Professional Documents
Culture Documents
MANUAL
1.1 QUALITY POLICY STATEMENT
regulatory requirements.
- Minimize losses due to lack of quality on the basis of “get it right first
time”.
Our work team could deliver and satisfy every stage of a Project Work
from the design to final commissioning with competitive cost and to
control Unsafe Acts.
C) GROUP SPIRIT
D) INDEPENDENCE
1.1 Upon award of contrast, QA/QC manager would request the Project
Manager to arrange Inspection Coordination meeting with the client’s
QA/QC representative (s).
1.6 The Quality Control Coordination flow chart is shown in figure (i).
Figure (i)
QC COORDINATION PROCEDURE
USE PROJECT
MANAGER
QA/QC
DEPARTMENT CLIENT’S PROJECT
TEAM + QA/QC DEPT
QC SCOPES OF WORK
- PRE-INPECTION MEETING
- CONTRACT DOCUMENTS
- ENGINEERING
- ERECTION & FABRICATION
DOCUMENTS
- QC LOGS, RECORD
- RELEASE AND REJECTION
NOTICED
- AUDITS
1.0 QC ROUTINE INSPECTION
1.1 The enclosed format of Routine Inspection shows how QC personnel will
carry out their functions, from where the Dept. gets the information. The
routine function does provide information about cooperation with other
department and the sequence in which the activities performed.
1.2 The QC will carry out inspection at stages of work site constructions /
erection and registered QC formats will be filled in and dates of inspection
performed
- Dimensional Inspection
- Visual Inspection (Ready for Welding )
- Verification of weld procedures
- Marking of welds
- Root-pass
- Back-gouging
- Drawing weld numbers
- Materials documents
- Pressure testing
- Clearing/ flushing
- NDT Reports
- Stress Relieving
- Final Acceptance / Signing
QA MANAGER RESPONSIBILITIES
-
QC INSPECTION RESPONSIBILITIES
PLANNER QC DEPT
- Detailed Plans Plan according to Client.
- Work Order Spec.
Action / Plans
Final Control
- Reporting
- Registration
- Signing
Fillings Documentation
SCOPE
1.1 This standard covers the mandatory requirements for making metallic
materials normally used at Owner’s Plant to permit positive material
identification in the Store House, Shop and field.
1.2 The color-coding portion of this standard does not apply to:-
b) Materials not covered by the Color chart (Table 1); they must be
identified by the other two marking methods.
MARKING REQUIREMENTS
2.2 In general, each piece of material can have three types of markings :-
2.4 A single color system shall be used. Color Code stripe(s) shall comply
with Table 1.
2.5 Paint used for identification shall be durable and of distinctive identifying
colors. Color-coding of material shall be by use of a marker equal to Metal
Marker, as manufactured by the John P. Nissen, Jr., Company, Glenside,
Pennsyivania. Paints containing sulfur, led, or other metals are not
acceptable
2.6 Surfaces to be color-coded shall be cleaned and free of dirt, loose scale
and oil.
3.1 Pipe, Fittings. Shapes, Tube and Bar – Stripe entire length as shown in
Figure 1, Boxes or bundles of tubing or bar 1-inch or smaller may be color
coded by striping the box or binding straps.
3.3 Plate, Sheet and Strip – Stripe along any two edges or on surface near
edge for entire length as shown in Figure 3
DEFINITIONS
4.1 The term inspector, as used in this standard, refers to the Owner’s
representative.
4.3 An inspection lot is a group of components from the same heat number
from which a sample is drawn.
5.2 Records of PMI results shall be kept by the vendor or fabricator from a
period of one (1) vear for audit by the Owner. For fabricated equipment,
these records shall include and itemized listing of all components and
weldments on the form provided (Table 2) on its equivalent. Tabulation of
tested items must be keyed to as-built drawings and Mill Certification
Document Stamping through the use of reference numbers. One (1) copy
of test results shall be provided to Owner’s Engineer as part of the as-built
documents.
5.3 All materials purchased with PMI required shall be analyzed for chemical
composition using an acceptable method as defined in this standard. Test
result must conform to purchase documents, be properly identified to the
applicable specifications such as ASME, ASTM and color coded as
required by EXES 18-9-1-1B when specified.
5.4 A chemical analysis test shall be made on each component (100 percent )
PMI inspection, unless specifically exempted by the Owner’s Inspector
when Owner’s Inspector authorizes random inspection, failure of any
representative sample in an inspection lot rejects all components identified
as being part of that lot by heat number until 100 percent PMI has proven
each item’s chemical composition.
a) Each piece shall be marked with the “PMI” code letters using a
Owner’s Inspector. The Owner’s Inspector shall approve the steel
stamp. In addition the PMI code letters shall be highlighted by a
small spot of green paint, and must remain readily visible during
fabrication and erection, until final protective coatings are applied.
b) Piping and heat exchange tubing shall be marked with the “PMI”
code letters near each end when length exceeds 10 feet. Less than
10 feet one marking is acceptable..
5.8 Any component of a fabricated assembly that has not been marked with
the ‘PMI” code shall be rejected by the owner’s Inspector if the
component’ chemical composition cannot be determined in its fabricated
location.
