Status As on 30.08.

2020
SL. NHDP Name of Project NH No. Length Sanctioned Awarded Cost Date of Start/Appointed Date Date of Award Cumulative Physical
No. Phase/ (Old/ New) (Km) Cost/TPC Rs. Rs. in crore progress %
Scheme in crore

Manipur
Bridge Work
Construction of permanent steel bridge over
1 NH (O) Barak and Makru river 53 2 141 109 2017-04-27 2016-12-02 51.91%

(a) Total 2.00 141.00 109.00


Widening to 2-lane /4-lane
2 laning of Tamenglong- Khonsang road
2 SARDP 137 37.97 471 296.25 01.08.2019 08.03.2019 25.52%

EAP (ADB) 4-Laning Imphal- Moreh from Km


3 330.000 to Km 350.000 (Contract Package I) 39 20 761.54 397 01.06.2020 2019-09-05 0.00%

EAP (ADB) Two Laning Imphal- Moreh from Km


4 350.000 to Km 395.680 (Contract Package 39 45.68 868.75 457.77 2018-10-16 2018-06-01 73.61%
II)
2-laning of Churachandpur Tuivai Section of
5 BMP NH-102B (Pkg- IA) 102B 13.75 206.88 92.71 24.06.2020 31.03.2020 0.00%

2-laning of Churachandpur Tuivai Section of


6 BMP NH-102B (Pkg- IB) 102B 19.09 216.49 139.8 24.06.2020 31.03.2020 0.00%

2-laning of Churachandpur Tuivai Section of


7 BMP NH-102B (Pkg- IIA) 102B 15.76 292.24 139.19 01.07.2020 31.03.2020 0.00%

2-laning of Churachandpur Tuivai Section of


8 BMP NH-102B (Pkg- IIB) 102B 21.88 365.53 206.41 - 30.06.2020 0.00%

2-laning of Churachandpur Tuivai Section of


9 BMP NH-102B (Pkg- IVA) 102B 11.15 167.95 114.68 01.07.2020 31.03.2020 0.00%

2-laning of Churachandpur Tuivai Section of


10 BMP NH-102B (Pkg- IVB) 102B 11.03 177.76 102.80 - 30.06.2020 0.00%

NH (O) 2-laning of NH-102C from Pallel- Chandel


11 (SARDP) 102C 18 108 71.01 24.06.2020 27.03.2020 0.00%

NH (O)
12 (SARDP) Construction of 2-lane Moreh-Bypass 39 3 48 21.51 01.07.2020 27.03.2020 0.00%

NH (O) 2-laning from Yaingangpokpi to Finch Corner


13 (SARDP) (Pkg- I) 150 16.9 232.99 124.81 01.07.2020 28.03.2020 0.00%

NH (O) 2-laning from Yaingangpokpi to Finch Corner


14 (SARDP) (Pkg- II) 150 14.07 365.33 135.63 01.07.2020 28.03.2020 0.00%

(b) Total 248.28 4282.46 2299.57

Rehabilitation
Short term routine maintenance and
improvement of Imphal-Jiribam road from Km
15 NH (O) 3.00 to Km 75.00 on percentage rate basis 53 51.67 46.76 2017-04-01 2017-04-26 100.00%

Short term routine maintenance and


improvement of Imphal-Jiribam road from Km
16 NH (O) 75.00 to Km 145.00 on percentage rate basis 53 43.05 38.44 2017-03-10 2017-04-17 100.00%

Short term routine maintenance and


improvement of Imphal-Jiribam road from Km
17 NH (O) 145.00 to Km 220.00 on percentage rate 53 66.86 60.36 2017-04-01 2017-05-08 100.00%
basis
83.00
Restoration/Reconstruction of Ukhrul- Toloi-
Tadubi road section from Km
18 NH (O) 0.00 to Km 28.00 covering 28 Km 102A 28.00 3.78 2.98 2016-10-27 2016-10-26 100.00%
length on NH-102A in the state of Manipur.

