Homework/Assignment 4

Full Name of submitter: Student ID:

Your Group number is: ……..


Group members are:
Full name Student ID
1
2
.
n

1. Company A plans to install an air pollution control equipment in its facility with the
following information of tasks

a. Find the total completion time of the project in the normal case.
b. If the Environmental Protection Agency (EPA) requires Company A to complete this project
within 16 weeks, which activities should be crashed?
c. If there would be a fine of $3000 for each day of delay, what should the company do

2. The following table provides the information necessary to construct a project network and
project crash data:

1|Page-Project Management-HW/Assignment 5
a. Determine the maximum possible crash time for the network, and crash the network the
maximum amount possible.
b. Compute the normal project cost and the cost of the crashed project.
c. Develop a mathematical model to optimize crashing

Note:

- Continue using this form to complete your works and submit on Blackboard
- Name your file
o If you submit individually: BT21_PJM_HW4_StudentID_FullName
o If you submit for a group (Group # are finalized by lecturer): BT21_PJM_HW4_G#
- Due Date is defined in detail at each “ ASSIGNMENT INFORMATION” from Blackboard
- Maximum score of late submission is two third of “Point Possible”
- If you can’t submit on Blackboard: Email your work to TA, copy your Lecturer, attached also the
screenshot of your Blackboard showing error in that transaction

---------

Answers/Works

2|Page-Project Management-HW/Assignment 5

You might also like