SAMPLING PROCEDURES
6.1 Testing shall be done per the procedures outlined by the manufacturer of
the portable alloy analyzer or alloy sorter being used. The Owner’s
Inspector must approve modification of these procedures. Each analyzer
must be calibrated using known alloy standards.
6.2 One hundred percent PMI inspections per Paragraph 5.4 are required.
Random sampling shall only be acceptable when approved by the Owner’s
Inspector and 100 percent inspection of all remaining components is done
using approved (per Paragraph 7.4b) see back effect alloy sorting
equipment.
6.3 If random testing for alloy chemical composition is approved, the items
tested shall provide a representative sample of the inspection lot. The
representative sample shall be 100 percent for lots of five units or less. For
lots greater five units, the greatest of five units or 5 percent shall be
analyzed.
ACCEPTABLE METHODS FOR PMI
7.2 Instruments or methods used for examination shall be of the type that will
provide quantitative, record able, elemental composition results for
positive identification of the alloy elements present.
7.3 The person(s) performing the PMI shall be knowledgeable about all
aspects of the operation. Qualifications of the tester, including training and
experience, shall be included in the PMI program required by paragraph
5.1.
“Panametrics Panalyzer.”
7.6 Chemical pot testing (qualitative, not quantitative) and other methods
using eddy current triboelectric testing, such as perimeter and
thermoelectric tests, are not acceptable unless specifically approved by the
Owner’s Inspector, and then only other quantitative methods are not
possible.
TABLE 1
COLOR CODE FOR METAL
IDENTIFICATION
Note : * Segregate
WELDER QUALIFICATION TEST GUIDELINES
1.0 General
Test booth with an approximate square area of 3.7m (12”) x 3.7m (12”) is
prepared to accommodate a maximum of three welders for testing in a
staggered system, i.e. first welder shall deposit he root pass and prepare it
- Preheat required.
4.2 Review the appropriate procedure chart containing the details for
welding the thickness of the material. Ensure that the test specimen
is in accordance with the relevant procedure chart. Check the
heading of the procedure chart to be sure the appropriate chart is
used relation to the test position in which the welder(s) are to be
tested i.e. 1G, 2G, 3G, 4G, 5G, or 6G inclined.
4.3 Ensure that each welder to be tested is made aware of what he will be
tested with respect to specific details of the governing code and an
approved WPS.
4.4 Prior to giving clearance to prepare and/ or fit-up test materials the
following shall be determined :-
4.5 After the requirement of step 4.4 has been followed and client
Representatives has given approval, the following must be done :-
- Travel speed
- Weld size
- Convexity / concavity
- Root penetration.
- Distortion warpage.
4.7 Fill in the welder test WQT form after verification and recording of details
in step 5.
4.8 Compare records with the specified details of the WPS and those of the
client representative. If details of test weld reveal that qualification test
welding parameters do not comply with welding procedure specification
and applicable code or client requirements the welder shall be rejected.
If test weld parameters are within the ranges and tolerances of the
approved procedure and client representative has given visual acceptance
of the finished test piece the following shall be executed with the approval
of the Owner’s representative.
Only after steel die stamping may the specimens be cut from the test piece.
The identification stamped shall remain identifiable through-out specimen
preparation and testing.
4.9 Transfer all pertinent data on the WQT form using typewriter or by hand
using black ink and ensuring legibility. Have these sheets signed and dated
on the spaces provided for by all interested parties and a legible copy
given to client representative.
NOTE : USE representative must ensure that all data entered on the welding
qualification record are factual. Thus, it is imperative and requires that
your signature be legible above your printed name. Be sure that all
relevant form are completed and properly signed by owners representative.
WELDING REPAIR PROCEDURE
GENERAL
- Any attempts beyond two repairs shall require client approval. A written
request shall provide all particulars necessary for client to evaluate
conditions to support AYE’S reasoning that additional attempts beyond
two are reasonable, practical and tempered with good engineering
judgment.
MAJOR DEFECTS: -
MINOR DEFECTS : -
Weld defects which are revealed by Magnetic Partide, Dye Penetrant or visual
Examination and are judged to be surface imperfections, which can be rectified
without welding to affect an acceptable repair.
WELDING REPAIR PROCEDURE
MAJOR DEFECTS : -
* Identity the location and record the depth of defect from the
surface of base metal from which NDT operations were performed.
* Identity the type, grade and thickness of base metal containing the
defect.
- Upon completion of the excavation and verified by NDT that the entire
defect removal has been accomplished, the excavation shall be contoured
to provide a groove geometry to deposition of required repaired weld
- The prepared excavation shall be measured , i.e. width of base of the
groove, width of the top of the groove, length of the deepest section of
groove and length of the groove at the surface which shall be recorded and
utilized in-development of the showing repair groove dimensions and base
metal thickness for attachment to weld repair report.
- The minimum width of repair weld shall be 12.7mm and the minimum
length of repair weld shall be 76.0mm for repair of major defects where
size of weldments permits.
- Prior to depositing the repair weld, the excavated area and surrounding
weld and base metal shall be preheat to a minimum temperature of 94ºC.
