Professional Documents
Culture Documents
Ii
llll
I
th Ed iti ( "1 )
ly ll
01 P® Exam Up
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileerHmamegroupinc.com 719-659-3658
Published by
This publication is a derivative work of A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) - Fifth Edition, which is copyrighted material of and owned by, Project
Management Institute, Inc. (PMI), Copyright 2013. This publication has been developed and
reproduced with the permission of PMI. Unauthorized reproduction of this material is strictly
prohibited. The derivative work is the copyrighted material of and owned by AME Group Inc.,
Copyright 2013.
PMP® Exam Simplified by AME Group Inc. All rights reserved. No part of this book may be
reproduced in any form whatsoever, by photography or xerography or by any other means,
without written permission from the author, except by a reviewer, who may quote brief
passages in critical articles or reviews.
"PMI" is a service and trademark of the Project Management Institute, Inc., which is registered
in the United States and other nations.
"PMBOK" is a trademark of the Project Management Institute, Inc., which is registered in the
United States and other nations.
"PMP" is a certification mark of the Project Management Institute, Inc., which is registered in
the United States and other nations.
"CAPM" is a certification mark of the Project Management Institute, Inc., which is registered
in the United States and other nations.
2 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileenr(/)amegroupinc.com 719-659-3658
I _________________________ , wi 11 u ire my PM ®
With e nd ry s m I q
m st th questi
ri ht nswer 1s corre w n
re 1n
________________________ (signature)
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 3
aileenr(/Jarnegroupinc.com 719-659-3658
E E
In the past 1 8 years, I have helped over 10,000 project managers obtain
their PMP® Credential through my workshops. Prior to taking my workshop,
these managers have often been studying on their own using a wide variety
of materials.
You'll find the approach I use in this program is very different. For
instance, let's address the items I listed above one at a time:
<II Passing the exam is not about memorizing the PMBOK® Guide. For
the most part, you need to understand the material and not simply
memorize the words. The only exception are lists of equations,
which we do need to memorize. Also a lot of material on the PMP
Exam is not found in the PMBOK® Guide.
<II If you review the material by knowledge area it won't make sense. In
saying that, I am not saying that the PMBOK® Guide does not make
sense. However, the PMBOK® Guide is a reference book and not a
study guide. Since project managers manage projects by process
group, project managers pass the exam by understanding process
groups. Therefore, my approach presents the material according to
process group and not knowledge area.
<II To pass a multiple-choice exam, you need to understand the content
and also know how to select the correct answers presented in a
multiple choice format. To be able to do this, you must practice on
sample questions, and not just a few questions. Instead, we need to
practice on, at a minimum, hundreds, and in some cases, over 1 ,000
sample questions.
I hope that this book will help you so much that you walk out of the testing
center with your PMP® Credential in hand smiling and saying .....
"Wow.... that was not too bad ... now I am a PMP® ".
4 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aiken@arnegroupinc.com 719-659-3658
0 0 0
Aileen Ellis, PgMP PMP is The PMP Expert. Because of her
, ,
Ms. Ellis began teaching exam preparation courses in 1998. Her years of teaching have given
her an understanding of the lesson types and teaching methods that most effectively
promote learning. Her books, which employ these same methods, reflect her years of
experience in exam preparation as well as project management. With respect to project
management, her approach is based on understanding processes and interactions of
processes rather than mere memorization. Ms. Ellis leads workshops to help students study
0 0
for and pass the CAPM PMP and PgMP exams through content review and practice with
0
, ,
Ms. Ellis lives in Colorado Springs with her husband, Terry, and their two children, Nick and
Alex. When not teaching, coaching, or writing, Ms. Ellis spends her days hiking in the
Colorado mountains.
Disclaimer: The purpose of this book is to help guide your study efforts. AMIE
Group, Inc. guarantees that every attempt has been made to check th.e accuracy of
all information presented. Project management is both an art and a science. You
may at times encounter differing opinions on th.e information presented in this
and other review books. In th.e end, your experience, education, test~taking
ability, and dedication wm determine your probability of passing the PMP® exam.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 5
aileenrZvamef!roupine,vnn 719-659-3658
PMP® EXAM - OVERVIEW............................................................................................................ 8
CONNECTING WITH AILEEN ............................................................................................................... 12
STUDYING FOR THE EXAM ....................................................................................................... 13
EQUATIONS TO KNOW FOR THE EXAM ............................................................................... 14
AILEEN's GAME **(Extremely Important)** ..................................................................... 15
NAMES TO KNOW FOR THE EXAM ......................................................................................... 18
EXAM QUESTION STRATEGY ................................................................................................... 20
INTRODUCTION ............................................................................................................................ 25
ORGANIZATIONAL INFLUENCES AND PROJECT LIFE CYCLES ....................................... 34
PROJECT MANAGEMENT PROCESSES ................................................................................... 43
INITIATING PROCESSES ............................................................................................................. 52
Develop Project Charter ...................................................................................................................... 53
Identify Stakeholders ........................................................................................................................... 62
INITIATING- l{nowledge and SkiUs ................................................................................................ 68
PLANNING PROCESSES ............................................................................................................... 79
Develop Project Management Plan ................................................................................................. 80
Plan Scope Management ...................................................................................................................... 84
Collect Requirements ........................................................................................................................... 88
Define Scope ............................................................................................................................................. 98
Create WBS ............................................................................................................................................ 104·
Plan Schedule Management ............................................................................................................ 111
Define Activities .................................................................................................................................. 114
Sequence Activities ............................................................................................................................ 118
Estimate Activity Resources ........................................................................................................... 124
Estimate Activity Durations ............................................................................................................ 128
Develop Schedule ................................................................................................................................ 133
Plan Cost Management ...................................................................................................................... 146
Estimate Costs ...................................................................................................................................... 150
Determine Budget .............................................................................................................................. 155
Plan Quality Management ................................................................................................................ 159
Plan Human Resource Management ............................................................................................ 169
Plan Communications Management ............................................................................................ 177
Plan Risk Management ..................................................................................................................... 185
Identify Risks ........................................................................................................................................ 189
Perform Qualitative Risk Analysis ................................................................................................ 194
Perform Quantitative Risk Analysis ............................................................................................. 198
Plan Risk Responses .......................................................................................................................... 202
Plan Procurement Management .................................................................................................... 207
Plan Stakeholder Management ...................................................................................................... 218
PLANNING - Knowledge and Skills ................................................................................................ 222
EXECUTING PROCESSES ......................................................................................................... 235
Direct and Manage Project Work .................................................................................................. 236
Perform Quality Assurance ............................................................................................................. 240
Acquire Project Team ........................................................................................................................ 246
6 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen1mamegroupinc.com 719-659-3658
Develop Project Team ....................................................................................................................... 252
Manage Project Team ........................................................................................................................ 259
Manage Communication ................................................................................................................... 2 70
Conduct Procurements...................................................................................................................... 2 7 5
Manage Stakeholder Engagement ................................................................................................. 281
EXECUTING- Knowledge and SkiHs ............................................................................................... 285
MONITORING AND CONTROLLING PROCESSES .............................................................. 298
Monitor and Control Project Work ............................................................................................... 299
Perform Integrated Change Control ............................................................................................. 304·
Control Scope ........................................................................................................................................ 310
Control Schedule .................................................................................................................................. 316
Control Costs ......................................................................................................................................... 313
Earned Value Management .................................................................................................................. 320
Con.troll Quality ..................................................................................................................................... 332
Validate Scope ...................................................................................................................................... 339
Control Communication .................................................................................................................... 343
Control Risks ......................................................................................................................................... 347
Control Procurements ....................................................................................................................... 352
Control Stakeholder Engagement ................................................................................................. 357
MONITORING and CONTROLLING -Knowledge and Skills .................................................... 361
CLOSING PROCESSES ............................................................................................................... 372
Close Procurements ........................................................................................................................... 373
Close Project or Phase ....................................................................................................................... 3 73
CLOSING - Knowledge and Skills .................................................................................................... 332
Cross-Cutting Knowledge and Skills ...................................................... ,..,. ....................... 391
Quick Review- Sample Questions ................................................................................................. 396
FULL SAMPLE TEST .................................................................................................................. 412
REFERENCES ............................................................................................................................... 485
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 7
aileerni/JamegJQ1!Pinc.i;;om 719-659-3658
®
0
The PMP Exam is based on the PMBOK® Guide fifth edition as well as other current project
management references. However, reading the PMBOK® Guide does not guarantee you will
pass the exam. Passing the exam is not that simple; it requires a detailed understanding of
the PMBOK® Guide including how to use the information provided by the PMBOK® Guide to
answer multiple choice questions.
0
While the goal of the book is to help you pass the PMP Exam, most people who study it find
that they have also learned a lot about being a good project manager. First work on passing
the exam, and then go back through the book to help improve your project manager skills.
Qualifying for the PMP® Exam - To qualify to take the PMP® Exam, at a
minimum, you must have a secondary diploma (high school or the global equivalent), 35
hours of project management training/education and, in the last 8 years either:
«> Three (3) years of project management experience with a bachelor's degree
or
«> Five (5) years of project management experience without a bachelor's degree
8 © Janumy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc.com 719-659-3658
Time - You will have up to four hours to complete the PMP ®exam. You may take a break
at any time. However, realize that the clock keeps running, even when you are taking a
break.
A recommended strategy with respect to time is to make sure you complete at least 50
questions per hour.
Number of questions - There will be 200 questions total on your exam. However,
only 175 of these questions figure into your exam pass/fail calculation. The other 25
questions are considered pre-release questions. These pre-release questions are included in
the exam so that PMI ®can collect data on questions prior to their becoming official exam
questions. These pre-release questions will be placed randomly throughout the exam.
A recommended strategy with respect to pre-release questions is to assume that every
question on your exam counts toward your passing grade. Don't try to guess which
questions count and which are pre-release.
Question - Some of the questions on the exam will be short, just a sentence,
while others will consist of multiple sentences. There are no questions having such answers
as "all of the above" or "none of the above". Instead you will be directed to select the best
answer out of the selections given.
A recommended strategy for longer questions is to read the last sentence first, before
reading the entire question.
Passing the exam - To pass the exam you must get a certain number of answers of
scored questions (that is, the questions that are not pre-release ones and so don't count
toward your grade) correct. You receive credit for each scored question you get correct.
There are no subtractions for wrong answers.
- Make sure you answer every question on the exam. Use a strategy that
involves eliminating wrong answers to increase the probability of passing the exam on the
first try.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 9
aiken@amcvrnupinc.com 719-659-3658
T IN
The exam has 200 total questions, of which 175 count toward your pass/fail
score. The table below shows approximately the number of scored questions
you will see from each of the five process groups. You must pass the exam
in total. You do not need to pass the questions in every process group to
pass the exam.
PLANNING 42
EXECUTING 31% 54
MONITORING
AND 25% 44
CONTROLLING
CLOSING 7% 1
TOTAL 100% 1 75 (Scored)
lO ©January 2016 AME Group, lnc. author Aileen Ellis, PMP, PgMP
aileen1G),amegroupinc.com 719-659-3658
on
in Aileen'? Private FACEBOOK Group. -
PMP<il> E)(arn Prep Tribe With Aileen
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 11
aileernc1)amel!'roupinc.com 719-659-3658
;~if' J;i le.e$•~i~~*'f~frCb
~fmaf!o~.c:pm.:in R.ot~,;Pr:.inta ;i.··.·..·· > ......·. . • • / ,
tl]q~§;t.~sti.t19.;H.aqyary 1.gJ ?~1 ~.1;~p l~ter. . .. ..\ . . \ ;0 . . •·. .• · • · . •.
·.>
12 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@ame1,,rroupinc.com 719-659-3658
The next few pages are the most important pages in this book. Do not take the ideas
presented here for granted. These suggestions entail a tremendous amount of work on
your part, but following these suggestions can often make the difference between passing
and failing the exam.
Before beginning them, please procure a set of index cards.
list Of equations - Here you'll need a set of index cards. The equations you'll
need to know to pass the exam are listed below. For each equation, write the equation's
name of on the front of the card and the actual equation itself on the back as shown in the
example below. As part of your study time, practice these equations for five minutes every
day. After you know and understand these equations, practice data dumping the entire list
of equations on a blank sheet of paper.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 13
aileernZuamegrnupinc.com 719-659-3658
I
Present Value Pres Value= FV/(1 +W
FV-future value, i= interest rate, t= time
PERT PERT= (P+4ML+0)/6
P= pessimistic, Ml=Most likely,
0= optimistic
One Standard Deviation 1 Standard Deyiation=. l(P-0)/61
\/(:lfi~nc:e=,= (~p)
2
.. Variance ............ ·.................
c&~t\/ahance(cvf . CVd:EV:.AC
. EY7earn~clvalue AC-:;= actual tost
c()~xr>ef"fon1'laf16e 1r1ae~ (CPI) ··
' ,,, ' ' ' ',
cr1~EV/t\c .
sch~dul~Vad~n~~(SV). .SV~EV~PV
. . .· .. . . . .E\{~ §<:tfl'.l~.dvalue P.Y::: planneqyalu~
§~h!edUNe ~~rf6rrii~~c~'.i t"lci~~ (S~I) SPl~EV/P,V
Esti1Tiate •.. ·a{ Completion (EACF EAC=BA<::JCPI
assume we Will continue to spend BAG= budget at completion
at the same rate · CPI= <:;ost performance index
Estim(J.te to·
Compfete (ETC)- ETC= EAC-AC
assume we win continue spend EAC= estimate at completion
at the same Jc;l;~e .........·. . ....... . AC= (lctual cqst
at
Varfance ~oiQpletion (VAC) VAC=. BAC>EAC
TCPFusing. BAC TCPl±::.(BAC-EV)/(BAC-AC)
TCPl-using EAC lCPI= .(BAC-EV)/(EAC.'.AC)
Number of Communication # ofchannels= n(o- l)/2
Channels n::: nurnberofpebple.
Point ofTotal Assumption.{PTA) PTA= . tc;trget co$t+ . . ((ceiling price-target
price)/buyer's share ratio)
14 © Januaiy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen<(llamegroupinc.com 719-659-3658
AU n's SS g e - Follow the process game described below goal by
goal. Start with goal one. Once you have achieved this, move to goal two. Once this is easy,
then move to goal three. Goal four may take several weeks to achieve. Make this process
game the first ten minutes of your study time every day. After the process game, practice
your equations for five minutes each day also.
Take ten (1 O) index cards and write the name of each knowledge area on the front of
a card and its definition on the back. See the example for the Integration area shown
below. Also create cards for knowledge areas Scope, Time, Cost, Quality, HR,
Communications, Risk, Procurement, and Stakeholder. Again, if you choose not to
write the definition on the back of the card, make sure you are able recognize this
definition.
Practice taking cards and building the table in the PMBOK® Guide shown on page 61.
Practice writing out knowledge areas and process groups in the appropriate orders
on a blank piece of paper until this becomes easy.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 15
aileenraJamef2Toupinc.com 719-659-3658
Practice sorting cards to build the table on page 61 of the PMBOK® Guide. Then, on
a blank sheet of paper try to write out the entire table shown on page 61 of the
PMBOK® Guide. See my example below and notice my use of abbreviations.
M&CPW
CloseP/P
PICC
x vs
c:s
4 PCM x
c
DB
3 Q PQM PQA
4 PHRM APT X
HR DPT
MPT
MC om
PRM X
IR
PQIRA
PQnRA
PRR
PPM CdP CP CloseP
4 ISH PSHM MSHE CSHE
16 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aiteen@amegroupinc.com 719-659-3658
Fourth
techniques for each process
Take the 47 index cards whose fronts you wrote the process names on and write the
names of the tools and techniques associated with each process on the back of each
card as shown in the collect requirements example below. You can find these tools
and techniques on the second or third pages of chapters four through thirteen of the
PMBOK® Guide. The tools and techniques on the back of the requirements example
show below are from Figure 5-1 of the PMBOK® Guide.
This goal may feel overwhelming at first. I suggest building just one card at a time
as you go through each process.
Interviews
Focus groups
Facilitated workshops
Group creativity techniques
(brainstorming, etc.)
: Group decision making techniques
Collect Requirements (unanimity, etc.)
Questionnaires and surveys
' Observations
. Prototypes
: Benchmarking
. Context diagrams
; Doc.umentation analysis
Practice looking at the back of each card and being able to name the process for
those tools and techniques. When that becomes easy, practice explaining to others
how each tool and technique would be used during that process. Do not write down
inputs or outputs. Inputs and outputs are important, but putting too much
information on the cards may make them overwhelming.
gi · .· EXAM Tlf: Always have yourcargs With you. It i~ critical that yqu kn?w the name.s
of ~II 47 pr().c~sses .and.are abl~ tp sprt the pr9ce5ses by ~11()\11/lep~e·are~ a.nd process
group: Alsocritical.i.s being ~~le~d recognizewhaMool~ and t~chniques.gowith which
processes; Also be sure tl1Jat you know the examples the fMBOK<i!l.Guide.Jists·for each
tool and technique. · ·
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 17
aiken1(/)ame1zroupinc.<:om 719-659-3658
Famous for Emotional Intelligence.
Theory that states work expands so as to fill the time available for
its .completion,
Defined quality.as fitness for use,
Defined quality as conformance to requirnment5. Famous for ideas
s1.1.<.:h a~:. Quqlity/s free and zero defects qre achievable,
oev~Joped f otaFQua1fr¥ Management (fQM).·
Shew hart Created th~Plan~Do:Check~Act Cycle.
and
.. e.···•.rn.
D.·
'
ing
-·'·.-- --- .''····'·•· ... · ... : •.. ·-····--··· .... .... ·'··' '. -·'- ·- '
Ishikawa Another na,me. for cause and effect diagrams. The first seven tools
of quality a;re known as the Ishikawa tools.
Taguchi Defined the Taguchi loss function, whichstates that"loss'' in value
progressively increases as variation increases from the targeted
condition.
ltaHaneconomist for whom the Pareto chart is named.
Tuckman F~rnOUS fordefiningthe fi"~ stages ofteam development'.
Maslow. Defined the hierarchy of needs.
McGregor Defined Theory X, which states that management Vi.ews workers
negatively and Theory Y, which states that management Vi.ew of
workers positively: A critical aspect of TheoryXandTheory Y is that
theth~()[i~S, are self{µlfiJlirig. .... .. . ·.· ..................................... .
Ouchi Defrned Theory z, which states that employee loyalty can be
increased. byproViding ajob. for life, etc.
McClelland Defined the Acquired Needs Theory, whiFh, C0f1~i~ts of the need for
...... · ...... a,chiev~mem,.n~.e.d .. f()L.P{)VIJ~r,. a,n.d peecLfor.affilJa,ti()tJ~ .......................................... .
Herzberg . Meeting hygiene Factors is not enough to motivate people. 'Their
motivators. must.also be addressed.to.•motivate people.
Vroom · Defined expectancyTheory which states that for people to he
motivated, they need to believe they can be successful, that they will
be rewarded for their efforts, and that the reward is something they
value.
18 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen!a)amegroupinc.com 719-659-3658
I
This book is organized by process group, not by knowledge area. The reasons for this are:
., We, as project managers, manage projects by process group, not by knowledge area .
.,
On the exam, you will see questions describing situations and asking "what would
you do next". These questions will be more logical and thus easier to answer if you
study by process group and not by knowledge area.
Sample questions will be provided throughout the material. The reasons include:
., You will very quickly be able to assess if you are understanding the PM!® point of
view .
., Sample questions make the material more interesting. If the material is more
interesting, you will be more involved and thus learn more .
., To pass the exam, you not only need to understand (but not memorize) the material
but also be able to determine the best answer. Only by practicing on sample exam
questions will you be able to do this.
Sample Qµestion: .•.....• ;·<>• , •.·•.. ·.. ·.............· ...·.•........ · ..· .·. . ·.· . ··.·
1.. We. are planni:qgJo have aneµtside orgam~~t~?t1 .revi~vv. ()!-fr quality .processes and reodmrnend
irnpm:"~~ents. The tool ancltechriique w~wilfuseJ,$:> ·• ·· ·
3:~ .. quality in~pections · · ·
11...•· · qual1t:y·~udit$
c. producfinspectioqs
d. risk audits .·. . . .. .
Solution:.Jfopt;Jfully .you were. able toeli1UilJate. answ~r ·a smce·this•quc?$tion· is not abou{risk.
Hopefully, you were able to eliffi,ilJate answe~s:a a~d c si:q~~ the qpesti9n is ~bput processes fnd not
deliverables. Inspections are associated. with deliverables~ not processes. Answer b is. the correct
an:swer:
One full length exam can be found at the end of this book.
More sample exams can be found at my website at: www.aileenellis._i;;;pJn.,.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 19
uilet'rni:uamegroupinc.com 719-659-3658
l. Read the question and ask yourself: "What process group am I in?" and "What knowledge
area am I in?" Once you can identify the knowledge area and the process group, you may
then be able to identify the actual process (see page 61 of the PMBOK® Guide). Consider the
objective of the process as well as its inputs, tools and techniques, and outputs for a clue.
2. Look for qualifier words in the question. Frequently used qualifier words include: every,
always, never, all, etc.
There are both "bad words" and "good words" on the exam. For example:
Bad words Good words
Always Often
Punish Coach
Force Encourage
4. As you practice for the exam, read each question and write the question number on a
piece of paper. Identify and eliminate any wrong answers. It is better to "guess" between
two choices than between four choices. When in doubt, remember that words from the
PMBOK® Guide are more likely to be correct than non-PMBOK® Guide words. Use definitions,
common sense, etc. Let's take a look at an example:
.. ·;··;,:···;·· ...... ,, ...; ... ···;,·,:·::··;·7;;·:;,·;·----·-·······--··;······,.:.·:·;,,\""
I.···w~ii~~tJ.¢ right.,
a. thi& answer I kno
h;. ~fiis~~~eriam it6
~· tl1is ~n~W~!I,kno~
ct tfils ~nswer I am n:ot
~' . ",>'.'.i.'. ':'.;,::;,'.·_" ;: <> \:,>· . -
; ,";,•/' . '/
Now go back and look at ""b" and ''d" and see if there is away to eliminate o~e of these two ans:wers.
20 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileenripamegroupinc.com 719-659-3658
on lnpu hn ue d
The PMBOK® Guide uses terms such as inputs, tools and techniques, and outputs. The
outputs of one process are often the input of another process.
@
PMIS (be careful ..procedures templates
@
@
Expert judgment @ measurement additional
@
@
techniques @ analysis (any planning
@ skills and kind) inspections
@
@
estimating @
flowcharts ..
software
Many questions concerning inputs and outputs as well as tools and techniques will ask
questions such as "Which of the following is an input of ... ?" or, "Which of the following is a
tool and technique of...?" If you can identify whether each answer is an input (document) or
a tool and technique (things we do to documents to create other documents), you may be
able to easily eliminate one, two, or three of the wrong answers.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 21
aileen1aJarnegJ]l1.LPinc.corn 719-659-3658
Let's take some sample questions. Yes, you are going to do some questions and get them
right before even seeing the content of the PMBOK® Guide.
ofc6urse., we have not c:o:1te.red c:cmtml cests yet, but use the ideas above to help you
~fft~i.~~~i~9 $)ft!e.~~ ~~J(~fers iG.~toht~~.lc~s~s", Je. a~~.d~itrij~~l~.•i~· th·~••·.p()ntm1.·casts
~ ··. · · · ~al~~it~·~?r:t~ro1Un9, tltei~~~.~ t? t~te{~l~~:t.budgec
ds s~~f"L~~."~qr;:9~(~?~·l~'::>···· · . ,.,,;> , • · ·•.·.....
~.. ~oql~antl J~P~fliHues, <?"~R~~J; 91.1~sti9n/ Knovvitlg
·ts,loo({Jppananswef tbat isa.cfoctimerit;
i·.,~~·:~~''tl!~ga·ati;~&rtj~h~ . #ns;~:f •·••,)·.~.·"~"1c~n~)JJ·~ ~~e:·~1{t~~t;·~~!~>f~~hh!q.J~~.
u · ··· · ·....•.l!V?rl;l. '.~n~lysl·~· and. ~:)lll(;>rd,}fcive~ast.rn.~l·as,·M~~fj~, i;e{,2 ·we ~r;~
~·i:w~·.are /for~casti~9,0 "flier¢fore. th,ese . . ~Jl~)lller$• .~l"~ .. tppls ... and
areis always a tool an.tlt¢t:h;1'.1ig1;1e
'},',.,;.,''";,''.",',".;';,Jc•·;•;,,'•·:;<
••_;•
.. ·Jhereforet'~a ~ mtr${.be\.~her!9ht
,,\'), ··:<.''··" ,'_,J,<;>.
;c,,,">.·'··•O·,,;·· ···/'.','!' ;,"i;!;'
1
,;,,,,;;'•.
a~y proc;:~ss. Therefore, vve.a:redeft yvithr "a".cind "d"; Whic;h;pre, is· more likely to be
associat.ed with scol:')e? HopefuHyyo~ will select "a", Once we cover·the material, "a"
should be an easier answer to determine.
22 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@arnegroupinc.com 719-659-3658
.. You are the project manager for the project. You are not a program manager. You
are not a portfolio manager.
"' The project manager manages only one project at a time (not groups of projects)
"' The project will span several years
.. The team has hundreds if not thousands of members
"' The project will cost millions of US dollars or the equivalent
"' The project manager has access to historical documents from previous projects
"' The organization has documented processes that the project management team will
use to guide the current project
.. The customer is internal to your organization and there is most likely an internal
agreement (not a contract) in place between your internal customer and your project
team.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 23
ai leeni(Vamegroupinc.com 719-659-3658
If you are struggling with the content of the PMP® Exam and you believe
you want more help please consider:
24 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@arnegroupinc.com 719-659-3658
Introduction
The PMBOK® Guide provides ideas for managing a single project, not a group of interrelated
projects (called programs). Within the exam, the focus is on a single project, typically a large
project. A project could be something as simple as planning and hosting a party to the
complex design and construction of the Sydney Opera House. As you go through this
material think of a project that you are currently involved in. Take the material and try to
relate it to your own work, and the work of others involved in the project.
Life cycle - The phrase "life cycle" is often a source of confusion. In this book, we will
discuss several life cycles.
The five process groups of initiating, planning, The phases of your project .. Some project's will
executing, monitoring and controlling and have a life cycle of just one phase. . Larger
closing projects will have multiple phases in their project
life cycle.
All projects will go through the project Specific to your organization or your industry.
management lifecycle regardless of the
organization or the industry.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 25
aileernll)ame12roupi11c.corn 719-659-3658
Introduction
What is project?
Most organizations carry out two types of activities: operations, which sustain the
organization, and projects, which change or grow the organization.
Project management includes turning the needs of the project stakeholders into
requirements and then planning and managing a project so as to meet those
26 ©January 2016 AME Group, lnc. author Aileen Ellis, PMP, PgMP
aiteenr@,amegroupinc.com 719-659-3658
Introduction
Projects are affected by constraints. Constraints may compete against one another.
If one of the six primary constraints changes, others may (but don't necessarily have
to) also change. The six constraints are as follows:
.. Scope
.. Risk
.. Resources
.. Quality
.. Schedule
.. Budget
These six constraints are based on the original triple constraint - scope, time, and
cost. Think about your current project. What would happen if a stakeholder wa,nted
to add more scope? Would you need to increase the budget, extend the schedule,
etc.? A big part of project management is managing change requests as they occur.
Progressive elaboration - allows for improving and adding detail to the plan as more
information becomes available. Adding additional objectives, requirements, or scope
is not considered progressive elaboration. Progressive elaboration is adding detail
to what we already have, not adding new objectives.
Relationship with
management
Framework utilizing project, program, and portfolio management. Also
links to organizational enablers.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 27
ailee1HrDamcrmn1pinc.cum 719-659-3658
Introduction
Provides low control. This structure provides the support the project needs
includlng training, etc.
Requi~e~ ~~bject•·
management
Temporary Permanent, process related work
Often, resources (including people) are transferred from operations to a project at
the beginning of the project or from the project to operations at the end of a project.
General
Personal
Management
Performance Knowledge
Area specific skills relate to the functional area of the project. For example, a project
manager managing a construction project should possess construction skills.
General management proficiencies include accounting, marketing, and finance.
