You are on page 1of 5

DEVIATION OF QUANTITIES STA

NAME OF WORK: Providing 21.00 meter roof tower on TE B Building terrace at Paderu,Visakhapatnam
Agreement No.69/EE/BSNL/CD/VM/2010-11 Dated 24/3/2011

Agreement No.69/EE/BSNL/CD/VM/2010-11 Dated Statement No.I Rs. 27,549/- by SDE ( C)


Name of agency: N.Appa Rao Statement No.II Rs. 37,800/- by EE ( C)
Estemated cost : Rs. 2,17,252/- Amount of this Statement Rs.
Agrement Amount: Rs. 2,76,076/- Total Deviation Rs.

Agt Qty Excess/ Dev % Dev %


Sl
Item Description Unit Agt Qty Executed / Deviated
No
No Anticipated Qty (+) (-)

1 2 3 4 5 6 7 11
Earth work (a) All kinds of
soil
1 1

cum 31.00 55.00 24.00 77%


2 4 CC 1:5:10 cum 20.00 10.00 -10.00 -50%
N OF QUANTITIES STATEMENT No.III
apatnam

7,549/- by SDE ( C)
37,800/- by EE ( C)

At Agmt Rates At Modified Rates


Total
Agt Rate Amount Modified / Deviation
Proposed
Quantity (Upto 50% (Absoulte Proposed Amount Amount
Qty
excess) value) rate

9 10 14 15 21

15.50 170.00 2635.00 8.50 170.00 1445.00 4080.00


10.00 2800.00 28000.00 28000.00
Total : 32080
Remarks

22

Some thing..
Some thing..