T7 - End of Study Project

T-ESP-800

End Study Project


Project

1.2
End Study Project
binary name: T-ESP-800_$AcademicYear_$GroupName.zip
delivery method: Moodle

• The totality of your source files, except all useless files (binary, temp files, obj
files,...), must be included in your delivery.

• All the bonus files (including a potential specific Makefile) should be in a directory
named bonus.

INTRODUCTION
______ _____

In the previous unit, you defined your project and chose your partners. It’s now time to start working !

You will have two milestones by the end of august.

Through this agenda, you must work on your project following the specifications defined before.

We assume that you will not have enough time to finish ! It’s your responsibility to give to the next con-
tributors all the tools, documents and processes that will allow new arrivals to integrate the project.

REQUIREMENT
______ _____

• You MUST define processes and working method


• You MUST define quality assurance processes
• You MUST follow the specifications defined before
• You MUST list technical fields needed by the project
• You MUST write jobs descriptions

1
DELIVERY
______ _____

You are expected to deliver in this project the following files :

• Source code of project


• A document that lays out development method, norm ect . . .
• Quality Assurance Testing (QAT)
• User Acceptance Testing (UAT)
• Specifications document updated