Professional Documents
Culture Documents
PERT
CPM
If late start, early finish and activity duration is 5, 8 and 4 days respectively, What will be
independent float?
-1
If early start, early finish and activity duration is 5, 8 and 2 days respectively, What will be free float?
-1
For the last node in the CPM, which of the following is true?
C
If Optimistic and pessimistic time for an activity is 10 hrs and 13 hrs, Variance of this activity will be:
0.5
0.25
If Optimistic and pessimistic time for an activity is 10 hrs and 14 hrs, Expected time of this activity
will be:
12 hrs
0.66 hrs
4 hrs
Insufficient information
Optimistic and pessimistic time for an activity is 10 hrs and 10 hrs respectively
Optimistic and pessimistic time for an activity is 10 hrs and 12 hrs respectively
Optimistic and pessimistic time for an activity is 12 hrs and 10 hrs respectively
Option A & C
B
What can be true for a PERT problem?
Project completion time can be more than the calculated completion time