- The preheat area shall as a minimum , be not less than six (6) times the
base metal thickness or 76.0mm in width whichever is greater. The
minimum length of preheat area shall be three (3) times length of the
completed excavation.
- The repair weld shall be performed utilizing the same welding procedure
and technique as was employed to deposit the original weld.
- In some cases where client approved any attempts beyond two repairs,
hardness test shall be conducted. Hardness Testing shall include the repair
weld metal and Heat Affected Zone. Test shall be conducted with a
portable hardness tester.
- In those instances where it is evident that the rejectable area of the weld is
superficial, grinding method shall be utilized to remove or correct subject
defects. The defect removal area and adjacent areas shall be contoured
neatly by grinding to eliminate sharp transitions. The ground area
thickness shall be measured utilizing Ultrasonic or “D” meter.
- All temporary tack welded supports, braces, dog leg plates, run-off plates
and strong backs used during fit-up operation shall be removed.
- The final finish and removal shall be by power grinding to the original
steel surface. After grinding, the surface shall be tested as per the
approved NDT Procedure.
P
ARC BURN REPAIR PROCEDURE
- Grind the arc burn area, preferably with a disc grinder, until evidence of
the burn is no longer evidence to the naked eye. Ground area shall be not
less than 50.8sq.mm.in area.
- Grind the arc burn area, preferably with a disc grinder; until visual
evidence of the arc burn is no longer exist. Grinding shall be accomplished
in a workman like manner, which leaves no sharp grooves in parent metal
and does not objectionably distort the geometry of the adjacent weld.
- The cross-sectional thickness of ground area shall be measured utilizing
ultrasonic / “D” meter measuring equipment. The measured thickness shall
be recorded in the thickness measurement report for use in determination
of final disposition.
SPECIAL INSTRUCTIONS :
Arc Burns which are located outside a welding groove, wherein the measured
distance from the center point of the arc burn to the edge of a completed weld
exceeds 9.5mm.
Arc burns which are located immediately adjacent to a completed weld wherein
the measured distance from the center of a completed weld is 9.5 mm or less.
WELD BUILT-UP (BUTTERING) PROCEDURE
- Root openings wider than those permitted in the drawings but not greater
than twice the thickness of the thinner part of ¾” (inch), whichever is less,
may be corrected by welding to acceptable dimensions prior to joining the
parts by welding.
- Built-up weldments shall be subjected to PMI and hardness test for sound
welds. The hardness test value shall not exceed 225 BHN
1.0 SCOPE
2.0 STORING
2.2 The newly open cans electrodes shall be stored in BAKING OVEN
and bake at 260ºC to 280ºC for minimum 2 hours.
2.4 Electrodes returned by each welder after each shift shall be placed
in the Baking Oven. Left over electrodes shall be removed and put
to scrap.
The returned or excess electrodes are again re-oven with color marking
(Red) and placing t the bottom areas. Wet or damage electrodes are not
allowed to be stored in the oven.
1.0 Fabrication Control for Tie – In of Spools
1.2 The prepared edges of the spools are brought in for correct
alignment and to avoid high and low configuration using set-
square sets or spirit – level gauges.
1.3 The bevel fit-up shall then meet the PQR welding docs as for root
gap and the closed bevel angle. The bevel shall be freed from
surface flaws and laminations.
2.0 Identification
2.1 All tie-in weldment shall be recorded with welder ID and pother
welding status requirement, i.e. process and RT exam inspection.
1.1 The intent of this procedure is to ensure that all bolts, nuts of
gaskets installed at flange locations are correct and comply to
Spec. and Code.
3.0 PRE-INSPECTION
* QC INSPECTOR TO REPORT
ISOTOPE STRENGTH AND TYPE OF
SEALED CONTAINER
APPROVED SOURCE
CONTAINERS
PROPER DOCUMENTATION
NOTIFICATION TO SITE
SUPERVISOR/
SUPERINTENDANT
LOCATION OFFSHORE
STORAGE OF PLATFORM AT SEA DECK WITH
ISOTOPES AT SITE PROPER MARKED
MEDICAL REQUIREMENT OF
MALAYSIA SINGAPORE
RADIATION WORKERS OF
MALAYSIA/ RADIATION SAFETY
CONTRACTOR AUTHORITY
(ORGANIZATION)
RADIOGRAPHIC PROCEDURES
ORGANIZATION CHART
RECORD KEEPING
!) PERSONNEL
2) MOVEMET OF ISOTOPES
WEARING FILM
BADGES/DOSIMETERS
i) Offshore - 20 Curies + 15
ii) Onshore - 40 Curies + 15
5.0 OTHER PRECAUTIONS
iv) To ensure that the average level at one meter from the
center of each source does not exceed 2 mrem/ hr. and the
maximum radiation level does not exceed 10 mrem/ hr.
4.3 The radioactive material storage locker shall be placed and secured
in a manner that it would not be accident dislodged from a height
that would damage the locker or fall into the sea.
3.2 The time of receipt and dispatch of all radioactive materials shall
be recorded by client Supervisor-in-charge.