You are on page 1of 3

Is it time to lift?

To determine if tilt-up concrete panels are ready for lifting, estimate


their in-place strength with field-cured, not lab-cured, cylinders

BY TIMOTHY S. FISHER

efore erecting tilt-up con-

B crete panels, you must allow


them to gain enough
strength to withstand lifting
stresses. Erecting panels be-
fore they achieve the proper
strength can lead to damage, costly
repairs and even serious accidents.
But how do you know when the re-
quired strength has been reached?
Many tilt-up contractors start
erecting panels after the concrete
has cured for a specific time. For ex-
ample, a contractor may cast panels
Monday through Thursday of one
week so all are ready for erection the
following Monday. Other contrac-
tors erect panels after a minimum
seven-day curing period.
But curing time alone isn’t an ac-
curate method for determining in-
place concrete strength. Because
concrete gains strength more slowly
in cold weather and more quickly at
higher temperatures, you may end
up lifting the panels too soon, before
they are strong enough to handle
the loads imposed during erection.
Or the panels may achieve adequate
Martin-Harris Construction

strength sooner than expected while


equipment and personnel wait idly
onsite for a specified curing time to
elapse.
Only reliable testing can produce
accurate estimates of in-place con- Lifting these 10-inch-thick, 36-foot-tall radius tilt-up panels during the construc-
crete strength. The most common tion of a Las Vegas church was a delicate operation for contractor Martin-Harris
testing method makes use of field- Construction. If the panels had been lifted too soon, they could have been dam-
cured cylinders. aged, resulting in costly repairs.
TIME TO LIFT continued

Field- vs. lab-cured


cylinders
Field-cured cylinders are prepared
at the same time as the laboratory-
cured cylinders that are used for ac-
ceptance of a concrete mix. How-
ever, the field-cured specimens are
left onsite until testing, unlike the
lab-cured cylinders, which are re-
moved from the site and taken back
to the lab for moist curing before
testing.
Because lab and field curing con-
ditions differ, lab-cured cylinders
should not be used to estimate the
strength of in-place concrete. Re- Field-cured cylinders can provide accurate estimates of in-place concrete strength,
search has shown that strengths of leading to safer, more profitable tilt-up jobs. Remember to keep cylinders covered
cylinders protected and cured onsite to prevent moisture evaporation.
to simulate good field practices can
be as much as 15% lower than stan- don’t delay the lift. required strength or if any of the
dard moist-cured laboratory cylin- During the panel pour, have the cylinders are damaged. You may also
ders. Field-cured cylinders also can lab make at least six field-cured need to test these cylinders if the re-
attain higher early strengths if they cylinders plus the required lab-cured sults from the first test are low or if
are cured at temperatures higher cylinders. The six cylinders should you don’t think the results are accu-
than the 73° F standard laboratory be made for each day’s pour, each rate. As the project progresses and
curing temperature. different mix used in the panels or your time-of-test estimates become
But even field-cured cylinders each 150 cubic yards of concrete de- more consistent, you can cut back
won’t provide a good estimate of in- livered. Be sure the lab technician on the number of field-cured cylin-
place concrete strength if they aren’t marks the cylinder mold with the ders taken. However, in case of low
handled properly. For the best re- panel number or location corre- breaks, never make fewer than four
sults, field-cured cylinders should be: sponding to the panel being poured cylinders.
n Maintained at the same tempera- with that truckload of concrete.
ture and moisture environment as Each test result is the average of Assessing strength
the concrete in the panel. This two cylinders. Thus with six cylin- uniformity
means keeping the cylinders un- ders, you can make three tests. The Cylinders taken from one truck-
der blankets during cold weather first test should be done after the es- load of concrete often are used to
if the panels are protected that timated curing time obtained from judge concrete from many truck-
way. the producer’s early breaks has loads that have been placed in nu-
n Stored as near to the panels as passed, though you may need to ad- merous panels. For example, let’s say
possible. just the timing if the cylinders are cylinders are made from one 10-yard
n Left undisturbed until tested. exposed to hot or cold weather. The truckload of concrete for each 150
other two sets of cylinders can be cubic yards delivered, and each
Proper use of field-cured tested if the first set doesn’t meet the panel being poured takes 15 cubic
cylinders
When scheduling a tilt-up job,
have the concrete producer give you What strength is required to lift?
compressive-strength test results at
one, three and seven days for the The required strength of a tilt-up panel before erection can be found in
concrete to be supplied. You can use the project specifications or contract drawings. Manufacturers of lifting in-
the results to estimate testing times serts also require that the concrete reach a certain strength to ensure the
for field-cured cylinders. These re- capacity of their hardware. One manufacturer, for example, requires a
sults will also help you determine if compressive strength of at least 3000 psi before panel erection. However,
the required lift strength (see box on not all insert manufacturers require the same compressive strength, so
this page) will be reached in the check with your supplier or detailer. If the project specifications and the
time frame allowed by the project manufacturer’s minimum compressive strength differ, the greater of the
schedule. If not, concrete mix ad- two must be met before erection can start.
justments can be made so low breaks
yards. This means 10 panels will be each panel (10 readings for each mate the proper lifting time. How-
erected based on the test results of test), and average the three results. If ever, some engineers may not allow
one batch of concrete. the average rebound number for any this use of the rebound hammer, so
If there are concerns about batch- panel is three points lower than the be sure the engineer on your project
to-batch variations in concrete reference panel average rebound approves of this method before you
strength, use a combination of test number, there’s a 95% probability rely on it.
results from field-cured cylinders that the concrete in that panel is dif-
and from nondestructive testing ferent from that in the reference Acknowledgment
methods such as a rebound hammer panel. If the field-cured-cylinder test This article is adapted from a story ap-
(ASTM C 805, “Standard Test results for the reference panel only pearing in The Concrete Facts (Novem-
Method for Rebound Number of slightly exceed the required lift ber/December 1997), published by
Baker Concrete Construction Inc., Mon-
Hardened Concrete”). To judge the strength, you may want to give any roe, Ohio. Tim Fisher is a project engi-
uniformity of panel strength, obtain questionable panels another day or neer for Baker and a former field-engi-
an average rebound number for the so of curing and recheck the re- neering editor for Concrete
panel made with concrete from the bound number before lifting. Construction.
truck represented by field-cured Rebound numbers aren’t intended
cylinders. Next, get average rebound as an alternative to determining con-
numbers for the other panels and crete strength with test cylinders. Publication #C99A035
compare them with the average for But the numbers are a useful supple- Copyright© 1999, The Aberdeen Group
the first panel tested. ment to field-cured-cylinder test a division of Hanley-Wood, Inc.
Conduct three rebound tests on results and can help you better esti- All rights reserved

You might also like