WEEKLY TURNOVER

Project: Jimma REPORTING WEEK WEEK NUMBER Commencement Date: Feb18,2013


Client: Oromia Educational Bureau Start Date MEGABIT 15 Scheduled Completion Date: Feb18,2014
Consultant: Oromia Educational Bureau End Date MEGABIT 30
7 Work Done (% of Total): 0.00147
(A) MAN POWER EXPENSE (B) EQUIPMENTS EXPENSE EXECUTED WORK SUMMARY
Trade Total Hrs Rate Amount Description Total Hrs O. Rate R. Rate Amount Description Unit Qtty Rate Amount
Project Manager 96 50.00 ETB4,800.00 Excavator - 0 ETB0.00 N/A
Office Engineer ETB0.00 Dump truck - 0 ETB0.00 Blok 16 N/A
Site Engineer 96 18.50 ETB1,776.00 Pick up - 0 ETB0.00 1.02Bulk Excavation 273.00 29.00 ETB7,917.00
Store Keeper 96 5.00 ETB480.00 Mixer - 0 ETB0.00 1.03 pit excavation 31.10 29.00 ETB901.90
Forman 96 16.00 ETB1,536.00 Formwork - 0 ETB0.00 Formwork 0.00 0.00 N/A
Daily Labourers 1 12,741.68 ETB12,741.68 ETB0.00 mild steel 0.00 0.00 N/A
Carpenter - ETB0.00 ETB0.00 masonry 0.00 0.00 N/A
Ass.Carpenter - ETB0.00 ETB0.00 Blok 18 N/A
ETB0.00 ETB0.00 1.02Bulk Excavation 159.36 29.00 ETB4,621.44
ETB0.00 ETB0.00 1.03 pit excavation 26.76 29.00 ETB776.04
ETB0.00 ETB0.00 Formwork 13.44 16.00 ETB215.04
ETB0.00 ETB0.00 mild steel 115.00 35.00 ETB4,025.00
2.1a lean concrete 13.44 16.00 ETB215.04
ETB0.00 ETB0.00 Blok 20 N/A
ETB0.00 ETB0.00 1.02Bulk Excavation 57.82 29.00 ETB1,676.78
ETB0.00 ETB0.00 1.03 pit excavation 26.61 29.00 ETB771.69
ETB0.00 ETB0.00 Blok 21 N/A
Sub-Total (A) ETB21,333.68 Sub-Total (B) ETB0.00 1.02Bulk Excavation 82.02 29.00 ETB2,378.58
1.03 pit excavation 28.06 29.00 ETB813.74
(C) CONSTRUCTION MATERIALS EXPENSE (D) CONSUMABLES EXPENSE N/A
Description Unit Qtty Rate Amount Description Unit Quantity Rate Amount N/A
Cement Qtl - ETB0.00 Deisel lt - 0 ETB0.00 N/A
Reinforcement Kg - ETB0.00 Engine Oil ls - 0 ETB0.00 N/A
Sand m3 - ETB0.00 Grease kg - 0 ETB0.00 N/A
Gravel 00 m3 - ETB0.00 Spare parts ls - 0 ETB0.00 N/A
Gravel 01 m3 - ETB0.00 Other ls 1 1000 ETB1,000.00 N/A
Gravel 02 m3 - ETB0.00 ETB0.00 N/A
Gravel 03 m3 - ETB0.00 ETB0.00 N/A
Other - - 0 ETB0.00 ETB0.00 N/A
- - - ETB0.00 ETB0.00 N/A
- - - ETB0.00 ETB0.00 N/A
Sub-Total (C) ETB0.00 Sub-Total (D) ETB1,000.00 N/A
Sub-Total (A)+(C) ETB21,333.68 Sub-Total (B)+(D) ETB1,000.00 N/A
Grand Total (Expense) ETB22,333.68 Grand Total (Income) ETB24,312.25

Week Turnover ETB1,978.58 Project Engineer Project Manager