Professional Documents
Culture Documents
1. Are there (What are) any legislations, administrative order or internal rules regulating
(hereinafter referred to as “Regulations”) construction bidding procedures with which
government authorities, public institutions and/or state-owned companies (“SOC”) shall
comply?
In Indonesia, the Regulations on construction bidding procedures are various depends on: (1) who the
parties are; and (2) which scheme chosen by the parties. If the counterparts are government authorities
and/or public institutions and an SOC, below classifications are applied:
If there is any matter that is not regulated in the regulations above, all of prior Government
Procurement of Goods/Services (Presidential Regulation No. 54 of 2010) is remain valid as
long as it is not contradictory and/or has yet to be replaced by PR 16/2018.
In PPP project, there is a procurement process which involves bidding stage. If the project is
an PPP project, then it subjects to Presidential Regulation No. 38 of 2015 on PPP in
Infrastructure Projects (“PR 38/2015”) and its implementation regulations, these are:
Other than general regulations above, the execution of PPP projects should consider the
sectoral regulations of the infrastructure that will be build.
b. SOC
1) The types/kinds of government authorities, public institutions or state-owned companies that are
regulated by the Regulations and the extent to which the Regulations reach to control their
procurement activities
2) Type of bidding procedure to apply for a specific construction project and criteria to apply a
specific type, for example:
2 (in case of competitive bidding) Open bidding or limited competitive bidding after passing a
prequalification procedure.
3) Details of each type of bidding procedure from bid announcement to entering into contract (as
summarized in brief manner)
4) How to evaluate bid for selection of successful bidder, for example:
1 Type of successful bidder: the lowest bidder or any other type, and details of each type
2 In case of any illegal actions in relation to solicitation and bribery (including illegal actions
committed for other projects or in other countries)
3 In case of termination of construction contract due to defective work or any other cause
attributable to bidder (including illegal actions committed for other projects or in other
countries)
6) Requirements to apply to only foreign bidders during such bidding procedure or restrictions
3. As we know, it is generally known that even if a construction contract is made between successful
bidder and project owner or anybody, the contract in respect to which any defective decision or breach
of the Regulation during bidding procedure is found may be acknowledged defective and might be
concluded null and void. Furthermore, the bidder might lose his firm position of the contractor to such
contract and his compensation for works done under such defective contract is possible not to be
respected.
1. Are there (What are) any legislations or regulations regarding construction industry and construction
contract (for examples in Korea: Framework Act on the Construction Industry, Fair Transactions in
Subcontracting Act, Construction Technology Promotion Act, Antitrust Policy, Civil Law,
Commercial Law and etc.)
2. Are there any other general requirements to doing business in construction services as a foreigner? For
examples:
1) The establishment of incorporate entity independent from its parent company in home country or
any branch office or liaison office
4) Whether or not partnering or cooperation with local staff or local companies is compulsory?
5) Any other additional explanations not included in the above questions?
1) If such discrimination exists, what are the major discriminative treatments in comparison to local
companies?
2) Is there any bilateral or multilateral agreement on investment including the Republic of Korea? If
so, what are the major contents in the agreement?
1) The extent to which such supervision system reaches to control construction services
2) Legal and contractual relationship among the supervisor, employer and constructions contractor
5. Is there public system or legislation regulating subcontract and relating issues like unfairness?
1) Are there classification and categories in construction industry? And is there registration system
or license in accordance with such classification and categories?
(for example, in Korea, there are two classifications of general construction works and
specializing construction work and, in class of specializing construction works are a total number
of 29 categories in details, including but not limited to reinforced concrete and construction
machine equipment, all categories of which are restricted construction services area beyond
which any specializing construction contractor do not work legally. Separate systems from the
construction industry exist for registration of electric and fire services.)
2) Is there any limitation or restriction in subcontracting construction works which are awarded to
contractor?
3 Subcontractor’s entitlement to claim directly against employer who has not direct
contractual relationship therewith. If allowed, any condition required to exercise such
4 For disputes arising in connection with subcontract, is there any special or separate dispute
resolution procedure from general civil procedure? If so, how does it work?
6. Is there any legislation or other rule to control on bidder’s engaging agent or consultant during bidding
and execution stages?
2) The effectiveness of awarded construction contract by engaging the agent or consultant, however,
which is found to be engaged in breach of the legislation or other rule.
7. Joint Ventures
1) The legal status of Joint Venture (or Consortium): Is it acknowledged as separate legal entity
from respective membership itself? If so (whether partly or wholly), to what extent does Joint
Venture may enjoy legal ability and competence?
1 Is it possible that parties to UJV enter into internal UJV or Consortium agreement, without
consent from employer, to divide/limit the scope of construction works to be carried out by
each party and their respective liability?
2 What are the liabilities of each member of UJV or Consortium for employer? And is it
possible that such liabilities for employer are limited by putting cap of liability on each
member?
3 In case that a member of UJV or Consortiums need to enter into an agreement with a third
party (including subcontractors), shall such agreement be signed by both parties or a
representative on behalf of both?
4 What are the liabilities of member of UJV or Consortium for third parties other than
employer?
Is it possible that property of UJV or Consortium (including right and obligation arising out
of construction contract with employer) is acknowledged as separate from each member of
UJV or Consortium?
5 Is it enforceable for employer or any third party to recover its loss or damage from
individual property that belongs to each member in case of such loss or damage occurring
due to UJV or Consortium’s act or omission or each member’s activity in the name of UJV
or Consortium? Otherwise (in reverse case)?