28 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen<Qlamegroupinc.com 719-659-3658
Introduction
pie e s
1. You managing tile development ofa new piece ofexercise eql.lipm.ent that wm
require a person to exerdse foronly minutes a daytoachiev~ the . . benefits
tl'lat another piece pf equipl11el'lt requires (iO min~tes per day to achieve.
discussion of terminating the project,. Projects often terminate because:
a. their ()bJectiyes have b~enmet
b. adqitional stakeryolders fiave been add~d. to th.e stakeholder register
c new c4st9m~r!) ljaxe erteredthe triarket ... •·. . . ·.. > ·•. . .•..
d. the project's. requirements. are not a,ctlievable with .currenttethnology or:funding
2. Af~~r aio,r.g d~Y of work, you ar~.sociali2fog.~hfrother p~oject lft<1na9erS i.n £our
organ!·~ation. ··It seems that.most of the other project l'l1C1na,~ers ar~. mana.~ing ~ne
large projectv,vh~reas YQU are 111a,,n~ging a grOl!P of rel~t~d:PJ()jects~ ~l\ereforeyour
go.CJJ is. t9 achi~;v~ certcain. benefits ..that) could !"lot be achieved if the proj~cts.were
man'"~~ $~para,t~I~, ",fh~refore; yoµ:. . . . . . . .· ·. . . . . · . · ·
a.' sh<?!JXd;b~paidmoresinc~you.h;;tV~ rnorE! respops,tlJ.ility
b: are~pq.r~folio managE!r si~ce you arE!n1anagin9 Cl: gro.upofr~.ICJ.t~d. projects
c. shoutd.hepromdted tose,n~i.or.rnanagement since you have sornuchrespppsibillty
d. are apttmram managersince ypu are managing a grq:µp ofrelated projects
'.r ,\·"·,,,/,:<,;, ,_,::> .. · ~:: :"
3. The $iX ~Qnjp$ting constraint~ .·. . .. . .iru:lude?
a; budget, quality, .~ccrne, res?urces, •. risk, and cost.
b; quality, 5:cope, bu~g~t. schedule, resourcE!~, and. time
c bu~~et; s<:heclule;s5ope, quality, n::s,ourc~~· an.d risk
d. nµdget 1 scope, cost;
..
. quality, resoµrces, and risk
, ·,,;; ,,,·.
© January 2016 AME Group, Inc. author Aileen EIJis, PMP, PgMP 29
aileen@amcgroupinc.com 719-659-3658
Introduction
$. All of the following are types PMOs (projed management offices) except:
a~ analytical
b. supq;o.rtive
c... 7qntr~Uing
'' d. ,,directive
,,'",,,, .· ,'
!···9. :vo.u,r:~()ft~e·.dist~tpu~i()n:~t;pj·~~t.~~s~:.hug~···~ti~(:es~
•.. the .senior•.·staf;ff<?cqsed ·.or\
: th,tan~i~le)~lemel}ts9f.b4sine~~v<d4e.<Foryou,.·which•of•thefollowin~rintangible
i.. elemenM ()f ·business,val u.e:}Va$ .01oslhnport~nt?
: a. mon~tatVt;l.~S,ets ·
: 6: ~t9s~ndrd . · liitv · ,·,).;!{:(;. . . . . . . . ·.
. J. . .·~ran(;J.reco
•'•!{~~Z~~<;~rci~e~;c;i~b{1}ti~j~~;<cf<l~~$~~!ij:·
' q. . tl·tHity .
· · ·· ·
f; Nl~fi)t!~vNTotlef ((Jf'fyl 3•~:
:~;i~~~~~e;~~~~,;::··f .
'I((!;, 1\ti:q/Jqg¢fJ<l~~t.
>,':,,'':,',/;,'.
14; One .of your fellow proJ~ct maoage,rs comes. to y~u for ~cl.Y\£E!. ln~tead. of
managing one big project, ~e feels· he is mana,.gin~ the ~~m.e sm~ll: l)toject .oye.r. and
over, fa.gain,> sometimes overl()O. ~imes a \Neek.· ·· N<> plan~i11g if require~· aod he
strugglestofollo.\V the Pfojec:ttt1ariagementmethodologies ~~t µp. ~Y: thePMO. ·Most
likelyilie is strug~Ung beca~5:~: . ··.. . ·. > >• {. : < ·•
a, . he does not 11ave th~>~xperience..to. be managit'lg s()•.~al"IY ~rpJ~cts
b. prol:ect managers shouldo~lyman~~e oneprqjeq.~t.Cl.t.iwe
·
he is .really involved not pr?jects .•• > · ...•.•. ·
in op? rations,
the.PMO hasr1ot. developed a good metho~9.logyto supP;qrt.d.iff(2rent projects
30 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amebrroupinc.com 719-659-3658
Introduction
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 31
ailetrnmamcgroupinc.com 719-659-3658
Introduction
INTRODUCTI N ~ lutions
1. d. PMBOK® Guide: Section 1.2
Y d. We terminate projects when the objectives cannot be met.
N a. Projects successfully close when their objectives have been met.
N b. Additional stakeholders may not be a reason to terminate a project.
N c. Additional customers would not cause us to terminate.
32 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@arnegroupinc.com 719-659-3658
Introduction
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 33
aikenr(Dameuxoupinc.com 719-659-3658
LINFL N
IFE LES
The culture of your organization influences your project and the likelihood of success
of your project. The organizational structure influences the culture and the culture
influences the structure. Know the differences between these different structures.
resources
Project Expeditor-
this person
functions as a
communications
link.
34 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileenrmame1,,!J·oupinc.com 719-659-3658
Organizational Influences and Project Life Cycle
Operational Management Responsible for an area of the core business. Deals directly with the
organization's salable products or services
Sellers External companies providing components or services
Business partners External companies that fill a specified role such as installation,
customization, training, or support
~ EXAM TIP: Questions may destribe situations in which you will need to able to
differentiate one stakeholder from another.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 35
aileern(umnegroupinc.com 719-659-3658
Organizational Influences and Project Life Cycle
Project governance is the framework in which the project operates. It includes the
structure, processes, and decision-making models for running a successful project. The
project management plan should describe the project's governance.
Project success should be measured against the most up-to-date baselines that
include all project constraints.
Project Team -
The project team includes:
• The project manager - Always considered the leader of the team regardless
of how much authority the project manager actually exerts.
• The project management staff - A core team that helps the project manager
manage the work of the project
• Other team members - The people who do the work of the project
There are several types of team compositions. Two to know for the exam:
• Dedicated - Most and perhaps all of the team members work full-time on
the team. The lines of authority are clear. This is often a more expensive
structure since the project manager has all resources full-time even if he
does not need to use them all full-time.
o We often see dedicated team members used in a projectized
structure
o Dedicated team members could also be used in a matrix structure
although this would most likely be a strong matrix structure
• Part-time - Most team members, including the project manager, are part-
time on the project. They may spend the rest of their time supporting
operations and/or other projects.
o Part-time team members are most often used in a functional
structures.
o Part-time team members could be used in a matrix structure
although this would be most likely be in a weak matrix structure.
Project life Cycle - Project characteristics may vary over the life of the project.
See examples below.
36 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@ame1,,rroupinc.com 719-659-3658
Organizational Influences and Project Life Cycle
as as
possible.
Not identifying the right stakeholders early enough and not engaging them strongly
enough may result in:
" More changes than expected
" Changes that cost more than expected
" Achieving requirements but having the product/deliverables being rejected
tipS,: . ...·..
If yo~ see a qu~stion that .stCl;tesyot( are experrenci~g mgre chang~s th~~
expected{ lqokfor .an answerstating .thatyot! did not idel)tify st~keholders, ~it:'
··not Jqentifv st(ikeh.olders · early en9ugh,;. or clid not· iclentifY' tl1e . rig~t
stakeholders,
•'.... ...·.·.
·:
· ,.·.. · ·
lfyotvs:ee;a(:f~estl~r ~hat s.tates. your .changes ar~ ·co.sting 1tt?retban•e;<pected,• ·
I()()~ f<Jf<if'l (lf1SVl/7FS,ta~jng.ttiatyou did not identify sta1$ehqld~fSf.~id not
ide9tifys~Clk.e~old~fS eerly.~~OU9h10~did/not. id~ntify ~he rig ht StakehoJ~~.rs.
If yo~. see a CjUe!?tiorr t9at ~tates .vou have m.et the re9uireme,nts l)utyour
·.·. m°:(juict is.still bei9g /eJected, l0dk for an answer St~ting that y()u dig not
Jp~ntify stakeholders, did not identify stakeholders early enough,, or. di.cl nqt
identJfy the right stakeholders. .
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 37
ailecnr(/)amegroupinc.com 719-659-3658
Organizational Influences and Project Life Cycle
Types of Life Cycles - Most likely the predictive life cycle is the only life cycle
you will need for this exam.
Adaptive
'·····- ·-------.,.,.,.. ,., ... ,..,.,
38 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc.com 719-659-3658
Organizational Influences and Project Life Cycle
1. · You have j4st .been hired by a goyernmerit agie11cy. Although your title is
systems engineer, your pdmary role seems !<l be ensuring different f~nctional groups
as elec:trk(\I engirieeriog, mechanical> engineering, . .. .. . structuraJ engine.ering
c:~mmunicatil'}g w.ith one other. With respect to this organization's projects you are really
operating as th.e:
a. prbjeh 111(.lnager
b; eroJect coordinatbr
c. project expeditor ·
d;• functional manager
3:Y()~h~v~s~ent;years•.1r1ana9ingsmanan9
Ol1>}(qur suc«:;e.ss, Yo tr ar.e .ma11,ging yo1..1r f~rst
unendinriJ'Ustof,pr;aject ~take.holders.. The
diff:icl,flt ~~ 9],.k,.m:()9r~~~·;T~emost likely .
a .. nRt.~rio1.tghrn,9ney in the .bu(;lget
b. noten1Jugn.ti1rre)n .th~S'~hedule
c. n9t eno1.1gh focu,s on .• ,stake,h9l~el" identification .and.a,na.lysis
d. no quaJity assuranc~. deparnrient a.,s,siflned •to. the project
4 •. ·•Your proJ~«;:t is to de~ig~ ~nd f>tlncl th~'~.t<t<fhim:f~r a fo~<ll uniyersity~ The ~tadium wm
be IJSe(j byb()th the UJ1iVersiwand local sports teamSi It is i111portan~ that Jh~ project adopt
the, tone of a mod~rn city \llfh,lle. not l()sing the cha~f!l of an•established university.
Suggestions have .been ·mac:Je to ov~rlap many of th(:'! projeCtl)h~~~$ ~9 ~s to. save time and
have the sta~jµ .m ready for a critical so(:ter toumame nt•. Your:eaUze.. ~hat ov¢rlapping phases
often le(;ld.s to: . .. .. . . ....·. . · ·
a ... improved resource optit1'1ization
b. buffers to account for prqJect uncertainty
c. activity rework
d. decreased risk
© Janumy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 39
aileen@amegroupinc.com 719-659-3658
Organizational Influences and Project Life Cycle
6. For years your organization has believed that project management is. all about schedules
and bydgets. Based on many failed projects, stakeholder 1t1a~agement is now being viewed
as m!-l~h more import.~~t; . IVl~ragement wants YC>Lt to focus 011 positive stakeholders who
can ~·~ in the success of the project~. v9~ remind manag~ment that. a primary r~a,son you
mus~.a,sofotus· on ·ne~<,ltive ~~ake~qltle.rs· is:
a; s,t,a~ehold er class ificatiqn earl be very d iff:ic;u It' . ·.·.· · •· · · .·.• .· ...·.. . .· . ·
h. 9yerlooking 11~~ativecst~k~hqlders can c:tecrease~he proQability of project success
c. ~~akeholdeps. mµst be. id~ritified and ~heir r~qtl i.~ements deterrrti ned
· d. satiety at large may M a stakeholder on your project •
40 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc.com 719-659-3658
Organizational Influences and Project Life Cycle
FLU lut s
L (. PMBOK® Guide: Section 2.1.3
y c. The project expeditor's role on a project is to serve as a communications link.
N a. The project manager's role is to manage the project, not just serve as a
communications link.
N b. The project coordinator is similar to a project expeditor but has some authority.
N d. The functional manager directs the work of the individuals in his functional area.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 41
uikenr(/)amegruupinccom 719-659-3658
Organizational Influences and Project Life Cycle
N d. Society at large may be a stakeholder on our project yet this does not explain why
we need to put a focus on negative stakeholders.
42 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileenr(Darnegroupinc.com 719-659-3658
M M
This chapter is an overview of the five (5) process groups presented in the PMBOK®
Guide. These five (5) process groups contain 47 project management processes
which may be repeated in each of the phases of your project.
. . .
li'.I ExarnTip: Revi~wand understan<;l Fi~ure 3~1. (page50) ofthe PMBOK®.Gfji~e; Notice
how the monitoring and. controlling proc::ess group surrovnds the other process groups.
Visualize monitoring and controlling .as: continuous overthe life of the project.
" Initiating -
These processes help us to begin a
project or a phase of a project. There are two initiating processes. The first
initiating process, develop project charter, occurs outside the boundaries of
the project.
.. Planning process group - These processes are used in developing
a plan for the project, including developing the project baselines (i.e. scope,
time, and cost).
.. Executing process group - These processes create the project's
deliverables through the acquisition, development and management of
human resources. A majority of the project budget is spent during executing.
® Monitoring and controlling process group - These
processes track the project's progress as well as initiate and manage changes
to the project. These processes are occurring continuously throughout the
life of the project, even while the processes belonging to the other groups are
occurring. Notice in Figure 3-1 of the PMBOK® Guide how the monitoring and
controlling process group surrounds the other process groups.
"' - These processes are used to close out a
project or a phase of a project or a procurement.
43 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
ailcen1Zt!anH;proupinc.com 719-659-3658
Project Management Processes
This is the raw data that comes from the direct and manage project work
process. No other process produces work performance data.
Data. generated by the project are analyzed and compared to the project
baselines to create useful information. Decisions are based off on this
information and, not on the raw data itself. Only processes in the
fTJQnitoring and controlling process group transform work performance
data into work performance information.
The product created (physical or electronic) from the work performance
information. Be aware that different stakeholders will need different
reports.
44 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileerl(l/)amegroupinc.com 719-659-3658
Project Management Processes
Role of the knowledge areas - The 47 processes are not only grouped into the
five (5) process groups but they are also grouped into ten (l 0) knowledge areas. See page
61 from the PMBOK® Guide for the five process groups, the ten knowledge areas, and the 47
processes.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 45
aikcnr(Damegroupinc.com 719-659-3658
Project Management Processes
3t ~~~k l?;~~f~r~~n~~~[~~:=j~=~:
a: ~n.ippµttp·p~.C!J~C:t,~~.ec:u~i~g . .
b; a,g9utput;of P ·· e~ecutin~
~ ~J;i 1:n~~t~iptgsc··.··.·.. . t)J~ct,.~rpn.~~e·······
.. ct . aiy;output tif9ve~Cl;ll:proj~~t·cO:ntrol
·;•·•1l~<~i~J~~~s.~f~i<>tien. separated\ into
fhe~prQcz~~s:$,of
proj~ct~s
~~!c~)~;ci~essQ~c>up··. af~~~r~·«illr
level Qf control? ... .
*·p;, initiating
planning
·r• .·
c,<execl.f~in~ .•.•.
d~·.. monitoring ancl e(:)~f(olling
46 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileenr(Vamcgroupinc.com 719-659-3658
Project Management Processes
to~ The processes that specify and create the project's product are called:
a. project management processes
b. scopemanagementpro.cesses
c, ·product management processes
d. quality management pr()<:;:esse.S
lJ• 'The proc~sses of which pfocess group occur atthe same time ;is the processes
<>f~U the other process. groups?· · ·
a:. Jniti.ating
b. planni.ng
c. executing
d~ mc>r'IJtdring and controlling
1
.a. initiating
b, pl~nning
c. executing
d. closing
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 47
ailce11@arnegn1upinc.com 719-659-3658
Project Management Processes
48 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@ame1.,rrnupinc.com 719-659-3658
Project Management Processes
EM s
1. (. PMBOK® Guide: Chapter 3 - introduction
y c. The five project management process groups are initiating, planning, executing,
monitoring and controlling, and closing.
N a. Monitoring and controlling together are the fourth process group; they are not
two separate groups. Closing is not on this list.
N b. Integration, scope, time, cost, and quality are knowledge areas, not process
groups.
N d. Concept, execution, and closeout are often names for phases of a project life
cycle, not the five project management process groups.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 49
aileerl!ivamegroupinc.com 719-659-3658
Project Management Processes
50 © Januaiy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileerni7)amegroupinc.com 719-659-3658
Project Management Processes
process group. The output of the closing process group is the final product, service,
or result transition.
© Janumy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 51
ai leen@ame&,rroupinc.com 719-659-3658
INITIATIN
Initiating Process Group - Based on the PMBOK® Guide, two initiating processes
are performed to define a new project or a new phase of a project. Although the work
involved in developing the project charter occurs outside the project boundaries, it
constitutes a first, critical initiating process, and the project becomes official only when its
charter is approved. The second initiating process, identify stakeholders, consists of
identifying, analyzing, and prioritizing the project's stakeholders.
Based on the PMP" Examination Content Outline (PMI®, June 201 5) there are eight (8) tasks
of initiating, and these represent 13% of the exam's content. Certain key phrases are
associated with each task:
The PMBOK® Guide, the most often selected reference in studying for the PMP® Exam, does
not list the tasks comprising the Initiating process group but emphasizes processes instead.
0
Although not as robust as the PMBOK® Guide for in-depth study, the PMP Examination
Content Outline presents the tasks shown in the table above. Although memorizing these
tasks for the exam is not necessary, reviewing them from time to time is recommended
0
because they form the basis of the PMP Exam's questions on project initiating. As we cover
the two processes in the Initiating Process Group in the upcoming pages, you can see how
these tasks relate to the processes.
52 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aiieen1(l)amegroupinc.com 719-659-3658
Initiating Processes
r
ltf Exam Review Figure 4-3 of the PMBOK® Guide.
A project charter formally declares that the project has been approved. It names the
project manager and states the level of authority the project manager has on this
project. Typically, the project sponsor signs the charter.
0 EX;<\lvf 11P\ T~e prdject statement of work (PSO\lll), wbich is often c;onfuse<;I vvith\the
scope statern~nt, des<:ribes what the project is ilJtencled to accomplish. The scope
stateme1Jt; w~iGhthe pr9Ject manager. and . other team .rrte!mbers develqp, describes. the
work on.the project required to deliverwhatthe PSOW describes.
Expert Judgment - An expert can be anyone who has knowledge that can
aid in the successful completion of a project. Finding ways to add the expertise of
such an individual can increase the project's probability of success.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 53
aileen@amegroupinc.com 719-659-3658
Initiating Processes
Project Charter - This document, issued by the project sponsor, puts the
organization on notice that the project has official standing. Its existence is critical
to the success of the project. It should list the project's objectives, the key
deliverables and identify the project manager. Most of the other information
contained in the document are at a relatively high level of detail.
0 .. ~)(AM TIP: The. work heeded to develop the charter is completed outside of the
pro,Ject's boundaries. Although the project manager participates. in its development, the
sponsor usually signs the project.charter.
~·· · ~~Af\11' TIP~ A~$ ~.r~J~ft ~el~cn~n me~h99 ·. th,~t ..·eBCfs •. wtth••••the . . worcl
·~progra_m ming!! is a.corrstraii;red op.timizati()IT method~·· You ~t:~t:bto
J;)e able .only
tOJ~Cogniz~.su~h items>Cl:S Constraln~d·optimization rnethods;y9udo.n,qt need
~¢1 be.able to.e:r<pJain th.~rr-i, ·
internal Rate of Rernrn (IRR), an accounting method used to compare the relative
profitability of investments.
li'.J. EXAM TIP; For the exa111, >he aw~r,~,.~h,~1: ~tiJg;l"{~r IRR{s pr~fon~:blf to a lawer
one.
Payback period, an accounting method used to determine the breakeven point of a project.
1i'.J EXAM TIP: ·Fotthe ~xam,l:r1:1 aware th.<;lt ashorter. payback peti6d is preferable
to a longer one.
Economic value added (EVA) is the profit earned less its cost of financing capital.
Present value (PV), an accounting concept used to translate the value of one future cash
inflow or outflow into today's dollars.
Equation:
54 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@ame~,.roupinc.com 719-659-3658
Initiating Processes
Net Present Value (NPV). This term is similar to the one above except that it contains the
word "net". Whereas a present value looks at the value of one future cash flow translated
into today's dollars, net present value translates a stream of future cash flows into today's
dollars. With respect to a project, these flows consist of the project's benefits (future inflows)
and the project's investment (outflows at the beginning and possibly throughout the life of
the project).
lt'l· EXAM TIP: For the exam, be aware tha.ta higher net present va.lue is better
than a lower one. Net present value is c.alculated with the: equation showrrin the
<following exarriple: ·
N~VExamlJle; ....···· .....• .
Project A has an initial investme,rta.t the st(lrt qfthe projeqt~f$ loo ,099 .. Atthe
end of year one, the proJeq will yielg G\ ~enefitof $SQ;O.OO, .aqd at the e11dqfyear
two it will yie,l~anoth~r ber1efft of $50,000 .. The pr0Je5fwillyield, nq o~~er
·benefits; .Assurrring a disc0tp1t~are,{i11terest ra~e).oft0%,vvhat is the ne.tpr~.sent
val.ue of Projet~A? · · ·
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 55
aileern(!Jamegruupinu;om 719-659-3658
Initiating Processes
····~/ •the.pr:oj~(i:tfl'J.cil'l.~~~T
nt;
W.nQ•aYi~~ri~e,.~~·.project? ·
: 1:1; '.the ~r · ·· .· · · ·
: ~i tl;iep.r··.
:ct .ttie :tu
56 © Janumy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
ai!eenrZDamegroupinc.com 719-659-3658
Initiating Processes
12, . Wfien ~ projectls being perfprrned for: an external ;CU~tomer, the mbst
m~ely fonn of ag~eement is what? . ..
a. servi.ce level.agreement
b. rnel'noran,cfµm ofundersi«i,ndlng ·
c. tetter of intent ·
d. contract
T~~·.portf()fio·reyiew be>ard
me~ting. Which oft.he following ·projects is
choose? Proje(;tA V\fith IRrt·of L2%} Project
with an IRRof9%,ot Proje<,'.tD.With RRRofl
a. Proje<;tA
b. ProjettB
c.. Project C
d. Project D
' ·.·
The. 110:r~f9lio i:evie"V .tio'C:lrd is. ~onClu~ti.ng its yearly project> selec,tion
meeti~g. Whkh of the.foUoWin.g projects is .the· revi~w ·board m~st like!y to
c~Q9s~? PrQject f wit"t an NPV (n.et pres~i'l~ yaJt.te), of $23 5Mil, Project· c:;.with
an 'NPV of $282Mil, Project Hwithan .NPV of $82 lMil, or Project I with anNPV
of$183MU?
a. Prpject~
b. Project G
c. Project H
d, Project!
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 57
aileen@amegroupirn:.com 719-659-3658
Initiating Processes
. As~4Te an ~~ter~~~,t~te ..
: P.roj~~~ A.,lnidalt~v.; ..... /. Bene!itatef1~ ofYe~rJ (}f $40;QQO.
<·.
· AdcUti .lbenefit.~t~n~: ............ r,.2 r • ,do(). ;l\fo oth~rBehefi~s;f['~ ) .·• .· ·•·•
Pr .. · ·... • l.nitial<in¥~stn,i~n.~C>f 1$JOO.()OQ. Noben~fi~tl.~ ti,ee.~d;9f)'~a,r }~
. B~nefit 0($42,000 ~t~nd.ofYear.2.. At:l.didona,1. behefitof $7:0,000 ~tenq· of
;Ye(tr3'. > · · · · · · · · · ·· · · · · ·· ·
· a. ~reject~
b. ProjectB . < .·... •.·.. . .. . • . •.. .···. .... ..... .·•· •
c. Both· proJec~s since they ea,ch ha"e a positive net· present value.
d. Neither project sin~e they each h.ave a negative net present value ..
58 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileenrl/)amegroupinc.com 719-659-3658
Initiating Processes
p utions
1. c. PMBOK® Guide: Section 4.1.3.1
y c. The charter is the official document that signifies we have an approved project.
N a. The project statement of work is a narrative description of the output the customer
would like from the project.
N b. The contract is a legal document between an external customer and our
organization. We still need an internal document (i.e., the charter) to show that we
have an approved project. A contract many be split into many projects.
N d. The business case shows the return on investment for the project. It does not
signify that a project has been approved.
© Janumy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 59
:iiken1i:1Jarnegr_Qgpinc.corn 719-659-3658
Initiating Processes
N c. The charter is the official document signifying that we have an approved project.
It may include a summary budget but not the cost-benefit analysis.
60 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aiieewmarneizroupinc.com 719-659-3658
Initiating Processes
Project B:
The Present Value of $42,000 received at the end of Year 2:
PV= FV/(1 + r)'
PV = $42,000/(1 .05) 2
PV= $38.095.23
The Present Value of $70,000 received at the end of Year 3:
PV = FV/(1 + r)'
PV = $70,000/(1 .05) 3
PV = $60,468.61
Therefore, the NPV for Project B = -$1 00,000 + $38,095.23 + $60,468.61 = -$1 ,436.16
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 61
aile<en1Zvarnegroupinc.com 719-659-3658
Initiating Processes
ti I r
Some of you may be wondering why this process is presented next in this book. The reason
is that the book's organization is based on process groups and not knowledge areas. There
were several reasons for our adopting this organization, but the primary one was to make
the material in the study guide more realistic and more representative of real world projects
and of those presented on the exam. You may find reviewing page 61 of the PMBOI<® Guide
helpful at this point. Review the columns in the table to clearly see the processes of each
process group.
Identifying and analyzing project stakeholders early allows us to develop a plan that
focuses the appropriate amount of attention on each stakeholder(s). Not all
stakeholders are the same, and we want our primary focus to be on the most
important relationships that drive project success.
Project charter - This document lists the name(s) of the sponsor, the project
manager, and possibly other key stakeholders. It also would include the project
objectives, key deliverables and many other elements.
Several models can help us with this. For instance, the Salience Model, shown
below, is based on three factors:
0 Power - A stakeholder's level of authority
0 Urgency - The level to which the stakeholder requires immediate attention
0 Legitimacy - The appropriateness of the stakeholder's level of involvement
62 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen!cvame&,'Toupinc.com 719-659-3658
Initiating Processes
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 63
ai!een1GJamcgrnupinc.com 719-659-3658
Initiating Processes
f·i'}ft,n. .
·?fl'
.·~J·j•
b:,·
<L'
d~i
64 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc.com 719-659-3658
Initiating Processes
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 65
aileen@amegn11ipinc.com 719-659-3658
Initiating Processes
66 © January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc.com 719-659-3658
Initiating Processes
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 67
aileen1mame~pinc.com 719-659-3658
Initiating Processes
I I I iU
These ideas discussed below are based on information provided by the PMP® Exam Content
Outline (PMI®, June 201 5) and may or may not be directly referenced in the PMBOK® Guide.
68 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc.com 719-659-3658
Initiating Processes
l<eep in mind that, although the project manager participates in developing the
project charter, he or she does tiot own the development or have authority to
approve the project's charter.
The Practice Standard for Project Estimating (Project Management Institute, 2011)
describes a four-stage life cycle in project estimation:
1. Prepare to estimate - This step includes such actions as determining the
estimation approach, defining the team tasked with formulating estimates,
constraints to the estimation process, etc.
2. Create estimates - In this step, actual time and dollar estimates are
formulated, including those associated with the resources needed to
complete processes.
3. Manage estimates - This step occurs after work on the project has begun. It
involves modifying estimates as new information becomes available,
comparing actual to estimated costs and durations, and calibrating project
cost and duration forecasts.
4. Improve the estimating process - Lessons learned throughout the estimating
process during the project's lifecycle should be preserved for use in future
project estimates.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 69
aileenc(/)arneimiupinc.1:om 719-659-3658
Initiating Processes
a.
