Professional Documents
Culture Documents
Contractor:
Consultant:
1 Sand m3 1 237.5
2 Aggregate m3 1 240
3 HCB 40x20x10cm m 2
1 75
4 HCB 40x20x15cm m 2
1 85
5 HCB 40x20x20cm m2 1 96
6 Stone for masonry m3 1 95
7 Stone for Hardcore m 3
1 95
8 Dressed Stone m 3
1 95
9 Selected Material 1 150
10 Eucalyptus Diam 12 Pcs 1 35
11 Diam. 10 Pcs 1 25
12 Diam. 8 Pcs 1 18
15 Cement PPC Qt 1 375
16 Cement OPC Qt 1 385
17 Water Lt 1 0.1
18 Ordinary nails diff. Size Pct 1 96
20 RHS 60x40x2.5 Pcs 1 530
21 RHS 80x80x3 Pcs 1 960
22 RHS 40x20x1.2 Pcs 1 190
25 steel Ø8 Pcs 1 80
26 steel Ø10 Pcs 1 105
27 steel Ø12 Pcs 1 150
28 steel Ø14 Pcs 1 200
29 steel Ø16 Pcs 1 225
30 steel Ø18 Pcs 1 255
31 steel Ø20 Pcs 1 450
32 steel Ø22 Pcs 1 350
33 steel Ø24 Pcs 1 600
34 steel Ø26 Pcs 1 650
35 steel Ø28 Pcs 1 700
36 steel Ø30 Pcs 1 750
39 J - bolt Pcs 1 650
40 Electric Sercute 1 230
41 Roof Rige Pcs 1 23
42 G- 28 CIS Pcs 1 50
43 skerting Pcs 120
44 Mastish Pct 1 43.75
45 Adhsive pct 1 130
Project Amount
Jekale CM Consultancy Commencement date
Material Schedule Completion Date
Months
1 2 3 4 5 6 7 8 9 10
Months
11 12
Project:
Contractor:
Consultant:
1 Forman hr 1 10.5
2 Carpenter hr 1 10
3 A. Carpenter hr 1 6
4 Mason hr 1 11.25
5 Bar Bender hr 1 8.75
6 Plasterer hr 1 10
7 Chiseller hr 1 6.25
8 hr 1
Tiller 13.75
9 Electrician hr 1 5
10 hr 1
Plumber 15
11 Painter hr 1 12
12 Glazer hr 1 12.5
13 hr 1
Welder 12.5
14 Operator hr 1
15 Gang Chief hr 1 8
16 Daily Laborer hr 1 4.375
17 hr 1
Helper
18 1
Truck Driver 12.5
Project Amount:
Jekale CM Consultancy Commencement date:
Labor Schedule Completion Date:
Months
1 2 3 4 5 6 7 8 9
Months
10 11 12
Project:
Contractor:
Consultant:
1 Dozer hr 1 150.00
2 Loader hr 1 56.25
3 Excavator hr 1 450.00
4 Back hoe Loader hr 1 56.25
5 Grader hr 1 250.00
6 Crusher hr 1 200.00
8 Mixer - 500 Lit. hr 1 31.25
9 Dump truck hr 1 162.50
10 Dumper hr 1 100.00
11 Vibrator hr 1 1.25
13 Compactor hr 1 25.00
14 Welding Machine hr 1 20.00
15 Grinding Machine hr 1 18.70
17 Set of Tools hr 1 0.50
18 Metal Cutter hr 1 50.00
20 Polishing Machine hr 1
21 Scaffolding hr 1
22 Tools hr 1 0.50
Project Amount
Jekale CM Consultancy
Commencement date
Equipment Schedule
Completion Date
Months
1 2 3 4 5 6 7 8 9
Months
10 11 12
Durisif General Water Warks Contractor
Project Name
Cost Break Down Format
Rophi Sinta SSIP
B. Indirect Cost = C + D
C. Overhead Cost
D. Risk Allowances
C1. Project Site Overhead C2. Head Office Overhead
Site Overhead Items % TDC % TDC Risk Items % Risk Risk Costs
Sundry Expenses
0.2 C = Total Overhead Cost = C1+C2 = 17.50 E. Total Costs = A + B =
C1 = Total Project Site Overhead Cost % 13 F. Profit Margin = 10 B. Indirect Cost = C +D = 15.00 F. Indirect Cost + Profit = 25.00
ANALYSIS SHEET FOR DIRECT UNIT COST
Excavation and earth work
PROJECT LABOUR HOURLY OUT PUT 0.9 m2 /hr
WORK ITEM Excavation for trench foundation to a depth not exceeding 1.50m. EQUIPMENT