Restoration/Reconstruction of Ukhrul- Toloi-


Tadubi road section from Km
19 NH (O) 28.00 to Km 50.00 covering 22 Km 102A 28.00 14.91 11.12 2016-11-07 2016-10-26 100.00%
length on NH-102A in the state of Manipur.

Restoration/Reconstruction of Ukhrul- Toloi-


Tadubi road section from Km
20 NH (O) 50.00 to Km 70.00 covering 20 Km length on 102A 22.00 11.40 11.35 2016-01-11 2016-10-26 100.00%
NH-102A in the state of Manipur.

Restoration/Reconstruction of Ukhrul- Toloi-


Tadubi road section from Km
21 NH (O) 70.00 to Km 90.00 covering 20 Km length on 102A 20.00 15.64 13.07 2017-05-24 2017-03-29 100.00%
NH-102A in the state of
Manipur.

Restoration/Reconstruction of Ukhrul- Toloi-


Tadubi road section from Km
22 NH (O) 90.00 to Km 115.00 covering 25 Km 102A 20.00 15.37 12.91 2017-05-24 2017-03-29 100.00%
length on NH-102A in the state of Manipur.

Rehabilitation/Strengthening of existing road


Churachandpur- Singhat-Sinzawl-Tuivai
23 NH (O) sector from Km 0.00 to Km 34.500 102B 34.5 47.82 37.69 2017-12-12 2017-11-28 92.00%

Rehabilitation/Strengthening of existing road


Churachandpur- Singhat-Sinzawl-Tuivai
24 NH (O) sector from Km 34.00 to Km 103.1 102B 68.6 69.31 54.08 2016-08-01 2016-06-08 100.00%

Rehabilitation/Strengthening of existing road


Churachandpur- Singhat-Sinzawl-Tuivai
25 NH (O) sector from Km 103.1 to Km 161.48 102B 58.38 59.4 45.12 2018-01-18 2018-01-04 100.00%

Temporary restoration of Khongsang-


26 NH (O) Tamenglong on item rate basis 137 40 19.1 17.48 2017-02-06 2017-01-30 100.00%

(c) Total 402.48 418.31 351.36


Cumulative Target date of completion as per contract Name of the Contractor
Financial
progress %

45.29% 31.12.2020 M/s Bhartia Infra Projects Limited (BIPL)

23.44% 2022-07-31 M/s Shivalaya Construction Pvt. Limited

0.00% 31.05.2023 M/s GR Infra Projects ltd

71.39% 2021-10-15 M/s GR Infra Projects ltd

0.00% 24.06.2022 Krishna Construction Co.

0.00% 24.06.2022 RSM Infra Projects

0.00% 01.07.2022 Bharat Vanijya Eastern Pvt. Ltd

0.00% - Bharat Vanijya Eastern Pvt. Ltd

0.00% 01.07.2022 GPT Infra Projects Ltd.

0.00% - GPT Infra Projects Ltd.

0.00% 24.06.2022 Krishna Construction Co.

0.00% 31.12.2021 M/s L.K. & Sons

0.00% 01.07.2022 M/s Varaha Infra Limited

0.00% 01.07.2022 M/s Varaha Infra Limited

100.00% 2018-06-30 M/s HVS Construction Materials Pvt. Limited

100.00% 2018-03-11 M/s Nidhi Creative Infrastructure Limited

100.00% 2018-06-30 M/s Bhartia Infra Projects Limited

100.00% 2018-01-26 M/s Bhartia Infra Projects Limited

100.00% 2018-02-06 M/s Shingvah Thanami

100.00% 2018-01-31 M/s Bhartia Infra Projects Limited

100.00% 2018-05-23 M/s Haokhotinlen Vaiphei

100.00% 2018-05-23 M/s Haokhotinlen Vaiphei

90.00% 2019-09-23 M/s Satya Builders

100.00% 2019-08-01 M/s Bhartia Infra Projects Limited

100.00% 2019-10-30 M/s Garg & Sons

96.62% 2018-02-05 M/s K. Morung and sons


Maintenance

Resurfacing of Ukhrul Tolloi from Km


1 M&R 0.00 to Km 28.00 on item Rate Basis 102A 28 4.34 3.3 2019-10-12 2019-08-07 30.00%

2
M&R Rate Contract of Imphal-Jiribam from Km 37 217 2.7 2.11 2019-09-19 2019-07-31 35.00%
3.00 to Km 220.00
Rate Contract Imphal-Moreh Pkg-I (Km
330.00 to Km 350.00) & Pkg-III (Km 395.680
3 M&R 39 49.73 1.24 0.85 2019-06-18 2019-05-23 65.00%
to Km 425.411)