Q.
c. r:>o.w~r ............
d. ~~;Htl-rat::\f'f .
z:t
pr(»ifr•
.· . •••irst~ t~~:.~r~Jed~s···•p•~n ned """''""'"""'
be,ne~i(ti~ t:h~=· · ·
a:•jfien:
·1:>.': H~111
c..~efi fl~!/.·.··
c1.:Heh· ;tu:rar;i
'/:</;::~::::',:>:':<,,:>::<' ,'','~;'>,., :.::<J/'·~>:~_:"· <,, ~i);··.'··:;::,"~':!;::,·<<:r '/< ;·,
_:{:·. :::;.-~::.:;s!X:·;:.:< ;< . ~·~.:. <V>·. ;'.. ': )~~;;;<1:~;.'.~i:r .<:·.: .·. i~~f:.~.'.:>. :<:~.·.-~.~.>:,<·:. ::.::::< :::; _ .·. ::o:
Dur;in.~< p~9J~c~·1rnp1~t(onf a. ·~~f!J~(!t··~sses
availa~le i.RJfgnn~~ion, ind~di11g;·tes$011s
lessons·l~ct,m~(I a~~ often f:~u9ci ln· tbe:
a: org~ni?(lti<m(ll P~9fess a~~~~s ·
b. ent~~pris~/~nyironr;n~l'ltillf£t~tqrs
c. prpJe~t ch,~~te~ > > · ·
d .. stal<ehold~qeglster
70 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc.com 719-659-3658
Initiating Processes
7~ During the implementation phase. . ·.. . .projei:;t . you working <>il•. many
deliverables· have been produced on time and within budget. At. this. poi11t, the
project's deliverabl.esareto be.tested to determin.e if th.e customer will accept the
deliverables b.eing produced. We are most likely to determine this during which of
the. follo"Ying processes?
a'. collect requJr:ements
b. perform quality assurance
c. control quality
d. validates.cope
'\- ..' ,,, '
lJ.. ~lexandra has be~r a<s~f::ces5:ful prOJ~ct m;:magerJor over ten y~ars;. Wanting
her to>c()ntiriueto progress, Ale}{~~dra's. f!1el1~<r has recommended tf:lat .she develops
l:msinessac1.Jriie11 skills. ~11 e?:Canr~leofJ:>usines~.acumen is:
a. spend.inQtime wit1ibuslness,J~a:~ers·e1ts,09i(J.I ~vents
b. cutting;project.cos.ts,$?as.to pr()tect the .~.usi.f'les51.
c.. lear~ing {llore abou~the organiz~t,ion'$.fiQci,rypral goa,ls
d •.. using.''business tmzz words" whenintera<;tingwith .merribers.ofbusiness units
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 71
aiken@amqLrnupinc.corn 719-659-3658
Initiating Processes
13•. You are a project 1nanager in an organizati()°' that provides 360~degree feedback
fof all project. managers, m~ttniryrt that not only does your .manager review your
pe~for,r,nctru::~. but that YOIU te~rn an~anbers «:llSO provide feedback,On)f()Uf i.nteractic;>ns
with th.em.' .. Assume tha,': you~ t~am states that you do not consider their feelings,
e$l1ed<:tlly ~uring d~c:.isi~n~an~~ing~ .·. ~;:lse(J <Hl l)aniel Goleman's mJxe.d model for
f!j'110tion;:\lintelligeh~e1 y()Ui"1~eq,t()increase your..m(lstery of:
a, self;awareness ··
b. ?~lf:·r~gglat1C)t1
c.. $oc:lal skflls
·d. ~m;tf:~tbV··.··
" ',;,,, -'
72 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc.com 719-659-3658
Initiating Processes
2l. The project management information is· a tool and technique of \11/'hich
process( es)? ·
a; develop proJect charter and c:Jevelbp.project managefl1ent.plan
b. develop P,raject•manaQen'lentplatiand direct 3,nd. manage.project1N0rk
c. dir(3ct and rpanage prQJect wor.k and monitor and co~trol project work
d. monitor an(;I control projectwork.ani:l.dose !Jroject or phase
24.
a. plan scope manageme,nt
b .. va,lidat¢ scqpe
c.. define ·scope
d.. create the WBS
© Januaty 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 73
aileerH(Damegroupinc.com 719-659-3658
Initiating Processes
31••.. ···Ei~~P~~$.of.·pr~~;{;~~e~d~1~~reser)tations
i:l· actiVirx.J.i~li•·•~i~r c. ~.~r.t{··r·~~yv;ork~?~agrarn
b ..• VN~~1 aC~i~~ti~~f r~s~pr112~S(Q~penef~ncie·~·
c.. fftt)g~l;P~X~~met~~~Y·.~J:itic~l 9M<l.i.r met.tl9d <:i•< ........•.. >
d. ·. def! !!le c:i.gt:ivitJe~,·,$·e(Ml~tlcE:'l a;ctiyJ~iesj E:~timq.te,• a,ctivity;. resqurces
32: EXa ; ,,·~:i;~f:i~J~fjj~:~i,~·s~h~~ij·f~~r~~~led ~a~a,~r irtfg~~~tiC>rt; i n¢1ude:
a. activriy i~ti•baf ctrart~·n:tvvorl~ . . ~m. . . . .. . . .
· b. ·. WBS,.activ!~J.es.,re~~urces, dePeJL.i. .ties •.
c. critical path meth9¢1,· crrtic~l chain rn;etllo~
d, define activities; seqirence. activities, estimate. actiVity resources
33. T:~~ docurru~nt that defi~~s the sd1edulhlg method and stlieduling tool,. as well
sets the fcmnat for the sc;hedl.IJe,ds called: ·
a. tt}e activity list
b. the project ~chedule network diagram
c. the schedule bc;tseline .
d~ the sch~dule managementplan
74 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileenri1)amegroupinc.con1 719-659-3658
Initiating Processes
r IN N lu s
l. b. PMBOK® Guide Section 2. 7. F
Y b. As the project manager, you should identify the decision makers and influencers
in the organization and work with them to increase the probability of the project's
success.
3. b.
y b. The benefits register lists the project's planned benefits, including a status or
progress indicator for each benefit. Not all projects have a benefits register. The
benefits register is often maintained at the program level.
N a. The benefits realization plan describes the strategy adopted to realize the project's
benefits.
N c. The benefits transition plan describes the strategy adopted to transition ownership
of the benefits to another organization.
N d. The benefits sustainment plan describes the strategy adopted to maintain the
project's benefits over the long term.
5. c
y c. Delivery of a training class is an example of a deliverable and not a benefit.
6. a.
Y a. Under a pull system, an organization carries less inventory, which is based on
demand rather than on history.
8 d.
y d. Project success rates are one means by which to measure the benefits of
knowledge transfer.
N a, b and c. These are all technologies used to apply transferred knowledge and are
not methods for assessing the value of knowledge transfer benefits.
9. d.
y d. Number of issues identified by customers during a month is a lagging indicator,
which informs us of past performance.
N a. A qualitative indicator cannot be measured numerically and so is often descriptive
in nature or is simply an opinion.
N b. A financial indicator is measured in monetary terms.
N c. A leading indicator is forward looking and helps predict the future.
10. a.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 75
ai leern(Vamegroupinc.com 719-659-3658
Initiating Processes
1 5. b.
y b. One reason for project managers to employ facilitators in conducting meetings is
so that the project managers can be active participants in the meetings.
N a. The facilitator should be neutral and not support or weaken our positions.
N c. I would eliminate this answer because of the term "force". Nominal group
technique is not appropriate in every meeting.
N d. Mixing meeting types should not be done. This is a standard rule for meetings.
16. d.
y d. The goal of a peer review is for the project manager to learn from his peers and
thus be able to improve documents or projects.
N a., b. and c. All three of these answers are negative. On the exam, if asked about
the outcome of implementing a best practice, look for the positive answer.
76 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileenrl-U,amegroupinc.com 719-659-3658
Initiating Processes
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 77
aileern1/)arnegroupinc.corn 719-659-3658
Initiating Processes
78 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileernG;ame1,,rroupinc.com 719-659-3658
I
Planning Process Group Based on the PMBOK® Guide, there are 24 planning
processes. These processes are performed to define the total scope of the project and refine
the objectives. These processes develop the complete project management plan required to
meet the project objectives.
There are two primary outputs of the planning process group:
" The project management plan (includes the management plans and the baselines)
" The project documents (examples include the risk register, the issue log, etc.)
Based on the PMP® Examination Content Outline (PMI ®,June 2015) there are thirteen (13)
tasks of planning. These tasks represent 24% of your exam content. Key phrases associated
with each task are:
The PMBOK® Guide, the most often selected reference in studying for the PMP exam, does
0
not list the tasks comprising the planning process group but emphasizes processes instead.
0
Although not as robust as the PMBOK® Guide for in-depth study, the PMP Examination
Content Outline presents the tasks shown in the table above. Although memorizing these
tasks for the exam is not necessary, reviewing them from time to time is recommended
0
because they form the basis of the PMP exam's questions on project planning. As we cover
79 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileell!(f!amegroupinc.com 719-659-3658
Planning Processes
the 24 processes in the planning process group in the upcoming pages, you can see how
these tasks relate to the processes.
roJ tM t I
~ Exam Tip; Review Fig we. 4-5 of the PMQOK® Guide.:
Think of this process as integrating the other 23 planning processes. The project
plan should include the project baselines, the subsidiary plans, as well as other items
such as the project life cycle, the change management plan, and the configuration
management plan. The first time we go through this process we are planning how
to plan. As we go through the other planning processes we will pull outputs from
those other processes into our project plan. The further we get with the planning
processes the more robust our project plan will become.
Project charter - provides us the initial data to help us build the project plan.
OUTPUTS
80 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileerni:/)arnegroupinc.com 719-659-3658
Planning Processes
we are really creating the framework for the plan. As we move through other planning
processes the project management plan becomes more robust.
The three baselines integrated together are often called the peirfoirma.tt'lce
measuirement baseline.
Iii E)U\M Ttf': Make<sureyou have a basi(;understanding of What the elemeQts <ire of the
proJect·. planversus whatdoc~ments are. ~onsidered·.·projectdpcuments ... Please .review
Table.4- l ()fthe PMBQK® i;uide. Tre left column of this table li$ts the documents that are
usually c011sidered part of tf!e projeq plan~ The. right twocolumns are project d.oc.uments
not usually ~onside red part of the project plan. The rows of this table have no meaning.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 81
aileernGJarnegroupinc.com 719-659-3658
Planning Processes
~.As a·project mam,lger,you have learned that technology.c:an be both a positive and
a neg~tive on projects. Yo1,1 11.e~~ .arr automated !oolthat will help you to be
successful. Which ent~r:prise environmental factor might focus on as you are
deyeloping your project .plan? ·. •.
a. configuration. managementknoll'\fledge base
b. change. control procedurf:!s . . .•......••.
c ... guidelines and criteria for tailoring the org.aniz:ations set of standard processes
d, projectmanagementinformation system·WMIS~
a.
b.
c.
d.
5. Th~ •. tonfigu rati()n ma1wgerrn~n~ ~n~wf edge
a. enterpri.~e environmeQtal. faot.or
b. or~anlf'.ationaLprocess asset
c. go\l~rnmentsta~darcl. · ·
d. industry;standartf. ...... ..
82 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aiken@an1c1,,rroupinc.corn 719-659-3658
Plaiming Processes
p EME s
1. d. PMBOK® Guide: Section 4.2.1.3 and 4.2. l .4
y d. The PMIS is an enterprise environmental factor. It may be an automated tool such
as scheduling software.
N a., b., and c. These examples are all organizational process assets not enterprise
environmental factors.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 83
aileen1(1)arne~roupinc.corn 719-659-3658
Planning Processes
I n t
Tip~ Review Figure 5-3 .of.the PMBOK© .Guide;
In this process the scope management plan and the requirements management plan
are developed.
Project charter- this document provides high level information including the
project context to help start planning for scope.
li21 EXAM TIP; It is not the scope baseline or part of the scope
baseline.
It is a subset plan of the project management plan.
84 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@arnegroupinc.com 719-659-3658
Planning Processes
Ii'.! EXAM TIP: It is not the scope baseline or part .of the scope
baseline.
li'.l EXAM Tip: .This. process is one of only two processes that ha.s two plans as outputs.
li'.l EXAM TIP: Know the difference between project and prodi-1ct scope.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 85
aileen@amegroupinc.com 719-659-3658
Plam1ing Processes
86 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileewGJamegroupinc.corn 719-659-3658
Planning Processes
lutions
1. d. PMBOK® Guide: Figure 5-3
Y d. The scope management plan will be input to scope processes, not schedule
processes.
© Januaiy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 87
aikenri/!amegroupinc.curn 719-659-3658
Planning Processes
t
· lt'f ExamTip: Revieyv Figure S-5 of the PM BOK® Guide.
This is the process of turning the needs of the project stakeholders into
requirements. This process has 11 tools and techniques. As you study each tool and
technique make sure you know when you would want to use one versus another.
Scope management plan - this plan describes the process for knowing
which requirements to collect and not collect
88 © Januaty 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc.com 719-659-3658
Planning Processes
Talking with a group of stakeholders usually more technical than focus groups as you are now
working ondeveloping the requirements
Used when only a limited number of Used when lots of respondents and/or lots of information
respondents to be collected
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 89
aileenraJarnegroupinc.com 719-659-3658
Planning Processes
Context diagrams - show the relationship between the business system, and
the relationship of everything and everyone who interacts with the system.
E2IEXAM ,TIP: There are many tools and techniques in this process, Make sure you
understand why you would use one over another when collecting requirements.
90 © Janumy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aile<:n1a)ame~roupinc.corn 719-659-3658
Planning Processes
pie e ions
Fun<:t.i9na1>req~trements .• describe:
a. ithe behaviors .ofJ~e.prqduct
b. secuf'itY · · ·
c.. safeJy
d. level efservtce
A
techniq"'e~
a . · inte:rviews
b. fO,tlJSQfQUps .... i
c. facilitqted ~or!<shpp~
d.. penchmarking · ·
,. ,'.' .. :., ~- ' '/ ;.·<> '·". '."
6. tonfi9uratlo11 maQ:~g~metJtct~ti~IH~~
. initiatecfare found .jrf wh~t.~!~~~~ri(: . • ·•
a~ requirements.managernelilt.PIC!-1) . ·
b. ·. requirements trace a bi Iity. matrix
c: scope management plan.
d. req4lrements document~tioh
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 91
11fil'fllli,Ufil1J~Qill2~1Jlill 71 9-6 59-36 58
Planning Processes
1·2.JJuality F!.lt1c:tion
im;fystry: ..•. • ·
a.. ~8n.str~ction
b .. marketing
c. s1JftV11are
d. manµfacfuring . .
.1.3. Tran~itiorlt~tjuit~~~~te:i·····
a. data. con\(ersion ~ritl ~ralni.ng r~
~4.i~~~~~~f~~iii:~. ~~~~2;6'~2~;"t~.dij~,~~~~~S:itw9~
discussion on their .expectations ofa
a, intervleVl!s
p~oppsed product. Th,is n)eiijod is calfed:
92 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen!a)amem·oupinc.com 719-659-3658
Planning Processes
,i
17.. The project team is w9rking with stakeho.lders to identify product and project
requirements~ You ~re using a voting pr()cess to rankt.he mo.st useful i.deas. This
voting process is>c;alled:
a. brainstotlr:ting.
b. nominalgrouptechnique
c the Delphi techh\que
d. idea/mind.rhapping
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 93
aileeni(/)amerm>upinc.com 719-659-3658
Planning Processes
94 © Janumy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileenrZDameg;roupinc.c:om 719-659-3658
Planning Processes
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 95
aiken@amcgroupinc.com 719-659-3658
Planning Processes
96 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen!ulameb'l'Oupinc.corn 719-659-3658
Planning Processes
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 97
ai kcnr(i)arnef!;roupinc.com 719-659-3658
Planning Processes
fi
0 Exam Tip:: Review Figure 5~8 of the PMBOK® Guide.
Define scope is the process of creating the project scope statement. Another key
element of this process is that the final project requirements are selected from the
project requirements list generated during the previous process (collect
requirements).
Think of define scope and collect requirements (the last process we discussed) as
being very iterative. As we get into the details of defining scope, this may lead us
back to the requirements we have just collected.
EXAM TIP: Sinte we ctreJn>the scope ~ryowledge area it is .a QO()d ass.u ITI ptionJhat the
scope(nottime,notcost etc>:manageme9tplan will be an in,put.
Project charter - the charter may describe the product and the project at a
high level. We will use this now to create the details of the project scope statement.
and
- is a tool of many though not all planning processes. On
the project it makes sense to connect with experts who can make our work easier
and our output better.
98 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen<ZDamei;,rroupinc.corn 719-659-3658
Planning Processes
EX,£\M !IP! >j\t. thi~ point il'l)'()ur studying, .make SU(~ you can diff§renti(lte. b€ltWeen
th~·pr;oJectcharterand·theprojectscope statefi1E!nt.· (SeePMBOK®·Guide: Table 5··1. to
nelp), 1 If a question is 9-Skiqg ~~Ol(t sol'rlething high level (or summary level) most likely
they are asking. aqcout ti:\€\ project charter;
Comes from sponsor Comes from project manager and key members of team
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 99
aileern!vamegrnupinc.com 719-659-3658
Planning Processes
···•·.~:·~An.~~~fu·~1~
a~>. ~f<:t111stornr1J99 .· .· . . . > .• ..
>~,:;lat~ral thin~lng .••· .· .•. · · . .< !i • ·
.~; /. pair wis~ ·~P:rl'.1 pa.ri$ ons . < ·. · .
d, •. systerns. e.ngJneering
d ..• product.reqqirem.ents
8~
a.
b.
100 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
ai leen!c/l,amegroupinc.com 719-659-3658
Planning Processes
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 101
aileenr{/Jamegroupinc.com 719-659-3658
Planning Processes
NE SCOPE - Solutions
102 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen1Z1)arnegroupinc.com 719-659-3658
Planning Processes
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 103
ai leern(/)amer1rnupinc.com 719-659-3658
Planning Processes
Create WBS (work breakdown structure) is the process of taking the deliverables listed
in the scope statement and subdividing them into small deliverables. This is a critical
process of planning as much of the other work in planning is based off of the WBS.
Put a real focus on understanding the ideas surrounding the WBS.
Control account (cost account)- the level above the work package level
Scope management plan - this plan describes how the WBS (and other
scope documents) will be defined and managed.
Expert judgment- this tool may be referring to people who can provide the
details to breakdown deliverables into even smaller deliverables or the use of
templates to help us do this.
100% rule - the WBS should represent all the work for the project. If a deliverable is
not in the WBS, there is no plan to create it. This rule is not a tool and technique but
often associated with the tools and techniques for the create WBS process.
104 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc.com 719-659-3658
Planning Processes
-';?
Ii'.! EXAM. TIP: The most likely question on this relates to project management work.
Make sure that you list all your proje<:t management deUverables in theWBS.
Ii'.! EXAM TIP:The control account isnot~l\NC'lYs.the second level, it is always the level
above the work package level.. The work package level. is not always the. third level, it is
always the lowest level.
Project Level
I
I • E
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 105
ailet'rHZDameg:roupinc.com 719-659-3658
Planning Processes
106 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileenrlllamef,rroupinc.com 719-659-3658
Plam1ing Processes
e s
1. The WBS should
a. a list of activities
b. a hierarchy of activities
c. a list of deliverables
d. a hierarchy of deliverables.
2. Plan11ing .· t~e. riear term deliyerab.les it1 m()re ~et~H and the far term de.liver~bles
in· less detail/or waiting untill~ter to plan the far term c:feliye~C;lbles is called:
a. rQJHllg wave/planning · · · ·
b. l.OO%T1.ile .··
c. so h6ur rule
d. scopetreep
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 107
ailet'.n!l1)ame12roupinc.com 719-659-3658
Planning Processes
108 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileenr(/)amegroupinc.com 719-659-3658
Planning Processes
u s
1. d. PMBOK® Guide: Section 5.4
y d. The WBS is a hierarchy of deliverables.
N a. The WBS is not a list and does not include activities.
N b. The WBS is a hierarchy but not of activities.
N c. The WBS is not a list.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 109
aikcnrc/)arnegroupinc.com 719-659-3658
Planning Processes
y b. The WBS dictionary describes in detail the work packages in the WBS.
N a. The scope statement describes the project and the product scope.
N c. The control account level is the level in the WBS above the work package level. It
is sometimes called the cost account level.
N d. The requirement documents describe the requirements.
110 © Januaty 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@arnegroupinc.com 719-659-3658
Planning Processes
I t
Project management plan - the project plan most likely is not fully
developed yet. Elements of the project plan though may help develop the schedule
management plan.
Project charter- this document provides high level information including the
summary milestone schedule to help start planning for the schedule.
and
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 111
aileenr(/)ameg,roupinc.cmn 719-659-3658
Planning Processes
112 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aile<Cn@amegrnupinc.com 719-659-3658
Plam1ing Processes
u ns
i. d. PMBOK® Guide: Section 6.1.1.3
Y d. Software in general is an enterprise environmental factor.
N a., b., and c. Templates, change control procedures, and historical information are
organizational process assets, not enterprise environmental factors.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 113
ailternG)amc11rnupinc.com 719-659-3658
Plam1ing Processes
i it i
Review. Figure6-6·ofthe. PM BOK® Guide,
In this process we take the lowest level deliverables of the Work Breakdown Structure
and break them down into even smaller components called activities.
' '', '
..
·li?f EXAM TIP~ The s:cope baseline contains: Scope statemeht, WBS, and .VI/BS Dictionary.
Decomposition - we use this tool to break the work packages (in deliverable
format) into smaller more manageable items (activities -in action format).
Rolling wave planning -we plan the near term work in great detail and the
far term work in much less detail. This is a type of progressive elaboration.
Activity list - this is a list of all the activities we need for the project. Of course,
if we are doing rolling wave planning, we will only have the activities for the near
term work.
114 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aiteern(/)amei,,rroupinc.com 719-659-3658
Planning Processes
Milestone list - this is a list of milestones for the project. Milestones may be:
@ Mandatory- required by physical nature of work or by a contract (hard logic)
@ Discretionary- based on best practices but not mandatory (soft logic)
©January 2016 AME Group, lnc. author Aileen Ellis, PMP, PgMP 115
aileerni7Jamcvnn1pinc.com 719-659-3658
Planning Processes
2, ·Milestones:
cl: frav~,~~fo,dura,tf?n ..... :
b, ·. ar~;;~fW:avs man·~~t~r
c: hai ·nne~:$ta:r·
d •. ate; u.tto
~c~~~J~J:' 1
<. .... ••
t~e :~~~r~~c· r
3
tr·· .,.
1
the'. . . . .· .. ••· . • .. '! •
t=:'
d, the.<scope.,S'tat,F!m~nf ·
•
...
D.~t~plp()~f~toh
d~~ineac:tivit~es .... · .· . <'
b. C,t~ifi~~ activ{t~es and create \i\f;B5 ·
• c. ge.fi~e.a:ctiyi'ties and define:Scppe ..•
d. gefin~activitlesandcoHect·reqJ.irements
5.;IJ~~~d::~cm }t:Ci~r cess•oll~~~l~ .. proje~ts y()u n~w h~ve·6~en. ·~~de· t~~. prpject
ma /~al~ . ··•· ·..·.. · j:Jlex, multi~y~~r,a:n·aj~ct. ln~he past; you have planne~ outall
the < of
JI$ the.activiti~s e~rly in the p~()j~ct, Fot your current project you are more
likely~~·~o progre~~iye elabor~tipn thn:mgij;
a. rolH ~ye plfl..IJ[ling
li a~ges;> ·
c. <:mary
a.. ternplat'es
5,·. •xour;proj'~ct¥~~P1•·ls n¢.VV t~.ijr~j~C:ttfieina.ge~~nt.
ide.a of aWB~ ver~l.1$ a11··a~tivity li$t,·; YolJ e><PJ~in that:
a:·. the activitylistjsreaHyth~Jgwestlevel oft,heWBS
~· the WBS shows the setju~nce~of ;;tctivities
·c~ the activity list drives th.e cre,ati()rt~fthe WBS
d. the WBS is deliverable oriented whereas the activity list is action Oriented
116 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileernmamegroupinc.com 719-659-3658
Planning Processes
E s
1. a. PMBOK® Guide: Section 6.2
y a. Define activities is the process in which we take the work packages of the WBS and
break them down into smaller components called activities.
N b. The activities are smaller than the work packages. We decompose the work
packages into activities, not the activities into work packages.
N c. We do decompose the work packages into activities but not a hierarchy of
activities. The output is a list.
N d. The activities are smaller than the work packages. We decompose the work
packages into activities, not the activities into work packages.
After we define activities we may begin sequencing activities and/or estimating activity
resources. These two processes may occur in parallel.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 117
ai leen!a)amc1miupinc.com 719-659-3658
Planning Processes
i it i
Tip: Review Figure 6-8 of the PMBQK® Guide.
During sequence activities we want to create a network diagram that visualizes the
logical relationships between all the activities. All activities should have a
predecessor (only exception- the first activity has no predecessor) and a successor
(only exception- the last activity has no successor.)
.. Predecessor- an activity that comes before (precedes) another activity
.. Successor- an activity that comes after (succeeds) another activity
Activity list - these are the activities we need to sequence. At this point we
will be thinking about predecessors and successors.
Milestone list - these milestones may need to occur before or after specific
activities or at certain dates (monthly status reviews).
Finish to start (FS) - this is the most common relationship. If a relationship is not
specifically listed on a diagram assume it is finish to start.
Finish to finish (FF) - the finish of one activity is driving the finish of another.
Start to start (SS) - the start of one activity is driving the start of another.
Start to Finish (SF) - this is the least common of all the relationships- the start of one
activity is driving the finish of another.
118 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileenrZDame~Fl'nupinc.com 719-659-3658
Planning Processes
~ EXAM TIP: 13e careful on the exam with these ideas. Leads only advance the proje,tt
when the lead falls on the critical path: Lags only delay a project schedule wh.en. the lag
is On the critical path.
© January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 119
ai leenw)amegroupine,cum 719-659-3658
Planning Processes
120 © Januaty 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aiteen@amegroupinc.com 719-659-3658
Planning Processes
·• .
9. In the Precedence Diagramming meJhod which.relationship is
a. finish to start
b~ finish to finish
c. start to .start
d; startto finish
· 1o. You are working with your core team d<weloping the network diagram for your
map making project. Your.team member tells.you th<ltthey suggest you plan in your
schedule .that you will do a fly over of the area before •researching the geography,
You.ask them:\11/hy and they tell you it isa best practice. This is an example of a(n):
a. rnanciatory dep.endency
b. dist:re~ionary.dep~nciency
c. hard Iggie
d, external dependency
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 121
aiieenr2Damegroupinc.com 719-659-3658
Planning Processes
122 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aiieenra)amegroupinc.com 719-659-3658
Planning Processes
N c. External dependencies are normally outside the control of the project team. They
may use hard or soft logic. ,
N d. Internal dependencies are normally inside the control of the project team. They
may use hard or soft logic.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 123
aileernmamcgrnupinc.com 719-659-3658
Planning Processes
ti
.Exam Tip: Review Figure 6-1 3. of the. PMBOK® Gulde.
Activity attributes - details listed in the attributes may help with estimating
resources.
Risk register- again you may be wondering about this input. We may not have
a risk register the first time we estimate resources but eventually we will want to
include risk in all of our planning. Think of the risk register as a spreadsheet or a
database that includes all of our current risk information.
Activity cost estimates - one more time you may be wondering where this
input came from. It is an output of estimate costs. The cost of resources may be
something we want to think about as we consider different resource options.
124 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc.com 719-659-3658
Planning Processes
activities for which data exists and the actual cost or durations or resources of the
closest comparable activity is selected from the data and used as the estimate. This
only works if there is published estimated data available.
Ex.- when you take your automobile in for service the service organization often
obtains labor requirements for the required service from a book or database.
Bottom-up estimating- -after the resources are estimated for all the
activities these estimates are aggregated (added together) so as to develop an
estimate for the entire project.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 125
ailecnrZ/JameglQ!!lJinc.com 719-659-3658
Planning Processes
1. QuriJ19 estimate activity re,sQurc~s we should' estimate the type and quantities of
~ll of ~he follow!rtg reso~rces except:
. a.. Jnt\terial ·
l:>. rnon~v
.c. peqpl~
d. .etjttrpment
?tt. ?
·. . ··.~~~:is~~ ~~~.r~~ti·i~~h~iqJ~:(};·~~.ti~at~~c~ivlt~r~·s.o.urc~s:··
.·~aata•; yc.r <. . .. .··. ...... ... .· ·····. .. mm ••••
C;
d:
~·~t:ifui~i.n~~.~~~·~·~~e.titillz~ti()~;
a; b~ttom~Ll~~~~imatfrrg
b .. proj.~~t rncinaf)ement ~pftyvate
c: prec.(t!izl~llc~idi~~~amming>metnod
d, critrcaf pathmt=rhod · ·
126 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
ailccn1i:Vamegrnupinc.corn 719-659-3658
Planning Processes
MATE ns
1. b. PMBOK® Guide: Section 6.4
Y b. We estimate money during the process estimate costs.
N a., c., and d. Estimating resources includes estimating equipment, materials, labor
(people hours, not the actual people we will use - that comes later).
© Janumy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 127
aikenri'/)mnegroupinc.com 719-659-3658
Planning Processes
In this process we estimate the number of work periods (not the number of person
hours) required to complete each activity. Example- Activity A will take 80 person
hours to complete. We have one person available half time and therefore we will
estimate four weeks to complete the activity.
Activity list -we will estimate the duration needed for each activity.
Activity attributes -details listed in the attributes may help with estimating
durations.
Risk register - this is the spreadsheet or database that contains our list of
risks, etc. Based on the risks, we may add contingency to our duration estimates.
128 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
ailcen!cllarnegroupinc.corn 719-659-3658
Planning Processes
listed)
lii'.L EXAM TIP: Know the difference between analogous and parametric estimating.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 129
ailecn({/~amegroupinc.com 719-659-3658
Planning Processes
130 © Janumy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileenrG!ameb'Tnupinc.com 719-659-3658
Planning Processes
MATE pie s
The PERT (program• evt{luation and review ·technique) .uses <tlf .c>t the following
esti111at~s ~f(tept: · · ·· ·
a. '!1o~t:'l~ely
b. optJll)istic (tfr~st"case)
c:•· .Pe~~imi~ti5(wqrst~qse)
d. mean. (average}
Manag~ment
a. knowmunknowns
b. accept~d risks
c. extra work to m,ake tfue customer happy
d. unfor¢seen workthatis within the stopeofthe .proJect
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 131
aileenr(/Jamegroupinc.com 719-659-3658
Planning Processes
132 © Januaty 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amei:_>-roupinc.com 719-659-3658
Planning Processes
I
0 Exam Tip: Review Figure 6-1 7 of the PMBOK® Gulde.
In this process we enter the schedule data into the scheduling tool so a schedule
model may be created. Each activity in the schedule should have a planned start and
planned finish date.