6 Are there any other forms of Partnering other than UJV or Consortium?
2. Defect Liability
1) When is the counting point of defect liability period? (For example, the Framework Act on the
Construction Industry in Korea basically stipulates that the counting point of defect liability
period is either substantial completion of works or the date of commencement of actual
possession or operation by employer (whichever is earlier); however, in some countries, the
counting runs when defect remedial period is expired, which is provided for contractor complete
outstanding works remaining at the time of substantial completion)
2) What are the details of defect liability period? Is it compulsory rule? Is there any possibility to
reduce defect liability period?
3. Payment
1) Local practice or legal regulation of payment method (Currency/Cash/Promissory Note and etc.)
2) Local practice or legal regulation about payment frequency/term between previous payment and
the next/advance payment/retention and etc.)
4) Local practice or legal regulation about payment timing (including subcontract): for example, is
there any regulation time schedule within which employer or prime contractor shall make
payment after invoicing or completion of work or part thereof?
5) Local practice or legitimate about delay of payment and delay charge(in case that contract is
silent for delay charge, contractor’s entitlement to delay charge)
6) Local practice or legal regulation about payment guarantee and security for guarantee
9) Local practice or legal regulation about the liabilities of prime contractor in the event that its
subcontractor does make payment to subcontractor’s employee, discharge its obligation for tax
authority or other public organizations
4. Liability
1) Is there any perspective in local practice or legal regulation describing the principle of liability
distribution between employer and contractor?
4) If limitation of liability is specified in a contract, are there items that have to be excluded in the
limitation of liability? (For example, willful misconduct, gross negligence or indemnity)
5) Whether or not does limitation of liability include remedial works for defect? (For example,
some commentators would say that defect liability is primary obligation of contractor so that
limitation of liability does not include, which means defect liability is good example of the
exclusion)
6) Local practice or legal regulation about compensation of consequential & indirect damages
7) Is it enforceable to compensate consequential & indirect damages incurred to the other party if
both parties enter into an agreement including the provision of such compensation?
8) It is normal understanding in English law that liquidated damages is compensation for genuine
damage as estimated upon both party considering but penalty is prohibited and not effective.
However, some jurisdictions acknowledge penalty provision agreed to be effective, which works
as compulsory and contractual mean preventing defaulting party in breach of contract from such
breach situation being remained. In this regard, both liquidated damages and penalty are
completely compatible. So, is it possible to have both liquidated damages and penalty which are
coexistence in the same contract in this country? If possible, is it possible to reduce the penalty
amount?
9) Please explain types and policies of insurances, in general, that contractor shall take out for
construction project
10) Please explain local practice or legal regulation for indemnity provision: the extent of loss,
damage and risk to which such indemnity provision covers in contract and exclusion items
5. Labor
2) Please explain local practice or legal regulation regarding employment conditions of foreign
labors
3) In case of hiring local labors, are there any things that foreign bidders need to be aware of?
(Working conditions, payment conditions, day-off conditions, termination of employment
conditions and any others)
4) Please explain penalties or legal effects when violating related labor laws.
6. Please explain types of taxes for which contractor shall be liable such as corporate tax, VAT, social
security tax, personal income tax
1) Are there any other legislations or local practices enabling that contractual parties discharge of
contractual obligations or get out contractual relationship prior to completion of contract other
than voluntary agreement by contractual parties or contract termination due to default by one of
contractual parties
2) Please explain the attitude of court toward the concept of Force Majeure and acceptability about
Force Majeure provided on contract
3) Please explain the timing of risk transfer (for example, timing of transfer of care and custody
obligations) and exception to risk transfer (for example, Employer’s risk)
8. Termination/Cancellation
1) Please explain causes of termination or cancellation of contract that legally recognized even
though contract does not expressly provide for
2) Please explain reality or the actual possibilities for contractor to exercise its right of cancellation
or termination in case that legally recognized or provided expressly for under contract.
1) Is it possible to prohibit the employer’s right to cancellation of project (restoring to the original
state) (for example, in Korea, the right to cancellation is restricted after taking-over of
construction works. However, in FIDIC standard contract, exercising the right to cancellation is
possible even after provisional acceptance (taking over) )
2) Is it possible for employer to exercise its convenient termination? If possible, where can legal
grounds be found? And, in case of employer’s convenient termination, to what extent can
contractor be compensate compared to employer’s termination for cause)
3) Any other advice not contained in the above question about rejection
1) Please explain contents in legislation or local practice for risk allocations regarding to ground
conditions in project site.
2) Is it legitimate that contract shall be liable for (all or any portions) unforeseeable ground
conditions?
3) In general, according to the local practice or legislations, to what extent shall contractor be liable
for unforeseeable ground conditions
12. Variation
1) Please explain whether or not employer has a right of change to work in the middle of
construction, and is there limitation of such right of change to work?
13. Is there a principle to resolve matters which are ambiguous or not expressly agreed by both
contractual parties?
14. Lien
1) Please explain whether or not contractor is able to exercise the right to lien, also can the right to
lien be excluded by specifying on a contract agreement?
15. In case that major construction project has been cancelled or terminated prior to completion, is there
legislation or regulation which is applicable to help contractor who has not been received proper
payment?
IV. Others
1. Does the New York Arbitration Convention apply? or is there any bilateral or multilateral treaty in
relation to enforceability of court judgement?
2. Please explain the credibility of court judgement in Thailand and any other things that foreign bidders
shall be aware of.
3. Please explain measures of dispute resolutions for construction project in Thailand other than court
ruling.
5. Please explain legislations in relation to environment which give direct impacts on construction
business