You are on page 1of 3

Construction details for

earth-sheltering
Drawings show walls, roof structures
and parapets with insulation,
waterproofing and drainage systems

PARAPET-ROOF CONNECTION
As the parapet-roof connection is
often a source of problems, two dif-
ferent details for the drain tile are
presented here, one in the box in-
sert. Both drain details are accept-
able, but a contractor may find one
method easier or less expensive than
the other. In both methods, EPDM
(ethylene propylene diene
monomer) flashing is placed over 90-degree bends. The drain tile is al- truded polystyrene insulation to
the parapet and on the roof to pro- so placed so it will not freeze up and reach the drain but rather will drain
vide extra protection from water at so heat will not be lost to the out- through the sand layer to another
the parapet-roof connection and to side. Note, too, that the polyethyl- drain at the roof edge. This drainage
establish a good base for the drain ene sheet which is laid over the in- layer of sand (shown in both details)
tile. sulation is dropped under the tile. also helps prevent plant roots from
In the drain detail shown in the In the alternate detail, the one penetrating and disrupting insula-
overall drawing, an optional con- shown in the box insert, the drain tion and waterproofing. A topsoil
crete cant is recommended to alle- tile acts only as a backup drain. with a clay content is recommended
viate the high stresses which are in- Most of the water will not penetrate because it does not allow as much
duced in sheet membranes by sharp through the polyethylene and ex- water to penetrate to the roof deck.
ROOF-WALL CONNECTION
Shown here is the connection of
a cast-in-place roof and a cast-in-
place wall plus an alternative drain
detail to that shown on the cover.
Polyethylene is placed under the
drain tile to direct and contain the
water. A space is left between the
two polyethylene sheets coming off
the roof to allow the roof insulation
to drain, if water does leak into it,
and folds are placed in the sheets
to allow for settlement of the back-
fill.

ROOF-WALL CONNECTION WITH


PILASTER
With the waterproofing, insulation
and backfill omitted, this detail shows
the connection of a hollow-core pre-
cast plank roof to a nonbearing, cast-
in-place wall. The roof load is sup-
ported instead by a steel beam and
pilasters that are cast-in-place on the
interior side of the wall. The beam is
welded to bearing plates embedded in
the top of the pilasters.
SPREAD FOOTING
Steel pipe columns are used many times in earth-shel-
tered design because they take up very little floor area. A 4-
inch-diameter, 8-foot-high, double extra strong, steel col-
umn can carry approximately 130,000 pounds and is narrow
enough to fit between 2x6 studs in a
wall. The steel column is usually
welded to a base plate, which is an-
chored to the footing by stud bolts. A
space is left under the base plate for
leveling. In order to prevent the floor
slab from cracking at the edge of the
spread footing, a 6-inch granular
base is placed over the top of the
footing and the slab is placed on that.

COVER DRAWING: SECTION and a 1⁄4- to 3⁄8-inch-wide isolation n o rt h e rn climate; in southern re-
VIEW OF BACKWALL joint filled with asphalt-impregnat- gions, 4 inches on the roof and 1
The construction detail on this ed felt should be constructed be- inch on the walls would be ade-
month’s cover shows the location of tween the floor and wall. quate.
reinforcing steel, waterproofing, in- To help prevent leaks, precast Drain tile should be placed at the
sulation and drain tile for a well-de- plank roofs should be overlaid with base of the footing, never on the
signed earth-sheltered wall in clay a concrete topping. Waterproofing footing. When soil moisture content
soil. The wall is cast-in-place con- is placed directly on this topping is high and natural drainage poor,
c re t e, and the roof consists of pre- and on the walls, followed by a layer tiles should be placed on each side
cast concrete planks, both typical in of polyethylene, a layer of extruded of the footing. To pick up most of
earth-sheltered construction. Wall polystyrene insulation and another the excess roof water, drain tile is
steel usually consists of either #4 re- layer of polyethylene. The insula- placed on the backfilled layer of
inforcing bars placed in a 12-inch tion is placed outside the water- clay. This clay “cap” is constructed
grid or #5 bars in a 24-inch grid. For proofing to both insulate the water- to prevent the granular backfill from
s t ru c t u ral reasons and electrical proofing from large temperature acting as a sink for the surrounding
c l e a ra n c e, it is usually placed 11⁄2 swings and protect it from damage terrain. Sands and gravels are best
inches from the inside face of the due to backfilling or soil settlement. for backfill, but compacted clay can
wall. The steel that extends from the Using polyethylene over the insula- be used if the structure is designed
wall into the footing or roof is tion helps keep the extruded poly- for the higher lateral pressures.
placed near the outside face of the styrene (itself a highly water-imper-
wall, and a waterstop is placed in meable material) dry and acts as a Acknowledgement
the connection on the exterior side slip surface if soil settlement does All construction details and recom-
of the steel. A 2-inch cover of con- occur. mendations are excerpted from
Clear polyethylene, not white or Builders’ Manual and Design Guide for
crete over the steel is adequate. Earth-Sheltered Construction, a forth-
To minimize slab cracking due to black polyethylenes, and extruded coming book by Brent Anderson and
settlement, the floor slab should not polystyrene insulation should be Charles A. Lane to be published by
be placed directly on the footing, used underground. Po l y u re t h a n e Concrete Construction Publications,
but rather 4 to 8 inches above the foam insulation is not recommend- Inc.
footing. Then, if the slab settles, a ed for use underground, and ex-
crack line will not form in the slab panded bead polystyrene insulation
at the intersection of the slab and should only be used underground in
the edge of the footing. Welded wire very dry climates. The amount of ex- PUBLICATION #C820521
fabric should be placed in the slab truded polystyrene insulation Copyright © 1982, The Aberdeen Group
to help prevent shrinkage cracks, shown in this detail is typical for a All rights reserved

You might also like