Arcs Actual Time

Activity Days Required EST From To Between starts


A 5 0 A B 4.999995
B 4 4.999995 B C 3.999996
C 5 8.999991 B D 4
D 8 8.999995 C E 5
E 9 13.99999 C F 8.000004
F 6 17 D F 8
G 8 17 D G 8
H 3 25 E H 11.000004
Minimum Sum 95.99996 F H 8
G H 8
Minimum Time
between Starts
5
4
4
5
5
8
8
9
6
8
Arcs Actual Time
Activity Days Required LST From To Between starts
A 5 0 A B 4.999994985099
B 4 4.999995 B C 6.000000014901
C 5 11 B D 4
D 8 8.999995 C E 5
E 9 16 C F 5.999999985099
F 6 16.99999 D F 8
G 8 17 D G 8.000000014901
H 3 25 E H 9
Maximum Sum 99.99996 F H 8.000000014901
G H 8
Minimum Time
between Starts
5
4
4
5
5
8
8
9
6
8
Activity Time EST EFT LST LFT Slack
A 5 0 5 0 5 0
B 4 4.999995 8.999995 4.999995 8.999995 -1E-08
C 5 8.999991 13.99999 11 16 2
D 8 8.999995 17 8.999995 16.99999 -1E-08
E 9 13.99999 22.99999 16 25 2
F 6 17 23 16.99999 22.99999 -1E-08
G 8 17 25 17 25 0
H 3 25 28 25 28 0