Concrete work
PROJECT 0 LABOUR HOURLY OUT PUT 1.25 m3/hr
Remarks
* Inclusive of waste transport handling etc…
**Inclusive of benefits,travel subsidies and cost of overtime related to targated output.
UF- Utilization Factor
Masonery work
PROJECT 0 LABOUR HOURLY OUT PUT 0.13 m3/hr
WORK ITEM Basaltic or equivalent stone masonry wall (above ground level) EQUIPMENT
Total (1.01) 579.77 Total of (1.02) 31.38 241.35 Total of (1.03) 31.25 240.38
0.13 0.13
Hourly out put Hourly out put Hourly out put
Direct cost A +B +C = 1061.50
Add overhead & profit 265.37
Total Birr = 1326.87 Take birr 1327.00 /m3
Remarks
* Inclusive of waste transport handling etc…
**Inclusive of benefits,travel subsidies and cost of overtime related to targated output.
WORK ITEM Basaltic or equivalent stone masonry wall (below ground level) EQUIPMENT
Total (1.01) 579.77 Total of (1.02) 31.38 165.13 Total of (1.03) 31.25 164.47
0.19 0.19
Hourly out put Hourly out put Hourly out put
Direct cost A +B +C = 909.37
Add overhead & profit 227.34
Total Birr = 1136.71 Take birr 1137.00 /m3
Remarks
* Inclusive of waste transport handling etc…
**Inclusive of benefits,travel subsidies and cost of overtime related to targated output.
SUPERSTRUCTURE
Concrete work
PROJECT 0 LABOUR HOURLY OUT PUT 0.15 m3/hr
Remarks
* Inclusive of waste transport handling etc…
**Inclusive of benefits,travel subsidies and cost of overtime related to targated output.
UF- Utilization Factor
Total (1.01) 1283.55 Total of (1.02) 21.75 29.00 Total of (1.03) 2.00 2.67
0.75 0.75
Hourly out put Hourly out put Hourly out put
Direct cost A +B +C = 1315.22
Add overhead & profit 328.80
Total Birr = 1644.02 Take birr 1645.00 /m2
Remarks
* Inclusive of waste transport handling etc…
**Inclusive of benefits,travel subsidies and cost of overtime related to targated output.
Total (1.01) 1078.82 Total of (1.02) 31.38 41.83 Total of (1.03) 0.50 0.67
Hourly out put Hourly out put 0.75 Hourly out put 0.75
Total (1.01) 947.59 Total of (1.02) 31.38 41.83 Total of (1.03) 0.50 0.67
Hourly out put Hourly out put 0.75 Hourly out put 0.75
3.ROOFING
PROJECT 0 LABOUR HOURLY OUT PUT 25.00 m2/hr
PROJECT
WORK ITEM G-28 CIS roof cover (Akaki)
