is greater than the AC source, power will be fed back into the AC source.
There are several actions which must take place for regenerative braking to occur:
2. The contactors for running the motors in normal mode are opened.
4. The SCRs are phased back (fired at an angle greater than 90 degrees) to achieve
regeneration.
When the DW motors have sufficiently slowed down, the following actions must take place:
2. The reversing contactor is opened/switched only when the other contactors are
open.
3. The contactors for running the motors in normal mode are closed.
Figure 9-6 shows the relay and contactor circuitry for DW motor running and Regenerative
Braking operations on SCR 2. This figure will be referred to during the rest of this
discussion of motor running and Regenerative Braking.
3. When Regenerative Braking is being used, the induced voltage in the motor
armature windings is in the opposite direction than when the motor is acting as a
motor.
To accomplish braking, the regenerative braking logic must be understood. This will be
discussed in Electronic Circuitry later in this section. During regeneration, the motor is
treated as a quasi shunt motor. This is accomplished by opening contactor 2K8 and closing
contactor 2K9. The motor field windings will now have current supplied by the Drawworks A
Regen Field Supply (refer to Figure 9-7). The motor now functions as a DC generator.
However, power cannot flow through the SCR bridge because the generated voltage will
reverse bias the SCRs. The armature polarity must be reversed. The armature polarity is
reversed by dropping K5T and picking up K5B. Closing K5B closes contacts 5 and 7 and 6
and 8 which reverses the armature polarity. This places the correct polarity on the SCRs
and enables the SCRs to conduct and feed power back to the source.
A printed circuit board inside the DC Control Module contains the electronic circuits that
controls the external relay logic. The DC Control Module initiates braking three to five
seconds after the FOOT THROTTLE is released. The DC Control Module electronic
circuits make the decision that braking is required and begin the braking sequence by
energizing relays K1 & K2 in the DC Control Module (refer to Figure 9-6). This action
switches Pins 127 and 135 of the DC Control Module to -14 VDC, picking up the 24 VDC
relays RL6 and RL7. These relays accomplish the following:
2.1.9 RL6
Drops Contactor K8 (SERIES FIELD) and allows K9 (REGEN FIELD) to pick up.
2.1.10 RL7
Picks up a motor starter to turn on the braking field (refer to Figure 9-6).
After the motor speed falls to the cathead value, the DC Control Module drops out relays
RL6 & RL7. This will return the contactors to the non-braking state (K5T and K8 energized,
K9 de-energized).
The electronic circuits in the DC Control Module make the decision to initiate braking. This
is done by comparing the speed setting from the hand throttle to the speed feedback
signal. The DC Control Module electronics are designed to handle the change in polarity of
the voltage feedback signal that occurs during braking.
Zero throttle interlock is overridden during the braking cycle. This is necessary because of
the operation of the armature reversal contactor K5. Braking logic brings -14 VDC into Pin
109 of the DC Control Module. This signal releases the current ramp so that the braking
current level can be obtained. Four conditions must be satisfied before the current ramp
begins:
1. DWA FORWARD is assigned (-14 VDC on Pin 138 of the DC Control Module).
2. The FOOT THROTTLE must be released. The initial braking logic decision will
switch Pins 127 and 135 of the DC Control Module to -14 VDC.
4. Main assignment contactors are energized (-14 VDC on Pin 116 of the DC Control
Module).
During braking, a -14 VDC signal is sent from Pin 135 on the Drawworks A DC Control
Module to Pin 135 of the Drawworks B DC Control Module. This signal prevents the
Drawworks B DC Control Module from being able to run the Drawworks and oppose the
braking action of the Drawworks A motor.
To achieve regeneration, it is essential that firing pulses are never removed from the SCRs.
On systems that have Dynamic Braking, the pulses will be phased back and disappear
when the bridge voltage is not required. This will not occur with regenerative braking. DC
Control Modules are designed to maintain a small firing reference at all times.
1. There is a bridge voltage when the SCR switch (CB) is closed. This voltage will go to
zero when the SCR is assigned.
2. When checking the resistance of the SCRs in a regenerative SCR bridge, not only
does the SCR switch (CB) have to be open, but the DC Control Module supply fuses
must be opened. Otherwise, the firing pulses will be present and the SCR will
indicate a low resistance.
2.2 Troubleshooting
The correct sequence of Regenerative Breaking can be noted by observation of the SCR
Bridge Cubicle:
2. Release the FOOT THROTTLE. The motor current will drop to zero. The motor RPM
will be high, so braking is needed.
