PT. Daya Panasindo Teknik 7"“?"**'*
‘Thermal Engineering Specialists and Services
1 Puskesmas No. 76 Tel 021 78834902
Kebagusan, Pasar Minggu Tel 021 78834903
Jakarta Selatan, 12520 Fax 021 78834905
vw: panasndo od mail: info@panasindo.co.d
To : Harbison Walker International
J, Australia II Kav. NI
KIBC Complex Cilegon
Banten 42443
Attn, Bapak Hendra Arief
Scope of Wor
Dry Out Services for 1 x Cyclone Coal Boiler, PT SUJ Sugar , Ciwandan Cilegon
‘To provide mobilization/demobilization services for HV Gas equipment and personnel to/from
your work site at PT. SUI Sugar , Ciwndan Cilegon , Banten
To provide Dry Out services to 1 (one ) unit Cyclone Coal Boiler in accordance with provided
procedure and client instructions.
To provide HV Gas equipment complete , consumables and tools together with senior and experience
gas techicians sufficient for the scope of work
2:Documentation
Copies of certificates of calibration for temperature recorders
Copies of certificate of conformance for thermocouple wire
Original of temperature recorder charts report
3.:Provisional Equipment List
Set HV Gas PWHT equipment
Combus 50 KVA power Transformer
Gas ConP 256 automatic Programmer
[12 points temp recorders, 0 - 1200 degC
Gas Mat triple cable sets, 3 way splitters and various
Flame
Set Temperature Recorder and Thermocouples,
1 Unit Thermos discharge type.
discharge type.
Preheat, Post Weld Heat Treatment, Refractory Dry Out, Thermal Engineering Specialists and ServicesPT. Daya Panasindo Teknik !*donesia.
‘Thermal Engineering Specialists and Services
= Notes
Specific procedure/s will be submitted on receipt of contract award. Procedures are available
immediately for client approval.
Our bid price is for dry out / curing services only up to 650 deg C for 25 hours
Any non productive time or standby time, through no fault of our technicians, in the period
exceeding the agreed contract period, the applicable daily rates cost will be charged.
Gas consumption only able to estimation if the cyclone being fitled with isolation bulkheads/
partitions to retain heat in the Refractory Dry Out area
Exceptio
Split of supply
All electrical power and primary connection cables from power supply to our PWHT
equipment to be supply by client
Client to make available at the job site /s first aid and medical, treatment for our personnel.
All cranage/forklift or handling movement for our equipment, site office, scaffolding,
weather protection /site shelter for the work piece at site to be provide by Client.
All bulk
is! / Partitions need and the LPG consumptions (Bulk)PT. Daya Panasindo Teknik /"@onesia.
Thermal Engineering Specialists and Services
6: Price Schedule,
Table L0
Deseription Unit_YUnit Price Total
Indirect Works :
Mob / Demob for our man and equipmd LS Rp2,000,000] Rp2,000,000
horfrom PT SUJ Ciwandan Cilegon
Direct Work
Dry Out Services to I x Cyclone LS | Rp78,300,000] _Rp78,300,000
|Coal Bumer come with
Senior
HV Gas Equipment, Consumables and Tools
‘Technicians
TOTAL (_Rp80,300,000)
Term and Conditions
~ Prices quoted are Net in Indonesian Rupiah
- Payment via telex transfer to our designated bank.
- Indonesian PPN tax is extra at Government prevailing rate,
- Payment @ 30 Days after receipt of invoice.
Wurl Praptiwi Sdebadi