Restoration/Rehabilitation of Churachandpur-
Tipaimukh road from Km 0.00 to Km 185.00
4 M&R on EPC 185 82.00 31.25 31.25 2019-05-15 2019-02-25 36.59%
mode
Restoration and Reconstruction of
Churachandpur-Tipaimukh road from Km
5 M&R 202 77.00 41.58 36.59 2018-09-17 2018-07-16 56.42%
185.00 to Km 262.00 on EPC
mode
Short term improvement & Routine
6 M&R Maintenance Ukhrul- Jessami- Nagaland 150 63.00 19 16.69 2018-08-01 2018-06-19 82.00%
Border
Imphal-Jiribam Pkg-III (Km 145.00 to Km 37 10.09.2018 31.07.2018 85.00%
7 M&R 220.00) 25.00 14 16.35

Rate Contract of Imphal-Jiribam Pkg- I (Km 37 27.04.2018 18.04.2018 81.00%


8 M&R 3.00 to Km 145.00) - 1.84 1.58
9
M&R Rate Contract of Imphal-Jiribam Pkg- II (Km 37 - 1.09 0.76 10.06.2018 09.05.2018 68.00%
145.00 to Km 220.00)
Rate contract of Ukhrul Tolloi Tadubi Km 0.00
10 M&R to Km 28.00 102A 28.00 0.69 0.55 20.09.2018 03.09.2018 49.00%

11 M&R Rate contract of Tolloi Tadubi Km 28 to Km 102A 87.00 2.1 1.48 2019-06-07 2019-05-23 8.78%
115.00
Repair and Maintenance of 35 km (NH-150)
in the State of Manipur from Yaingangpokpi to
12 M&R Finch Corner (Km 488.15 to Km 522.86) on 150 25.00 10.94 8.41 2018-04-19 2018-04-02 89.00%
item rate basis

Restoration/Rehabilitation of Churachandpur-
Tipaimukh road from Km 0.00
(Churachandpur) to Km
13 M&R 185.00 (Bukpi) on NH-150 in the State of 202 - 4.62 4.61 2018-05-07 2018-05-05 100.00%
Manipur on item rate basis

14 M&R Imphal-Jiribam Pkg-I (Km 3.00 to Km 75.00) 37 7.00 11 12.82 02.10.2018 29.08.2018 100.00%

Imphal-Jiribam Pkg-II (Km 75.00 to Km 37 22.09.2018 17.08.2018 100.00%


15 M&R 145.00) 15.00 14 15.83

Short term maintenance of Temporary


Restoration of Tamenglong-Khongsang road
16 M&R from Km 0.00 to Km 40.00 37 40.00 0.81 0.77 17.08.2017 31.07.2017 100.00%

Repair and Maintenance of Pallel- Chandel


(NH-102c) from Km 0.00 to Km 18.00 in the
17 M&R State of Manipur 102c 18.00 1.03 0.89 21.08.2017 31.07.2017 100.00%

Balance Construction for left over structure of


retaining walls and culverts along Imphal-
18 M&R Jiribam road from Km 0.00 to Km 220.00 37 - 2.65 2.77 30.08.2017 31.07.2017 100.00%

De-launching and replacement of (i) Chera


Thok Bailey Bridge (Nung Dolan Bridge) at
Km 150.700 at Imphal-Jiribam road (NH-37)
of span 100 feet (DD) & (ii) Makru Bailey
19 M&R bridge at Km 189.300 at Imphal- Jiribam road 37 - 0.9 0.905 11.04.2018 11.04.2018 100.00%
(NH-37) of span 30 feet
(DS)