3. The system has a three to five second delay designed into the braking sequence so
immediate braking will not occur. After the delay, braking will begin.
4. K8 will drop out and K9 should pick up, (both K8 & K9 or located in SCR 2). K5T in
SCR 2 will switch to K5B.
5. The SCR bridge current will ramp up and the Drawworks A motor speed will return
to the cathead RPM. The SCR Cubicle VOLTMETER will indicate a negative voltage
during the braking action.
6. At the end of the braking cycle, the power contactors will switch back to their pre-
braking position.
7. The SCR bridge will phase up and the Drawworks A motor will resume running at
the cathead RPM.
If the breaking sequence does not function as stated, check the following:
1. Verify that DWA is assigned. The Dynamic Brake does not work on DWB
(Drawworks B) or DWS (Drawworks Series).
2. Pin 135 of the DC Control Module should read -14 VDC when braking is required. If
it does not, but -14 VDC is present on Pin 138 of the DC Control Module. The DC
Control Module is defective, replace it.
3. Contactors K8 and K9 should change states. If they do not pick up, check and
ensure that RL6 is energized.
4. Verify that -14 VDC is being applied to Pin 109 of the DC Control Module.
If problems occur during Regenerative Braking, stop the braking sequence by removing the
input from Pin 138 of the DC Control Module located in the SCR Bridge Unit where the
faulty braking operation is taking place.
Operation Manual
D25RSTD-1200-MAN-015 01
www.nov.com
REVISION HISTORY
TABLE OF CONTENTS
1.1 Purpose
The purpose of the Programmable Logic Controller (PLC) in the control system is to reduce
interconnect cabling and overall components required to operate the system. This is
accomplished through the use of a single, serial communication cable between the various
PLC remote I/O racks located throughout the system. These remote I/O racks are located
as close as is possible to the device that is to be controlled thereby reducing the required
wiring to said components.
The PLC System is made up of a main PLC Rack (refer to Table 1-1) using the S7-315-
2DP CPU manufactured by Siemens, and variable number of Profibus-DP remote I/O racks
utilizing Profibus-DP interface modules manufactured by WAGO. Profibus serial
communication cables are used to interface the main PLC to the remote I/O racks. The
protocol used is Profibus-DP running at 1.5 MB (Megabaud) communication rate.
In addition to providing a serial link for communication of commands between the PLC and
I/O locations, the PLC logic also provides:
1. Useful diagnostic information from all throttles, switches, and various other points in the
system. Status information for the overall system is displayed on the HMI and can aid
in easier troubleshooting of faults and errors.
2. All speed and torque references are programmed to ramp their outputs rather than the
outputs mimicking the signals of the potentiometers. This feature enables gentler start
on the motors and is easier on the engines. By default the ramps are disabled (ramp
time set to zero), but can be activated easily by customer request.
3. Delaying closure of the Assignment Contactor. Setting the Assignment Switch and
switching a drilling function to ON will cause the auxiliary motors to turn on. Once all
motor starters have closed and no alarm exists (for that unit), the Assignment Contactor
will close after a delay of five seconds. Loss of an auxiliary motor after assignment will
cause an audible alarm to sound and the corresponding light on the Driller’s Console to
blink. However, the assignment will remain. The alarm can be canceled in either of two
ways:
A lamp on the SCR House PLC Panel indicates the communication channel status.
2 CONNECTION RECOMMENDATIONS
Figure 2-1 shows the serial communication interconnections between the PLC Racks. All
twisted-pair Profibus lines should be wired with Belden Cable #3079A (or equivalent) cable.
The multi-line bus extension cables that connect the Central Racks and Extension Racks
are made by Siemens (Part Number 6ES7368-3BB01-0AA0). All cables should be
connected as shown in Figure 2-1.
The termination resistors built into the Siemens Profibus connectors for each Belden Cable
should be switched on (there is a switch located on the side of the connector) if the
connector is located at the end of the transmission line. Both ends of the line should be
terminated for proper communications.
NOV drawings designate each PLC connection by use of a specific terminal block symbol.
The terminals on each of the I/O Modules are very similar. PLC addressing is configured in
the software. It is thus independent of the order in which the I/O Modules are installed.
Each termination must have a unique identifier. Therefore, the Rack, Slot, and Pin numbers
used to identify each termination are unique.
The unique terminal block designation number is constructed in the following manner:
Example: If a certain PLC output is located at the Driller's Console Central Rack 1 in slot 4
on pin 15, the terminal block designation would be derived thusly:
Slot 2 in SCR CR1 (SCR House PLC Panel Rack 1) contains a CPU. Racks that
do not have a CPU do not have a Slot 2.