0 EXAM TIP: Know the difference between the. processes sequence activities and
develop schedule:
The output is the network diagram. This The outputs include the schedule as well as eventually
diagram is a graphical representation of the schedule baseline. Both of these documents
the logical relationships. present linked activities with planned dates,
durations, milestones, and resources.
INPUTs schedule
Schedule management plan~ the schedule management plan describes
the process for developing the schedule. The plan will list the scheduling software
to be used, as well as what methods (CPM, critical chain, etc.) will be used in what
order. The plan may identify who owns the review for accuracy for each activity once
the initial schedule is developed.
Activity attributes - the attributes provide finer detail of the activities on the
list. This detail may help in developing the schedule.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 133
ailcen1(/)amegroupinc.cmn 719-659-3658
Planning Processes
134 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
ai!een@ameg[Qllpinc.com 719-659-3658
Planning Processes
Activity duration estimates may Contingency reserve (safety No contingency reserve (no safety
include: margins) margins)
When used: Before critical chain method After critical path method
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 135
aileern(/Jamegrnupinc.com 719-659-3658
Planning Processes
GOAL: Balance demand for resources with supply GOAL: Ensure demand for resources does not
exceed certain limits
Critical path may change- usually get longer Critical path not allowed to change
GOAL:> a$ses~ feasibiHt'/ of schedule, preparing GOAL: understand probability of hitting project
contingency plans objectives
METHOD: eva.luating sce11arios to predkt effect on METHOD: using three-point estimates to simulate
project objectives scheclule (note: to simulate the. schedule a network
diagram is also required). Ex. Monte Carlo
Only affects project end. date. iton the criti.cal path. Only affects project erid .date if on the critical path
Ex,- allowing testing to ~egin eyen thou!;Jh we have Ex. Waiting a time period after painting a wall
not completed wding before nanging art work on the waU (the lag is
required for the paint on the wall to dry)
METHOD: add more resources to the critical path METHOD:· overlap activities. or phases that we would
activities prefer to complete in sequence ·
EFFECT: increased cost to the project. The risk is EFFECT: increased risk for the project. In simple
also increased but not nearly as much as in Fast terms, no increased cost unless a negative risk event
Tracking. occurs because of overlap.
136 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc.com 719-659-3658
Planning Processes
the answer Fast Track,, If we have tnoney we should .crash since crashing raises our
risk.less than Fast Tracking, ·
Schedule tool- this is usually a software based tool that allows for scheduling.
Can be changed by the project manager (without Can only be changed through a formal change
formal change control) control process
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 137
aile.:rnc/JameWill!Jinc.com 719-659-3658
Planning Processes
Activity
A
B
c
D
E
f
G
138 © Januaiy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@arnegroupinc.com 719-659-3658
Planning Processes
s. The most common type ofsirtHJlation techniq4e used to.develop the schedule
a~ earned value method
b; Monte Carlo Analysis
.c, dedslon tree a11alysis
d. ·.expected• monetary value
!o. You.are fuanaging the developfn,e~t. . neV1f me~icaldevke. Hittirig the m•uket
window is.cri~ic;aH()rp(9ject success; To analyze t.l}e a111ount of float activity
has you will most likely. use what method?
a. bottom-up estimating
b. expertjudgment
c. critical. path method
d. resource leveling
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 139
aileenra)amegroupinc.com 719-659-3653
Planning Processes
Now that we have the logic we will want to do a forward pass to identify the early
start and early finish numbers for each activity. Try it on your own and then use the
notes below to check your work.
140 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen!ZV,amegroupinc.corn 719-659-3658
Planning Processes
8 13 14 21
StaIt Flnlsh
Since A is the first activity it begins on day l (early start). A is 2 days long. A's early finish=
A's early start of 1 plus A's duration of 2 days minus l = l +2- l = 2.
Bis the successor to A. The early start of Bis the early finish of A (2 days) plus l = 3.
B's early finish= B's early start of 3 plus B's duration of 5 minus 1= 3+5- l = 7.
C is the successor to B. The early start of C is the early finish of B (7 days) plus l = 8.
C's early finish= C's early start of 8 plus C's duration of 6 minus l = 8+6-1 = 1 3.
/
Dis also the successor of B. The early start of Dis the early finish of B (7 days) plus 1= 8.
D's early finish= D's early start of 8 plus D's duration of 3 minus 1= 8+3-1 = 10.
Eis the successor to C. The early start of Eis the early finish of C (1 3 days) plus l = 14.
E's early finish= E's early start of 14 plus E's duration of 8 minus 1= 14+8- l = 21.
G is the successor to both E and F. We look at both these predecessors to determine which
one has the largest early finish value. The early finish of Eis 21 and of Fis 20. Therefore,
E has the largest early finish value and that is the number we use. Therefore, the early start
of G will be the early finish of E (21 days) plus l = 22 days.
G's early finish= G's early start of 22 plus G's duration of 4 minus l = 22+4- l = 2 5.
The critical path duration is 25 days.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 141
uileernc/)amegroupinc.com 719-659-3658
Plam1ing Processes
2.To calculate the float of activities we do a backward pass through the network.
Start Finish
12 15 21
To do a backward pass we begin at the last activity which is G. We take the early finish of G
(25 days) and bring that number down into the box for the late finish of G (now also 25
days).
Late start of G= late finish of G (25 days) - duration of G (4 days) plus 1= 25 - 4+ 1= 22 days.
Late finish of C is trickier. C is the predecessor for both E and F. We ask which successor to
C (E or F) has the lower late start date. E has a late start of 14 days. F has a late start of 1 5
days. Therefore, E has the lower late start date.
Late finish of C= late start of E (14 days) minus 1= 14-1=1 3.
Late start of C= late finish of C (1 3 days) - duration of C (6 days) plus 1= 1 3 - 6 + 1= 8 days.
142 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amei,,rrnupinc.com 719-659-3658
Planning Processes
Late finish of B is trickier. Bis the predecessor for both C and D. We ask which immediate
successor to B (C or D) has the lower late start date. C has a late start of 8 days. D has a
late start of 12 days. Therefore, Chas the lower late start date.
Late finish of B= late start of C (8 days) minus l = 8-1 = 7.
Late start of B= late finish of B (7 days) - duration of B (5 days) plus l = 7 - 5 + 1= 3 days.
The late finish of A now should be easier. Late finish of A= late start of B (3 days) -1 = 2
days.
The late start of A =late finish of A (2 days) - duration of A (2 days)+ l = 2-2+ l = l.
The question is asking for the total float of C. Total Float of C= late finish of C (1 3 days)
minus early finish of C (l 3 days)= 13-1 3= 0. Since this answer is 0 this also tells us that C
is on the critical path.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 143
aileenr2/Jamevrnupinc.com 719-659-3658
Planning Processes
8 13 14 21
Start
1\;1•
11¥1
i![
II
!
5. a. PMBOK® Guide: Section 6.6.2.3
y a. The project buffer is placed at the end of the critical chain to protect the project
end date.
N b. and c. Feeding buffers are placed at the end of the feeding chain before it hits
the critical chain to protect the critical chain.
N d. The project buffer is placed at the end of the critical chain to protect the project
end date.
144 © .Tanuaiy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc.com 719-659-3658
Planning Processes
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 145
='-"-==="--====-"' 719-659-3658
Planning Processes
tM m t
· ~ ExatflTip: ReviewFigur¢ 7•3 ofthe.PMBOK® Guide-.
Project management plan - the project plan most likely is not fully
developed yet. Elements of the project plan though may help develop the cost
management plan. Examples include:
Scope baseline- scope statement (contains constraints and assumptions), the WBS,
and the WBS dictionary.
Schedule baseline- contains the approved start and finish dates for project activities.
Project charter- this document provides high level information including the
summary budget to help start planning for costs.
146 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc.com 719-659-3658
Planning Processes
Ex. Wages· the more people the more we spend in Ex. Rent for building- the rent does not
total on wages change based on the number of people
© January 2016 AME Group, Inc. author Aileen Ellis, PMP, Pg MP 147
aileern?Damcgr.r.uwinc.com 719-659-3658
Planning Processes
148 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen1ZDamegroupinc.com 719-659-3658
Planning Processes
EM ns
1. a. PMBOK® Guide: Section 7.1.3.1
Y a. The amount of rounding allowed with numbers is called the level of precision.
This should be defined in the cost management plan.
N b. The level of accuracy defines the acceptable range on numbers. Maybe we will
accept numbers that are+/- 50 % early in the project.
N c. Often we specify how much variance we will allow in actuals before escalation
needs to occur. As an example we may say that if the project's CPI gets below .90 or
above 1.1 the sponsor needs to be notified.
N d. Performance measurement rules relate to earned value. As an example the 0/1 00
rule states that an activity gets earned value credit only when the activity is 100%
complete. The 50/50 rule states that an activity gets 50% earned value credit when
it begins and 50% earned value credit when it completes.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 149
aileerna)ameg:roupinu:.om 719-659-3658
..
Planning Processes
ti t
Review Figure 7"5 of the PMBOK® Guide;
In this process we determine what we think it will cost to complete the project.
Usually, we estimate in some form of currency though terms like labor hours may be
used. Cost estimates should improve over the life of the project.
Human resource plan -we may not have created this plan yet but once we
do we will need to update our cost estimates. This plan will include information on
costs related to training, rewards, etc.
Project schedule - tells us when we plan our activities and the type and
amount of resources required for each activity. We may estimate costs at this level.
150 © Januaty 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileenra),amegrnupinc.corn 719-659-3658
Planning Processes
and TECHNIQUEs
Less costly
Quicker Slower
Bottom-up estimating - after the costs are estimated for all the activities
these estimates are aggregated (added) so as to develop an estimate for the entire
project.
The standard deviation is a measure of how The variance of a number is the square of the standard
spread out the numbers in a distribution deviation.
are.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 151
ailcenr(/Jamegroupinc.com 719-659-3658
Planning Processes
Cost of quality - often an organization will estimate the cost of the project
and then add on a factor to cover the cost of quality. Much more on this when we
get to plan quality.
decision-making -
more accurate estimates, and
greater commitment to the project, may be obtained by working as a team on
estimates. Examples of these techniques include:
Delphi technique- a technique in which we only work with experts in an anonymous
fashion to reach a consensus
Nominal group technique- a voting technique used after brainstorming to rank the
most important ideas
Brainstorming- a technique in which lots of ideas are generated often from lots of
people
It! EXAM TIP: No'tice h~wrmu1ybf the tod!.~;~nqt~chniqries of •e,stfmate c;osts ·are also
tools anct t,echrtiq ues of estimate a~tivitydur(ltions. euild a list of the tools and techniques
that these two processes have .in common. ·
152 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileern(/)amebrroupinc.com 719-659-3658
Planning Processes
ESTIMATE p s
1~ All of the following estimate except:
a; cos.t of quaHty
b. project management software
c. vendor bid analysis
d. benefit cost analysis
As you are plarming your pr,oject,y~urteam members are asking about amount
vc:trianc~
that will be allowed; They are really a,sking.youabout:
a. .precision. level ·
b. cot1tr~lithrtshold~
c. e~i.rned,value.r~les
d. report formats
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 153
aileen@ame12:roupinc.com 719-659-3658
Planning Processes
ESTIMATE utions
L d. PMBOK® Guide: Figure 7-4
y d. Benefit cost analysis may be used to create the business case before the project
begins and as a tool in the quality project management processes.
N a., b., and c. The cost of quality, project management software, and vendor bid
analysis are all tools and techniques of estimate costs.
154 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileenrl1larnegroupinc.com 719-659-3658
Planning Processes
r t
Tip~Review Figure 7-7 bf the PMBOK® Guide.
Cost aggregation- the cost of the individual activities (or work packages) are
aggregated (added up) to create the cost baseline.
Funding limit reconciliation- when we plan to spend money (see the cost
baseline) needs to be in line with when money will be available. If this does not
reconcile, the timing of activities may need to be adjusted.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 155
aik<W(1Jamegroupinc.corn 719-659-3658
Planning Processes
156 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc.com 719-659-3658
Planning Processes
INE BU ET'- e s
l. "fhe total value of the control atcmmts. is equal ~o:
a. value. ofworl< package cost estimates plusv§l,lue of contingency reserve
.· b. value of the cost baseline plus the value of the management reserve
c. valu.e .of the actiVity cost esti.mates plus the value of the activity contingency reserve
d. · valu:e of the work packagetost estimates plus Value of the adiVity contingency res.erve
2. Cos!aggregatiort~esults in:
a. cost. estimat~saUocated to eClch acJiVity
p'. .. qostestim~te~ aHocatE:d ~e·each work package
c. cost es'.Nmates .added tbgetherto ere.ate anestimate for the..ejltir¢ project
d. costestimates added togethe,r to create an es.ti mate for the i:>rodyqlife, cycle
>', ,,,",', , ',,
'
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 157
aileenrmamevroupirn.:.com 719-659-3658
Planning Processes
158 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
ailcen@amegroupinc.com 719-659-3658
Planning Processes
Ii t
Tip: Review Figure 8-4 of the PMBOK® Guide.
The outputs include the quality management plan and the process improvement plan.
la .. EXAM TIP: The first two tools ancLtechniques h(;lve .the word cost in their name.
Remember they belongin .Quality. There is a strong link.between cost. and quality
Cost-benefit analysis -some people will say that all money spent on quality
is money well spent. That is not the view we want to take. We should only spend
money on quality initiatives if the benefit is greater than the cost.
Cost of Quality - includes all money spent to ensure quality. The costs are
often broken down into two categories (cost of conformance and the cost of non-
conformance) and then sometimes even into two more subcategories under each
category (see PMBOK® Guide: Figure 8-5). In theory we want to invest more in the
cost of conformance (spend money proactively) and invest less in the cost of non-
conformance (spend less money reactively).
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 159
aikenr1/Jamef-..>Toupi11c.com 719-659-3658
Planning Processes
Prevention costs - incurred to prevent Internal failure costs -incurred to remedy defects
quality problems. Example: training discovered before the deliverable is shipped to the
customer_ Examples: waste, scrap, reword
Appraisal costs- associated with measuring External failure costs ..:incurred to remedy defects
and monitoring activities related to quality, discovered by customers. Examples: repairs, warranty
Example: quality audit claims, returns
160 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileerl((/)amegroupinc.com 719-659-3658
Planning Processes
These are vertical bar charts that;' also show a line. The bars often are listed in
descending order (the highest at the left) and the line (curve) shows the cumulative
total.
Pareto diagrams show what is most important (the highest bar) from multiple factors.
In control quality, the bars often represent:
.. the most common sources of defects
.. the highest occurring type of defect
.. the most frequent reasons for customer complaints
--
-·---~- 3 standard deviations of the mean
95%within
2 standard deviations
68%within
.,,,.__ 1 standard ---*
deviation
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 161
aileenra)anHcbrroupinc.com 719-659-3658
Planning Processes
162 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
ailcenr(/)amegroupinc.com 719-659-3658
Planning Processes
Other Ideas:
Degree to which a product meets requirements Category for products having the same use but
· different characteristics
Value of results forms a cluster - little scatter Value ofresults is close to true value
Not all precise measurements are accurate. Not all accurate measurements are precise.
INITIATING
PLANNING PLAN
EXECUTING DO
CLOSING
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 163
=-'-"~=""""""'-="===-'-' 719-659-3658
Planning Processes
Total Quality Management (TQM) - know the name Deming for TQM.
Everyone inside and outside the organization has responsibility to continuously improve the
quality of products and processes.
164 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileernal,ameg.,rroupinc.corn 719-659-3658
Planning Processes
le ns
1. Rework is an
a. preventiontost
b; appraisal cost
c. in.ternal failure cost
d. external.failure cost
·6. Testing ?rily parto.fa popul~tion thatisr~presentalive of the whole is known. as:
a. statisti~al samplfng
b. l'.)enchmarking
c. design ofexpedments
d. the costofquality
7. Trainfog is an example
a. prevention cost
b. appraJsa.I cost
c. internal failure cost
d. external failure cost
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 165
aileenr(/)arnegrnupinc.com 719-659-3658
Planning Processes
166 © Januaiy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegrnupinc.com 719-659-3658
Planning Processes
s
1. (. PMBOK® Guide: Figure 8-5
y c. Rework is an example of an internal failure cost.
N a. Training is an example of a prevention cost.
N b. Testing is an example of an appraisal cost.
N d. Customer returns is an example of an external failure cost.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP. PgMP 167
aikcn1(/)amegroupinc.com 719-659-3658
Planning Processes
168 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen(i7)amegrnupinc.corn 719-659-3658
Planning Processes
t
1i'.:1 Exam Tip: Review Figure 9-3
In this process we are planning for the team. This includes deciding what positions
we need, what tasks people will perform in each position, how positions will report
to each other, and when each position will join and leave the team.
Reality- we may not get the people we want in the positions we want. We need to
plan for this reality and also think about using resources outside of the organization
if skill sets cannot be found or are not available inside.
Project management plan - the project plan is not complete yet. Still
there are elements in the plan that may help us plan for human resdurces.
Hierarchical-type charts - there are several of these type charts that may
be used to help plan for human resources.
1i'.:1 TIP: Make sure you are very clear on the difference between the organizational
chart (Org chart) and the organizational breakdown structure,
© Janumy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 169
aileenrZvamegroupinc.cum 719-659-3658
Planning Processes
Matrix based charts - the most likely example of this will be a RAM
(responsibility assignment matrix). This matrix shows who (by person, position, or
group) is responsible for what activity (or work package). Only one person is allowed
to be accountable for each activity.
Text-oriented -
here we are talking about a positional description.
This is a document (may be electronic) that describes details of a particular position.
These descriptions help the project manager when he goes out to recruit people to
fill specific positions.
170 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen!lllamegroupinc.corn 719-659-3658
Planning Processes
Expert judgment - there are many details related to planning for human
resources. If we utilize experts, both on and off the team, then most likely it will lead
to a better human resource plan.
lif· EXAl\ll TIP: KrioW t~e differenc~ ~etween the human, resource plan and the staffing
ma11agement plan. Know the orgchart is part ofthe hum.an resource plan.
Other ideas:
The halo effect-
" applied to project management: assuming that if someone is good at
something .. they are good at everything.
" Ex. Assuming that because someone is a great engineer they will make a
great project manager.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 171
ai leenra)ameg;rnupinc.eom 719-659-3658
Planning Processes
Sample question.
From the ihfonnation be I.ow, which activity i.s fikely to cause the project manager the· most
frustration?
Re.sponsible Consult
-· . ,............... ·-· · ....:.:. _.:..:.: ·>· · ;· · · ;-~...; ··<·::·< <:- :.:. . . . . . . :.-: ·: :.: :,.-·.:::". .-.. :.<.;.:.. :· .- .
:.~.: :.:.~
1
a; Writ~ ·r~~;~ ireMents .·.dodij m~·~:~~~f~rl
b: .Dev~fop tracea,.bjlity matr.ix , . .. . . . c ·;.· ·
c; Developt~quige.r:nentsm~nagerf1ent plan
d . .Develop sqQpe•sta:ternent
- .
ex<:lusions •,,• '
-~. -·_:;. ,. - ;• -:·:-
The cC)t~~ctanS':'f~r.is ans,wE¥rJ~): W~en using a RAcrchart notn,divldoal activity should have more
· thanpne·pets~m·a(','c91J~:tal:lte, ·.
172 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileernZDamegroupinc.com 719-659-3658
Planning Processes
u ons
6. All .of the follo~ing .are document team member roles and
respo~sibilities ~xcep~:... ••• ·· ...••..•...
~: ens u.re each wqrkpack~ge h~s (111 C>\,o/l'ler ....·
b. ensure each: team rne~ber ~nders.t,a,1;1ds, t~eir role
c. .. ensure each team member ~nderstan~~.t.he rep.orting relationships
d. ensure each team member uriqerstantlsthe cornmunication plan
7. Th.e.resource.breakdown structu.re:
a. may contain multiple categories fnduding human resources
b. shows .the reporting relationships
c. shows .the pr0ject deliverables
d. defines the communjcatioll protocols
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 173
ai leenr(Dameg;roupinc..com 719-659-3658
Planning Processes
174 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileernZDame1..,rroupinc.com 719-659-3658
Planning Processes
HU s
1. a. PMBOK® Guide: Section 9.1.3.1
y a. The project organizational chart shows reporting relationships.
N b. The WBS shows the project deliverables.
N c. The communication plan would describe communication protocols.
N d. The organizational breakdown structure (OBS) shows which work packages fall
under which departments.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 175
aileeni(Damegroupinc.com 719-659-3658
Planning Processes
176 © Januaiy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
ailecn!{i)arnegroupinc.com 719-659-3658
Planning Processes
I I t
It! Exam Tip: Review Figure l 0~3 of the PMBOK® Guide.
In this process we develop our plan for ensuring stakeholders have the information
they need, when they need it, using a method that works for them, in a format that
works for them, based on what assets we have available. The project manager
shot11ld spend 90% of his time commt1111kating. Communicating involves more than
talking, it also involves listening.
Ii!:! EXAM TIP: This process and in fact this whole knowledge area is· focused on the
stakeholders, not jus.t the team,
management
Communications requirements analysis -we want to analyze what
the stakeholders truly need as far as communication. It is important to understand
what value different types of information, in different formats provide to the
stakeholders.
One specific question that may come up in this area relates to communication
channels.
Persdl'.l
Otre
Person Person
Three. Two
Let's assume there are three (3) stakeholders total on your project, including you.
You could get a question asking how many communication channels you have. To
solve:
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 177
aileernl/)amegruupinccom 719-659-3658
Planning Processes
liZi EXAM TIP:# of communication channels"" n(n~l)/2 where n is the number of people.
liZi ~XAM TIP: Be careful ifth£Ht~.~m question states tha~ you are interacting with 9 other
stakeholders: This means there are 1Opeopleand you needtosolve the problem for n"".
to people. · ·
Feedback
178 © January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen1(llamegroupinc.corn 719-659-3658
Planning Processes
- encodes the message, based on who they are, their experiences, etc.
- decodes the messa'ge based on who they are, their experiences, etc.
The tricky part is the receiver may not decode the same way the sender encodes.
Acknowledgement - the receiver should acknowledge that he received the
message.
The tricky part- acknowledgement does not mean understanding or agreement.
Medium - the message is sent through some medium (e-mail, face-to-face, etc.)
Noise - the message may experience noise (distance, etc.)
There should be a feedback loop. Remember in the feedback loop the original
receiver will encode the message and the original sender will decode the message.
Again, this provides a chance for miscommunication.
Used for large volumes of info and/or large Intranet sites, e-learning, knowledge
audiences. People may decide to access or repositories, etc.
not access information
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 179
ai lee1Hfiiamcg.rr1!!.pinc.com 719-659-3658
Planning Processes
Preferred- Posted on
face-to,face team site
Acceptable- (no e-mails)
phone
conference
l.Jll
!:ib
Ii>
tiZf.>·. EX,l\l\ill"IP:·Qn the ex~Q1 you.ITla)f be. given an.example such ..as reports. You will then
be asked if reports are fgrmal or informaJ,written or oral,
,ii)
When we communicate face-to-face with each other, much (more than 50%) of the
meaning is communicated through our non-verbals. In simple terms, we trust what
we see (non-verbals) and hear (para linguals such as pitch and tone), more than the
actual words spoken.
Ill! non-verbals
paralinguals
words
180 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileernmamegroupinc.com 719-659-3658
Planning Processes
MM N EM e s
3.
c.
d.
s. In the.communkatiorismodel, distance is an
a. encoding
b. the m~ssage
c. the medium
· d, noise
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 181
ai lee1va)amef!;roupinc.corn 719-659-3658
Planning Processes
182 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
ailcen@ame;,,TJ·oupinc.com 719-659-3658
Planning Processes
MU NS ENT~ ions
1. a. PMBOK® Guide: Section 10.1.1.2
Y a. The stakeholder register is an input to plan communication. It lists the
stakeholders. It gives us details to help us begin to plan communication with these
stakeholders.
N b. The team directory would be associated with processes in the human resource
area, not the communication area.
N c. The human resource plan would be associated with processes in the human
resource area, not the communication area.
N d. The communications plan is an output, not an input to plan communications.
liJ.. EXAM TIP~ The communication plan is associated with the stakeholders. The team is
a subset of the project stakeholders.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 183
aile<:n!lVarnegroupinc.curn 719-659-3658
Planning Processes
fi:I EXAMTIP: The pre>Ject r11ana1:gm1ent plan is an input of. all processes that begin .with
. the term .. ''plaJ1\ ~~ample$ indµcJe but are not limjted to: plan scope management, plan
>schedule management, e~c:~
184 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc.eorn 719-659-3658
Planning Processes
I t
ll2f Exam Tip; Review Figure 11 ~3 of the PM BOK® Gulde.
In this process we determine our strategy for the other risk management processes.
This may include our risk methodology, roles and responsibilities, etc.
Risk event that would lead to a positive Risk event that would lead to a negative
outcome outcome
Opportunities that occur are called benefits. Threats. that occur are called issues.
Risks that have been identified and analyzed, Risks that cannot be managed proactively.
making it possible to plan responses~
Contingency reserves may be set up for known risks Management reserves may be set up for
that cannot (or we. chose not to) be managed unknown risks.
proactively.
li'.l·.. EXAM.TIP: W(:'! want to spendtime managing risks before they occur instead of dealing
with issues after the fact.
Often we purchase Insurance for pure risks. Threats that occur are called issues.
INPUTS
~
many areas of this plan may be reviewed to
help plan for risk management. Most importantly we will review the information on
the triple constraint of scope, time, and cost.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 185
aileen@amegIQ!ll)inc.com 719-659-3658
Planning Processes
Project charter - the charter includes much information about the project.
We will review the project objectives to think about how certain risks will effect these
objectives. Also, we will look at the high level risks defined in the objectives as a
starting point when we begin to identify risks.
Risk management plan - this is our strategy for all the risk management
activities on the project. It may include:
"' Risk management methodology - the principles and rules we will use to drive
action in the area of risk.
"' Roles and responsibilities - we want to answer the question: who owns risk
on this project? Will we have a risk manager? Will we have a risk management
team? Will risk management ownership be spread across all the team
members?
@ Risk categories - many organizations visualize their risk categories using a
risk breakdown structure (see Figure in the PMBOK® Guide).
"' Definitions - it is important to define our terms we will use in risk
management analysis. See PMBOK® Guide: Table 11-1.
186 © Januaiy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
ailecn@amegroupinc.com 719-659-3658
Planning Processes
EM s
2.~ The risk breakdown structure (~BS) is a hierarthkal breakdown of risk by:
a~~ .
b.> prol?ability
c. timing
d. category
meetings
arialytk:al techniques
c. sta)Seholder re,gister
d. prqject cl)atter
© Januaiy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 187
ailecrnaJamegrnupinc.com 719-659-3658
Planning Processes
Ii?! EXAM TIP: The project management planJs an input of all.processes.that begin with
the. term "plan". Examples i.ndude butare not limited to: plan scope manager:nent, plan
schedule management, etc.
Ii?! EXAM TIP:Remember there are no risks listed in the risk management plan. The risk
register is not an .element of the risk management plan. The plan describes how to create
the risk register, etc.
188 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc,com 719-659-3658
Plmming Processes
ti I
In the process identify risk we identify potential opportunities or threats that may
affect the project objectives. Often, a large group of people may be involved in this
process. Risk identification is so important that we may even include risk experts
from outside of the team or even the project stakeholders.
Risk management plan - this was the output of the last process. It
includes our risk methodology, etc. It should include how we plan to conduct the
identify risks process.
Scope baseline -
e Scope statement - includes the list of project constraints and assumptions.
We need to ask what risks are present in the project assumptions.
e WBS and WBS dictionary - these are key inputs. We may look at each
component of the WBS (at the control account level or the work package level)
and ask: What risks might there be associated with this component?
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 189
aileen@amegroupim:.Gom 719-659-3658
Planning Processes
May be free form or Nominal Group Technique, etc. Only experts involved
RBS (risk breakdown structure) may be used Anonymous
Be careful of Group think Questionnaire
Multiple rounds
OrgaR11izational What project opportunities may be What project threats may we have
Weak.messes diminished because of the because of the organization's
organization's weaknesses weaknesses
190 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc.com 719-659-3658
Planning Processes
systems we
needed
Resources Terry moved Last timeTe.rry
off project· was pulled off
need we got him 10%
replacement of the time to
mentor his
replacement
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 191
aile<:n!ZDame12:niupinc.c:orn 719-659-3658
Planning Processes
192 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen\(/Jame&,rroupinc.corn 719-659-3658
Planning Processes
FY ions
1. a. PMBOK® Guide: Section 11.2.2.5
y a. Delphi is not a diagramming technique.