TOTAL QTY OF WORK ITEM OVERHEAD & PROFIT 25
61.206 40.125
97.32 2.6
A =Material unit cost B =Manpower unit cost C = Equipment unit cost
Direct cost A +B +C = 63
Add overhead & profit 15.72
78.61 Take birr 79.00 /ml
Total (1.01) 850.00 Total of (1.02) 29.25 46.43 Total of (1.03) 2.00 3.17
Hourly out put Hourly out put 0.63 Hourly out put 0.63
Remarks
* Inclusive of waste transport handling etc…
**Inclusive of benefits,travel subsidies and cost of overtime related to targated output.
Metal Works
PROJECT 0 LABOUR HOURLY OUT PUT 0.50 m2/hr (For fixing)
Total (1.01) 950.00 Total of (1.02) 29.25 58.50 Total of (1.03) 2.00 4.00
Hourly out put Hourly out put 0.50 Hourly out put 0.50
Direct cost A +B +C = 1012.50 5.78
Add overhead & profit 253.13 4.62
Total Birr = 1265.63 Take birr 1266.00 /m2
Remarks
* Inclusive of waste transport handling etc…
**Inclusive of benefits,travel subsidies and cost of overtime related to targated output.
Finishing Work
PROJECT 0 LABOUR HOURLY OUT PUT 0.75 m2/hr
Total (1.01) 27.85 Total of (1.02) 22.25 29.67 Total of (1.03) 2.00
2.67
Hourly out put Hourly out put 0.75 Hourly out put 0.75
Direct cost A +B +C = 60.18
Add overhead & profit 15.05
Total Birr = 75.23 Take birr 76.00 /m2
Remarks
* Inclusive of waste transport handling etc…
PROJECT 0 LABOUR HOURLY OUT PUT 1.13 m2/hr
Total (1.01) 535.57 Total of (1.02) 22.94 20.39 Total of (1.03) 2.00
1.78
Hourly out put Hourly out put 1.13 Hourly out put 1.13
Direct cost A +B +C = 557.73
Add overhead & profit 139.43
Total Birr = 697.16 Take birr 698.00 /m2
Remarks
* Inclusive of waste transport handling etc…
PROJECT 0 LABOUR HOURLY OUT PUT 1.50 m2/hr
Total (1.01) 122.00 Total of (1.02) 21.75 16.73 Total of (1.03) 2.00
1.54
Hourly out put Hourly out put 1.30 Hourly out put 1.30
Direct cost A +B +C = 140.27
Add overhead & profit 35.07
Total Birr = 175.34 Take birr 176.00 /m2
Remarks
* Inclusive of waste transport handling etc…
Total (1.01) 430.95 Total of (1.02) 21.75 Total of (1.03) 2.00 2.63
28.62
Hourly out put Hourly out put 0.76 Hourly out put 0.76
Direct cost A +B +C = 462.20
Add overhead & profit 115.55
Total Birr = 577.75 Take birr 578.00 /ml
Remarks
* Inclusive of waste transport handling etc…
Total (1.01) 174.90 Total of (1.02) 26.13 Total of (1.03) 2.00 1.79
23.33
Hourly out put Hourly out put 1.12 Hourly out put 1.12
Direct cost A +B +C = 200.01
Add overhead & profit 50.00
Total Birr = 250.01 Take birr 251.00 /ml
Remarks
* Inclusive of waste transport handling etc…
Total (1.01) 17.78 Total of (1.02) 31.13 20.75 Total of (1.03) 0.00
0.00
Hourly out put Hourly out put 1.50 Hourly out put 1.50
Direct cost A +B +C = 38.53
Add overhead & profit 9.63
Total Birr = 48.17 Take birr 49.00 /m2