Slot 3 of SCR CR1 (SCR House PLC Rack 1) and SCR ER1 (SCR House PLC
Expansion Rack 1) each contain a back Plane Interface Module.
To aid troubleshooting, NOV drawings show the logic associated with each discrete output
in equation form. Understanding what the PLC terminal block designations mean is
essential if you are to gain an understanding of the NOV drawings' logic equations.
All of the input terminal designations for that specific discrete output.
The logic sequence that must exist for that specific discrete output to be switched on.
Figure 3-1 shows a Typical Output Module block and terminal connection diagrams that
show the association between pin numbering and LED location.
In Figure 3-1, note that six Pins (Pins 4, 8, 13, and 17 are common, Pin 1 is +24
VDC, and Pin 20 is Zero VDC (ground)) are not connected to a Channel
Number LED, and that eight Pins are connected to a Channel Number LED on the
Digital Output Module. Pin 3 is connected to LED 0, Pin 5 to LED 1, Pin 7 to LED 2,
Pin 9 to LED 3, Pin 12 to LED 4, Pin 14 to LED 5, Pin 16 to LED 6, and Pin 18 to LED 7.
If the Siemens Step 7 User's Manual is available, refer to its Chapter 17.
Study of the following example will help gain an understanding of the logic process used
when troubleshooting system problems that involve the PLC. Figure 4-1 is a PLC program
shown in a ladder equation that assigns Drawworks A/Rotary Table motor's forward
rotation to SCR 2. The ladder equation of the PLC program states (starting at the left side
and proceeding to the right):
Figure 4-1. Ladder Equation Assigning DWA Motor's Forward Rotation to SCR 8
ALL parts of a ladder equation must be TRUE for the equation to be satisfied.
In this equation, MODE 3, MODE 7, and MODE 11 are set to TRUE by software that
monitors the position of the Driller's Console Assignment Switch. If set to MODE 3
(position 3 closed on the switch) or MODE 7 (position 7 closed on the switch) or MODE 11
(position 11 closed on the switch), this part of the equation will be TRUE.
DWA/RT-FWD-SW is set to TRUE by software based on the position of the Driller's
Console Forward/Off/Reverse Lockout Switch. If this switch is set to the FORWARD
position, this part of the equation will be TRUE.
SCR2 ON is mapped to SCR ER1/4-3 (SCR PLC, Expansion Rack 1, Slot 4, Pin 3). If
SCR 2 is turned on, this part of the equation will be TRUE.
DW-ASSIGN is true if the auxiliary devices are in operation. In this equation, it is ORed (if
either condition is TRUE, the equation is TRUE) with DWA/RT-FWD-SCR2-ASSIGN (the
output of this equation). Therefore, for the overall equation to be TRUE when the
Drawworks A/Rotary Table motor is initially set to run in the forward direction, the auxiliary
devices must be operating. However, once the motor is running in the forward direction, the
auxiliary devices can be turned off and the motor will continue to be powered in the forward
direction.
COM LOSS ALARM is set to ON (the contact is OPEN) when the equipment has detected
a loss in communication. In this case, if the contact is CLOSED (no communication loss
has been detected), this part of the equation will be TRUE.
In the following steps, referral to a specific Pin # indicates that Pin # shown on
the schematic in Figure 3-1. Referral to a specific Channel Number LED #
indicates the appropriate LED of the eight SM322 Module Block LEDs shown on the
left side of Figure 3-1.
The software used to program the PLC is SIMATIC STEP 7, by Siemens. This software is
an easy-to-setup-and-use Windows-based software package.
If you require a copy of this programming software package, the software manual, or the
hand-held programmer, contact NOV’s parts sales department by calling (713)935-8000,
Monday through Friday 9:00 AM through 5:00 PM Central Standard Time (CST ).
6 Purpose
The purpose of the touch screen is to monitor the assignment of the SCRs, display meter
readings, for standard diagnostics and alarm annunciation. The touch screen is NOT
designed to be used for any control, but only for monitoring purpose. The touch screen is
usually mounted on the door of the PLC cubicle, but it may be mounted elsewhere
depending on circumstances.
The touch screen system consists of a Flat Screen Touch Panel (Proface PF3600 family)
communicating with the main SIEMENS PLC (315-2DP CPU) using the MPI
communication port. The communication rate for the MPI port is set to 187.5KB (Kilobaud).
The standard node number assignment for the PLC is 2, and 5 for the touch screen, but
this may change depending on the application.