N b., c., and d. Cause and effect, system or process, and influence are all examples of
diagramming techniques that may be used to identify risks.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 193
aiken!(/Jamegroupinc.com 719-659-3658
Planning Processes
.I . .
r I I I
In the process perform qualitative risk analysis we analyze the risks from a qualitative
(not quantitative) standpoint so as to prioritize them for quantitative analysis and
planning responses.
Know the difference between Qualitative risk and Quantitative risk analysis.
Goal .. ···prioritize •risks. for quantitativ¢ {.'.;oal" .understand overall risk for project
developing re~poflses .
Quick
Cost effective . More expen$iVe
Uses terf11s like- low, moderate, high Based on statistics
Can. use numbers relative to each other , Uses numbers
Scope baseline-
• Scope statement - includes the list of project constraints and assumptions.
• WBS and WBS dictionary - .We may look at each component of the WBS (at
the control account level or the work package level) and ask about probability
and impact of risks associated with this component.
Risk register- all the information we have so far on the project risks are in the
risk register.
Low Moderate
RISK C High Moderate
RISK D Moderate Moderate
RISKE High High
194 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileenrl/)amegroupinc.com 719-659-3658
Plam1ing Processes
Risk data quality assessment - we need to ask how good is the data
we are using to perform risk analysis. What is the accuracy, quality, reliability, and
integrity of the data.
Risk categorization -there are several ways to group our risks. It is a best
practice to group them by root cause (not by their effects).
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 195
ailee111(/)amegroupinc.com 719-659-3658
Planning Processes
c.
d.
s. If w~ tl()P~J().d~v
a. the delfve.rable af .. ~a
b~ the. ohJectiye ~~feet~~)
thtrflrojeo~ pf-las.~
the•JqoJ cause ·
196 © Janumy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileenrZDamegroupinc.com 719-659-3658
Planning Processes
u ns
L b. PMBOK® Guide: Section 11.3.3.1
y b. A risk watch list is for low priority risks.
N a. Be careful of the term all.
N c. High priority risks do not go on the watch list.
N d. The watch list is for low priority risks, regardless if they are threats or
opportunities.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 197
ailetwa)arncrmrnpinc.com 719-659-3658
Planning Processes
"
r ti I I "
I
At this point we want to take the higher priority risks and put them through
quantitative analysis.
Be sure to know difference between Qualitative risk analysis and Quantitative risk
analysis.
Goal- prioritize risks for Quantitati\/e analysis or Goal- understand overall ris.k for project
developing respohses
Quick Slower
Cost effective More expensive
Uses terms lil<.e.: low, moderat~. high Based .on statistics
Can use numbers relative to each other Uses numbers
Risi< register- all the information we have so far on the project risks are in the
risk register.
E'.I EXAM TIP: The term sensitivity makes us thinkofpeople. Be careful, make sure you
associate sensitivity analysis with quantitative risk, nofwith the team or the stakeholders.
198 © Januaiy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc.com 719-659-3658
Planning Processes
Your project has 30% probability of having to pay $2Q,O()O in damages and a 40%
probabiHty of rec:eiving $30,000 in damages. What is.the e~pected monetary value of this
situation? ·
a, "$ 6,000
b. + $ 6,000
c. ~ $ 121000
d. + $ 12,000
b.
~ EXAM
@ When uS;ing a. ~oc:lelto sJmµlate a costrisk we need cost ~stimates.
@ Wh~nU$ing. m6d~.Fto/1trnulate sched~le risk we need adivity dutatlons asw~lf
as an activity network diagram,;
it Most often we sirnulate using Monte Carlo:
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 199
uileen@mner!;ruupinc.com 719-659-3658
Planning Processes
200 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileenr(uamegcroupinc.com 719-659-3658
Planning Processes
SK lu s
1. a. PMBOK® Guide: Section 11.4.2.2
y a. The tornado diagram is often associated with sensitivity analysis. See PMBOJ<®
Guide: Figure 11-1 5.
N b. and c. Sometimes expected monetary value is applied to decision tree analysis.
See PMBOJ<® Guide: Figure 11-1 6.
N d. Simulations are often performed using the Monte Carlo technique. See PMBOJ<®
Guide: Figure 11-1 7.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 201
aileernmamefzroupinc.corn 719-659-3658
Planning Processes
.
I
In this process we develop our responses to particular risks, both threats and
opportunities.
Risk management plan - This plan includes a description of how to plan risk
responses.
Risk register -All the information we have so far on the project risks are in the risk
register.
Avoid- changing plan so that eith~r the risk will.not Exploit- changing the plan to ensure the risk
occur or therlsk will not affect the project. wil 1·occ.urand •affect the.project.
Ex, C:hanging .schedule, reducing scope, cancelling Ex. Assigning the most talented resources to
proje.ct the· project
Transfer· changing plan by moving ownership Share: changinQ.Plan .by sharing ownership
(partially offully) to another party. with an outside .party
Ex. lnsuran.ce.. subcontractor Ex. Partnerships, teams, joint ventures
Mitigate: t;::hang.ing pl<=m to reduceprpbability or E11hance- change plan to increase probability
impact or .both or impact or .both
Ex. ·Designing redurdancy Ex: Adding more resources
li!l. EXAM TIP: Contingency .plans are. associated with·. ct,ctive acceptance,· .and only. a,ct.ive
acceptance.
202 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc.com 719-659-3658
Planning Processes
Mitigate-
Proactively work
with supplier on
delivery dates
Residual risk - accepted risks and risks that are expected to still remain after
plans have been activated
Secondary risk - some.times called an emerging risk. Risk that arises out of
implementing a response.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 203
aileern,vamegmi1pi11c.com 719-659-3658
Planning Processes
204 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc.com 719-659-3658
Planning Processes
p K s
1. b. PMBOK® Guide: Section 1 1.5.2.1
Y b. A contingency reserve is set-up for risks that have been actively accepted.
N a. If a risk is passively accepted, it means we do nothing, including not setting up a
reserve.
N c. Mitigation means we change our plan to either lower the probability of the risk or
lower the impact of the risk or both. With mitigation we do not set-up contingency
reserves.
N d. Avoidance means we do something so either the risk does not occur or if it does
occur it does not affect the project. With avoidance we do not set-up contingency
reserves.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 205
aileernZi!ameg::roupinc.corn 719-659-3658
Planning Processes
N b. A residual risk is a risk that remains even after we execute planned responses.
Also, risks that have been accepted are called residual risks because they remain
risks because of our acceptance.
N c. A fallback plan is the plan you have in place in case your first response does not
fully work.
N d. A risk trigger condition is a situation that leads us to utilize a risk response
strategy.
206 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileernlllamegroupinc.com 719-659-3658
Planning Processes
t t
Ii:! Exam Tip: Review Figure 12~3 of the PMBOK® Guide.
In plan procurements we think about what we need on our project and does it make
sense to have the work performed inside of the project team or outside. If we feel it
makes sense to have an outside organization perform the work we start to think
about what contract type we should use, writing a procurement statement of work
for the potential supplier, developing a request for proposal, invitation for bid, etc.,
and also coming up with criteria to help us decide from whom to buy.
register - based on the work of plan risk responses, we may have already
decided to utilize contracts. As an example, we may have decided to purchase
insurance as a risk transfer technique.
Activity -
if we request bids, quotes, or proposals from
potential suppliers, we may compare their pricing to any estimates we have already
developed.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 207
ai leen1mame1rruupi11c.corn 719-659-3658
Planning Processes
Fixed Price with Economit Price Adjustment- usually used on contracts that span
rnultiple years. The final price of the. contract is adjusted based on changing
conditions such as inflation, cost increases, cost decreases, etc. Designed to
protect both buyer and seller.
Cost Plus Award Fee Contract- seller reimbursed for all legitimate actual costs.
Fee (profit) based on subjective criteria and awarded at buyer's discretion.
Used to help align the seller's objectives to the buyer's objectives.
208 © Januaiy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc.com 719-659-3658
Planning Processes
Seller paid a fixed price by the hour or day and reimbursed at cost (or cost
plus a handling fee) for material.
Buyer has more risk since they are paying by the hour or day ( and not for
finished deliverables).
Seller has.lower risk since they are being paid for time ... not deliverables.
Statement of work (SOW)- often a clear, well defined SOW cannot be created.
These contracts can be set-up (and cancelled) very quickly.
li1 EXAM .TIP: On Contract types- for the exam make sure you know for each category:
., Is seller paid base(;! on delivery; effort, or time?
., Who nas more risk on the contract?
• Details on type of statement of work.
Make-or-buy analysis -
., general management technique
., deciding if we should perform the work internally or externally
., if we decide to go external may need to further decide to buy or lease
., while comparing internal and external costs must look at all costs
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 209
====""=~== 719-659-3658
Planning Processes
possess. Working with these bidders early may have very positive long term results
on the project.
Used when we want information from our potential bidder but do not want them to
make. an offer. to sell at thist.ime.
Often used before the other two below.
Used when the decision is l!kely to be made to the low price technically acceptable
·11
1
offer (LPTA).
Usedwhen the decision will be based on more than just low price. Other items that
may influence the decision are:
" Technical approach
" Reputation and past performance
210 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@ame&,CJ'Cmpinc.com 719-659-3658
Planning Processes
., Reputation
., Past performance
., Many others
Make buy decisions - if we decide to make the item in house (and not
use an outside source) we will continue with the other project management
processes. If we decide to purchase the item, we then continue with the three other
processes from the procurement management knowledge area.
Ii'.!. E)(A~ TIP: Remern bertr~t this is the .qril/ plan n irg pr°:c~ss vvith change r~q uests as
an o,utp~t f\lo/initi~ti?g pr;o~esses have, change requests. as arr output. No dosing
pro~es.ses have chftnge.n:iquests as an otitput, · · ·
A few other
., Com itive and non~com ng - in
general we want to use competitive contracting methods in order to find the
supplier who can provide the best product and relationship to match our
needs.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 211
aileen!l'./)ame1zroupinc.corn 719-659-3658
Planning Processes
212 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc.com 719-659-3658
Planning Processes
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 213
ailee111(Damegroupinc.com 719-659-3658
Planning Processes
214 © Janumy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc.com 719-659-3658
Planning Processes
M u ns
l. c PMBOK® Guide: Section 12.1.1.9
y c. The key term in the question is "subjective". The award criteria in a cost plus
award fee contract is subjective.
N a. and b. With these contracts the criteria for acceptance should be extremely clear.
N d. In time and materials, the supplier is paid based on time worked. Therefore, we
do not see broad subjective performance criteria.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 215
ai leen@mnegroupinc.com 719-659-3658
Planning Processes
N d. Time and materials contracts carry more financial risk for the buyer than fixed
price contracts. In a time and materials contract the seller is paid by the hour or day,
not the deliverable.
216 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen<ZDarnegroupinc.corn 719-659-3658
Planning Processes
iWill the seller's fee be increased or decreased for Decreased by the seller's % of the
an overrun? overrun. (go to share ratio-take 2nd %)
Decreased by how much? 40% of $5,000= $2,000
Seller fee=target fee-adjustment Seller fee= $8,000-$2 ,000
Seller fee= $6,000
Is fee between max and min fee? Yes, so Seller fee=$6,000
Actual price= actual cost + actual fee Actual price= $105,000+6,000=
$111,000
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 217
~=~~'-"--"~=='-'-'--' 719-659-3658
Planning Processes
I rM t
Tip~ ReView Figure J3~6 .of:the PMBOK® Guide.
Once we have identified our stakeholders we now need to plan how to engage them.
The stakeholder management plan should be very specific on how we are going to
engage different stakeholders in the best interest of the project.
· Stakeholder 2 C,D
Stakeholder 3 c D
C- current engagement D- desired engagement
218 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc.com 719-659-3658
Planning Processes
plan
Stakeholder -
the stakeholder management plan
may take on many forms. At a minimum it should be specific in our strategy to
engage our key stakeholders. The stakeholder engagement assessment matrix may
be part of the plan as well as a table like the one below that lists the stakeholder, and
the strategy to engage the stakeholder as well as the owner.
E){t\,IM rlP~ Npt engaging the stakeholders, or.the right stakeholders, early and. often
o~ a project; may le~~to more <:bange requests.than.usual and> more expensive change
requests, Ignoring negative stakeholders is often found after the fact .as· a key reason of
projectfail.ure.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 219
aileen@arnermrnpine,com 719-659-3658
Planning Processes
220 ©January 2016 AME Group, lnc. author Aileen Ellis, PMP, PgMP
aileenriilamegroupinc.corn 719-659-3658
Planning Processes
E lutions
1. a. PMBOK® Guide: Section 13.2.3.1
y a. The stakeholder plan is used to increase stakeholder support and decrease their
negative impact.
N b., c., and d. The stakeholder register is used to identify, analyze, prioritize, and
assess our stakeholders and their potential reactions to various scenarios.
©January 2016 AME Group, lnc. author Aileen Ellis, PMP, PgMP 221
ai leen@amegroupim:.corn 719-659-3658
Planning Processes
I I i II
These ideas discussed below are based on information provided by the PMP® Exam Content
Outline (PMI®, June 2015) and may or may not be directly referenced in the PMBOK® Guide.
222 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aiieerl(G)ame&rroupinc.com 719-659-3658
Planning Processes
4. Deliver fast - Break a project into a series of smaller, more easily achievable
interconnected projects so;as to deliver value earlier in the project. Perform
active pipeline management.
5. Amplify learning - Plan for training. Communicate often, get feedback and
learn from it.
6. Optimize the whole - View the whole project as more than the sum of its
parts. Determine how the project aligns with the whole organization.
7. Build quality in - Ensure quality throughout the life of the project and not just
at the end. For example, through refactoring, - restructure existing code to
improve readability and reduce complexity.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 223
llilS'.rlli!$.fil[}fgI.ill!llliJ.'~@ 71 9-6 59-3658
Planning Processes
!tis strongly recommended th~t you: Do not circle the answers below so that you may
attempnhese questions again later, .These questions are drawri from all areas of the PMP®
Exarrianq many are n<?t included in thePMBOK® Guid~. Aftercompletir19 each of the.other
prqcess groups.. c;ome backand try to ansyverthese questi°:ns again;
[)~compo$ition:is fl toed an,d·technique of what process(es)?
cre~teWBS ·. ··....... · ·.... · · ·
creat,e WBS.an,dd~fi.ne ~ctMties ·... ·
c. cfefine activities anc! deyelqp ~chedtlle
d:;de:velop sctted!Jle · · ·
2..•P~o~a.~~~fl~lys;i~)~ ~~°'o·r··~·nd'i~c~niq~~
a. s~l.lectrequiren:rer;i~s . .
·. J.f .define.ss~R~.··.·. >£:: 1
. . .•••·· . •·. ;<;:
· c:.· c9lletitr~tluirernen~~ arjq:f.f~fii;ie;~cope
.d. define activities. ·'· · ·.
s~~~~~~j~!;~ri~1~lf/i~ ~ t~ol• .
1
3.
.a. de,,'i,'elOg:;~roJe~t c~arte,r
· ib~ i . ..... lf:y ,~tal<.eholders
c. ge'IJ' . . p ~~be,clL!l.e
d. calt~ct.r~qµit1E'!trients
4.
a. i/'.·.•••· . ··.····:
b, s~<:f9.eQt::e<r
.c; .deve'lol? ~cije'~
o; estimate activitY durations
' ', .,, ,
6.' R~~~µr:c~x~~~llh~9;i~~t~cu
defineattivlti~s ........ · ·
b, seque~~eactivities
c. develop schedule
d, estimate activity durations
7. Affinity diagrams are a tool and technique of what process(es)?
a. coUectrequirel1J¢hts · · ·
b. define scope
c. coll.ect n~quireinents,and clefirre scope
d. define activities ·
224 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen((1)arnegroupinc.com 719-659-3658
Planning Processes
Alternadye ana(y'sis is a
a: defl.fle aetivi:ties
b, ~eq.uence@tivitie~
c, develop,s ule
d. estifoate iyityresqtirces
© Janumy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 225
=~~~~~~ 719-659-3658
Planning Processes
'"
'"
226 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@ameb'l·oupinc.com 719-659-3658
Planning Processes
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 227
ai leernaJamegroupinc.com 719-659-3658
Planning Processes
~: rn~r:tM~ti~Q 1..• ·
• <t ..•<tp~£pt~~<·; /. .
• d. cfo{111$~!Jfrg ., >i;t'
228 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileenra)amegroupinc.com 719-659-3658
Planning Processes
38. ·.. YOIJ hctV~ j~st l:re~n as~iglJed i<tS the project manager of a very large project
that involves peopfo from many c;ultur~s. Alth9ughyour projects have bee~ Hoss,-.
ctdtural h1nature before, this project· indudes the opportunity to work witlt people
from. many•cultures new to yc:m,· Vl{bile cultures awareness on projects is important
in g~neral; one ofthe mos~important times for cultural considere1tion is when:
a. determining rewards and ;re,~ognitJon
b .. aS,signing reporti.ng relationships
c. deciding on promotions
q, .. tasking team members to cornplet~ work packages
39, An important
identifkation.··w11ich ,.. ,..,,,,,,, ..
a. stake no.Ider analyS,Js
b . ·bottom-up ('}stirrrating
c. pararn.etrieestirnatfng
d: qualltl{plan ·
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 229
~~~~~"-"'-'..'-~~ 719-659-3658
Planning Processes
230 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen({/)amermrnpine,com 719-659-3658
Planning Processes
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 231
aiken!a)ame11.roupinc.com 719-659-3658
Planning Processes
232 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen1a)amegroupinc.com 719-659-3658
Planning Processes
N a. and d. The term "hard" and "mandatory" logic mean the same thing. Therefore,
neither can be the right answer. ;
N c. External dependencies could be hard or soft logic. An external dependency is a
link between a project and a non-project activity.
30. c.
Y c. Benefits provide value when they are utilized.
© .Tanumy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 233
ailecnra)amegroupinc.com 719-659-3658
Planning Processes
33. d.
y d. Counseling may be required when a team member is able to complete a task on
time but refuses to do so.
34. d.
y d. Based on PMI® research, less than one third of organizations have processes in
place to assess the benefits of transferred knowledge.
35. b.
y b. Satisfying a key success factor is necessary the organization to be successful.
N a. l<Pls measure the success of an organization or project.
36. a.
y a. Active listening does not involve sharing our ideas on the topic being discussed.
While sharing our ideas may be a good practice, it is not part of active listening.
37. d.
y d. Learning about your organization, learning about the competition, and learning
about the marketplace are all examples of business acumen.
234 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc.com 719-659-3658
Executing Process Group Based on the PMBOI<® Guide, there are eight (8)
Executing process of project management. These processes are performed to complete the
work defined in the project management plan. A large majority of the project budget is
spent during the executing processes. Along with completing the work defined in the project
management plan there also is a strong emphasis on acquiring, developing and managing
the team. Stakeholder engagement is a large part of executing and often a key factor in
determining the success or failure of the project.
0
Based on the PMP Examination Content Outline (PMI ®,June 201 5), there are seven (7) tasks
of Executing. These tasks represent 31% of your exam content. l<ey phrases associated
with each task are:
The PMBOI<® Guide, the most often selected reference in studying for the PMP. exam, does
not list the tasks comprising the executing process group but emphasizes processes
instead. Although not as robust as the PMBOI<® Guide for in-depth study, the PMP'
Examination Content Outline presents the tasks shown in the table above. Although
memorizing these tasks for the exam is not necessary, reviewing them from time to time is
0
recommended because they form the basis of the PMP exam's questions on project
executing. As we cover the eight processes in the executing process group in the. upcoming
pages, you can see how these t
asks relate to the processes. Assume all seven of these tasks occur concurrently.
235 © Januaty 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileernt'/)amegroupinc.com 719-659-3658
Executing Processes
r
6?1 Exam.Tip~Review Figure4-7 of the PM BOK® Guide.
In this process, we complete the activities described in the project management plan.
The project manager with help from the project management team ensures that all
the work, and only the work that is defined in the project management plan, is
performed.
li?1 EXAM TIP: rvh:.lchof thE!·proJedhud~~tis speht during theprdc~s$direc~ and manage
t>r<?Je2tWor~. ·. · · .
236 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc.com 719-659-3658
Executing Processes
·I
It!·. EXAM TIP: The PMJS is a tool and 'technique of some processes and an input (as a
subset of envirnnmental.fC!ttors}.for other·processes. ·
Deliverables - this is the most important output of all the processes. Some
people will call project management: deliverable management. These deliverables
will become inputs to the control quality process where they are measured for
correctness and then inputs of the validate scope process where the customer will
inspect them for acceptance. During the close project or phase process, the
ownership of the deliverables will transfer to the customer or the operations group.
Work performance data -we discussed this in chapter 3. This is the raw
data collected as you implement your project. This data will become an input to
several controlling processes for analysis. l<Pls (key performance indicators) are an
example of this data.
elements of the plan or other documents may need updating as part of this process.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 237
aileen!a)amcgroupinc.com 719-659-3658
Executing Processes
h As t(1e project ~C\~ager, you ate expetienced in managing a small t~am of peopl~.
Now: Y()Ur team in.dudes over 500 mempers located i~ 4different countries. lt looks
li~E! <=<Ycmmunicati()nJs ~ .prob,J~m •. As an, pie, ·Hiram wa.~· runn•nQJ(lt.e finishin,g
the ~~yel.~proe~t ?ft~:,pr~du.c:t.~ Ravi dicl .... ·. knQwthisiand .started te~ti.ng .before
the1lrf1d~ftwas,re~t:1y; ~h~t may. f1ave helpeclprevent~his situation:
Cl· asba;t1~~co~~rolsyst~rp •••...·
b....•.'l vvor~ ~!Jthqriz:ation. ~Y~~.E!m· ..
c. qqtt:>r¢·(:(~t,ail¢d comJ'nupJcation plan
d.. q.fl'IQr~·defined h11m~n'r~soµrn~ plan
J>;
a. """~r~·P~r:~?1nT1;ance
··•: ·• ....... ·•· ... · · · · · ·•·•·.· .·.~el?~rts
;;' •'•.• '. · .
.6. app~oy¢~.{ch.ahge;r;~que~ts .•. . ··•
cL 4E!nied.cbang¢requests · ·
3•. ~h'it~ ~f 1.~~f~1~w·~~~i~~~i~~;:~~~\~~~·~iqu~~;. d~r:e~~ artd 1·~~riage.··~~6Jeci··~orl<?
a. cha119e ·.c~ntro1J>t.¢in ..... • · ·· . . · •· ·.· ··.•. . . · .. · · ·
h. conflgurafignnl~ea?"emen~·plarr ····•
c. pr?Ject·rn~pageITTJ~ntJnform%tiorr..systerfl
Cl. orgar'l.izationalprocessasse.ts ·
Ci· wor~:·~~rforrpance r~
b. 'No(~ p~rforrn}1'.f1 c:e . · ··
c ()rQ~niz.ationaj:.pr().c
d. ent~rprise en\(i.ron .
238 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen(l/),amegroupinc.com 719-659-3658
Executing Processes
E ions
1. b. PMBOK® Guide: Section 4.3.2.2
Y b. A work authorization system is a tool that ensures the work is done by the right
team member, at the right time, and in the proper sequence.
N a. There is nothing in the question to tell us that there is an issue with change
control.
N c. and d. The question uses the term communication and the term team. Be careful
not to get distracted by these terms. The real issue in the example is that Ravi started
work without authorization. We need a work authorization system.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 239
illli'.s'.lliQ@lrill_gLQl!illll~!ill 71 9-6 59-36 58
Executing Processes
r u
Exam Tip; Review Pig:ure 8-9 ofthe PMB@k® Guide.
Understand the difference between perform quality assurance and control quality.
Quality metrics - lists and details the attributes that will be measured and
how they will be measured.
decision program -
is a technique designed
to help prepare contingency plans. The emphasis of the PDPC is to identify the
consequential impact of failure on activity plans, and create appropriate contingency
plans to limit risks. Process diagrams and planning tree diagrams are extended by a
couple of levels when the PDPC is applied to the bottom level tasks on those diagrams
240 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen<<'7Jamegroupinc.com 719-659-3658
Executing Processes
Tree Diagram - this tool is used to breakdown broad categories into finer
and finer levels of detail. It can map levels of details of tasks that are required to
accomplish a goal or task. Developing the tree diagram helps one move their thinking
from generalities to specifics. Examples of its use in project management include:
WBS (work breakdown structure), OBS (organizational breakdown structure), RBS (risk
breakdown structure), RBS (resource breakdown structure), etc. In this figure we have
a horizontal view but we may also use a vertical view.
Matrix Diagram - This tool shows the relationship between items. At each
intersection a relationship is either absent or present. It then gives information about
the relationship, such as its strength, and the roles played by various individuals or
measurements.
Quality audits - this is a review by someone outside the team to see how we
are doing from a quality standpoint and to correct any negatives .
.ltl· . EXAM TIP:> }\udits in general Jefer to/processes while inspections in general refer to
deliverables ()r products. Therefore 1 we are more likely tg:
., Audit a process (and not a deliverable).
• Inspect a deliverable (and not a process).
assurance
Change requests - most monitoring and controlling processes have change requests as an
output. All change requests go to perform integrated change control for approval or
rejection.
© Janumy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 241
aikcnr(Damcr1.roupinc.com 719-659-3658
Executing Processes
. 6.
a~
b~
c.
d.
7. VI/hat diagram is used to visualize the pareilt,;to-child relatiqnship in a
decomposition hierarchy?
a. tree diagram · ·
b. activity network diagram
c. matrix diagram
d. affinity diagram
242 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileernmamebrroupinc.corn 719-659-3658
Executing Processes
9. The tool used to understand a goal in relation th~ steps for getting the goal
is:
a. tree diagram
b. actiylty netWorkdiagram
c. processc:lecislon pro9rctm charts
d, affinity diagram
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 243
aileenr!vamegroupinc.com 719-659-3658
Executing Processes
Ii'! EXAM TIP: Audits are related to processes. Inwectiotls. are related to deliverables and
products.
6. a. PMBOK® Guide: Section 8.2.2.1
Y a. An affinity diagram is used to group like ideas together.
N b. An activity network diagram is used to show the logical (predecessor and
successor) relationships between project activities.
244 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
ai leen<(fiamegroupinc.corn 719-659-3658
Executing Processes
N c. A matrix diagram looks like a table with items listed across the top and down the
side. It provides information abdut the relationship (or lack of relationship) between
the different items.
N d. An interrelationship diagram visually shows the relationship between various
items. It is often used in problem solving.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 245
aikewmamegroupinc.com 719-659-3658
Executing Processes
UI
Exam.Tip: ~eviewFigure9,.8. of the PMBOK® Guide.
In this process we work to acquire the people we need to make the project successful.
At times the project manager and the project management team have some control
over who gets selected (or assigned) to the project team and at other times they do
not. Sometimes the skill sets required are not available, or even if they are available
are not assigned to the project team. Project managers need to ensure that the
project plan is updated based on the actual people assigned to the project team.
Negotiation - the project management team will need to negotiate with other
teams, functional managers, and external organizations to obtain the skill sets
required to make the project successful. The ability to negotiate and influence will
affect the success of the project.
Acquisition - this sounds like a procurement term and it is. The project
management team may need to go outside of the organization if the skill sets are not
available internally. This could mean hiring a consultant or using a vendor to do
some of the project work.
EXAM."fl.P:Be. carefofon the exam \Nitn the to.ol (lnd technique called acquisition.
Remember it is part of human resources and not>procurement
246 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
ailecwiiJarnegroupinc.com 719-659-3658
Executing Processes
" Considering projects that may be would not have been considered because of
geography, etc. '
" Ability to obtain very skilled resources that would not have been available
locally
" Lower costs associated with office space, relocation of individuals
" Etc.
© Januaiy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 247
aileen(GJamegroupinc.com 719-659-3658
Executing Processes
4. lf·th.e·.•proJ~~t(~~nag~riS,;1~~~;
proj~c.t,f;l~~h?':"lq:
·a:·•try•to . . . )·••.•.·>·;
move:it~ abette~
. · · · · · · · · ·'
project
b, be clea,r th<:1;t1TJa,.~~~em · .tlsre.sp9nsiblef()rpmjettf&ilunf·
c. cut~ ..·~,~r~:'«o .... ·. ;~PPt/~i:>Q~en9t19~s
d. r GJ:gementsul2)por;.tte'.gat.tfrer;E!quired re.sources
s. · .· l~struc;tt:re •l~ ~n ~~~fu~i~~t~
a: prg .· •. . / . • .· . proce$s asset
b. e11ter~rise envtrqr:tmenta,l factor
c. ; ne,gpticition ·
d. a,.cqyisi.tion
','' \,.,' j';' '<' '' ._, .,,'
6. .. ·•HJr·i~~/· ~<lfl"ls.~1~ants
exa[n~Jet~f? >\ h \.••..• ~./.·····/·.\ . . .·. >
a... or9a~i~atiqnal.. :.: ~SS assef: .• .