Remarks
* Inclusive of waste transport handling etc…
Total (1.01) 54.91 Total of (1.02) 10.38 Total of (1.03) 2.00 2.08
10.81
Hourly out put Hourly out put 0.96 Hourly out put 0.96
Direct cost A +B +C = 67.81
Add overhead & profit 16.95
Total Birr = 84.76 Take birr 85.00 /m2
Remarks
* Inclusive of waste transport handling etc…
Total (1.01) 53.16 Total of (1.02) 22.63 Total of (1.03) 2.00 0.32
3.62
Hourly out put Hourly out put 6.25 Hourly out put 6.25
Direct cost A +B +C = 57.10
Add overhead & profit 14.27
Total Birr = 71.37 Take birr 72.00 /ml
Remarks
* Inclusive of waste transport handling etc…
Total (1.01) 54.91 Total of (1.02) 26.13 Total of (1.03) 2.00 1.18
15.37
Hourly out put Hourly out put 1.70 Hourly out put 1.70
Direct cost A +B +C = 71.45
Add overhead & profit 17.86
Total Birr = 89.32 Take birr 90.00 /ml
Remarks
* Inclusive of waste transport handling etc…
Total (1.01) 54.91 Total of (1.02) 26.13 Total of (1.03) 2.00 0.40
5.23
Hourly out put Hourly out put 5.00 Hourly out put 5.00
Direct cost A +B +C = 60.54
Add overhead & profit 15.13
Total Birr = 75.67 Take birr 76.00 /ml
Remarks
* Inclusive of waste transport handling etc…
Total (1.01) 170.00 Total of (1.02) 26.13 Total of (1.03) 2.00 4.00
52.25
Hourly out put Hourly out put 0.50 Hourly out put 0.50
Direct cost A +B +C = 226.25
Add overhead & profit 56.56
Total Birr = 282.81 Take birr 283.00 /ml
Remarks
* Inclusive of waste transport handling etc…
Painting
PROJECT Hourly out put LABOUR HOURLY OUT PUT 2.10 m2/hr
Hourly Cost
450
0.5
56.25
56.75
87.14 100.00
ment cost(1.03)
Hourly Cost
150
250
400
80.48 100.00
ment cost(1.03)
Hourly Cost
450
0.5
450.5
95.98 100.00
ment cost(1.03)
Hourly Cost
0.5
25
25.50
40.53 100.00
ment cost(1.03)
Hourly Cost
0.5
25
25.50
78.56
ment cost(1.03)
Hourly Cost
450
4062.5
4512.50
99.44
ment cost(1.03)
Hourly Cost
ment cost(1.03)
Hourly Cost
31.25
1.25
25.00
3.13
60.63
5.070 100.000
ment cost(1.03)
Hourly Cost
62.50
2.50
25.00
90.00
3.89
ment cost(1.03)
Hourly Cost
5.00
12.50
ment cost(1.03)
Hourly Cost
1.50
1.50
1.26
Hourly Cost
0.00
0.00
ost(1.03)
Hourly Cost
4.1
4.06
22.65
ost(1.03)
Hourly Cost
31.25
31.25
18.09
ment cost(1.03)
Hourly Cost
62.5
2.5
2
67.00
15.03
ment cost(1.03)
Hourly Cost
5
10.28
ment cost(1.03)
Hourly Cost
1.50
1.50
1.26
Hourly Cost
2.00
2.00
0.20
Hourly Cost
2
2.00
0.06
Hourly Cost
2
2.00
0.07
ment cost(1.03)
Hourly Cost
0.00
0
Hourly Cost
3.91
1.50
5.41
0.37
0.22
Hourly Cost
1.50
1.50
0.03 100.00
Hourly Cost
1.50
2.44
Hourly Cost
2
2
0.13 100.00
Hourly Cost
2
2.00
0.35
Hourly Cost
2
2.00
0.40
Hourly Cost
2
2.00
4.43 100.00
Hourly Cost
2
2.00
0.32 100.00
Hourly Cost
2
2.00
2.10 100.00
1.33
Hourly Cost
2.00
2.00
