Professional Documents
Culture Documents
TEC-031100A-MET-DoR-001
Name) (Rev No.)
METHOD STATEMENT Issue Date 02 October 2013
Rev. Date NA
Method statement for formwork erection and dismantling
Pages 1 of 7
TABLE OF CONTENTS
TECHNICAL DEPARTMENT-CIVIL (Replace by the Project Doc. No.
TEC-031100A-MET-DoR-001
Name) (Rev No.)
METHOD STATEMENT Issue Date 02 October 2013
Rev. Date NA
Method statement for formwork erection and dismantling
Pages 2 of 7
1. REVISION RECORD............................................................................................................................................3
2. PURPOSE............................................................................................................................................................3
3. SCOPE OF WORKS.............................................................................................................................................4
4. REFERENCES.....................................................................................................................................................4
4.1. Contract documents.........................................................................................................................................4
4.2. Contractors Submittal.......................................................................................................................................4
5. DEFINITIONS / ABBREVIATIONS.......................................................................................................................4
5.1. Definition..........................................................................................................................................................4
5.2. Abbreviations....................................................................................................................................................5
6. RESPONSIBLE FOR QUALITY CONTROL.........................................................................................................5
7. PROCUREMENT & FABRICATION.....................................................................................................................5
7.1. Specification Requirements.............................................................................................................................5
7.2. Shop Drawings.................................................................................................................................................5
7.3. General.............................................................................................................................................................6
7.4. System Form for Wall “W3” & “W4”..................................................................................................................6
7.5. System Form for Columns................................................................................................................................6
8. TEST & INSPECTION..........................................................................................................................................6
8.1. Site Inspection Plan..........................................................................................................................................6
8.2. Laboratory Testing Plan...................................................................................................................................6
9. CONTINGENCY PLANS......................................................................................................................................6
9.1. Formwork Hoisting Equipment.........................................................................................................................6
9.2. Night Time Works.............................................................................................................................................6
9.3. Traceability of Products....................................................................................................................................6
9.4. Control of Non-conforming Products................................................................................................................7
10. HEALTH, SAFETY AND ENVIRONMENT.......................................................................................................7
11. ATTACHMENTS..............................................................................................................................................7
11.1. Inspection Checklists...................................................................................................................................7
11.2. Inspection Test Plan....................................................................................................................................7
11.3. Risk Assessment.........................................................................................................................................7
TECHNICAL DEPARTMENT-CIVIL (Replace by the Project Doc. No.
TEC-031100A-MET-DoR-001
Name) (Rev No.)
METHOD STATEMENT Issue Date 02 October 2013
Rev. Date NA
Method statement for formwork erection and dismantling
Pages 3 of 7
1. REVISION RECORD
This page is a record of all revisions of the document identified below by number and title. All previous revisions
are hereby superseded and are to be destroyed.
Rev Date By Chkd. Approved Description of Revisions
0 First issue
Signature field
Revision
Revision
Number
Date
Prepared by Checked by
Reviewed
By Construction Technical QA/QC MEP Co-
Manager Manager Engineer HSE Officer coordinator Sub-contractor
Approved
By Project
Manager
TECHNICAL DEPARTMENT-CIVIL (Replace by the Project Doc. No.
TEC-031100A-MET-DoR-001
Name) (Rev No.)
METHOD STATEMENT Issue Date 02 October 2013
Rev. Date NA
Method statement for formwork erection and dismantling
Pages 4 of 7
2. PURPOSE
1. The following is a document of the Quality Control procedures for formwork work for the project.
The objective of this document is two folds:
1. To demonstrate our total quality commitment in implementing, managing and executing of the works for this
project,
2. To assure the client and their project managers and Engineer the confidence that the contract requirements will
be satisfied by the contractor every respect of the works.
3. SCOPE OF WORKS
This document summarizes the general details of the quality assurance plan for system forms as well as traditional wooden
forms including:
1. Management Responsibility
2. Shop Drawings
3. Procurement
4. Fabrication
5. Erection
6. Inspection
7. Striking
Regarding the above procedures, not only the quality aspect of concrete formwork but the work methods will be described to
a relevant extent so that the actual work process can be envisaged.
