Calculation Sheet for BM Importing

Descrption Time (mins)


Sorting Time for Single Channel 1
Importing Time for Single Channel 1
Adjust / Arrangement Time for Single Channel 2.5
Verification Time for Single Channel 2
Total Import Time for Single Channel 6.5

Total Floors Candidate for data import 51


Channels to be imported / Floor 7
Total Channels to be Imported 357
Shift Time
Total Import Time Required for Project (mins) 2320.5
M Importing
Time (Hrs) Days

8
39 4.875