;·.bi·el'.l~ernl'is·~ envr nienfafiactor'
· c. ·negotiation
d. acquisiU()h
-_ .-' -. : _,~ ·._._-_._H >_/:'._'< ·_ :· <,·:·::.<:. ' ''.,{:
7. M1.dti~C:rite~l~ dedsionan~lysis involv~s:
a. ·hiring individual sonsultapts
b: negdtiatipgwit.hfonptlo~al managers
c. fw.mif1gtearns whq~e members liveinwidespread geographic ar~as
d; usingcriteriato rate potential team members
248 © Janumy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileerna)amegroupinc.com 719-659-3658
Executing Processes
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 249
aileen@arnegroupinc.com 719-659-3658
Executing Processes
250 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileerna)amegroupinc.corn 719-659-3658
Executing Processes
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 251
aileerHZDamegroupinc.com 719-659-3658
Executing Processes
There are two parts to develop the project team. One part is developing the
competencies of the individual team members. The other part of this process is to
develop the individuals into a working team. Both of these ideas together should
lead to improved project performance.
Building trust is a big part of building a successful team. And building a highly
effective working team is a big part of being a project manager. As a project
manager, we often have team members representing many different cultures.
Learning to work with these other cultures and even using the different cultures to
the advantage of the team is critical to team success.
Human resource plan - this plan, as a subset of the project plan, provides
guidance on how to develop the competences of the individual team members and
also how to develop these individuals into a team.
Resource calendars - the calendars show when team members are joining
and leaving the teams. They may also show when members are available for different
team activities, including training and team building.
Interpersonal skills - these are those soft skills that help us get things
accomplished, especially accomplished through other people. Empathy is an
example. Empathy means to put ourselves in someone else's shoes to try to
understand what they are experiencing.
ra·· EXAM TIP; An interesti~g ql.testion is who pays for the training ofa project team
member. If \the trainiqgis specific to proJect needs often the project budget will. cover
· the cost; ff the training will be useful on other projects,\the11 often the organization will
cover the cost
Team building activities - team building should start early on the project
and continue for the life of the project. The goal is to improve relationships so as to
improve the performance on the projects. Some organizations believe in
professionally facilitated team building activities. While this is great, day-to-day
activities may have just as much of a positive effect.
252 © Janumy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc.com 719-659-3658
Executing Processes
Most teams progress through teach development in various stages. One such model
was developed by Tuckman. He first developed a four stage model and then later
added a fifth stage. Most teams progress through this model sequentially. Teams
need to be careful to not get STUCI< in a stage or even move backwards. If new
people join the team or current people leave the team, the team will often go back to
stage one- Forming. The five states of Tuckman's model are:
l. Forming - this is when team members first meet and learn about the project
and each other. Individuals often are on their best behavior and work
independently.
2. Storming - at this stage different ideas and ways of progressing are often
discussed, conflict may arise. Some teams get STUCK here, while others are
more collaborative and move through this stage quicker.
3. Norming - at this stage the team members often agree to a common goal and
a common approach to achieve the goal. Members begin to put team goals
ahead of individual goals.
4. Performing - often at this point team members are motivated and begin to
achieve results. Positive results lead to more positive results. Not all teams
reach a performing stage.
5. Adjourning - at this stage the work of the project is complete and the team
members go their separate ways.
E:~ftll JIP:: Know the name "[l.lckmana,s the ortginato.r of thi.s model (sometimes called
the T~c~man Ladder), Also know that son;1~:teams get STUCl'(j n a stage and .some teams
even move backwards, questions this model,
Colocation - this means that most if not all of the project teams members are
physically located together for a period of time. The goal of colocation is to improve
project performance. Examples include:
• Kickoff meeting that may span several days with most team members present
.. War room for team meetings, etc.
While colocation may be very beneficial there are also some benefits of using virtual
teams. The two ideas need to be evaluated to determine which, or a combination of
both, is optimal for team performance.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 253
aileen@arneg]Q!lpinc.corn 719-659-3658
Executing Processes
rnatflx. the term colocationJs ?ften associated with a projectized team though a team
may he. projectized and not collocated.
254 © Januaty 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@arneg;roupinc.com 719-659-3658
Executing Processes
p e e s
1. Which pfaut is. ~ninput of (jevelop project team?
a. com municc1tions.managernent. plan
b. humanreso~r~e.plan
c. pn:kuremet)t m~nagement plan
d. stakehol.der management plan
7. Intangible rewards!
a. sho.uld never be used if money is availat>le
b. include money · .·
c. may be equallypreven more effective than m9ney
d. should be .the same for everyone, to ensure fairness
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 255
aileernmamegrnupinc.com 719-659-3658
Executing Processes
9.. WhicftJnput to develop project team has ~he purpose to identify the people who
are otfthe team: · ·
a. hurnan resource plan
b .. staffing. management pl.an
c proje5tsfaff a$signments
d. resource calendars.
256 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileerna)ame12.roupinc.com 719-659-3658
Executing Processes
p u ons
1. b. PMBOK® Guide: Section 9.3.1. 1
y b. The human resource plan is all about the team and therefore would be an input
of develop project team.
N a. The communications management plan is about communications and not about
the team. It would be an input of manage communications.
N c. The procurement management plan would describe the processes of
procurement. It would be an input of conduct procurements.
N d. The stakeholder management plan is about the stakeholders. The stakeholder
management plan would be an input of manage stakeholder engagement.
©January 2016 AME Group, lnc. author Aileen Ellis, PMP, PgMP 257
aileerni:/)amegroupinc.com 719-659-3658
Executing Processes
N a. Because intangible rewards may be as effective or even more effective than money
they should be used even if money is available.
N b. Money is a tangible, not an intangible reward.
N d. Different people may value intangible rewards differently. Not everyone needs to
receive the same one.
258 © .Tanumy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
ailet"nriDamegroupinc.corn 719-659-3658
Executing Processes
In this process we interact with our team members on a day-to-day basis to work on
improving project performance. This may involve dealing with issues and conflicts,
etc. Regardless of the tools that we use, the goal is always improved performance
for the project. This is the process in which the project manager really must utilize
his management skills to not only provide appropriate feedback but also provide
assignments that help the team members grow as individuals and as a team.
Human resource plan -this plan, as a subset of the project plan, provides
guidance on how to manage the project team.
li!I EXAM TIP: Since we are in the H,R. chapter it is a good guess that the HR plan and not
a.nother plal'l i? ?.rl inpqt. ·
Team -
these assessments, along with
other inputs, drive improvements in team communication and interaction, as well as
issue and conflict resolution.
Input of the manage project team. process Tool and technique of the manage project
team process
The assessment of the effectiveness of the team. The yearly performance reviews that
The project manager may evaluate the team on managers perform on their people
performance against the requirements, the
schedule baseline and the cost baseline.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 259
aileen<a)ame&,'1'ot1pinc.com 719-659-3658
Executing Processes
002 Terry moved off Medium Alex April 14, Complete April 1, Jose
project~ need 2013 2013 brought on
replacement a team to
replace
Terry
Project -
the title of this tool may be
confusing. These appraisals are the yearly performance reviews that managers
perform on their workers. On some projects, the project manager owns these
appraisals on their team members. On other projects, the functional manager owns
these appraisals and the project manager provides input. Either way, the goal of the
appraisals is to improve performance through communication, feedback, etc.
lt'f EXAM TIP:. Notice .this Hst has numbers (1 ,2,3). Almos(all the. at.her lists in this book
are Just bullets. For the exam,knowthe top 3 sources of conflict.in Ord.er.
When project team members initially run into conflict, they should try to resolve it
themselves. Only if they cannot resolve it on their own should the project manager
get involved. The success of a project, the project manager, and the project team is
very much determined by how well they can overcome negative conflict and use
healthy conflict to foster innovation and higher productivity.
For the exam know these five (5) conflict resolution techniques and when you would
use each one:
260 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileernaJamegrnupinc.corn 719-659-3658
Executing Processes
IZl . . . TIP~<N~1:i:~e e~stt techt:iiq'y;~ ha~'tyvo names U~tecl,. Q~ ~he. e)(am if you . a
ques.ti.on wi.th ~f!s""'~r;(a~ 9E:lrg wit.l'rc;lr:<;;t)11~1 <;f!"c:l~psw~r (b)belpg avpid,, bq~h ·answers n.~ed
to be·w $.jnce ttietwo,t~~)t)~m~a11tbe.s~1n~thi.n9 antl.YgH.canl'.lot. have two answers
that.a t · · · · ·
Interpersonal skills - these are those soft skills that help us get things
accomplished, especially accomplished through other people. Several specific skills
to consider for the project manager include:
Leadership - inspiring others to meet their goals and commitments.
Influencing - often the project manager is not the manager, in the
official reporting structure, over his team members. Therefore, the project manager
cannot use positional power to influence the team members. He may need to rely on
his ability to influence, without power, to get the work of the project accomplished
in a timely manner. Great communication skills, including listening skills will help.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 261
aileen!(/)arnegroupinc.com 719-659-3658
Executing Processes
Change requests - Changes related to people may have a huge effect on the
project plan and other project documents.
~.
~.1
~1
11
,I
·,.
262 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@ameg;roupinc.com 719-659-3658
Executing Processes
Theory
J
- created by a psychologist, David McClelland,
it is a motivational model that attempts to explain how
.. the need for achievement
.. the need for power
.. the need for affiliation
affects the actions of people from a managerial context.
Fiedler's Contingency - the model states that there is no one best style of
leadership. Instead, a leader's effectiveness is based on the situation. This is the
result of two factors - "leadership style" and "situational favorableness". He states
there are two leadership styles: relationship oriented and task oriented.
Leadership Styles -
Autocratic: traditional view of a management- a boss who makes decisions without
asking for input, valuable for quick decisions
Laissez-faire: hands off view of management, valuable when creativity is required,
may be viewed as positive in the appropriate situation
Democratic: manager involves team members in decisions
., Participative- decisions made jointly
.. Consultative- manager asks for input but makes decisions alone
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 263
ailcen@amefs;roupinc.com 719-659-3658
Executing Processes
Harmonizers
summarizers Devil's advocates
Gate Keepers
Special rewards given to a specific team member Standard benefits given to all team members
usually for performance above expectations
Example: Team member of the month award Example: health insurance
264 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileenra)mnc}zroupinc.corn 719-659-3658
Executing Processes
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 265
aileenr(/)amegroupinc.com 719-659-3658
Executing Processes
process: .· ....
a... Plcici. hum a? r~soµrce m~nagemem
b.. ITJanage .stake ho.Ider engagel'tlent
c. ··develop project team
. d. acquire pl'OJecttearrr
a.
.b.
c.
d.
266 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen!r1hmegroupinc.com 719-659-3658
Executing Processes
E s
1. b. PMBOK® Guide: Section 9.4.2.3
y b. Collaborating is the conflict resolution technique that incorporates multiple
viewpoints in order to get to a better solution.
N a. Smoothing is the conflict resolution technique in which we agree on what we agree
on and often do not resolve the disagreement.
N c. Withdrawing is the conflict resolution technique in which one party pulls back,
either on a temporary or permanent basis.
N d. Forcing is the conflict resolution technique in which one party makes the other
party accept the forcer's solution. It is often used as a last resort. This technique
may be appropriate in a safety or security situation. The outcome is win-lose.
© Januaty 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 267
aileen<ll)amegroupinc.com 719-659-3658
Executing Processes
~
1f:
9. d.
y
PMBOK® Guide: Section 9.4.2.2
d. The project performance appraisals are a tool and technique of manage the project
.f'h
,~
team. These are appraisals on individual team members .
N a. Plan human resource management is too early for project performance appraisals.
You need to have team members to use this tool and technique.
N b. Acquire project team is too early for project performance appraisals. You need to
have team members to use this tool and technique.
N c. Develop project team is too early for project performance appraisals. The purpose
of this process is to develop the team members, not appraise their performance.
268 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
fililTI.\i!Ufil[illgIQ!!lli!]!~'ill 719-6 59-36 58
Executing Processes
© Januaiy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 269
aileern(1)amegrnupinc.com 719-659-3658
Executing Processes
M I
In this process we follow the communications plan which includes all the details
related to project communications including creating the information, sharing the
information, and finally disposition of the information. Most people think this
process is just about sharing information with the stakeholders. There is a lot more
to it than that. We need to ensure that the appropriate information is created and
put into a format that adds value. We need to think about the communication
methods (push, pull, interactive) to ensure the best method is Selected for the
situation.
li2f . EXAM ;TIP: If¥()~ get a q~~stion asktng whoyouwHI be providing specific information
to; the bestansweri.s 1,1sually~ follow the communications plan.
270 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileernli)arnegroupinc.com 719-659-3658
Executing Processes
Sentto specific recipients, does not ensure Letters, memos, reports, e-mails,
receipt or understanding faxes, voice mails, press releases,
etc.
Used for large volumes of info and/or large Intranet sites, e-feaming, knowledge
audiences. People may dedde to access or repositories, etc.
not access information
el ~)(AM. Tn'.': Make certain you are yery cl~ar that every project should have three. (3)
baselines: ·
Scope baseline~made up of.three co:mppnef1ts
o $cope statement
o Was
o WBS Dictionary
"' Schedule baseline
111 Cost baseline
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 271
ai lcen!a)amcr1rnupinc.com 719-659-3658
Executing Processes
s. · Ther,etfotfij~ijge·meastir~ment b~~~1fo~
· c;t. s,co~e,sch~d.ule;ctn~.<:()~t·.·
b; SChE!d~JE!, , Ein.tlf:J'iSk; ;
c ··.c9sh ri~f('·· .·. · .· Rr,ocur~t;rlent.
d, risk, procurement, ani:Lscope
/,,, '· ',, '
272 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
ai leen@amegrnupinc.com 719-659-3658
Executing Processes
E MM N u ns
1. a. PMBOK® Guide: Section 10.2.1.1
y a. The communications plan is an input to manage communications.
N b. The human resource plan would be associated with processes in the human
resource area, not the communication area.
N c. The procurement plan would be associated with processes in the procurement
area, not the communications area.
N d. The project management plan is an input to both plan communications
management and control communications.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 273
aileenla)mnegroupinc.com 719-659-3658
Executing Processes
274 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
ai leen@amegroupinc.com 719-659-3658
Executing Processes
t
Tip; Review Figure 12-5 ofthe PM80K® Guide,
Sellers' proposals- the term proposal here is used to represent bids, quotes,
and proposals.
The timing of this input is interesting. In general, we (the buyer) send out the request
for proposal. We may hold a bidder conference. The bidder (seller) then submits
their proposal. (This is the input we are discussing). At that point we evaluate the
proposal (see tools and techniques). Then we decide who we will buy from and award
the contract.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, Pg MP 275
m.lS:5110aJ.filU'-'EIQ!!J2ill'~UI! 71 9-6 59-36 58
Executing Processes
~ .. · EXAM TIP,=: A mdst likely question .. : When are We n;iore.likely·~o want an indepe11dent
· ·es.tirn~te; vyhen.we.r,eceiye a{e'11!.PU?Posals pack or..when ~e·receive rr1any proposals?'fhe
answer is just a few. TheJewer the nljmber of prop.osals .the lessHRelywe are to really
know a fair price.
276 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
ailecnfr/)amegroupinc.com 719-659-3658
Executing Processes
The procurement group is a corporate group. There is a procurement person sitting on your
project team.
Advantages: Advantages:
Volume discounts More loyalty to team and project
Better able to specialize Quicker response to project requests
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 277
aileenfr/)ame&,IJ'oupinc,com 719-659-3658
Executing Processes
Contract terminology
Force majeure - translated as "a major force'', often translated as an act of
God or an act of nature. A party of the contract may be temporarily relieved of
contract commitments if a force majeure clause is in the contract and the force
majeure occurs.
Typical force majeure includes: an epidemic, an earthquake, etc.
Typical items not considered force majeure include: an employee getting sick, the
organization running out of money, etc.
Other documents-
A letter of intent is not a contract. It states that if the buyer decides to buy they
most likely will buy from the seller (who receives the letter). A letter of intent is not
a commitment. It is not a contract.
278 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc.com 719-659-3658
Executing Processes
2. Bidder conference~:
a; are us,~dto ensu.lfethatall<selled have a dear understanding of the requirement
b. art:!;HEt!.c;!~after theprpposals have been s1Jl;>mitt~d ·
c. arect:me¢ting bet¥veen.tl,1e;f:myer and d1ewinning
d. a~~.U%~~jpyth.e~~yer.tp.i~electthe.wil;lning.seller(s)
n. q;pds~ls
Ci ,vt.ocHl'ertfe.ri:t;Statt!mefut or. v\lqr.l<r .
cL make."or-qµy gecif;•iQIJS
a.
b.
c.
d.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 279
aikeniZiJamegroupinc.com 719-659-3658
Executing Processes
280 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileern(/)amegroupinc.com 719-659-3658
Executing Processes
r t
Exam Review Figure 1 PMBOK® Guide,
In this process we follow the stakeholder management plan to actively engage with
our stakeholders to increase the likelihood of success.
should be utilized to ensure that all project issues are resolved and
closed. They also are a great communication tool as they let our stakeholders know
that their issues are important to us, that owners have been assigned and resolution
will occur.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 281
ill.!S~].ill:IJ.£i,?;!lillJ2ill'~!fil 71 9-6 59-3658
Executing Processes
002 Terry moved off Medium Alex April 14, . Complete April 1, Jose brought
project- need 2013 . 2013 on team to
replacement replace Terry
282 © Januaiy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
ai leenr2V,amegroupinc.corn 719-659-3658
Executing Processes
MANAGE pie s
1... Jhe ability c)f the stakeholders to influence the project is:
a. lowest atthe start and gets progressively higher .as Jhe. project progresses
b. flat througb~ut the life pf the proJ~~t
c highest att~e start and get~ pro~rnS,s,ivefy lpweras the pmjeer progr~sses
d. lowest atthe:start, peaks during.exec;qtion,and gets lower.throughoutcldsure
.2.. How is. the. cha;nge log related to/ marjage stakel,10lt(er engagement?
a~ an input ·
· h; a to9Land tec:hri.iqu:~
· c: a°' ~utp~t
· d. not.related
..
tn~erpe~sonal·skUIS,Ci~~lud~:
a. pr~s:en;ta,ticm sldlls ·
b. negotiating
s
writing kilts
building trust
cbange.log is aQ.oiltpi.1,t."ofwhat•process?
n;ian<J:~~stakeholc!er er19.a,9eQie~t
fl).9riJtqrcind contrpl project work
c. ~erf°:rn;i i1"1tegrated chan!:jecontrol
d. control ~takeholder engagement
© Januaty 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 283
aileernmamegroupinc.com 719-659-3658
Executing Processes
284 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileenr(/)arnegroupinc.com 719-659-3658
Executing Processes
I i II
The ideas discussed below are based on information provided by the PMP® Exam Content
Outline (PMI®, June 2015) and may or may not be directly referenced in the PMBOK® Guide.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 285
aikenrZDamegroupinc.com 719-659-3658
Executing Processes
~.anci~!:!r ha~
. l ...... Your Ju.st. returned. from. a tJiYo"hour.e~~cutiVe 6,riefin,g on project
rn~~agemem.....1-feha$ t~e Pf!'l~CJ.I(®: Guide in.~andand·f~Very ~Cite~ to teach you
eyerythipg he.•has l~a.rl'}~q. Viffl~~ sh~uld b.eyour·response• when Ii~ . explains the
irripor~~9<.:~ pf foUc.lWin~:~~~ PM~()K~ G9f'd<?, pro~esses on alt your proj~cts? ...· .· · ·..•·.· . •. •
,a_ .... th~H'.}r()Je~IJl~f'l~g~r,~19.r!.9·yvltfl:t11le.P;rbJEtftlTlal1~gem.eot;t7~rrvsh91,!l~cf~)E\rmine wh.lc.h
· PA!f/3.q~~Oui4e·p;r~~e51~#s~~E\·<r!p·~rnpri~tli! a~'\il{e~J.a~ t~.~ approi:rria~~ degr~e'qf .rigor
.<b; tn.~..R. · · · ~ Gtlhf~pro~~ss~;s sijpul.d ·~~!J,~am:;j!Ied uniforrn1¥ t() every· pr,oJett
. ~~ /tn(p ·•· · ility. of.P:roJe?t)'~;~~s~ · inct~~~~s based on ··t~e;~prnher of>tMf3PK~.. Gu{'Je
proc~~~.e
d.the ·
PUed~o th~.P~6J<itjt • < < ....···.· ..· · . . . . ;i;.
c.• > .. '· <· • · ·•.•.. ·
K~1~aideiscr O'Jethodqlo~y~·Jtshould .eitherb~a,pplie(fc,0rT)pletelyor not at
all pn<p ects .. . .· . .· . . . .
4. Thz.·P~()j~s:thl'tr~ger\;h6u1:~partidp~te]ll••thec1~vel()J1.ment.Oft~e··pr9Jectdfarter
af!d inf(lrni:,stak~~c::>,ld~r~ {;)fth~'.c;ipproved p~oject charter. The charte.r sho1,1h:t indyde:
C1· •a strat~gy tQ err~tige pr&Ject sta~~holders . . .
· b, keY~eliverables · ·· ..· ·. .·. · ·
• c. the proJ(i!ct e?<cluskms
. d. th,.e proJettsc:.he.dule .has'elirle
. s.AU oftbe follm111ing: «:lre .~oQsidered characteristks ola good estimate except:
a. clear identification of tasl<.s
h: narf()\N partidpationin preparing the estimate
c. recognition of inflation
ct recognition<qf excluded costs
6. Currently you are overseeing the planning for a large software upgrade project.
Your t~am is in the process of deco11structi11g the scope. Alikely tool and technique
they may use is: ·
a. the scope ba.cklog
b. a precedence diagraining method
c. a cause and effect diagram
d. dependency determination
286 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileenra),amegroupinc.com 719-659-3658
Executing Processes
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 287
aiken@amei:roupinc.com 719-659-3658
Executing Processes
g~n~faf ~inancial/111
~on$idered Part ofprpj
. a. f<:H· everyproJe.c;t .• · · • i•x.> •·. ;.'.
b. fof~lf prpj~cts witli >lar!;J~· .budg~t$
c for c~glt~I fa.c:i.litiE!~ projects · ·
d~ neye r for projects ·
288 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
ai leen!i:llamegroupinc.com 719-659-3658
Executing Processes
2/.·•Histo~.ic~1lr~~ou~·~rgani~a~i~n··hai;~i~~~61~~.with·•·ct.ffalit'/'r1l~i1•~g¢me6t~
.. 1n• fac;tJf
y9u ask~drno~t·.tea01 mem~~fS,.abot.1tquality ~.n .proJ~@t~ theirr,spons~.l'r}a~ be ·
•·~.~at Clti<,11ity?· rr~ere~qr~. yoµ ·~ave cledd.E!d :on·your curr~nt.l)roJ~.9t to pu~.:~. mµch
sl~on,g~~ fo~us <>11 q~~li~y IT)an(J.gernent. At an ~arly teamfrn~eting ~h~ m~111.pe~s of.
t~~.f~~e..teama~~ ~r!1J~,ii1Q a· · at iS tfr~ firsttbing td.d(Jto adclr~$$~thi$
iss~~¥·Y~y<~~llth~if1W~ m .. .. · · · · ·
a~ a.~alyzing '!Jeq~~litvpr~<;.rsses
b. a~?.~ss 11~perf9trn~nce .. • ·. !'/.>/.
c: r~f:Orn ..• ·. •·· · ··.·.. ~~?lt19@S:~:,;'. <• •• !> . .
d. a~velopingaq1;1ality ..rrana.gemem·.;plan
shewhart andpe;rlin~~reiatrio~sfo.rwh~tcyde~
c9ncept~d~y~1 opm~nt·ex ~cutio1N:lqseo1Jt ·
b. plf!:.n·~~-~ti~ck-act.< .•..•·· · •· . . . ... >
c; forrningJ~~~frning~narrni'1ftP:erforrr!r:t~.< .....·· ...·· ... < . < •. . .. ·
d. ··ini:tiating•rplanning~execµtit'l~!kmonitoring, and.co:ntrolJing·closing
"-, ,,,',,',,,:,/,,,, ':
2~ ·.~onf:o~~a~~e t~.:re4~iferm~nt£'fueans: .
.. ?'· .. ·
>a. th~ Rf:OdU(;tpr Senlk~ nee9~~qsatjsfythe r~al m~e~Sc •· . . . ·. <
b. category fen products havirig ~he same use butc!rffen~nt cl)<lracteristiCS
. C; fitness.for use. · ....·.. ·
d. t~E;rproject produces what it was created tOproduce
2 S.. Fitne~s f()r ~s~ mea~s:
a. the !)roduct or service ~eeds.to saHsfy the real neeciS:
b. <;ate!;joryfor pr()ducts ~avi119 same use but differe.nt characteristics
c. conforma.ncetorequirei;Ylents >< . ·
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 289
aileernmameR;roupinc.com 719-659-3658
Executing Processes
29f
· a?F
~·~·.\
(;},
ct
\~~;r~$~tr~~r~4~:frt~ ~,~~fr~I ~~a$ui~rn~~~s'is ~~Ue·~=
.a9~ITT¢~t,:S······
~ssurahce
.·a:t/~~~ti~Y;~~J~~;~~~it ns:.
·.·~. cts >., .:...i··· •. > . •.
.·
·
,~::~~~,~~~;11~.'······ ~r;m~~t~"tfU;~~r1t~
a:·.·lovy.qu~[it:ym~f.ri~f al~~Y~ ™~ a'pro~l~l:J1 ·· ·
l).·.~esh()uld.E,th1v~'l~.~~liv&r.highgt~cl~
· ·C.• CJ ua1itv-anq~ra9e· are Q~Si~all'f tfie Sarne th tf1g
d: JowgrC1,de may;notalways b~ aproqlem
34~ oxatle is: .. .· .·. > •·· ..... ··. . . · ...• ···•· .. •.·....... . . . . ·•. ·.. . .. . •.
. ab ••· ca:tegoryfor.proclu~tshaving thesam.e use but.tjifferent ch<1.racteristies
co~fonpance to reqtiJrements . .
C; fitness for .use
d; a measure ofexactness
290 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileewGJ,arnegroupinc.com 719-659-3658
Executing Processes
At the .end last project your team spent a amoun.t of time collecting
lessons learned. . . most important lessons, were related to the project t~am itself.
Ma~y teafl1 m~mbers diij not under~~~ncj .itae~r responsibilities but also did
understaryd the re5ponsibHities of ot~~r mell)bers ·of th(;ll project team. Most
mell)berscHd not uf'lder~t.~t1d .the·re~~rtinq~tfU~ture <;»r"Vh~ffa.nd
releC{se otherteam rnern~er~~ Therefo~e~ Y9ll .h*'yededd~d~oput
hull)~n re.source man~Qell)e.nt,.•cm ycn,tr ctn-rent project~ You belieye
~·~ . .
a'. hirem9reexperiencedte~un r)'lember? for~eniorpOsitiops
b~ monitor more cJo.sely.h<JW S~n.ior te<.\m mernbersinterattvvi.thjuhidfteamntembers
c. l;Je.·rnore .involved with the <:l.cquisition and release of •each.team·. member
d: create t;t human resource mana.getnei;:it pl<;1,n ·
c
d. ''. >,'' ' .,, ,; ·'.''', ··:'.
"" i,, ', '", ~ ,, /,, ';//
c,
d,
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 291
aileerni:/)amegroupinc.com 719-659-3658
Executing Processes
7. b.
y b. The key term in the answer is "critical".
N a. I would eliminate this answer because of the term "all".
N c. Knowledge originating both inside and outside the organization may be captured.
N d. An important aspect of knowledge sharing is sharing across boundaries.
9. a.
Y a. If there are concerns related to safety we must investigate and take corrective
action as required.
N b. We should not force our contractors into situations where they feel unsafe.
N c. The last part of this statement makes it wrong. We need to address the safety
concern, not just make people feel better.
292 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileernil)ameirroupinc.corn 719-659-3658
Executing Processes
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 293
aileen@amegroupinc.com 719-659-3658
Executing Processes
294 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
ail een12Vamegroupinc.corn 719-659-3658
Executing Processes
y b. Accuracy is a measure of how close a measurement is to its true value and thus;
it is a measure of correctness. '.
N a. Fitness for use defines how well a product or service meets the real-world needs
it was created to satisfy.
N c. Conformance to requirements measures how successful a project is in producing
what it was created to produce.
N d. Precision is quantified by the degree to which repeated measures produce the
same results. Thus, it is a measure of exactness.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 295
aileen@amegroupinc.corn 719-659-3658
Executing Processes
296 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen10)ame&,rroupinc.com 719-659-3658
Executing Processes
N a. During the process 'of plan human resource development we want to develop our
human resource plan, including tfi'e organizational chart, staffing management plan,
etc.
N b. During the process of acquire project team we acquire the people we need for the
project team. Be aware that, in all likelihood, we will not acquire the whole team at
once, but rather in stages, based on our need for particular skill sets.
