Construction Management
Assignment No 2
Q. 1 Completely crash the following network schedule using complex compression and find the
optimum time and cost. Take indirect cost as Rs: 200/- per day.
A
7
B
5
C E G
3 4 3
F
3
D
6
1
Q. 2 (a) Explain basic probability theory.
(b) Three critical paths of a project are given as under:
Path TE σ TE
1 55 3.8
2 52 2.7
3 59 1.9
Q.3 5-days Status Report for the project shown in figure, is as under:
Status Report
A, C complete
B, F started, 1 day left
E started ,4 days passed
H cancelled
I’ new duration, 6
J, New activity (Dur 4, IPA G,I)
2
Q.4 Perform CPM calculations of the following network:
LTi = 1 LTj = 2
B
LTj = 3
LT = 2 LTi = 2
C F
A D G
LTj = 3
LTi = 2
LTj = 2
E
Q.5 Perform normal CPM calculations for the Project given in Figure and Reschedule the same keeping
in view the Max. limitation of Resources L to be 8 per day and M to be 6 per day.:
D
A 4 4 H
3
B E I K
3 5 3 2
C G J
2 3 3