JANGKA WAKTU PELAKSANAAN

No URAIAN PEKERJAAN UNIT VOLUME PEK HARGA/ UNIT JUMLAH HARGA BOBOT MINGGU 1 MINGGU 2 MINGGU3 MINGGU 4 MINGGU 5 MINGGU 6 MINGGU 7 KET
2-7 ,MARET 9-14 MARET 16-21MARET 23-28MARET 30MARET-4APRIL 6-11APRIL 13-15APRIL
I Pek. Instalasi listrik lantai I
1 Pek. Pems armature 4x36 W bh 120 IDR 245,000.0 IDR 29,400,000.00 9.635% 3.212% 3.212% 3.212% 100%
2 Pek. Pems armature 2x36 W bh 30 IDR 175,000.0 IDR 5,250,000.00 1.720% 1.720%
3 Pek. Pems lamp DL 18 W bh 12 IDR 60,000.00 IDR 720,000.00 0.236% 0.236%
4 Pek. Titik instalasi Lampu ttk 162 IDR 125,000.0 IDR 20,250,000.00 6.636% 3.318% 3.318%
5 Pek Titik inst kotak kontak ttk 40 IDR 180,000.0 IDR 7,200,000.00 2.359% 2.359%
6 Pek perpanelan PL-A/PP-A pcs 1 IDR 1,200,000 IDR 1,200,000.00 0.393% 0.393%
7 Pek perpanelan SDP I pcs 1 IDR 6,500,000 IDR 6,500,000.00 2.130% 2.130%

II Pek.Inst Fire Alrm lantai I


1 Pek.Inst Smoke detector bh 10 IDR 125,000.0 IDR 1,250,000.00 0.410% 0.410%
2 Pek Inst ROR bh 10 IDR 160,000.0 IDR 1,600,000.00 0.524% 0.524%
3 Pek Inst Lamp Emergency bh 2 IDR 80,000.00 IDR 160,000.00 0.052% 0.052%
4 Pek Titik Instalasi ttk 22 IDR 100,000.0 IDR 2,200,000.00 0.721% 0.721%
5 Pek Sub- Panel FACP pcs 1 IDR 850,000.0 IDR 850,000.00 0.279% 0.279%
6 Pek Central panel FACP pcs 1 IDR 3,500,000 IDR 3,500,000.00 1.147% 1.147%

III Pek. Inst listrik lantai II


1 Pek. Pems armature 4x36 W bh 144 IDR 245,000.0 IDR 35,280,000.00 11.562% 3.854% 3.854% 3.854% 75%
2 Pek. Pems armature 2x36 W bh 30 IDR 175,000.0 IDR 5,250,000.00 1.720% 1.720%
3 Pek. Pems lamp DL 18 W bh 14 IDR 60,000.00 IDR 840,000.00 0.275% 0.275%
4 Pek. Titik instalasi Lampu ttk 188 IDR 125,000.0 IDR 23,500,000.00 7.701% 7.701%
5 Pek Titik inst kotak kontak ttk 180 IDR 180,000.0 IDR 32,400,000 10.618% 3.539% 3.539% 3.539%
6 Pek perpanelan PL-B /PP-B pcs 1 IDR 1,200,000 IDR 1,200,000 0.393% 0.393%

IV Pek.Inst Fire Alrm lntai II


1 Pek.Inst Smoke detector bh 12 IDR 125,000.0 IDR 1,500,000 0.492% 0.492%
2 Pek Inst ROR bh 12 IDR 160,000.0 IDR 1,920,000 0.629% 0.629%
3 Pek Inst Lamp Emergency bh 2 IDR 80,000.00 IDR 160,000.0 0.052% 0.052%
4 Pek Titik Instalasi ttk 26 IDR 100,000.0 IDR 2,600,000 0.852% 0.852%
5 Pek Sub-panel FCAP pcs 1 IDR 850,000.0 IDR 850,000.0 0.279% 0.279%

V Pek. Inst listrik lantai III


1 Pek. Pems armature 4x36 W bh 144 IDR 245,000.0 IDR 35,280,000.0 11.562% 3.854% 3.854% 3.854% 50%
2 Pek. Pems armature 2x36 W bh 30 IDR 175,000.0 IDR 5,250,000.0 1.720% 1.720%
3 Pek. Pems lamp DL 18 W bh 14 IDR 60,000.00 IDR 840,000.0 0.275% 0.275%
4 Pek. Titik instalasi Lampu ttk 188 IDR 125,000.0 IDR 23,500,000 7.701% 7.701%
5 Pek Titik inst kotak kontak ttk 180 IDR 180,000.0 IDR 32,400,000 10.618% 3.539% 3.539% 3.539%
6 Pek perpanelan PL-C/PP-C pcs 1 IDR 1,200,000 IDR 1,200,000 0.393% 0.393%

VI Pek Inst Fire Alrm Lt III


1 Pek.Inst Smoke detector bh 12 IDR 125,000.0 IDR 1,500,000 0.492% 0.492%
2 Pek Inst ROR bh 12 IDR 160,000.0 IDR 1,920,000 0.629% 0.629%
3 Pek Inst Lamp Emergency bh 2 IDR 80,000.00 IDR 160,000.0 0.052% 0.052%
4 Pek Titik Instalasi ttk 26 IDR 100,000.0 IDR 2,600,000 0.852% 0.852%
5 Pek panel FCAP pcs 1 IDR 850,000.0 IDR 850,000.0 0.279% 0.279%

VII Pek Inst Penyalur Petir


1 Pek Pems elektroda splitzen bh 18 IDR 65,000.00 IDR 1,170,000 0.383% 0.383% 25%
2 Pek Inst hantaran kwt BC m 220 IDR 50,000.00 IDR 11,000,000.00 3.605% 3.605%
3 Pek Box Control pcs 10 IDR 40,000.00 IDR 400,000.0 0.131% 0.131%
4 Pek Pems Elektroda Tanah bh 10 IDR 150,000.0 IDR 1,500,000 0.492% 0.492%

TOTAL IDR 20,205,000.0 IDR 305,150,000.00 100.000% 13.369% 9.662% 20.695% 9.697% 24.876% 9.697% 12.004%
TOTAL RENCANA PROGRESS MINGGU KE 13.369% 23.031% 43.726% 53.423% 78.299% 87.996% 100.000% 0%
AKTUAL PROGRESS MINGGU KE
TOTAL AKTUAL PROGRESS MINGGU KE