De-launching and replacement of Bailey


Bridge at Km 70.300 at Churachandpur-
Singhat-Sinzawal road of span 140 feet
(DDR) Standard width IRC Class 40R loading
20 M&R complete with bearing and Steel decking in 102B - 1.78 1.69 14.03.2018 26.02.2018 100.00%
the State of Manipur

(d) Total 761.73 167.56 160.21


Grand Total (Civil Work) 1414.49 5009.33 2920.13
(a+b+c+d)
M/s Shongvah Thanmi, Khanasom Phungdhar, Village Ukhrul
13.53% 2020-03-11 Central

13.53% 2020-09-18 M/s Continental Construction & Co Kakwa Lamdaibung

30.0% 2020-06-17 M/s LK & Sons. Limited

18.94% 2020-11-15 M/s GR Infra Projects Limited

44.43% 2020-07-10 M/s Nidhi Creative

60.58% 2019-07-31 M/s HVS Construction Materials Pvt. Limited

19.06.2019 M/s Bhartia Infra Projects Limited


62.14%

26.04.2019 M/s NDS Construction


60.00%

55.26% 09.06.2019 M/s G Panmei

49.00% 19.09.2019 N Jugindra Singh

8.78% 2020-06-06 M/s Shongvah Thanmi, Khanasom Phungdhar, Village Ukhrul


Central

36.74% 2019-04-20 M/s LK & Sons. Limited

100.00% 2019-05-06 M/s NDS Construction

99.45% 28.06.2019 M/s HVS Construction Materials Pvt. Limited

21.06.2019 M/s Nidhi Creative Infrastructure Limited


92.55%

100.00% 16.02.2018 M/s K. Morung and sons

100.00% 20.04.2018 M/s K. Morung and sons

100.00% 30.04.2018 M/s NDS Construction

100.00% 30.05.2018 M/s Bhartia Infra Projects Limited

100.00% 10.06.2018 M/s Bhartia Infra Projects Limited


Inception Report Feasibility Report Draft DPR
NHDP Alignment LA
SL. Name of NH No. Length Date of 3a Notification
Phase/ Name of Project Approval
No. Consultant (Old/ New) (Km) Award date/ Area in Ha
Scheme Status
Target Date Actual Date Target Date Actual Date Target Date Actual Date

DPR
Final Feasibility
report recevied
on 30.06.2016
Land acquisition has been proceed through direct
M/s CE Testing
1 ADB Ukhrul -Toloi- Tadubi 102A 115 23.11.2015 14.01.2016 05.01.2016 finalized 14.04.2016 31.07.2017 02.08.2016 purchage mode. LA estimates for Ukhrul and Senap
Pvt.Ltd.
Districts sent to HQ for Approval.

2
NK Two laning with paved M/s CE Testing 129A 204 26.10.2017 21.12.2018 15/01/2018 finalized 03.03.2018 13/10/2018 01.04.2018 26/03/2019 DPR work hold up to draft DPR stage
shoulders from Maram- Pvt.Ltd.
Peren Dimapur

3
NK Two laning with paved M/s SM 202 12 28.12.2016 _ _ Not finalized - Final Feasibility 22.07.2018 - Alignment is not finalized
shoulders from Jessami Consultant report on
to Nagaland Border 29.07.2017

A Total 331

Bharatmala

1 BMP Shangshak- Nampisha M/s CE Testing 102A 90 26.10.2017 21.12.2018 15/01/2018 finalized 03.03.2018 27/10/2018 01.04.2018 11/03/2019 10.08.2019

DPR preparation is hold due to non-finalization of sche


2 BMP Imphal-Jiribam M/s CE Testing 37 220 26.10.2017 21.12.2018 15/01/2018 finalized 03.03.2018 2018-03-11 01.04.2018 18.05.2019

published on
Churachandpur- 26/10/2018 for
3 BMP M/s CE Testing 102B 89 26.10.2017 21.12.2018 15/01/2018 finalized 03.03.2018 12/10/2018 01.04.2018 03.05.2019 Pkg-I
Sinnghat-Tuiavi

