Gang Way Tower Schedule (Updt as of 10 Feb 2021) R2 10-Feb-21 14:16

Activity ID Activity Name Original Start Finish 2021 2022


Duration
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
Gang Way Tower Schedule (Updt as of 10 Feb 2021) R2 113d 11-Jan-21 A 12-May-21 12-May-21, Gang Way Tower Schedule (Updt as of 10 Feb 2021) R2

MILESTONE 69d 22-Feb-21 08-May-21 08-May-21, MILESTONE


MIL.001 Shippement of the Tubing & Fitting 0d 22-Feb-21 Shippement of the Tubing & Fitting
MIL.002 Test Bed Readiness 0d 05-Mar-21 Test Bed Readiness
MIL.003 Installation Tower 1 To Foundation 0d 07-Mar-21 Installation Tower 1 To Foundation
MIL.003a Installation Tower 2 To Foundation 0d 07-Apr-21 Installation Tower 2 To Foundation
MIL.004 Completion of The IFAT Tower 1 0d 27-Mar-21 Completion of The IFAT Tower 1
MIL.004a Completion of The IFAT Tower 2 0d 27-Apr-21 Completion of The IFAT Tower 2
MIL.005 Ready For Shipment Tower 1 0d 16-Apr-21 Ready For Shipment Tower 1
MIL.006 Ready For Shipment Tower 2 0d 08-May-21 Ready For Shipment Tower 2
Test Bed Construction 106d 11-Jan-21 A 04-May-21 04-May-21, Test Bed Construction

Foundation 58d 11-Jan-21 A 13-Mar-21 13-Mar-21, Foundation


TEP.GW.101 Preparing the Area 3d 11-Jan-21 A 14-Jan-21 A Preparing the Area
TEP.GW.102 Lean Concrete 2d 14-Jan-21 A 16-Jan-21 A Lean Concrete
TEP.GW.103 Installing the Rebar 7d 16-Jan-21 A 24-Jan-21 A Installing the Rebar
TEP.GW.104 Pouring Concrete - Slab 1d 11-Feb-21 A 12-Feb-21 A Pouring Concrete - Slab
TEP.GW.105 Pouring Concrete - Pedestal 2d 06-Feb-21 A 06-Feb-21 A Pouring Concrete - Pedestal
TEP.GW.106 Settlement of Concrete 28d 12-Feb-21 13-Mar-21 Settlement of Concrete
Marine Gangway Tower #01 44d 17-Feb-21 04-Apr-21 04-Apr-21, Marine Gangway Tower #01
TEP.GW.106a Electrical Assembly 7d 17-Feb-21 23-Feb-21 Electrical Assembly
TEP.GW.106ab Hydrolic System Assembly 7d 23-Feb-21 03-Mar-21 Hydrolic System Assembly
TEP.GW.106abc Installation of Replacement Tubing & Fitting (Depend On Tube) 10d 03-Mar-21 13-Mar-21 Installation of Replacement Tubing & Fitting (Depend On Tube)
TEP.GW.107 Installing the Tower to Foundatio n 2d 05-Mar-21 07-Mar-21 Installing the Tower to Foundatio n
TEP.GW.108 Check and Align the perpendicularity 2d 07-Mar-21 09-Mar-21 Check and Align the perpendicularity
TEP.GW.109 Installing the Elevator 2d 09-Mar-21 11-Mar-21 Installing the Elevator
TEP.GW.110 Installing the Gangway 2d 11-Mar-21 13-Mar-21 Installing the Gangway
TEP.GW.111 Installing the Electric & Hydraulic System 5d 13-Mar-21 19-Mar-21 Installing the Electric & Hydraulic System
TEP.GW.113 Internal Check and trial the MGT 3d 19-Mar-21 22-Mar-21 Internal Check and trial the MGT
TEP.GW.114 IFAT Activity 5d 22-Mar-21 27-Mar-21 IFAT Activity
TEP.GW.114b Dismatling the MGT #01 7d 27-Mar-21 04-Apr-21 Dismatling the MGT #01
Marine Gangway Tower #02 65d 24-Feb-21 04-May-21 04-May-21, Marine Gangway Tower #02
TEP.GW.114a Electrical Assembly 7d 24-Feb-21 03-Mar-21 Electrical Assembly
TEP.GW.114ab Hydrolic System Assembly 7d 03-Mar-21 10-Mar-21 Hydrolic System Assembly
TEP.GW.114abc Installation of Replacement Tubing & Fitting (Depend On Tube) 10d 10-Mar-21 21-Mar-21 Installation of Replacement Tubing & Fitting (Depend On Tube)
TEP.GW.115 Installing the Tower to Foundatio n 2d 05-Apr-21 07-Apr-21 Installing the Tower to Foundation
TEP.GW.116 Check and Align the perpendicularity 2d 07-Apr-21 09-Apr-21 Check and Align the perpendicularity
TEP.GW.117 Installing the Elevator 2d 09-Apr-21 12-Apr-21 Installing the Elevator
TEP.GW.118 Installing the Gangway 2d 12-Apr-21 14-Apr-21 Installing the Gangway
TEP.GW.119 Installing the Electric & Hydraulic System 5d 14-Apr-21 19-Apr-21 Installing the Electric & Hydraulic System
TEP.GW.121 Internal Check and trial the MGT 2d 19-Apr-21 21-Apr-21 Internal Check and trial the MGT
TEP.GW.122 IFAT Activity 5d 21-Apr-21 27-Apr-21 IFAT Activity
TEP.GW.123 Dismatling the MGT #02 7d 27-Apr-21 04-May-21 Dismatling the MGT #02
Shipment From Netherland to Surabaya 8d 15-Feb-21 22-Feb-21 22-Feb-21, Shipment From Netherland to Surabaya
TEP.LCR.1000 Tubing & Fit ting (Swagelok) 8d 15-Feb-21* 22-Feb-21 Tubing & Fit ting (Swagelok)
TEP.LCR.1001 Pressure Transmitter & Temprature Transmitter (Yogokagawa) 8d 15-Feb-21 22-Feb-21 Pressure Transmitter & Temprature Transmitter (Yogokagawa)
TEP.LCR.1002 Flexi Hydraulic Hose 8d 15-Feb-21 22-Feb-21 Flexi Hydraulic Hose
TEP.LCR.1003 Cable Gland (Hawke) 8d 15-Feb-21 22-Feb-21 Cable Gland (Hawke)

Actual Work Critical Remaining Work Summary Date Revision Checked Approved
Page 1 of 2
10-Feb-21 Gang Way Tower Schedule - Draft
Remaining Work Milestone
Gang Way Tower Schedule (Updt as of 10 Feb 2021) R2 10-Feb-21 14:16

Activity ID Activity Name Original Start Finish 2021 2022


Duration
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
Shipment From KPME To CSTS My Gresik 30d 13-Apr-21 12-May-21 12-May-21, Shipment From KPME To CSTS My Gresik
TEP.LCR.1004 Packaging MGT #01 7d 13-Apr-21 19-Apr-21 Packaging MGT #01
TEP.LCR.1005 Transport MGT #01 5d 16-Apr-21 20-Apr-21 Transport MGT #01
TEP.LCR.1006 Packaging MGT #02 7d 05-May-21 11-May-21 Packaging MGT #02
TEP.LCR.1007 Transport MGT #02 5d 08-May-21 12-May-21 Transport MGT #02

Actual Work Critical Remaining Work Summary Date Revision Checked Approved
Page 2 of 2
10-Feb-21 Gang Way Tower Schedule - Draft
Remaining Work Milestone