Professional Documents
Culture Documents
12/06/2019
This report is a follow up on the Application for Contract Price adjustment made by
the contractor on Contract 34D/2017 on the Rehabilitation of Southern Areas
Sewage Treatment Works’ Maturation Ponds and focuses on the variances
between the estimated quantities at the time of tender and on measurement of de-
sludged quantities on pond 1 to pond 7 sludge volumes. In addition, the report also
takes note of the introduction and justification of the apron for the fence that was not
included in the original scope.
1.0 BACKGROUND
The contractor has done up to 90 % of the works in terms of de-sludging with works
still ongoing but progress at stand still due to increase in costs as Tender was
awarded when the rate of the US$ was 1 to the bond thus eroding the capacity to
recapitalise towards project completion. The contractor has also done pond slope
repairs. The erection of the fence around the perimeter is almost complete. However,
laying of the concrete slab has since been finalized.
Fuel challenges and the escalating of prices for some of the material resulting in
variances at tender award and course of implementation have inhibited the progress
to fully rehabilitate the SAST Maturation Ponds.
3.0 WORKS DONE BY CONTRACTOR:
De-sludging of Ponds 90%
Fence erection 90%
Outflow meter Nil
Security Lights 40% (poles for security lights have since been
erected)
Fig 1.1
Dewater, excavate the pond, haul load and dump sludge and reeds from ponds to
an identified site. Approximately 200 loads of capacity5m 3 loads of weeds and
sludge will be ferried to a distance not more than 500m from the farthest ponds.
This is a guide; actual number of loads will be determined on site.
200 loads of 5 m3 per pond translates to 1000 m3 per each pond.This standard
measurement was then subsequently used as a basis of rates in the
ContractDocument on page 16.This meant that for each pond the volume to be
excavated was at contract signing based at 1000 m3/pond, giving the table below;
100,085.40m3 from the table above is the total excavated sludge measured
according to method 1. This is inclusive of moisture content and organic
material such as reeds from the embankments of the seven ponds.
The total excavated sludge of 100,085.40m3 is based on the sludge levels
measured after two months with in which there was drying.
From the total excavated sludge, we remove factor of rocks that are in the
ponds and the factor that we calculated area of the ponds as rectangular prism
instead of trapezoidal
It is estimated there is 50% reduction of sludge due to water loss by pumping
out, biodegradation of biological matter that is in the sludge, moisture loss
and evaporation.
41,229.03m3 is total approximated sludge according to method 1 after
factoring in the loss of moisture content and shrinking of organic matter
assumed and agreed upon as 50%.
Fig 1.2
Note:- The 2 methods used above can then be used to estimate volumes of slug
which were excavated from the ponds giving a range of between 35 000 m 3- 45 000
m3.
4.2OTHER CONSIDERATIONS
The contractor should level the slopes of the ponds according to the designs.
The contractor claimed for bacteria seeding but it has not been seeded yet.
Bacteria seeding is done few days after the ponds have started working.
To install membrane in all ponds was not part of the scope of works.
Pond 1 there is an area affected by tree roots, the area needs to be revisited by the
contractor.
According to the scope of works there is repair of stone pitching, the contractor
claimed for repair of stone pitching but there is no stone pitching on the ponds.
Therefore, there was no repair of stone pitching.
There are eight installed poles already for security lights, we want to clarity
fromprocurement that security light should be installed in house or the contractor
should continue and install the lights.
Second gate installed by the contractor needs to be painted.
Call the contractor to clarify on the outflow meter, if the meter has already been
procured.
Notes:
From the new Engineer/Project Manager’s measurements there was 50,278.314m3 of
sludge excavated against the 22,499m3 captured/shown on site records. This translates to
2.23 times more than what is recorded. Further investigations as to how the such a
discrepancy occurred shows that all recorded loads were taken and recorded as 5m3 loads
where-in some cases a 10m3 truck was used.
Financially the recorded volumes add up to 22,499m3 and only 7,000m3 was claimed for
as shown below;
6.0 CONCLUSION
The costs for extra volumes de-sludged as determined in-situ and the apron on the bottom of
the fence summed and itemized up are as follows;
7.0 RECOMMENDATIONS
7.1 On Desludging measurement confirmations and the Apron
Having out lined the above and consideration being given that the said extra volumes
were necessary for the completion of de-sludging per each pond, it is therefore
recommended that:
That the price review for extra volumes de-sludged be considered as variation and
granted at the rates submitted by the contractor and as depicted on the tender
document that the approximate 200 loads of capacity 5m3 were guides with actual
number of loads to be subsequently determined in-situ. Here-in, inference is made to
the tender document Section V, Scope of Works on page 42 second paragraph, bullet
1 and last sentence that reads;
Dewater, excavate the pond, haul load and dump sludge and reeds from ponds to an
identified site. Approximately 200 loads of capacity5m3 loads of weeds and sludge
will be ferried to a distance not more than 500m from the farthest ponds. This is a
guide; actual number of loads will be determined on site.
That the suggested variation be granted and paid based on the following
breakdown as submitted by contractor since measurement checks have been
done;
Pond Tender Contractors’ Additional Unit Additional
3 3
No. Document Excavated B.O.Q Volume m Rate/m Volume Cost
3
Volume/BOQ (m ) (Extra Over) $
1 1,000 6,030 5,030 19.33 97,237.80
2 1000 4,995 3,995 19.33 77,229.62
3 1000 3,330 2,330 19.33 45,042.56
4 1000 3,870 2,870 19.33 55,481.60
5 1000 2,665 1,665 19.33 32,187.06
6 1000 2,330 1,330 19.33 25,710.99
7 1000 1,885 885 19.33 17,108.44
Total 7000 25,105 18,105 349,998.07
Table 1.7
That the addition of the apron below the fence be also be considered as a
variation and be granted as follows;
Item
Phase Perimeter Rate Cost
No.
1 One 1,250 m $1.50/m 1,850.00
2 Two 1,250 m $4.50/m 5,625.00
Tota
7,500.00
l
Table 1.8
7.2 On works that the contractor claimed and was paid for without these being
done. (see accompanying table below)
It is recommended that any of the following options be explored with the contractor
so as to recover the money paid for without service being rendered;
i-the contractor be instructed to implement the activities that can be done e.g. seeding
ii-that the contractor reimburse the money through a subtraction on the variation to
be granted e.g. as I the case of stone pitching.