All twisted-pair Profibus lines should be wired with Belden Cable #3079A or equivalent
cable. The termination resistors built into the connectors on either end of the cable should
be switched on (there is a switch located on the side of the connector).
The touch screen will always display the NOV banner (Main Screen) by default after power
up. From the main screen it is possible to go to other screens. The Main Screen will
contain the National Oilwell Varco contact information. The touch screen may have a
variable number of display screens depending on the application and system configuration,
however there are always a set of standard display screens that are present in every
system. Some of the display screens are explained in detailed below.
The “One-Line” screen will display the overall system status and also the selected
assignment for each SCR. Refer to Figure 7-1 for a pictorial representation of the “One-
Line” screen for a system with 3 GENs and 4 SCRs. Besides the Generator and SCR
status, this screen also shows the Power Limit, Ground Fault and MOV status.
Assignment screen will show a mimic of the Driller’s Console Assignment Chart, with each
square box highlighted if that assignment is active. Touching the square box will bring up
the corresponding assignment status/diagnostic screen.
Once the touch screen is set up with the proper software and a working connection is made
to the PLC, it will monitor the driller’s console assignment.
The touch screen will only let you monitor assignments, and will not let you
change the assignments.
Figure 7-2 shows all the possible assignments. We will use the SCR1-DWS assignment as
our example. Touching the screen on the SCR1-DWS square will bring up the screen
shown on Figure 7-3.
This is the STATUS/DIAGNOSTIC screen for SCR1-DWS assignment. Green circles are
used to indicate O.K. or “On” condition, and Red circles indicate a fault condition, while the
shadowed out circles indicate an inactive condition.
On the left side of the screen are a series of auxiliaries and conditions required for that
particular assignment (such as if the SCR is on and if the motor auxiliaries are on). At the
top of the screen are readings for bridge current, voltage, the percent speed reference, and
if applicable, torque reference or current limit references. In the middle of the screen, it
displays the status of the SCR bridge. On the bottom right of the screen is a display of fault
or lockout conditions for that assignment. In the middle of the screen is a real-time trend
chart displaying the voltage, current, and reference signals for the selected assignment.
The color of the lines/pens in the trend chart correspond to the color of the labels used for
the data on the top portion of the screen.
Drillers Console screen displays all the status information for devices physically mounted
on the Driller’s Console. This screen can be used to monitor for the proper functionality of
all the switches and throttles used on the Driller’s Console. Figure 7-4 shows a typical
Drillers Console screen. This display screen may not be present in every job.
Diagnostic Screen displays the health status for each remote node in the Profibus or other
Communication Network. In some systems, this screen may contain additional information
related to the PLC control system (such as PLC error codes, I/O faults, etc…). Figure 7-5
shows a typical Diagnostic Screen. This display screen may not be present in every job.
FINAL DOCUMENTATION
SCR System
Section 1.2
Spare Parts
www.nov.com
10877885-IDX 01
www.nov.com
www.nov.com
8535-ONGC BARODA
SCR House
10691194-SPL 01
www.nov.com
REVISION HISTORY
CHANGE DESCRIPTION
www.nov.com Page: 2
Quantity to be Ordered
Quantity to be Ordered
Recommended
(In Weeks)
(Currency)
Item No.
Item /
Description of the Recommended Spare Parts NOV Part No.
Ref. No.