This document is the beginning, not the end. This document should be communicated reiterated, regularly reviewed and
developed to suit changing condition, standards and technology as the site situation requires
4. REFERENCES
4.1.Contract documents
1. Project Specification :- Division 3, Section 030100
2. Contract Drawings :-
4.2.Contractors Submittal
3. Project Quality Plan :-
4. Project Safety Plan :-
5. Material approvals
Sr. No. Description Material Sub. No. Rev No. Date Remarks
1
2
3
6. Shop Drawings
Sr. No. Description Shop Drawings Rev No. Date Remarks
1
2
3
1
2
3
5. DEFINITIONS / ABBREVIATIONS
5.1.Definition
1. Project -(Replace with project name)
2. Client -(Replace with clients name)
3. Developer -(Replace with developers name)
4. Consultant -(Replace with consultants name)
5. PMC -(Replace with PMC name)
6. Contractor -(Replace with contractors name)
7. Sub-contractor -(Replace with sub-contractors name)
8. Supplier -(Replace with suppliers name)
5.2.Abbreviations
1. Engineer - Representative of “Name of engineering consultancy”
2. ICL - Inspection Check List
3. IR - Inspection Request
4. ITL -Independent Testing Laboratory
5. ITP - Inspection and Test Plan
6. ITR -Inspection & Test Requests
7. MAT - Material Submittal
8. MEP - Mechanical Electrical Plumbing
9. MET - Method Statement
10. MIR - Material Inspection Request
11. MSDS - Material Safety Data Sheet
12. PPE -Personal Protective Equipment
13. PQP -Project Quality Plan
14. PTW -Permit To Work ( Working at Height or enclosed spaces)
15. RA -Hazard Identification and Risk Assessment
16. RFIA - Request for Inspection and Approval
17. SPD - Shop Drawing
18. TBM - Temporary Bench Mark
6. RESPONSIBLE FOR QUALITY CONTROL.
1. The Site Manager will be responsible for the concrete formwork works. His duty also includes coordination with
Engineer for inspection prior to concreting work. Or closing the shutter.
2. The QA/QC Manager will be directly responsible for assuring compliance with the contract documents. His duties
further include:
3. Implementation of the Quality control plan to ensure accurate and adequate inspection compliance with contract
documents and direct corrective action upon any occurrence of noncompliance to contract documents.
4. Record all Quality Control activities including inspection and take appropriate measures to correct defective works.
TECHNICAL DEPARTMENT-CIVIL (Replace by the Project Doc. No.
TEC-031100A-MET-DoR-001
Name) (Rev No.)
METHOD STATEMENT Issue Date 02 October 2013
Rev. Date NA
Method statement for formwork erection and dismantling
Pages 6 of 7
5. The implementation of the Quality control plan will be the responsibility of the Project Manager who will have total
support of the company’s management and staffs for review and approve the all documents and letters related with the
concrete formworks and submitted to ENGINEER.
7.2.Shop Drawings
1. Shop drawing showing location of construction joints as well as precise dimensions of the structure form design
and other details will be submitted to Engineer for approval.
2. Only after getting approval, shop drawings will be released to the subcontractors for form fabrication. Sufficient
numbers of copies will be prepared on the site to assure that actual works are undertaken in accordance with the
approved shop drawings.
7.3.General
1. System forms will be used for the larger portion of this project. Conventional plywood forms will be also used in the
sub-structure, stair, and other relatively small or odd parts of formwork. Subjected to the approval of the Engineer.
2. System forms will be procured from the manufactures that are specialized in both design and fabrication of custom-
made forms for the specific projects.
9. CONTINGENCY PLANS
9.1.Formwork Hoisting Equipment
One mechanic will be on standby to service any breakdown of the tower cranes. Even if one tower crane is completely
out of operation due to mechanical troubles, another tower crane can serve for hoisting forms, allowing that the
productivity goes down considerably while repairing work takes place.
9.3.Traceability of Products
Formwork itself is a temporary work after all. Therefore, “traceability of products” will not be directly applicable here.