Professional Documents
Culture Documents
TO
PMBOK
1. Aspirational Standards
• Describes the conduct that we strive to uphold as practitioners. Although adherence to
the aspirational standards is not easily measured, conducting ourselves in accordance
with these is an expectation that we have of ourselves as professionals— it is not
optional.
2. Mandatory Standards
• Establish firm requirements, and in some cases, limit or prohibit practitioner behavior,
which if not followed will make a person subject to disciplinary actions by the PMI’s
Ethics Review Committee.
• Temporary Endeavor – (However, temporary does not mean a short duration.) The
project ends when:
• Projects objectives have been achieved (or when objectives cannot be met).
• Funding or resources are exhausted or unavailable.
• Project is no longer needed or is terminated.
3. Directive: Provides the project managers and takes control of various projects,
directly managing projects, and is responsible for the results of those projects.
(High control.)
• Predictive
• Incremental
• Iterative
• Adaptive
• Hybrid model
• Iterative: repeating until reaching a desired goal. Scope is known early, but
time and cost change.
Elements
Predictive
well-known or
Fixed requirements Life Cycle
Attributes Examples
Name Phase A, Phase 1, Proposal Phase
Number Three Phases in a Project
Duration One Week, One Month
Resource requirements People, Buildings, Equipment
Entrance criteria to move into Specific Approvals, Specific Documents
phase Completed
Exit criteria to complete a phase Documented Approvals, Completed
Documents, and Completed Deliverables
• “Good practice” does not mean the knowledge described should always
be applied uniformly to all projects.
Enterprise Organizational
Environmental Process Assets
Factors (EEF) (OPA)
• OPAs include:
• Artifacts, practices or knowledge
• Lessons learned, historical Info
• PM works to:
• Increase competency and capability
• Provide knowledge transfer, and integration initiatives
• Demonstrate the value of project management
• Increase acceptance of project management in the organizations
• Advance the value of the PMO to the organization
1. Project managers work with the project sponsor to understand the strategic
objectives and ensure the alignment of the project objectives with those of
the portfolio, program, and business areas.
2. Project managers are responsible for guiding the team to work together and
focus on what is really essential at the project level. Using integration of
processes, knowledge, and people.
• It is assumed that the project has been approved before this point by the
Sponsor or other decision-making body and that they have reviewed the
business case and benefits management plan before authorizing the
project.
• Key Benefit:
• Provides a direct link between the project and the organization’s strategic
objectives.
• Creates a formal record of the project and shows organizational commitment.
Interest Involvement
Influence Impact
Interdependencies
• Key Benefit : Enables the project team to identify the appropriate focus
for engagement of each stakeholder or group of stakeholders.
• Key Benefit: provides guidance and direction on how scope will be managed
throughout the project
• Requirements include:
• Quantified and documented needs and expectations of the sponsor,
customer, and other stakeholders.
• *Work Packages - the work defined at the lowest level of each branch of
the WBS for which cost, and duration are estimated and managed.
• The key benefit is that it breaks down the work packages in the WBS into
specific schedule activities used for estimating, executing, monitoring and
controlling the project work.
• Key Benefits: Work is defined logically to obtain the most efficient schedule
given all project constraints.
• Project Schedule Network Diagram
Start
A
C
• Key Benefit: Provides the amount of time each activity will take to
complete.
• Estimating durations uses data from the scope statement, resource skill,
experience and number to determine the activity durations.
• Should be done by the person or group most familiar with the work.
• Progressively elaborated as information becomes known.
• The key benefit is that it generates a schedule model with the planned
dates for completing the project activities.
• Key Benefit: Provides guidance and direction on how the project costs
will be managed throughout the project.
• Key benefit is that it determines the monetary resources required for the
project.
• Cost estimates should be reviewed and refined during the course of the
project to reflect any additional information.
• The key benefit is to determine the cost baseline and then ensure
performance against it is monitored and controlled throughout the life of
the project.
• The key benefit is that it provides guidance and direction on how quality
will be managed and verified throughout the project.
• The key benefit is to make sure that the degree, type, and visibility of risk
management must be in line with both the risk and the importance of
the project to the organization.
• The key benefit is that there is a documented record of the existing individual
risks and the sources of overall project risk.
• Identification of risk is a team event, and it is critical that ALL stakeholders are
involved and are responsible for risks for the life of the project.
• The process begins with the charter continues until close and is very much an
iterative process.
• The majority of risk identification is done during planning using three critical
components; WBS, cost estimates and time estimates.
• The key benefit of the process is that it quantifies overall risk exposure
with other supporting quantitative risk data to support the needed
response.
• The key benefit to the process is that it identifies the best ways to
address overall and individual project risks with specific activities and
resources as needed into project documents and plans.
• Responses should be appropriate for the significance of the risk and realistic
to the constraints of the project
• The key benefit is that the work is done here to meet the project
requirements which is also why a large part of the budget , resources and
time is used in the process.
• This is about making sure the skills, experience and expertise of the
project team and other stakeholders are used before, during and after
the project.
• Manage Quality uses the data and results from the control quality
process to reflect the overall quality status of the project to the
stakeholders.
Functional or Procurement
Resource Process
Manager
Internal External
Resources Resources
• The key benefit is that it influences the team’s behavior, manages conflict,
and resolves issues.
• The key benefit of this process is that it ensures that agreed upon risk
responses are executed as planned to address overall project risk
exposure as well as minimize individual threats and maximize project
opportunities.
• The key benefit of this process is that it selects a qualified seller and
implements the legal agreement for delivery.
• The key benefit is that it allows the project manager to increase support
and minimize resistance from stakeholders.
• The key benefit is that it allows stakeholders to understand the current state
of the project, recognizing actions taken to address performance issues, to
have visibility into future project status using cost and schedule forecasts.
• The key benefit is that it allows for documented changes within the project to be
considered while addressing overall project risk which can happen from changes
made without the consideration of the overall project objectives and plans.
• When required, change requests and impacts are sent to the Change Control
Board (CCB) to be approved, deferred, or rejected.
5. Enterprise environmental
factors
6. Organizational process assets
• The key benefit is that it brings objectivity to the acceptance process and
increases the chance of final acceptance by validating each deliverable.
• The key benefit of this process is verifying that project deliverables and
work meet the requirements detailed by the key stakeholders for final
acceptance.
• The key benefit is ensuring the right resources are available at the right
time, in the right place, in the right amount, and are released when no
longer needed.
• The key benefit is that it ensures both the seller’s and buyer’s
performance meet procurement requirements per the terms of the legal
agreement.
• The group verifies that the defined processes are completed within the
Process Groups to close the project or phase and formally establishes
that the project or phase is complete
• The key benefit is that phases, projects, and contracts are closed out
appropriately.
• The group may also address the early closure of the project such as a
cancelled project.
• The key benefits are the project or phase information is archived, the planned
work is completed, and the organizational team resources are released to
pursue new endeavors.