1 150AT,250AF,690VAC,80KAIC,3P,THERMALMAGNETIC TRIP UNIT 10065902‐001 1
2 2.0HP,50HZ, M1400/G 10651263‐001 1
3 ASSY DUAL OUTPUT DC EXCITATION FOR 50HZ 10858869‐001 1
4 ASSY‐600V GND FLT W/RELAY OUTS 10050042‐001 1
5 ASSY‐MTR CAL CKT BD FUO 3" MTR 10050037‐001 1
6 ASSY‐PWR LMT CNTLR FUO STD SYSTEMS‐SAME AS STD PWR LMT 10050064‐001 1
7 BDGE‐30V, 1000V, 1PH 10040541‐001 1
8 CAP‐ 1 MFD, 400V,MYLAR,.450WX 1.20L,1.40LS,AXIAL,GLASS WR 10048849‐001 1
9 CB‐ SHUNT TRIP, 120 Vac 10049615‐001 1
10 CB‐1600AF,E3,3P,690VAC, 75KIC,FIXED MOUNT,PR121/P LSI TRIP 10049527‐044 1
11 CB‐UVR(YU),24VDC,FOR E1 THRU E6 FRAME SIZE 10049598‐001 1
12 CONTR‐CONT,0A4B0C, 10A, 600VAC(4)NC CONTACTS 10042430‐001 1
13 CONTR‐CONT,4A0B0C, 10A,600VA 10040445‐001 1
14 CT‐ 10:5 RATIO 10696064‐001 1
15 CT‐ 750:1;2. A;3.25X1.25 MAX WDW 10049358‐001 1
16 CT‐ 800:1;2. A;4.25 X 1.25 WDW 10049363‐001 1
17 DIODE 600V 3A MOTOROLA IN5551 10056131‐001 1
18 DIODE‐ 400V, 3A,GENERAL PURPPOSE 10049907‐001 1
19 DIODE‐ 600V, 1A, STAY BAKED 10048867‐001 1
20 DIODE‐1000V, 1A 10503535‐001 1
21 DIODE‐ZENER, 8.2V, 5W,5% 10049891‐001 2
22 DISPLAY, 0‐1mA INPUT, 85‐264 Vac, integrating totalizer 10641328‐001 1
23 FIELD SPLY‐REVERSING,50 HZ 10507902‐001 1
24 FUSE‐ .6A, 500V C, 10KIC, CLASS M 10056809‐010 20
25 FUSE‐ 2. A, 500V C, 10KIC, 10056809‐017 20
26 FUSE‐ 6. A, 500V C, 10KIC, CLASS M 10056809‐027 20
27 FUSE‐ 50. A, 690V C, 80KIC, CLASS J,GENERAL PURPOSE, 10049487‐001 10
28 FUSE‐ 80. A, 690V C,80KIC,URCLASS,SLO‐BLO mfg#18059 10049488‐001 10
29 Fuse 1.5" FUSE,UL RECOGNIZED,CLASS CC 10042493‐001 20
30 FUSE 15. A, 600VAC, 200KIC 10041937‐036 20
31 FUSE 3.5A, 500V, 10KIC 10056809‐022 20
32 METER‐AAC, 0‐2000, 0‐1MA INPUT 10073344‐001 1
33 METER‐ADC;0‐ 100;DB40;0‐50MV RATING;TAUT BAND;SHUNT 10050299‐001 1
34 METER‐ADC;0‐1000;DB40;0‐1MA RATING;TAUT BAND;SELF‐ 10050283‐001 1
35 METER‐ADC;0‐2000;HOYT;0‐1MADC;200 OHM;N.O.V. LOGO 10050282‐001 1
36 METER‐ADC0‐1550MVDC INPUT 10073345‐001 1
37 METER‐DIGITAL;5V INPUT 10066477‐001 1
38 METER‐FREQ;45‐55HZ;115V INPUT;MINI SWITHCBOARD INSTR;2180 10050337‐001 1
39 METER‐GND;0‐100%AC;GND AMPS;1MADC FULL SCALE; 200 10050357‐001 1
40 METER‐GND;100‐0‐100%ADC;1‐0‐1MADC FULL SCALE; 200 10050355‐001 1
41 METER‐HOUR, 50 HZ 10041452‐001 1
42 METER‐KVAR, 0‐2000, 0‐1MA INPUT 10073341‐001 1
43 METER‐KW;0‐2000;0‐1MA INPUT;MINI SWITHCBOARD INSTR;2180 10050271‐001 1
44 METER‐mADC, 0‐250, 0‐1MA INPUT 10073343‐001 1
45 METER‐PWR LMT;0‐100%;PANEL;EDGEWISE;HORIZONTAL;0‐1MA 10050332‐001 1
46 METER‐TEMP,100 OHM,250DEG C W/FORM C ALARM CONTACT 10051420‐001 1
47 METER‐VDC;0‐1000;HOYT;0‐1MADC;200 OHM;N.O.V. LOGO 10050324‐001 1
48 MODULE‐AC,50HZ OPERATION 10510739‐001 1
49 MODULE‐DC;SHUNT JOB CAL'D 50HZ 10545460‐001 1
50 MONITOR CURRENTMULTITEK M200A1U 120VAC POWER SUPPLY 10056928‐001 1
51 PB‐ILLUM;120AC/VDC;AMB LED 10066871‐001 1
www.nov.com Page 3
Quantity to be Ordered
Quantity to be Ordered
Recommended
(In Weeks)
(Currency)
Item No.
Item /
Description of the Recommended Spare Parts NOV Part No.
Ref. No.