N d. During the process of manage project team we interact with our team members
in a way to help them perform their work on the project. This may include conflict
management, etc.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 297
aHeernmamegr.Q.!J_pinc.corn 719-659-3658
N
Based on the PMP" Examination Content Outline (PMI ®,June 201 5) there are seven (7) tasks
of Monitoring and Controlling. These tasks represent 25% of your exam content. l<ey
phrases associated with each task are:
Task 3 Verify that the project deliverables conform to the quality standards
Task 5 Review the issue log, update if necessary and determine correct
actions
0
The PMBOK® Guide, the most often selected reference in studying for the PMP exam, does
not list the tasks comprising the monitoring and controlling process group but emphasizes
processes instead. Although not as robust as the PMBOK® Guide for in-depth study, the
PMP. Examination Content Outline presents the tasks shown in the table above. Although
memorizing these tasks for the exam is not necessary, reviewing them from time to time is
recommended because they form the basis of the PMP® exam's questions on monitoring
and controlling. As we cover the 11 processes in the monitoring and controlling process
group in the upcoming pages, you can see how these tasks relate to the processes.
298 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
::iileerni:l)amegroupinc.corn 719-659-3658
Monitoring and Controlling Processes
r t r
It! Exam Tip: Review Figure 4~9 of the PflllBOK® Guide.
Monitor project work is what we do day by day to track, review, and report on how we are
progressing against the project plan. This process is important because the project reports
are created to keep the stakeholders informed of project status and forecasts.
Monitoring should be continuous over the life of the ControlHng helps the project manager
project. It gives the !Jroject manager and the determine what:
project management team insight into how the " corrective action is needed to get the
project is going, proj.ect back on pfan and
"' preventative action is needed to make sure
the project doesn't. get off of plan.
Process ofthe Monitoring and C::ontrolling Process Process Group composed of.11 processes
Group.
. .....
... -·. .. '
The process of tracking, reviewing, and reporting Those processes required to track, review, .and
the progress .to meet the. performance objectives orchestrate the progress and performance of
defined in the project plan. the project, identify any areas in which changes
to the plan are required, and initiate those
changes.
"' the baselines of the project plan are used to help you see how your project is
progressing against the plan
The management plans are used to help you control the project
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 299
aileen@amegroupinc.com 719-659-3658
Monitoring and Controlling Processes
Cost fore.casts - these forecasts come from the control cost process. They
help you understand how your project is performing against the cost baseline and if
you need to request changes.
Meetings -used to help you monitor and control project work. Remember the
types of meetings and rules for meetings?
EXAM Al.I monitoring and controlling processes and many of the executing
processes have change requests as an output.
300 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileern(-r)arnegroupinc.corn 719-659-3658
Monitoring and Controlling Processes
management -
after change requests are
approved through perform integrated change control they may lead to project
management plan updates.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 301
aileen1Glamcgroupinc.curn 719-659-3658
Monitoring and Controlling Processes
~'~~:r;~;,ij';;~?'
c. perf()rmance .reports.c ~ ·.
S,<;:ope·~aseHne·>·• · · • ./)>.·.··. \T ·. ~><••·••·•· ·•·.·.· . .· ·•
4. THe prQj~(tiJl~na ~¢n~inf()rnf~ti(>~sy~t;tn~l\1Mt5)..Js:
a. rnnsiq¢:r:~d V\l<irk . foqnante lnf~rl)Jattcm. . .
b. CO(l~i(j~.f~fil<·~nC orw·t,~.iZG!;!i(}naf.pr;o~~S;i ~s.set . < •.
.C:\·.t!Joh~~dt~~hnfi;iueofmonitorc~!?99()n~rn1·pr9jectWork
a tool ~r:\g technique of integr:ated c~al)gecontrol
Wht~W~~f~~~~t~11~wi~~·'st~~~~;~~~$ i$:,ru~ a~qut . requests: . . . . . ·. .·.. .
rn,ost ~011it~r:Jn9rcr(Id <=:o,ntn:Hling.r:>rqcesseshaye•Ehange requests as<9µtput
(il11.exety~!!il9P~~~es~~~~~~e~p8;nge;requests as outPllt ·
c. ·au pl infr~r9ces.~e.5.·na){echa.nge requests ·as.•output
d . au ini.t ;n·g.prQ.<::~sse!t:bave chang.erequests as output
···<·······.·· i~~~:tk~~~~~~r~l•.tif.1~.~.·deli\fer~bf esi·.•du~·toaay. dd••.•l1.rit meet. the
· · · · · · ·. f.1.t1eSt 11~ be~•J gen.~r~~gd. ~nfj,~pproved,. Tile
irY}l~Hf~~Hyano.t~er name fon · ·· ·
7.. ,t seerns thJ01t pr~jec~.~cdvi~i~snever follow the· sequence of .the pfoject plan. what
systen:i may help a.ddress tf-dsproblem?
.a. the configuration management sYstem
b. thechangec.ontrol system
c. the inf.orm.ation distributi9n system
d .. the work authorization system
302 © Janumy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileenrmamq..,rroupinc.corn 719-659-3658
Monitoring and Controlling Processes
l s
L d. PMBOK® Guide: Figure 4-7
y d. The project plan and the approved changes are inputs to direct and manage
project work.
N a. Change requests are an output of monitor and control project work.
N b. Approved changes are an output, not input, of perform integrated change control.
N c. Approved changes are not an input or output of develop project management
plan.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 303
aileen@arnegroqpinc.corn 719-659-3658
Monitoring and Controlling Processes
r n t
liZI'· Exam ReviewFigure4~11 ofthe·PMBOK® Guide.
Perform integrated change control is the process where change requests are evaluated and
either approved or rejected. Notice Figure 4-11 in the PMBOK® Guide. On the left hand side
of this Figure, we can see that change requests come from many processes (most of the
monitoring and controlling processes and many of the executing processes).
It is important to ensure that only approved changes make it into the documents.
A few important ideas about perform integrated change control
0 Change requests may come from any stakeholder
.. Change requests should always be put in writing
'" When a change request is initiated:
1. Evaluate the change request to see how each of the six constraints may be
affected.
2. Determine options along with a recommendation
a. One recommendation may be to not accept the change request
b. Another recommendation may be to accept the change request but
add X amount of money to the budget and Y amount of time to the
schedule
3. Get change approved through the change control board (CCB)
4. If the customer is not on CCB, get change approved through customer
'" This is a high level way to think about integrated change control.
Project management plan - this plan contains information that will help
us with change control.
.. Change management plan
.. Configuration management plan
.. Scope baseline- scope changes may drive changes to other baselines
304 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc.com 719-659-3658
Monitoring and Controlling Processes
Change requests - this is the only process where change requests are an
input. Remember that all change requests are processed for approval or rejection
through integrated change control.
lit EXAM TIP: .· Ccmective .actiorl <lnd, preventative acti011 affect performance
agains.phe baselines, not the baselines themselves.
- the change control board (or boards) will have meetings to evaluate
change requests and approve or reject changes.
© Janumy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 305
aileen@amegI.Ql!.pincJ;om 719-659-3658
Monitoring and Controlling Processes
Question• You h~vejust been hal1c1E!d achange request. Your team member tel.ls you that
the change will lead to .a three week delCl.Y i.n project completion; What should .you do
next: ·
a. recommend optie:mstoyour manC).gement ..
b, make ,the changE! as soonas possibl:e ~o as t8 shorten the three week.de!ay
c. rejecqhe change since itwill delaythe.project
cl. evaluate the change request
"' If the approved change requests have an effect on the project besides the project
scope, then the corresponding schedule baseline and cost baselines are revised and
reissued to reflect the approved changes.
Updating baselines -
"' The schedule baseline may be updated to reflect changes caused by schedule
compression techniques.
e In some cases, cost variances can be so severe that a revised cost baseline is needed
to provide a realistic basis for performance measurement.
306 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileerni:/Jmnegroupinc.com 719-659-3658
Monitoring and Controlling Processes
rnana9 ~rnent>b;
...
f,oc(Jsed .op l:i~setlnes ··.<... > ..·
be ~~~n!le·rn~~ci.geITlent is focused on confrguriltion control is
foc:usea on baselines·•
c..• a corip~w~tic>n ma11<:tgernent< RJ!Owterge base arid change contrql pfocedures are
corJ~i~ered~~nf~rPris7 environmental fa<::to~s .. ··.· ·. <•.• ..·. ·......... · · ·(' \ } • ·· . ./ ···•·
d;. ··ci.. config·~r<:ltion· rnanageinent 1<901Nlrd9.~ b,ase .• i~>c.onsi~ered a~ organizatiqnalJlr(j~ess
a.sset whlle change control/prpcedures are;considered.e~terprtse envirn,nmenfat·factors
6. thecf'aangefog.isa(n):
a. subset of the project plan
b .. PfO:i~C(d()c~rnent. · . .. . ..·
c. subsetoftheworkauthorization system
d .. enterprise environmentalfactor
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 307
ailcerHi:/Jamegroupinc.com 719-659-3658
Monitoring and Controlling Processes
308 © January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
ailecwiDarnegroupinc.com 719-659-3658
Monitoring and Controlling Processes
RM I E s
1. b. PMBOK® Guide: Section 4.5
y b. The primary purpose of perform integrated change control is to approve or reject
change requests.
N a. and d. Change requests are an output of direct and manage project work and of
monitor and control project work and therefore cannot be approved or rejected in
these processes.
N c. Change requests are not an input to develop a project management plan and
therefore cannot be approved or rejected in this process.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 309
aileewa)amegruupinc.corn 719-659-3658
Monitoring and Controlling Processes
t I
Iii Exam Tip: Review Figure sq 7 of.the PMBOK® Guide.
CONTROL SCOPE, CONTROL SCHEDULE, and CONTROL COST are similar to each
other. Seeing trends in processes may make the processes easier to understand and
remember. We will look at these three processes one after the other in this book.
Monitoring how the project is f\/lohitoring how the project ls Monitoring how the
performing from a scope performing .from a• schedule project is performing from
standpoint standpoint
... ··' .,
a. cost standpoint •
Managing changes to the Man,agil1g changes to the Managing changes to the
scope baselin.e .schedule baseline cost baseline
INPUTs scope
Project management plan - contains multiple documents that we may
use now .
., Scope baseline- made up of three documents:
o the scope statement
o the WBS
o the WBS dictionary
., Other plans inside the project management plan:
• Scope management plan- describes how to develop and manage scope
"' Change management plan- defines how we make changes
., Configuration management plan- defines items that fall under the
configuration management system and how to make changes to those
items
"' Requirements management plan- describes how to manage requirements
- related to scope
310 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc.com 719-659-3658
Monitoring and Controlling Processes
- related to scope
TECHNIQUEs
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 311
aiieen1l/),arnegn>upinc.com 719-659-3658
Monitoring and Controlling Processes
l. Which of.the·foflowingisaninp1.ftof~ontrol.scope?
a'. cost. baseline · · ·
b> . !)ch~dl;l.le baseline
c,. scoi)e baseline ..
cf, performarn:;e measurement baseline
,, "
·
"
2~ .Tne cn~nge >re:~u~sts th(:lt are ~n output of .validate sc;ope become· an ·input of
wnkh pro<;ess? . . . . . ..
a. de\f¢t9pproj~ct ~~ rhentplaQ.
· t:, ..,rnpnJ;tpfa.'}f19ont~o ...• ~ojed\J1'otk
. J:t.: :t:>,~f19rlJ1;int~g:r~ted ~?~ng~,~ontm1<•.··
q.. c1~$e·.proJectli)r:p.has~;/ · · ·
~ivaii~~~~ ·
~·P
x· ~q.H9 •....··. ··.·•· .~~~.·'{·)"';:>····
· g~ qo.ntrqFs<Jl@p"e ·. ·
•4. ~9rki~~rt~~~~nc~'i~~~rrnati~~;~is«1~';hput
a .. de~~lop.p170Je~ 111an.:t9ernent pJ~n ·
b'. .Jnonite,;r and cont.r,olJ?roiect;\lllor~
· c. pe~f9rm .(nt~§Jratecl cfgmge contr()I
d: t2los~;p(ojector pllqs.e ·
,... - '.... -:: .-: •' ''.
5~ S:t$p~~r~~s;fJs an<ltii~·r.IJ.~~ef()r;
a, q~contrt:>ll~d e)(pa:n~ron ofproj~ct .s~pl'.J~ · ·•· ·. .·.• /. . .·•
.· b;. !sr,naik~9tu19e5c t~~t ~r~Prgf~s,se<jtthrough the. ch,a~g~· ~g~tr0Jsyste111
C. chan~estb~tare rejected•dt;!'f(ng the change controlpr~KeSS
d, c:haf:)ges £;entto iritegrated.cl:lange.control for processing
- ·:_. . _ ':·"· - ' "; ... - "''."y-;.,·:. ::'.,' ''.: ·_;_::.,:'.:·~ -' :· .:: '"" : ,/ '
312 © Janumy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileernmarne~'l·oupinc.com 719-659-3658
Monitoring and Controlling Processes
.. .
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 313
aileen@amegroupinc.com 719-659-3658
Monitoring and Controlling Processes
NTROLSCO - Solutions
1. (. PMBOK® Guide: Section 5.6.1.1
y c. Since the process is about scope, the input will be the scope baseline.
N a. The cost baseline is an input of control cost.
N b. The schedule baseline is an input of control schedule.
N d. The performance measurement baseline integrates scope, schedule, and cost.
314 © Janumy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aiken@arnegroupinc.com 719-659-3658
Monitoring and Controlling Processes
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 315
aile<en@amegroupinc.com 719-659-3658
Monitoring and Controlling Processes
nt
ReviewiFigl;Jre 6~23 ofthePMBOK®·Guide.
Control scope, control schedule, and control cost are similar to each other. Seeing
trends in processes may make the processes easier to understand and remember.
Monitoring how the project is Monitoring how the project is. Monitoring how the project
performing from a scope performing from a schedule is performing from a .cost
standpoint standpoint standpoint
Managing changes to the scope Managing changes tO the schedule · Managing changes to the
baseline baseHne cost baseline
INPUTs schedule
316 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileenr(iJarnegroupinc.com 719-659-3658
Monitoring and Controlling Processes
"' Trend analysis- collects dp.ta to see if project performance is getting better
or worse against the schedule baseline.
"' Critical path method- looks at how the project is performing on the critical
path.
"' Critical chain method- looks at how the project is performing on the critical
chain. Specifically asks if we have enough buffer left to protect the project
end date.
"' Earned value method- earned value looks at schedule performance based on
what work should be complete (from the schedule baseline) to what work is
complete. Much more on this when we get to control costs.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 317
aileen!Zl)amegroupinc.com 719-659-3658
Monitoring and Controlling Processes
t t
0 EX~rnTip:ReviewFigure7-J 1 of the PMl10K®.Guide:
Control Scope, Control Schedule, and Control Costs are similar to each other. Seeing
trends in processes may make the processes easier to understand and remember.
Monitoring how the project is [Vfonitoril1g how the project is Monitoring how th.e project is
performing from a scope performing from a schedule · performing from a cost
standpoint standpoint stand poi ht
Managing changes to the scope Managihg 'chang.es to the sc.hedule Managing changes to the cost
baseline bi:lselfne baseline
We already reviewed Control scope and Control schedule. Now, do you see how
control cost is similar?
0. EXt(MTlf:Noti¢e,.h.o~~o~e§fJhe;f~PYtsh~y~m.itchlf19°'u{puts.
As an example: the rost b~selin~ is>an inputi"lnd tFre.cgstbaseJine updates are th~ Qµtputs.
318 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileernl:/J,amegroupinc.com 719-659-3658
Monitoring and Controlling Processes
Cost forecasts - based on actual performance. Now that we know how the
project is performing against the cost baseline we can forecast future performance.
Scope baseline. (scope statement, WBS, and Create WBS Control scope
WBS .Dictionary)
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 319
aileenrZDameg;roupinc.cum 719-659-3658
Monitoring and Controlling Processes
Critical Terms:
320 © Jannary 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@arnegroupinc.com 719-659-3658
Monitoring and Controlling Processes
Let's walk through an Earned Value example using the scenario below.
Yoq ar~ l:>Ui ldlr\g a fence; foiyour tJtjrses. Th.e J~.~cie wjll ~avffollr sJd~s, .~ll<exattly. the
same ... 't?.urb~dget for the,Prpje9t is $400, or $190 per side. The.$,Ch~quleJqrthe project
is. foµr day5,;pne.siqe.p~.rqay,·'69u started.the proJect.on· Mondav.·m.orr1ng:Jtfs noyv the
end of the day<onTuesday; X91uhave 2~%oftlle tot(l.!work complete. You have spent
$400 for thework, that is complete. ·
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 321
aileen@amegroupinc.com 719-659-3658
Monitoring and Controlling Processes
Earned Value .
Exarripl~ 2. What is the earned value as,oftoc:lay?
. a. $ 100 ·
b. $ 200
' Ci $ 400.
d>$ 1600.
~ead RM~QK®/;;~Lqe, page ?>18, . Ori, earr1ed Vallje .• EV (e~r,nedvaJue)js the blldget~c! cosfqf
the,wo,f k performEr,cf; ·····I~~ s<::en~riq stat~$; !'¥ou. ~ave.· 2S% of the tgtal work c9mplete/ J:he
,. bLl~get;f9T:}he/~Qt~l.proJes~ is$4QO. Tp.~refore.x;qu h~ye/2~9ij·.of ·<:1• $400 projec:;t compl.ete.
Tne·value<.of .tfrework•compl:ete is{$lOJh":Therefore, E\l:::i: $1 oo, Ans.wen a .
. . Aqtaa1J~ost .•.•.• • >.,;r;~;: .· · ....• !;/>.~ ':Yt:·l ·; •·; '.·. . . .,.• i;:1, ;i·~• .•~
E.){i!Jflp'le 3o. Wltafjsthe (1.CttJ~l COstffortfre..prQJect( . ·'':.• ·••/ '/<
. . ·. . •.
Readf~~()Kl@;Gqide,pag~·2l8cStl~. ·P~ra9raphori;·actualcost •.. A§.(ac~~alcq~t).is tlJ.e,~moyrit·
. ()f ·n:t?ney$1JE1rt:f6r,J9e · k.cerpple,t~cj. }[bf! q.~estton.s~~te~ ..·1Y991iav,e spepf $400/for the
work1tJ1at.is :Compl~t~'· refQi;e;:AXi?:ii' $,4(10.< Ahswei: <:. · · · · · · · • · ·
' ,,>//>-'~' ·' ·::"\"/!';:',. ;~:>·:> ''.~:;:,,';.:\.: ~'.:\' '\·.·.:· '<,·. \
Sch~ff ulE!/Variance i.X~ ·•.• ....·•. : < f ;' '..•.•.••.•.• ··•. '
Example~: The9t9J¢ct sc:he.~~;le v~~ianc~ls·:
1
a, -$> ·3QO, ·• · • ·• y·· ···.;· · · \?.· ·• ·•·• ·
b;;:$ 200< . > .. } ·~. <;. > .••.•.••
322 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileenrZ1)amemlntpinc.com 719-659-3658
Monitoring and Controlling Processes
Schedule. . Performance
. ··..· . . ·..
Index.· .(SPI).
. . . . . •!
Example 6. The schedule performance index for the scenario is:
a: o,s
Q; 1
c. 0.25
d. LS .. · .. < .•. ·. . ··. ·.·.... ·... .. . .· ..· ·.
.· Read f'MBOK® Guide page 219, the.paragraph cm schedµle performance Index. SPl=EV/PY,i,,
100/200""' }'2'.":'. 0:5. Answer a. Sil'.lce the. SPI is l~ssthan one, the project Is running behind
s~hedule'.. What t~is re(lllymeans i~ th~t the projectisprogressingat %the .rate expested.
We expected to hav~ tvvo sides complete as oft?day and we only have one side complete.
NOTE> iftheSPl:=l ·t.he prpJec:t is n,1nnin~.9n schedul~.
· If.the .Sf'I iS.gxea.ter.than one the project is running ahead of sched'ule .(a g0 qd tiling).
~.,6:zs
d~.:1;,.s···<• .>•>..·> .
• .· ·.• •· ·.· • .:, ,.>· ·•· .. :. ·...;,<.•.
·>
J •.. 1•... • . . •
~ea~ P[Vf.~qt<.® Guide p~ge •• ~p9;.the> parqgragr on cost performance. ind~x. tl'.)1= E\f(~t==
lOP14:98""J 14"' .z·~.~ . Answer f<·Sins~ tn~ pPIJ~ l~ss .than on~ the prnje~~ is run.~in9.pVer
5
EAC.::{·~At:;/C,:P;I).·;= $.40Q/(.25J~ ll
600.:••· We.·no~.~.xpec:t .~hee~tire .• project·.r9·cost ...$160() •.
· Ans~~r d. ·vv~s~~:\nt ~f-lOpfcn·.the fl~St sid~·•··lfvve continue..:to spend•at the. sarrtera.te e~ch
srdewULcosf $400. ··.:Sincetnere . are four sides the estimate.tor.the.total. project is 4sides'~
$400/side = $1600; . ·.. · . · ·
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 323
aileenril!,amegroupinc.com 719-659-3658
Monitoring and Controlling Processes
·v~c-v~ri~nce ·c()rhci1~ti6.~• · · · •
....·. .·; \.•.·scenariowhati$tl"le
.• at. .qn.•theabove
.· Example.Jl: Based •.<·c:.}: :• .· · · · · · .· .'•· · · · · · · · ~·.· · · · · · j·•· ·L/><•·
· · · ·.· · .·. .·····················/j;•i•.••. ··········•·· ........• ... ·
V.AC·(va:riance at completion)fbrthe
' proje~t?. · ·· ···· • · •.: < · · > · tj, ·. \ ). ' ... ) . . · · <~ • . ·.·
a,. ·$1.609.
b/.-~1290··
·. <U·: ·'
·•/<·.···.•·· .· .·.
!J~.
·• . . ·:·
>• .•\1'
··;:;>• •...
••.•.
•~
·····y···:··· . . :... .
<•<··• . ••. ;
·y
....•... ··>··/>
'C .
. "$l600 ·.... . . . • . . ····- ...... ·•·. .. . . . . .. ·. •0. •· - •.. .
•·VAC
·~ · · · ;$1600 .·..•.••.. ··•·• c:~ . ·- ···••>\·. ·..• ·•. ·~ c-~J:?\; ·;.> :·!;:· . .·;:>······ ~.:.·\\···
i~ ·.f"lol/V. mu~hl(lle e}\pectt9ya1yfrQrn ~t:tebu?g~t,.,~inq;i lfu~ bu~~.et was.;$400 (tl'lt3>'s.pur
•••.. -. ••.••.. ··••··••· ... ··•·••·••
BAC) .ancf our .es.tlttt~te.to com pl~te the yv~.O;le-prQject i.s;$l 60~ {(Ills ts ourJ~~C~<then o~t¥AC:
fs -$1200, tn.e af1~W~l\i5.d,.t"lega~.iV:E? h~J11Qe~ bec~r;Jsewe txpe~t to: overrun th~p[Oject
budget. lfyoulikeeqµations: VAC~ B,z\f>EAc,;;, 40Q-l600=· :.1200.
ETC is hoWmuchmoreweestirnatewe;need;.tespend<ove.riNhatweh~vealr)~dY.speri.t··. ~e
are estimC(ting a total co~t ()f $J\6qo~ w~.hayf! ~lready spent .$4QP. Therefor~ 9L1rJTC is
$1,200, . ... · . ·.·.· . · ·. . ·· . ·..· . ·.. . . . . .· .
If you li.ke equations:/·................. .· •/.. ..•. . ·
ETC= Ej.\C-AC:;; $1.,609~ $400=;$1,2.00;
Under budget
324 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileerl((/)amegroupinc.com 719-659-3658
Monitoring and Controlling Processes
Trick- CPI and SPI indexes greater ~han one are good, less than one are bad.
Fixed formula- a specific percentage of the PV (planned value) is assigned to the start
of a work package (or activity) and the remaining percentage is assigned to the
completion. Often used for smaller work packages.
0/1 00 rule. The activity obtains 0% credit when the activity begins and 1 00% credit
when the activity is completed. The 0/100 rule is often used for material delivery.
20/80 rule. The activity obtains 20% credit when the activity begins and 80% credit
when the activity is completed.
50/50 rule. The activity obtains 50% credit when the activity begins and 50% credit
when the activity is completed.
Weighted milestone- this method breaks the work package into milestones. A
weighted value is assigned to the completion (not partial completion) of each
milestone. Often used for longer work packages with tangible outputs.
Percent complete- at the end of each time period the percent complete of the work
package is multiplied by the BAC of the work package to calculate the earned value
(EV). For this method to have real meaning, the measurement of percent complete
should be as objective as possible.
Ex. The value (BAC) of the work package is $1 000. 75% of the work is complete and
therefore the EV (earned value) for the work package is 75% of $1000= $750.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 325
aileent?iJamegrnupinc.com 719-659-3658
Monitoring and Controlling Processes
taniroFs5~ge~.:~~~·~r~l
a., wo.rk
1
~~h~~~~J$,a~·cr,b~ritr.01~iostsaff~¢l~eW~~f<>~i~~t
~~.r;fo)?m.al'}e<a m~~~u11~!11ents
· ··· ·· · ·. · ·· ··· ·· ·· · ·· ·
ik·<;~trl•m<rn:
· · ·
'· b, workperforma;nc~l~for;mati0n
c, wprk p~gprmanfe data· ··
cf. va,rianc;e/at1alysis.
.· ~····~~rtle~,S~i~e·rtl~ria~~ffi~nti~~a··i~~!;~na. i~Eh~iq~~<·6rw.~i~~·pfbc;~§~;··
<t-• plarr?0~5 ajanagem,eni · · · · ·· · · ··
b ;<e~thnat~·•.c6sts ..·
c.' •cqntr.otso?ts
d, d~terf1'linebuqget
326 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileenrl"Damegroupinc.com 719-659-3658
Monitoring and Controlling Processes
14 .. Ill~P.l;l~ned.vi;llue (PV)
(EV) is $3()0;: The sc11t.ea1me
··a~:··$4Q.o
b.. ~$JOO
C; ~.$200
d.$100
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 327
aileen@arnegroupinc.com 719-659-3658
Monitoring and Controlling Processes
17.. Your orgctnization wlHbe using E!arned value for the first time. You
diffe.rent types of work packagesshg(Jllq utili;zedifferent earned v,alu:e
methods. Worf<. packages a$sodated with equipment deliveries often
a; the O/lOO rule · · ·
b. the20/80rule
c the 50/50 rule
. d. the 100/0 rµle
328 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@arnegroupinc.com 719-659-3658
Monitoring and Controlling Processes
L L s
1. a. PMBOK® Guide: Section 5.6.1.1
y a. The scope baseline is an input of control scope.
N b. The schedule baseline is an input of control schedule.
N c. The cost baseline is an input of controls costs.
N d. The scope baseline would not be an input of a schedule process.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 329
aileen1Zhame;,,T1·oupinc.com 719-659-3658
Monitoring and Controlling Processes
330 © Januaiy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileerH(/Jamcgroupinc.com 719-659-3658
Monitoring and Controlling Processes
Control Quality and Validate Srnpe -: Understand the terms deliverables, verified
deliverables and accepted deliverables.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 331
aikewi/)amei,,,IToupinc.com 719-659-3658
Monitoring and Controlling Processes
nt I
Tip~ Review Figure s~12 ofthe PM BOK® Guide.
······-·············--·-···--
Keeping errors out of the process Catching errors before the customer does
Example: A person must be 48 inches tall to ride Example: You are 65 inches tall. Your son is 46
the roller coaster, Your son ls 46 inches tall and inches tall.
therefore he is not allowed to ride.
332 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aitecn@arnegroupinc.com 719-659-3658
Monitoring and Controlling Processes
Work performance data - this is the raw data related to elements of the
project. It is an output of direct and manage project work.
Seven basic quality tools- at this point you should recognize what tools make-up this
list.
"" Cause and effect diagrams
"" Flowcharts
"" Checksheets
"" Pareto diagrams
"" Histograms
"" Control charts
"" Scatter diagrams
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 333
aileen@amegjll!l_pinc.corn 719-659-3658
Monitoring and Controlling Processes
JtJ· .EXAM TIP; Audits ill gene rat r'eferto processes while insf}ections refer to deliverables
and·prdduct5,Therefore1 vve are mQre ljkely to:
·• Audi\C! process (and not a deliverable),
• ln~pect a deliverable (and not a process):
T~is little tip may help you get .multiple 9µestions on the exam correct,
334 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileern{{)amerzroupinc.com 719-659-3658
Monitoring and Controlling Processes
l pl~ e s
s~ O.uall~~ce>n
a. an input: ofc / quality
b. an inpu(of perf();rrtf.quality assurarke.
c: an.·.input.of.vali~ftt~~cop~
d. · an hwut ofciirectanc;I.
