Professional Documents
Culture Documents
SELECTRION OF A PROJECT:-
Expected return can be measured as NPV or IRR or some other criterion of merit.
Variability of Return can be measured in terms of Standard Deviation or some other dispersion
index.
Given the information about expected return and variability of return, the next question is:
The risk adjusted discount method calls for adjusting the discount rate to reflect project risk.
a) If the risk of the project is equal to risk of the existing investments of the firm,
the discount rate used is the average cost of capital of the firm.
b) If the risk of the project is greater than risk of the existing investments of the
firm. , the discount rate used is higher than the average cost of capital of
the firm.
c) If the risk of the project is less than the risk of the existing investments of the
firm, the discount rate used is less than the average cost of capital of the
firm.
The Risk adjusted Discount Rate is:
rk = (i + n) + dk
where:
rk = Risk Adsjusted Discount rate of the project k
i = Risk Free Rate of Interest
n = Adjustment for the firms normal risk
dk = Adjustment for the differential risk of project k.
(i + n) = measures of the firm’s cost of capital.
Page 2 of 3
Where:
Despite its popularity, risk-adjusted discount rate method suffers from serious limitations:-
i) It is difficult to estimate to estimate d k consistently as it is determined in an ad
hoc and arbitrary manner.
ii) This method assumes that risk increases with time at a constant rate as this assumption may
not be valid.
Page 3 of 3
Illustration:-
The expected cash flows of a project , which involves an investment outlay of Rs 1,00,000, are
as follws:-
---------------------------------------------------------------------------------------------------------------------
Year Cash Flow (Rs)
---------------------------------------------------------------------------------------------------------------------
1 200,000
2 300,000
3 400,000
4 300,000
5 200,000
---------------------------------------------------------------------------------------------------------------------
The risk adjusted rate for this project is 18%. Is the project worthwhile?
Solution:-
We need to find out the NPV, using risk adjusted discount rate.
= [A1 /(1 + rk)1] + [A2 /(1 + rk)2] + [A3 /(1 + rk)3] + [A4 /(1 + rk)4] +[A5 /(1 + rk)5] - I
= [200,000/(1 +.18)1] +[300,000/(1 +.18)2] + [400,000/(1 +.18)3] + [300,000/(1+.18)4] +
[200,000/(1 +.18)5] – 1,000,000
= - Rs 129,440