52 PB‐ILLUM;120AC/VDC;RED LEDW/O GUARD 10067327‐001 1
53 PC‐ASSY GEN CURRENT DEMOD PC FUO 3" HOYT METERS 10049978‐001 1
54 PCA‐VOLTAGE FEEDBACK 10050023‐001 1
55 PC‐CONTR AUCTIONEERING 10049998‐001 1
56 PC‐DC SLIDE FOR ABB CB 10049982‐001 1
57 PC‐DRLS CONS;ADD:JUMPER‐PIN 1TO D23 CATHODE 10050015‐001 1
58 PC‐GEN EXC;REV 120 OR 240V RATED 10050053‐001 1
59 PC‐S&A;FREQ MTR LOW PASS FLTR2.56" X 2.70";1" METER POST 10042975‐001 1
60 PL‐ 18V;CLR LENS;RND HD 10049347‐001 1
61 PL‐120V,AMBER,LED,FV,OIL TIGHT 10040442‐001 1
62 PL‐120V,GRN,LED,FV,OIL TIGHT 10040440‐001 1
63 PL‐120V,RED,LED,FV,OIL TIGHT 10042347‐001 1
64 PL‐120V,WHT,LED,FV,OIL TIGHT 10042348‐001 1
65 PL‐120V;BLU;W/O BULB;FVMIN OT 10042219‐001 1
66 PL‐FV MIN OT 120V AMB LENS 10042212‐001 1
67 PL‐FV MIN OT 120V CLR LENS 10042213‐001 1
68 PL‐FV MIN OT 120V CLR LENS 10042211‐001 1
69 PL‐FV MIN OT 12‐V RED LINES 10042210‐001 1
70 REGULATOR‐W/FILTER,0‐15PSI W/GAUGE,20 MICRON 10041246‐001 1
71 RELAY 120 VAC 10040997‐001 1
72 RELAY, 3PDT 10A 24VDC COIL 10032547‐007 1
73 RES‐ 2.0 KOHM,225W, 5% 10049916‐001 1
74 RHEOSTAT‐ 1KOHM, 25W, %,TY 10049950‐001 1
75 RHEOSTAT‐ 1KOHM; W; %;DUAL SECTION 10049953‐001 1
76 RHEOSTAT‐ 1KOHM;DUAL ASSY F/HAND THROTTLE 10049319‐001 1
77 RLY‐ 26.5VDC;DPDT;M39016;700 OHM COIL; MIL# J2K‐4730‐109L 10040956‐001 1
78 RLY‐ 26VDC;0A0B2C; A;3000 COIL;(26.5 VDC);DT 10048955‐001 1
79 RLY TIME DELAY, 120 VAC 10054781‐001 1
80 RLY‐120VAC,2A2B0C,UL & CSA APPROVED 10041268‐001 1
81 RLY‐120VAC,3A1B0C, 10A,IEC D 10042138‐001 1
82 RLY‐120VAC,4A0B0C, 10A,IEC D 10042139‐001 1
83 RLY‐120VAC,SPDT,6A TB RELAY INTERPOSING ISOLATION RLEAY 10049696‐001 1
84 RLY‐TMR,1.0S‐180S 10042599‐001 1
85 RLY‐TMR;24V AC/DC;220..240VAC;.1 S‐ 10S; DIN RAIL MTG ERE 10049712‐001 1
86 RLY‐VOLTAGE SENSING 120VAC PROTECTIVE, UNDERVOLTAGE WITH 10049689‐001 1
87 XFMR‐ 1.1KVA; 380/440/550/660:11 10699397‐001 1
88 XFMR‐ 1KVA; 660;120/208/240CVT 10699393‐001 1
89 XFMR‐ 20KVA; 660/480;400/200 10699396‐001 1
90 XFMR‐ 2KVA; 660; 240/120, CPT 10699385‐001 1
91 XFMR‐ 3KVA; 660:600;3PH;50HZ 10702701‐001 1
92 XFMR‐ 50VA; 660:26.5;CPT 10699382‐001 1
93 XFMR‐ 50VA; 660:32Y 10699383‐001 1
94 XFMR‐ 66VA; 660:115/11,CPT;3PH 10699372‐001 1
95 XFMR‐ 800VA; 660:115/66,CPT;3PH 10842317‐001 1
96 XFMR‐ 150VA; 660:120 50/60HZ 10699384‐001 1
97 XFMR‐ 150VA; 660:45, CPT 10699374‐001 1
98
99
100
101
102
www.nov.com Page 4
FINAL DOCUMENTATION
SCR System
Chapter 2
Technical Document & Drawings
Package
www.nov.com
FINAL DOCUMENTATION
SCR System
Section 2.1
General Drawings
www.nov.com
10877887-IDX 01
www.nov.com
ASSEMBLY DRAWING
www.nov.com
www.nov.com
FINAL DOCUMENTATION
SCR System
Section 2.2
Data
www.nov.com
10877888-IDX 01
www.nov.com
www.nov.com
- CONTENTS -
1 Introduction
1.1 General Information 3
1.2 Inspection 3
1.3 Storage 3
2 Safety 4
3 Installation
3.1 Location - Ventilated units 4
3.2 Location - Encapsulated units 5
3.3 Preparation for service 5
3.4 Installation 6
3.5 Pre-service tests 6
3.6 Operation 6
4 Maintenance
4.1 Routine maintenance 7
4.2 Drying of core and coil assembly 8
4.3 Troubleshooting 8
5 Warranty information
5.1 Standard Warranty Information 9
5.2 Liabilities 9
5.3 Exclusivity 10
5.4 Returned Transformer(s),
Switch(es) or Reactor(s) 10
Section 1 - Introduction
1.1 General Information
These instructions are applicable to all Olsun dry type, ventilated or encapsulated
transformers either single phase or three phase, including general purpose,
substation style and padmount transformers.
