REVIEW
IMPORTANCE OF SCHEDULES/PROGRAMMES
STANDARD FORMS OF CONTRACTS
SESSION 1
The Engineer shall Review the initial programme and each revised programme submitted
by the Contractor and may give a Notice to the Contractor stating the extent to which it
does not comply with the Contract or ceases to reflect actual progress or is otherwise
inconsistent with the Contractor’s obligations. If the Engineer gives no such Notice:
- within 21 days after receiving the initial programme; or
- within 14 days after receiving a revised programme
the Engineer shall be deemed to have given a Notice of No-objection and the initial
programme or revised programme (as the case may be) shall be the Programme.
The Contractor shall proceed in accordance with the Programme, subject to the
Contractor’s other obligations under the Contract. The Employer’s Personnel shall be
entitled to rely on the Programme when planning their activities.
Nothing in any programme, the Programme or any supporting report shall be taken as,
or relieve the Contractor of any obligation to give, a Notice under the Contract.
If, at any time, the Engineer gives a Notice to the Contractor that the Programme fails (to the
extent stated) to comply with the Contract or ceases to reflect actual progress or is
otherwise inconsistent with the Contractor’s obligations, the Contractor shall within 14
days after receiving this Notice submit a revised programme to the Engineer in accordance
with this Sub-Clause.