Professional Documents
Culture Documents
Addis Ababa
Ref: - Construction of 2B+B+18 Apartment and 2B+G+M+11 Office Building project
Subject፡- Impartial Determination of Post Tensioning (PT) Unit Price
We acknowledge the receipt of contractor’s letter with Ref NO. ATC/03393/12/20 dated on
22/12/2020 through which the company requested provisional price after the final PT unit price
approved by the client. On this letter, he also referred a letter with Ref No. AA/4867/12/20 dated
21/12/20 that you confirmed your impartial determination for PT unit price is different from
what you sent to the contractor with REF No. AA/3926/07/20 dated on 06/07/20 and re-asserted
it with Ref NO. AA/4666/11/20 dated on 23/11/20. We hereby would like to inform you the
following:
1) The PT unit rate that you sent us with Ref No. AA/3804/05/20 dated on 29/05/20 is for re-
evaluation and approval. Therefore, the declared unit cost is not impartial
determination because of the re-evaluation and approval stage is from our office.
b) The one who signed on the referred letter is the representative of the engineer that we and the
contractor were not notified. The representative of the Engineer shall not be authorized to sign on
such critical issues as per GCC 12.3, GCC 12.4 and GCC 12.5
Therefore, it is necessary to waive what you disclosed about the PT unit rate impartial
determination resolute through the unauthorized personnel and respond the contractor’s request
in relation to provisional PT unit rate.
With Regards
CC
With Regards
Cc
Federal Government Buildings Construction Project office
F/G/B/C/P/ Office