1.2 Inspection
Upon receipt, the equipment should be thoroughly inspected for any damage
which may have occurred during transit. The inspection should include all
auxiliary components such as fans, meters, C.T's, P.T's etc.
Locate and remove any special packaging or blocking that may have been
inserted for protection during transit.
The equipment should be checked for loose connections or bolts, and these
should be tightened if necessary to the appropriate torque value (see Appendix
A).
1.3 Storage
Section 2 - Safety
It is essential to protect personnel from coming into contact with live parts.
Access to these parts should be prevented. Before any work is carried out on the
transformer, the supply should be isolated and safeguards introduced to prevent
inadvertent energization during the work period.
The unit must be operated within its design limits at all times. Rated values are
shown on the rating plate attached to the unit. This plate should not be
permanently removed.
The total weight of the unit is shown on the rating plate and on the drawing of the
transformer. Before attempting to lift the unit, check that lifting equipment is rated
for at least the weight of the unit.
Section 3 - Installation
3.1 Location - Ventilated units
When selecting the location for a ventilated dry type transformer, factors such as
ventilation, accessibility for maintenance and atmospheric conditions should be
carefully considered.
Transformers should be so located that there are sufficient clearances from walls
and other obstructions to permit the opening of doors and the removal of covers
and panels for the purpose of inspection, testing and maintenance.
Olsun Electrics Corporation - Richmond, Illinois
Transformers specified for use in outdoor locations will be supplied with weather
resistant enclosures.
The heat generated within the transformer during normal operation must be
dissipated by the transformer enclosure and so adequate ventilation is essential
for proper cooling.
If the transformer has been stored prior to installation, the inspection detailed in
section 1.2 of this manual should be repeated.
3.4 Installation
During installation, use only the lifting and jacking facilities supplied by the
factory. See Appendix B for the recommended method of lifting for substation
and padmount transformers.
After the transformer has been placed in its permanent position, all special
packaging and blocking must be removed. For ventilated units, the core and coil
holding down bolts should be loosened one half turn, to allow the anti-vibration
pads to perform correctly.
Verify that the correct primary tap has been selected for the available supply
voltage. All transformers are shipped with the nominal tap connected, but this
should be changed as required to match the supply voltage. Information
regarding the available taps is shown on the rating plate attached to the
transformer.
The core and enclosure of the transformer should be permanently grounded with
a properly sized strap or conductor in accordance with the National Electrical
Code.
Before energization, check all wiring and operation of cooling fans and any other
auxiliary devices which may be fitted.
It is recommended that the following pre-service tests be carried out before the
transformer is placed in service, to ensure that the transformer is in satisfactory
condition and to provide a reference for future comparison:
3.6 Operation
When the transformer is initially switched on, it is desirable that the load be
increased gradually where this is possible, checking that the rating is not
exceeded. If there are no visible or audible signs or stress during this process,
full load may be applied.
Check the temperature indicator (if fitted) at intervals after placing the
transformer in service.
If it should be necessary to change the primary tap position, this may be carried
out by changing the position of all links as required. Information regarding the
available taps is shown on the rating plate attached to the transformer.
IT IS ESSENTIAL THAT ALL THREE LINKS ON THREE PHASE
TRANSFORMERS ARE IN IDENTICAL POSITIONS.