1.10 100.00
Hourly Cost
2
2.00
2.04 100.00
Hourly Cost
2.00
2.00
0.57 100.00
Hourly Cost
2.00
2.00
0.89 100.00
ment cost(1.03)
Hourly Cost
0.00
0 100.00
Hourly Cost
2.00
2.00
1.03 100.00
Hourly Cost
2.00
2.00
3.07 100.00
Hourly Cost
2.00
2.00
2.46 100.00
Hourly Cost
2.00
2.00
3.64
Hourly Cost
2.00
2.00
0.56
Hourly Cost
2.00
2.00
1.65 100.00
Hourly Cost
2.00
2.00
0.66 100.00
Hourly Cost
0
Hourly Cost
2.00
2.00
1.77
Hourly Cost
2.00
2.00
1.79
1.77
Hourly Cost
2.00
2.00
1.76
1.33
Hourly Cost
2.00
2.00
3.29
0.57
Hourly Cost
2.00
2.00
0.35
0.95
Hourly Cost
4.00
4.00
0.30
0.30 100.00
1.90
Hourly Cost
2.00
2.00
0.13
0.95
Hourly Cost
2.00
2.00
2.88
1.00
Hourly Cost
2.00
2.00
1.64
1.00
Hourly Cost
2.00
2.00
0.14
1.00
Hourly Cost
2.00
2.00
0.09
1.00
Hourly Cost
2.00
2.00
0.21
1.00
Hourly Cost
2.00
2.00
0.02 100.00
8.00
Priced Bill of Qunatity
Unit Quantity Unit Price
It.No Description
(1) (2) (3)
A-SUB STRUCTURE
1.EXCAVATION AND EARTH
WORK
A. SUBSTRUCTURE
6.60 60mm high PVC tile skirting stuck to wall Ml 579.27 72.00
41,824.51
27,874.00
1,795,236.66
13,262.52
63,359.76
439,698.00
21,337.38
2,402,592.83
7,500.00
649,936.25
53,592.25
54,911.80
811,338.05
54,911.80
770,524.60
-
5,374.74
16,542.97
12,326.66
23,481.49
12,326.66
22,300.28
33,045.61
164,922.03
43,467.97
34,190.00
20,378.02
3,599.96
2,340.00
4,687.54
32,755.19
1,456.00
131,466.40 511,668.72
39,360.00
3,006,736.27
51,165.00
33,175.00
84,340.00
252,322.80
588,530.30
8,255,844.50
67,018.60
3,063,166.10
39,551.52
81,425.07
126,705.93
7,483.23
84,100.02
-
226,928.00
214,188.00
33,709.52
39,429.78
91,384.15
96,361.20
44,179.07
43,305.73
22,082.06
4,728.10
28,915.64
13,411,359.32
691,558.00
2,149,181.88
142,072.88
1,364.58
-
146,440.80
36,295.18
10,763.12
33,601.92
23,541.21
76,603.30
3,311,422.86 327,245.52
16,628.40
23,362.54
120,555.90
50,043.64
862.68
211,453.16
43,875.00
15,750.00
6,750.00
11,250.00
11,250.00
2,250.00
7,875.00
1,125.00
100,125.00 427,370.52
-
1,266.00
1,266.00
1,266.00
1,266.00
1,266.00
1,266.00
1,266.00
1,266.00
1,266.00
-
1,266.00
1,266.00
1,266.00
1,266.00
1,266.00
2,532.00
1,266.00
-
2,532.00
1,266.00
1,266.00
1,266.00
1,266.00
1,266.00
1,266.00
-
15,192.00
25,320.00
6,330.00
78,492.00 505,862.52
298,961.20
638.40
293,439.20
188,818.96
130,490.40
41,707.44
229,366.20
24,138.80
45,936.00
16,754.20
192,647.40
48,902.33
1,379.00
1,687.50
665.00
85,561.04
23,605.83
769.20
33,211.60
45,728.66 922,550.60
1,704,408.36
86,541.40
404.80
65,648.00
152,594.20
149,358.00
337,931.00
487,289.00
`
844.80
1,180.80
1,760.40
1,563.30
1,100.40
470.00
496.00
224.00
1,989.00
-
8,350.00
7,995.00
11,550.00
-
1,350.00
900.00
-
455.00
-
-
40,000.00
10,500.00
120,000.00
130,000.00
340,728.70
23,587,133.34