M/s SM
4 BMP Moirang-Imphal 150 42 28.12.2016 22.02.2017 02.02.2017 Not finalized 22.07.2017 29.07.2017 22.08.2017 29.12.2017 Greenfiled alignment is not finalized
Consultant

Jessami- M/s SM published on


5 BMP 150 170 28.12.2016 22.02.2017 02.02.2017 finalized 22.07.2017 29.07.2017 22.08.2017 29.12.2017
Yaingangpopki Consultant 21/08/2018

6 Kohima -Imphal M/s Stanley 39 125 14.07.2015 01.01.2016 04.01.2016 finalized 31.03.2016 07.03.2019 31.07.2016 under progress

B Total 736.00
Status Of Pre-Construction Activity
Final DPR
LA FC Utility
3A 3G Stage II Approval Shifting Estimate d
Notification date/ Notification date/ Stage I Approval date/ date/ Area in Ha Estimate (in Cost
Area in Ha Area in Ha Cr) Target Date Actual Date
Area in Ha

1.Not initiated as
payment is
awaited from HQ. MSPDCL:
Land acquisition has been proceed through direct Received: 2.Animal Passage PHED: Yet
purchage mode. LA estimates for Ukhrul and Senapti FC-29.08.2018 WC- Plan pending from 15.09.2016 31.08.2016 1610
to be
Districts sent to HQ for Approval. 07.09.2018 Consultant submitted

DPR work hold up to draft DPR stage Not yet submitted - - 20/06/2018 _ 1624

Alignment is not finalized Under survey - PHED: - - 168


04.08.2018

3402

1. FC application
submitted for package-3
& 4,
remaing application are
pending from consultant.
_ _ 2.WC application is _ _ 20/06/2018 _ 1260
pending form consultant

DPR preparation is hold due to non-finalization of scheme


Yet to be applied. _ _ 20/06/2018 _ 3080

DPR to be carried out, however LA


process to be kept hold as per MOM
held at HQ, NHIDCL. Yet to be applied. _ _ 20/06/2018 _ 1290.5

FC not applicable. WC
proposal is applied but
the proposal is on hold
Greenfiled alignment is not finalized as per direction. _ _ 20.09.2017 Submitted 609

3A notified on 4 FC & 1 WC
29.07.2019 for proposals are applied.
Imphal-East FC is in CF stage and
District and 3A WC is under DFO stage.
uploading for other
Districts are under _ _ _ 20.09.2017 Submitted 2465
progress

_ _ FC yet to be appied _ _ 31.07.2016 _ 1325

10029.50
NH-In Principle
2 laning with paved
shoulder from
Tamenglong in Manipur
to Peren in Nagaland
M/s CE Testing
1 NK via Longdi Pabram 100 26.10.2017 21.12.2018 15/01/2018 finalized 03.03.2018 2018-12-10 01.04.2018 _ DPR upto Feasibility stage
Pvt.Ltd.

Two laning with paved Final Feasibility


shoulders from report recevied
Hafflong- Tamenglong on 03.08.2018
Via Lia Sang & Tausem State
2 NK M/s L.N.Malviya 150 21.11.2016 31.01.2017 06.03.2017 finalized 30.06.2017 - - DPR upto Feasibility stage
Road

Two laning with paved Final Feasibility


shoulders from Jiribam report recevied
to Tipaimukh on 03.08.2018
State Under
3 NK M/s L.N.Malviya 105 21.11.2016 31.01.2017 06.03.2017 30.06.2017 - - DPR upto Feasibility stage
Road finalization

C Total 355.00

Grand Total (DPR) (A+B+C) 1422.00


Not yet in the stage of
DPR upto Feasibility stage 06.05.2018 _ 20/06/2018 _ 1329
application

Not yet in the stage of


DPR upto Feasibility stage - - - - 2100
application

DPR upto Feasibility stage NO DPR - - - - 1470

4899.00

18330.50