Section 4 - Maintenance
4.1 Routine maintenance
The maintenance interval for dry-type transformers will be dependant upon the
loading of the transformer the environmental conditions. It is suggested that a
maintenance check be carried out after the first three months of operation and
then at twelve month intervals after that. This interval may be increased or
decreased according to site conditions.
It is essential to protect personnel from coming into contact with live parts. Before
any maintenance is carried out on the transformer, the supply should be isolated
and safeguards introduced to prevent inadvertent energization during the work
period.
2. Check that all winding air ducts are free from dust and foreign material.
These must be kept free by blowing out with dry compressed air.
3. All terminals and connections, accessible nuts and bolts and fittings
should be checked for tightness. Refer to Appendix A for recommended
torque values.
Drying time will depend on several factors and the insulation resistance should
be monitored during the drying process in order to determine when drying is
complete. Measurements should be made before starting the drying process and
at two hour intervals during drying. As the transformer is heated, the insulation
resistance will drop to a minimum value and then gradually increase until a
relatively constant value is obtained. When the value has remained constant at
an acceptable level for three to four hours, drying will be complete.
4.3 Troubleshooting
In the event of a fault condition occurring within the transformer, the unit should
be isolated from the incoming supply and the following procedure should be
carried out:
5.2 Liabilities
This warranty does not include expenses for transportation except as
previously stated, removal, installation, losses or damages due to a
transformer(s), switch(es) or reactor(s) failure, or any other expenses that
may be incurred in relation with repair or replacement. In no instance shall
Olsun be liable for any consequential damages, secondary charges,
expenses of installation or disconnecting, or losses of damages resulting
from an alleged defect of Olsun’s product(s). Olsun’s liability shall be limited
to cost of repairs, or cost of the product, whichever is the lesser.
Olsun shall not be subject to any other liabilities of any kind, except as
specifically noted in writing by Olsun in relation to transformer(s), switch(es)
or reactor(s) which Olsun has manufactured. UNDER NO
CIRCUMSTANCES SHALL OLSUN BE LIABLE FOR ANY
CONSEQUENTIAL DAMAGE OR ANY SPECIAL INDIRIECT OR
INCIDENTAL DAMAGES, WHETHER ARISING OUT OF ANY BREACH OF
ANY EXPRESS OR IMPLIED WARRANTY, BREACH OF CONTRACT,
NEGLIGENCE, OR ANY DEFECT IN, OR MALFUNCTION OF, ANY
TRANSFORMER(S), SWITCH(ES) OR REACTOR(S).
5.3 Exclusivity
This warranty is exclusive and in lieu of all other written, oral, express,
implied or statutory warranties except warranties of title, including but not
limited to warranties of merchantability and fitness for a particular purpose.
Appendix A
Recommended Torque Values for Connection Bolts
The following values are based on grade 2 steel bolts with dry threads.
1/4 - 20 5.5
5/16 - 18 11
3/8 - 16 20
1/2 - 13 50
Appendix B
Transformer Fan Control Recommended Set Points
Olsun Electrics utilizes digital fan controllers for the operation of cooling fans on
transformers it manufacturers. Unless special requests or requirements dictate
otherwise, the two types of controllers typically found on Olsun Electrics manufactured
transformers are the TEC System Model T2612-B and the Cimco Model A21.
For typical applications, Olsun Electrics recommends the following set points for the
digital temprature controllers supplied with its transformers.
Transformer
“Trip” “Alarm”
Transformer Temperature Fans ON Fans OFF
Setting Setting
Type Rise (Degree C) (Degree C)
(Degree C) (Degree C)
(Degree C)
Conventional
150 210 200 180 170
Dry type
Conventional
115 210 200 145 135
Dry type
Conventional
80 210 200 110 100
Dry type
Cast Coil 80 185 175 160 150
Settings above assume 100% base loading at the listed temperature rise, and no
overload due to temperature rise overload potential.
Appendix C
Recommended Method of Lifting Substation Style Transformers
For proper and safe lifting and handling of an Olsun Electrics substation or
outdoor compartmentalized padmounted style transformer, an appropriately rated
lifting beam and straps MUST be used. The “Lifting Details” drawing below
illustrates the proper method of lifting the transformer utilizing this equipment.
Failure to handle the transformer in this manner may result in damage to the
transformer or more critically, injury to handling personnel.
FINAL DOCUMENTATION
SCR System
Section 2.3
System Diagram & Specifications
www.nov.com
10877889-IDX 01
www.nov.com
www.nov.com
FINAL DOCUMENTATION
SCR System
Section 2.4
Electrical / Instrument
www.nov.com
10877890-IDX 01
www.nov.com
www.nov.com
www.nov.com