'\',
l"tlStnage project work
'~. '
Quality metdC::$.are:
a. inputs ofva(idate sC:qpe
b. outputs of validate scope
c. inputs of.control quality
d. outputs of .control qualitY
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 335
aileernmamegroupinc.com 719-659-3658
Monitoring and Controlling Processes
· lO~ Co.n.tt:PI qua,lity i~:./ > <>i. •· ..•. ··.•.... . . .... · . ·· .• ·. . . •. •·.·.·• ...• . . . . .· ·,
a... ·.·ai:;>pl~ing•;the pJan111;ed; systemati.c qu~litY;.a~tivities. t(} ensure .that•·the project··em,pfoys
all,pm~ess;es;n~~de{.f•t(lJ11~~t.re9yirerrie.Qts . •.••.•. •....· •. . · ·.....······ . . <<.>
b, id~~~ifvtrgwhigb q~ality·stand(l~d~.~~erel~y~ntt~.the.·•pmje~~.and•. detertpfning ·nowfo
satisfy;·t~em•; ····•i ~, > ···.····J'•;•·· •....·.·.· .•. :.·'.•·· . ·x.......................•··... / • . ··. ..·t. .....•.·•· ...... ·•<
.··•·•··.··.··•·· ··..
336 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aikcn@arnebrroupinc.com 719-659-3658
Monitoring and Controlling Processes
l u s
L d. PMBOK® Guide: Section 5.5.3.1
y d. Accepted deliverables are an output of validate scope.
N a. Deliverables are an input of control quality.
N b. Verified deliverables are an output of control quality.
N c. Verified deliverables are an input of validate scope.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 337
aikenrmamerQ:Q!!pinc.com 719-659-3658
Monitoring and Controlling Processes
y c. Quality metrics are an output of plan quality and an input of control quality and
also perform quality assurance.
N a. and b. Quality metrics are not an input or an output of validate scope.
N d. Verified deliverables are an output of control quality.
338 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
ai leen12/)amegroupinc.com 719-659-3658
Monitoring and Controlling Processes
Ii
Tip; Review Figure 5-1 5 of the PMBOK® Guide.
The process validate scope is often confused with the process of control quality. Here
is a table to get at the high level differences.
fierformed internally
Usually performed before validate scope Usually performed after control quality
Product may fail control quality and the customer Pr.oduct may pass control quality and the
may accept the .product anyway as part of validate customer may not accept the product as part of
scope validate scope
Input of control quality is: deliverables (from direct Input of validate scope is verified deliverables
and.manage project work) (from control quality)
Output of control quality is: verified (meaning Output of validate scope is: accepted
correct) deliverables deliverables
~. E,XA.~ TIP,: ValkJ~te s99i;>eJs> not about maJdng sllre. the customer agrE!es with o~r
pl.arysf<Jr~~ope, 'feUii~t~ scope is. a process of monitoring and controlling. It is.· about
maJ<:ing.sure thecust9merac;cept$the·complete.ddeliverables.
Project plan - the plan includes two documents that we will use at the point:
e Scope management plan - since we are in the scope knowledge area I hope
it makes sense now that the scope management plan tells us the processes
for obtaining acceptance of the completed scope from our customer.
e Scope baseline - contains 3 documents that are used to ensure we are
delivering everything we said we would deliver. The 3 documents of the scope
baseline include: Scope statement, WBS, and WBS Dictionary.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 339
aileenr(/)arnegrnupinc.com 719-659-3658
Monitoring and Controlling Processes
340 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
ailcerna)arnegroupinc.com 719-659-3658
Monitoring and Controlling Processes
VAU pie e s
~cc;:ep~ed (JeHyerabl~s
a. a~
irmu,t ofcontrol quality
b. a,n output of control q4ality
c. at) inpt1tofvalipates.cqpe
d. an outputof vaHdatesc9pe
4, \)~ti{~~didel
an
a .... tnpu~ ~f.y<;lli
b. ~nlf'lpu~9fcoptl'
c.. an lnput'9fdftett ..... rn~~age projectyvprk
d. an outpqtqfva;!Jdate scope ·
Sr V~~~f.i~k~~tiy~r~b,.~~:
.cL·•·.•. 11~ye .P~~S'e(:I. tHe vaJidat~.. ~coi::>;~
'<< ..... c.
~,w
.
. . .~~~~h~"follo~i~~····1s··a~Yri~~t·•··i~to·v~11date
ti;; ,11Vox~,;~~rfor~anc:e111fqrrn,a,tlqp ·
, . /·. · · ·· · ·· · · · ·· · · ·
Jdrrtj~f1~e ci:a:~~.
"'"' ..,11.J'' "'
.c;;,::'fvQ:r,~perftjrmarice r~I?:~f:fa;. ·
Cl.·. qualify me trio~
; •• ' , • • ' ' ' - 0 '. -· ' - :·._-'' ; ' ' '·)_"'.' ~::. ' ; ' -_ ',' / /','; ' ' ''.,,"_ N :. ' ~·;; ''' ' ',' ;' '~
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 341
aileen@amegroupinc.com 719-659-3658
Monitoring and Controlling Processes
VAUDATE PE - Solutions
1. d. PMBOK® Guide: Section 5.5.3.1
y d. Accepted deliverables are an output of validate scope.
N a. Deliverables are an input of control quality.
N b. Verified deliverables are an output of control quality.
N c. Verified deliverables are an input of validate scope.
342 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
~c\'.Illi~~rr!l!JR.llli~ill 71 9-65 9-3658
Monitoring and Controlling Processes
. m
t I I
In this process we follow the communications In this process we .ask if the communications
plan. plan is working and we may recommend
changes to the plan,
002 Terry moved off Medium Alex April 14, Complete April 1, Jose
project - need 2013 2013 brought
replacement on team to
replace
Terry
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 343
ailecnil:/)amegroupinc.com 719-659-3658
Monitoring and Controlling Processes
Meetings - this is a tool and technique of many processes. There are three types
of meetings.
• Information exchange- to give updates to other parties
" Brainstorming, etc.- to generate ideas
® Decision-making- to come to a decision
344 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileern(i),amer.'J'oupinc.com 719-659-3658
Monitoring and Controlling Processes
l MM ons
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 345
aiken@amegroupinc.com 719-659-3658
Monitoring and Controlling Processes
346 © Januaiy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileerna)amegroupinc.corn 719-659-3658
Monitoring and Controlling Processes
t I
It! Exam Tip: Review Figure 11 .. 6 ofth~ PMBOK® Guide.
Risk register - all the information we have so far on the project risks are in the
risk register.
Work performance data - this is raw data from the direct and manage
project work process. We will review this data to check for new risks, etc.
Work performance -
these are the reports that compare what is
actually occurring on the project to our project plan. We will review these reports to
check for new risks, etc.
Variance and trend analysis -we want to review project variances (cost
variance, schedule variance, etc.) as well as trends (cost performance index, schedule
performance index, etc.) to review risks in the variances and trends.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 347
aileenri'/)amcgroupinc.com 719-659-3658
Monitoring and Controlling Processes
Tricky·.·q1.1esti9,l on c6rtting~f1ty:
SolUtion:HqlJefUHy,ygu•vvere•ab.letosee thatthisunusedcontirygencyshoul<:{her:et~(ned
to free. up resources for qth~r ,p~oject,s and;'or operations; lfwe require it)ater for a new
risk we would need tpitequestit<:i.F)d beC\ble tojus~ifythat request. ·
348 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
ai leen<(iJamegrnupinc.com 719-659-3658
Monitoring and Controlling Processes
l pie s
l..
a:
b.
c
d:
6~
pf6J~c'F sev
r~sp~1;1s~ plan~ in place.
a. cpnt.in9~ricyptan. ·
b. fa.Hback; plan'
c. backup<plan
d~ workaround
7. ProJ~ctdsks are:
a. always negative
b. always positive
c. may be positive or negative
d. rnc:\Y l;H:~gln positlv~.butaJwayst4r11
8. Workarounds are:
a. unplanned before the risk~vent ocel!rs
b. developeato aid in risk .avoi.dance
c. associated with risk mltig~tioll
d. the.same as contingency plans
© Janumy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 349
aileen@amegroupinc.com 719-659-3658
Monitoring and Controlling Processes
350 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
ailecn1aJamef,rroupinc.com 719-659-3658
Monitoring and Controlling Processes
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 351
aileen@amegroupinc,com 719-659-3658
Monitoring and Controlling Processes
t t
In the process control procurements we are ensuring that the contracted supplier is
meeting all their obligations under the contract and that we (the buyer organization)
are meeting all of our obligations.
Due to the legal implications of actions and decisions, often the contract
administrator for both the buying and the selling organization reports into an
organization separate from the project organization.
Work performance reports - these are the reports from the seller on
their work performance. We may take these reports and make them part of our work
performance reports on the project.
Work performance data - this is the raw data collected. This data will be
turned into work performance information and then later the information will be
documented in the work performance reports.
TOO Ls TECHNIQUEs
352 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileencl/)arnegroupinc.com 719-659-3658
Monitoring and Controlling Processes
some organizations this system is linked to the integrated change control system on
the project. :'
Procurement performance -
this is a review of the seller's
ability to meet the requirements of the contract. Requirements may include technical,
schedule, cost, quality, and others.
Inspections and audits -the buyer will inspect the deliverables of the seller
to ensure these deliverables meet the requirements of the contract. The buyer will
audit the seller's processes to ensure these processes meet the requirements of the
contract.
ltl EXAM TIP; Keep in. mind the~lfference ·betweknanjn,spectlo~ and anauc:Ht.
• We inspect delJv~.rables (or products).
• We audit proc~s~f s.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 353
ailcenrll)amegroupinc.com 719-659-3658
Monitoring and Controlling Processes
Other Ideas -
Privity of Contract - privity is the legal relationship between two parties of
a contract.
" Buyer A buys from Seller B who then subcontracts to Subcontractor C.
" Buyer A has privity with Seller B but not with Subcontractor C. In simplistic
terms, Buyer A should not be giving direction to Subcontractor C.
354 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileerna)amegroupinc.com 719-659-3658
Monitoring and Controlling Processes
l E pie e ons
2 ....•·'o/bkh. of.t~~/f:()I
a, lf'.1$pections foq1.,1$
b. i.nspecyons
c •..tne·.oust9m
ct w~ ~E?:rrcli:rni
3. Th~ pr r~d\~;~ih'~~···1J;• ~~ifitri;~·J1~f~~ap~disp~i~~i$:.·. .
a; litlgatk~ri / ..·.
b. arbitration •.
c: niecli'atiorl
d. negbtia~i2h
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 355
aileen((/)amegroupinc.com 719-659-3658
Monitoring and Controlling Processes
356 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileern@,amegroupinc.com 719-659-3658
Monitoring and Controlling Processes
t t
:np; Review Figure 1 3~ H of .the PMBOK® Guide.
In this process we interact with our stakeholders. The primary question to ask: Is the
stakeholder engagement strategy working? Stakeholder engagement strategies, as
found in the stakeholder management plan, may need to be adjusted.
Late delivery of
computer:: progress
systems
002 Terry moved off Medium: Alex April 14, Complete April 1, Jose brought on
project · need 2013 2013 team to replace
replacement Terry
Work performance data - this is the raw data as collected during direct
and manage project work.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 357
aileenl2vamegroupinc.com 719-659-3658
Monitoring and Controlling Processes
Change requests -as we work with our stakeholders we may request changes
on the project.
358 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
ui leenra!mnerzroupinc.com 719-659-3658
Monitoring and Controlling Processes
J~e;issiletog · d.Jhe
a: proJectdpc~ > ~··.·.
/ .••
Ii workp.e~f:C>trryanc~•data
c. project m,<;Jn~g.ement plan
d. work perf9rmanc~ infd).f frl Citt lqn
,', ,,,,;,:" ,' '''. ;;/;;,,,/ '/';' ,{,;", ',
© January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 359
aileen!GJameb'fOupinc.corn 719-659-3658
Monitoring and Controlling Processes
360 © Januaiy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen1ipamegroupinccom 719-659-3658
Monitoring and Controlling Processes
iU
The ideas discussed below are based on information provided by the PMP® Exam Content
Outline (PMI®, June 201 5) and may or may not be directly referenced in the PMBOK® Guide.
- Many organizations
that produce standards related to quality best practices. An example of a few are:
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 361
aileen@amevrnupinc.corn 719-659-3658
Monitoring and Controlling Processes
BS - British Standards are standards produced by the BSI Group. The BSI
Group produces British Standards.
Verification addresses the question: Are we building the product correctly? This
process looks at specifications, standards and guidelines. The PMBOK® Guide associates
the process Control quality with the verification process. You may remember that
verified deliverables are an output of control quality.
Validation addresses the questions: Are we building the correct product? If we place
the deliverable (or product) in the proper environment does it fulfill the needs of the
end user as expressed in the requirements? The PMBOK® Guide associates the process
validate scope with the validation process. The customer is testing the deliverable (or
product) to determine if the customer will accept the deliverable. The requirements
along with the verified deliverables are inputs of the validate scope process.
362 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileenrll),arneg;roupinc.com 719-659-3658
Monitoring and Controlling Processes
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 363
aileen@amegrnupinc.com 719-659-3658
Monitoring and Controlling Processes
. . ,.~· ·.
a .. e~trap~o~e~ses.: ) .•. .• ·•. . .. ·..•.•.·. .•. . •.. ...· ..·· .. ..... . ..
. . ·.· . ·~~qtr~11~)2i~t~J1ig~n<:~in91J~~s•
a, fortl'l:ifig, 5:.t9Ern .........·.· !TiitJg; perf())rrttigg a~d a9Journing ·. )/ ..... < ·•
!:) ••. sglf-awaren~ss;· . •~e.lf~r~gqla~igr;r 1 ,sa;~ia;lf$kilh em pa.thy and mQti\latton ·
:•·c; . w.i.~bdraw, smooth, com~romi~e;iforc;~ ang cotla,borat~
d. formal, reward, punisl:)ment ex@ertandrefe.rent ·
,,·'. . ; >
12. Change management <=C\n he a long and tedious process, In y9ur organization,
th~ last step of change managernent is often oyerlooked. From the list below, which
iternwould vo.uperformtast? ·
a .. subt11it.chang~request
b. establish or adjust 1Afork. packages
c. implementchange ff approved
d. approvedthang.e request review
364 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc.com 719-659-3658
Monitoring and Controlling Processes
14~ Ypur ~f~~ni.iatJol'l . is ~tr~ggH~g with the pere~iyec;J attitudes. a.nd. Jack. c)f
eXP~rience ?.f: ¥ou.f Y()µnger•. w~rk~rs. Many ()f ~~.¢ P;ld¢r. ·atjd m9re experience~
·workers se:emt.on9tv~lt,1e th,e 1,1siasm of tlJese.newer employees. One proactive
~ay tq µ .. . e gap isthtbli 1
• ·. . . • . . . • / > . ...•· . •.• . .
cL traini!l~•.~e~ ns for·the m.~re, ecp~ri.ence(l wor;ker~ onJhe value .ofour neWhlres
b .. rev~rse.ri;ient()ri~g ...•.·.•· · .<:
> ?/ ·.. >.· ·..·./ . > · .· . . ·
c: .•.•~ns.~I~r:l$.thatt~a.m~.. dor1C>t···l;ra,'.(e n1i)(e,~ 9~.11erel;ti9ns so.. tn~t
·
• \Norka:~$·~Jll npt·pe frllstrated/l:>Y..these youngerworl«~rs ·
d. limiti11gtlie.n1;imber o.toewbires · ·
J5. AL\t·~~e~eria. ~f ;~Or·•·las;··~r~j::t t<>,ur·t~ctn1.~P:~•fir~r~f:g~ ~m~.~nt of• ti.~~·.c~
le$SPf1~\ 1~an1e~. . ·Tn~. m.9st ·· t~'1t·.··•less()ns>·wer~·relate<;t fo.
com,m~rti.~~tio11s~ .Many,;J.~~m~,;mem ...•..... di<f n~t. ~ndef:~tan~·i1Nh?,sh2.'11d;9~;t ... · ·
info.tn1a~i9n and:l11•·what.fg~mat. M~n)f: s · old~rs.c()m,ph1i~ed ·thattij~y.Je,.ltJfJ~y
did r1~R ~av~ visibiljt}'..l!?tf!.th~.proje(;t~ ·. . . . . . • thCJ.t!~,y.str1,1.g9t~~ t9ntake
9~t?d dec:isions .1:iased.on·~·1~c~ 9f rl:'. ·. 1nu~resting"¥1scH·nJf s~it~el:lo~ders
~ta~ef;:I that they r~..ill. it:t.f?.rn:-.a,~19 . . . . . . . . . . · • · .. ·. ~~d there:fot•e l()q~ed ·. . U~tl~.·of the
' ·. .. t9 them. T~e~~fore y~u ~ave deci . . . pt1t stn:,mg focus 911 a.
tc)rf1'.aj1,1.~iea~ n,~.gei:nem. Yot.1·0.~~iE!)l~ tb~2 fir$itt~irig! ...· •. ~ is~ Y.. .. .. . < ·
9:~ cJistriQ:q~e eve 6 ~~v~rY st~.ikehold~r-. There(ore,. no stakeholder can
(,Orn(:Jlaifltb~y\JI/ f~heproJ.ectst<:lWs·; .. . .. .......
b. ppst allp.roj~ Hsi11g an.. el~c~ro11it, ~nowl.~d~e rep()sitot;y.
tnerefore, ei:i.ch :d th~ informationaJ1g onlytbe informatio11 they
requite.> ·. ·
c:. develop'a ca ,, ,, ,',,,,, ,,
Communication with
a. vertical
b. horizontal
c. up
d. down
1 The
a. official
b. ul1-official.
c. verbal
.non-verbal
©January 2016 AME Group, lnc. author Aileen Ellis, PMP, PgMP 365
aile<en@amegroupinc.com 719-659-3658
Monitoring and Controlling Processes
366 © Januaiy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileernGJ,arnebJJ'Oupinc.curn 719-659-3658
Monitoring and Controlling Processes
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 367
ailet:n@arnegroupinc.com 719-659-3658
Monitoring and Contrdlling Processes
5. b.
y b. Multiple people may be involved in creating an estimate. It is important to
include the person who will be performing the activity in the estimate if reasonable.
6. b.
y b. It is important to prioritize the items in the product backlog.
7. d.
y d. A typical knowledge transfer life cycle includes identifying, capturing, sharing,
applying, and assessing.
N a. These are the five stages of team development.
N b. These are the five process groups.
N c. This life cycle is the basis for quality improvement.
8. d.
y d. Six sigma means reducing variation and defects on any iilroduct.
N a., b. and c. Lean focuses on waste. Extra processes, extra' features, and wait time
may be examples of waste.
l 1. b. Wikipedia-Emotional Intelligence
368 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileernGlameg;roupinc.corn 719-659-3658
Monitoring and Controlling Processes
Y b. Based on Coleman's mixed model, the five main emotional intelligence constructs
are: self-awareness, self-regulation:, social skill, empathy, and motivation.
N a. These are the five stages of team development.
N c. These are five methods for conflict resolution.
N d. These are five sources of power.
14. b.
y b. Reverse mentoring is often a very proactive method to bridge the generation gap.
It allows people of different generations to get to know each other, to learn from each
other, and to value each other.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 369
aileernch1rnegJ1!.llpinc,com 719-659-3658
Monitoring and Controlling Processes
370 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aikcnrmamegroupinc.com 719-659-3658
Monitoring and Controlling Processes
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 371
ailecn1ll)amegroupinc.com 719-659-3658
Closing Process Group - Based on the PMBOK® Guide, there are two (2)
processes of closing. These processes ensure that all processes across all process
groups are finished so as to close out the phase, project or contractual obligation.
Closing may occur when all the work is completed or may occur prematurely. An
example of a premature close would be a terminated contract with a supplier.
Normally we would close out all procurements on a project before we would state
that the project is officially closed. Also releasing final resources is often the final
activity on a project.
Based on the PMP" Examination Content Outline (PMI ®,June 201 5) there are seven (7)
tasks of Closing. These tasks represent seven (7) % of your exam content. l<ey
phrases associated with each task are:
0
The PMBOK® Guide, the most often selected reference in studying for the PMP exam, does
not list the tasks comprising the closing process group but emphasizes processes instead.
Although not as robust as the PMBOK® Guide for in-depth study, the PMP" Examination
Content Outline presents the tasks shown in the table above. Although memorizing these
tasks for the exam is not necessary, reviewing them from time to time is recommended
because they form the basis of the PMP. exam's questions on closing. As we cover the two
processes in the closing process group in the upcoming pages, you can see how these tasks
relate to the processes.
372 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileeniGJ,amegroupinc,corn 719-659-3658
Closing Processes
I t
!ti Exam Tip: Review Figure 1 2.-9 ofthe PMBOK® Guide.
In the process close procurements we take the steps necessary to close-out each
procurement. This may include many administrative items (administrative close-out)
such as:
e Dealing with claims and disputes
e Managing records
Some procurements close even before all the deliverables are complete. We call this
early termination. There are three (3) types of early termination:
The contract ends because one. party believes the other party is not living
up to its obligations.
Both parties agree it is.in their mutuaJ best interest to end the contract even
though there are still. open dbligations.
The contract may stipulate that the buyer has the right to. terminate the
contract at anytime V11ithout a reason other than "it is convenient." In .some
countries the government of the country s.ets. up all .their pun:hases this
way. In reality, the .seller could also have this right stipulated in the
contract though the focus here is on the buyer having the right.
INPUTS
Project -
the procurement management plan, as a
subset of the project management plan, provides guidance on the process of close
procurements.
ltl EXAM Rernerriber the word audit is ~s~dciated with processes not deliverables. We
are auditing the procurement processes, not inspecting the del.iverables from the supplier.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 373
aileen1(/)amci!roupi11c.com 719-659-3658
Closing Processes
374 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileerna)amegroupinccom 719-659-3658
Closing Processes
p e ons
Adminiitrativ~
ro11owi~9.exc=ep~ •.• /
a, Vn~lizing.,op~.~ daims
b. ll"pdating rec0;rds . •·•· •·.
<i· ~rc8ivi.ng•lnf9n11ation < , ... •......
.. d, respon(;fjng ta;c~equ~S:tfotprqpqsals
b.
c.
ct, v' ,__ ; - , '
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 375
aileen1(/)amegrnupinc.com 719-659-3658
Closing Processes
gr·.. ·· EXAM "[IP: Rernember>the' W(frcl audit fs. a~~odate~ with· pro(]e~~~~ ~ot deliverables.
We are auditing t.t:Je procurel)1'et;1t processes, not jnspecting the deljverables from .the
supplier.· · · · · ·
N b. Mediation means bringing in a third party to help us work out the issue. If we
cannot work things out between ourselves and the supplier through negotiation, then
mediation may be a good fallback option. Mediation is preferred over litigation.
N c. Arbitration means bringing in a third party to hear both sides and make a decision
on the issue. If we cannot work things out between ourselves and the supplier
376 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
uileen@arnegroupinc.com 719-659-3658
Closing Processes
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 377
aileern2/lamef,rroupinc.com 719-659-3658
Closing Processes
r
Tip; Review Figure 4-13 of the PMBOK® Guide.
Close project or phase is the process of completing all work for the project or the
phase. Closure is measured against the scope baseline.
TECHNIQUEs of close or
Expert judgment - bring in experts to ensure all closure standards are met.
Meetings - multiple meetings may be needed at the end of the project or phase.
Ex. Lessons learned session.
378 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileerHi1)arnegroupinc.corn 719-659-3658
Closing Processes
~ EXAM TIP: The exam may ask multillJle questions about dosing the project.
We have to make sure: ·
" Completion of the proj~ct is rn,easured agaipst the project management plan, We
must make sure we. have cqmpleted thevyork .of the project.
" Completing the work of the project is not enough: We m!Jst.acijieve acceptance
from the.customer. ·
Records rriustbe managed and lessons learned collected.
The finaf .. "evel1t'1 .is to release the. final resources.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 379
ailcenrlllameg;roupinc.com 719-659-3658
Closing Processes
1....• ··Jhe projE!c~ has E!~ter~d th~ d()se pfoject or phase process. Along with the
orga~fzati9nal. pr~cess ass~ts updat~s armther critical 0,utput
a,\ verifie<;f deliv)rahle$
h•. final p.roduct,.seryi~e,·.orJeS,uittransition
· c. accepted deJiveraples
d.• procurement documents
·,, '., .·.·.·\' .. ·;· . .
380 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileerHa)ameg[Q!lpinc.com 719-659-3658
Closing Processes
s
1. b. PMBOK® Guide: Sectiorn 4.6.3.1
y b. At the close of a phase or a project, ownership of the deliverables is transferred
to the sponsor or the customer.
N a. Verified deliverables are an output of control quality. Verified means the
deliverables are correct.
N c. Accepted deliverables are an output of validate scope and an input to close
project/phase.
N d. Procurement documents are not related to this process.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 381
aileen@amc&,rroupinc.com 719-659-3658
Closing Processes
I iU
The ideas discussed below are based on information provided by the PMP® Exam Content
Outline (PMI®, June 2015) and may or may not be directly referenced in the PMBOK® Guide.
The PMIS (project management information system) may be used to gather and report
on l<Pls as well as other key success factors.
382 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aiteenrZDamegroupinc.corn 719-659-3658
Closing Processes
Ml r ons
It is strongJy recomryiended th.at you not c.ircle the answers below 5o yoµ tn<l.Y a.ttempt
t.h.e.se. questions againJater.
,, ' ,,, ,''
·
4./va,tije ~h.~~•.·.{~X£e~·w.•·h.•.en.{
~:)~e'.b ·f~ries're~e\ve the pfdJect deliverables
p; .t'1t~·h .· . . ··· ci;;frles:.:yt~ffzet.tie; prqject ?enefits •
.•· c:~l'.l~·~ep~frti~ti.¢~·~c;·E¢J'.)t ~·h·~··verified Cf eliverables
· c;I. tog bene'.fl.ciades8.c<;:epttheiJroJect.benents
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 383
aileern(1)amegroupinc.corn 719-659-3658
Closing Processes
8!/• Org~iiizations
•oft;n struggle ···te> get··.tJletjrlformation ·they e~pect•.from •. KPls.
t~pi<:;al ooistake many o~ganizati.ons miike •wh;en se~ting .~Pis is:
a-the Q(~an}zat,iQ!1.m~~es;l<Pls toq s~mple an~ ?asy t<:> understand
b-.~h~.o~gJni~~ion· relatese~PI · .o .•corp()fate.• ~n.cf prgj~ct. g9a.I? ·
>c,5h~9~Qctqi4~tioncr~
<i. tbe•ornani2:atiqn in \>m ..... fl'l·~~Js · · •· · ·• . .i . .·.•••···>·•·... · ·•
~S,Je(ldirig·indkat.0.rs.ofp~rform.an.ce
lpi )t .hA~
req~irernent~~ ........· · .•. ~~e·;i~~as llav~ Jjeen.gene.rated~ the:v7
. , !~~yr~~I~ •a~.~~.,~~~ ..·... .. . . . , .·· . . e&?"s()li~•lt~d i~ia
yi$.t1al wayte> r.~flec:;t .~~m11'1·orjalityanq dlfferem:.E!sJn•4nder:standing and fo.ge,ne:rate
new ideas, W,h. • p .cr:eativi.tyJdea is being t1!;ed: · ·
i~c.triteria ion ~nel!IYs.ls • •· ··
•·· ...•...•. ity dia~ret.t:l'Js •.·..... .•
c.. ia~~LQ'l1n9 ma.r:iP:f ng · <./
d: .r'lO:minal grpuptechn;iq.µe
1. J·<P.n···~·~g~niz~;:tfan sc:Q;r~~··.•~.r~1b·•·on;C~ertH~fstede's·
.
a, likesJJl'lc:ertaif)tyand candeatwit~ it easily ·
9.. has i;l;.pqsitiv~•·.·.i:tttit1.Jcle.•.tgwarc;l,~h~nge.
c. f'rnf~rsacompetit!v~s~irna\~· ,· x.······•
ct· hasa>lowtoleranceforunusual.behavior
· j 2.: • .• Eaj~ti.ohalJ~telli~~~~~··i;••{~~~'.ca~acity.,tQ be·~~~r~ .o~.~9f(t~qJ, . •a.ijd .. e~pre~~"··~ne'~
em9dons. af1d ~oha,ndle.lnJer~.ersqf}~ln~l~tior:i~hips.Judiclouslx a~~··empathetica.11y~
The,term.Qai.ned•pro~in.encfi!.. iPl~~5whe,nWhkhprominentp~ydwfogist p1,1blished.
· a boOk on the topic? · ·· · ·
a. · Goleman.
b. Goidratt
c•. McGregor
d. Maslow
384 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileenrc/)arnegroupinc.com 719-659-3658
Closing Processes
A1~~~~'.~··.~~i·t~~~r~o?rro~~t~i~·~~J·t1~i~t}···~~s~d.. c,n1)~istqryvdti;r;~a1i~e
ls.ag · cq1f~~tJ~ss,~ns l...... ~~;:·1 l~~~~ns l~~rned.~h~~'d ·be:
a.~ . f\ ~~·tti~y S.VP:P<Jr~..~~ . . s!r~tegicvisi(Jr(qf the orga~izatiorl . .· · ·.•· ·. ·.
q,•.·. p~.!?li · f<JD?9.~ate IJlle~r:.lt~.?:!?'~fi~t otner? \'11<lY bel'lefit .• f~qm Ye>urknowleggg
~' dlscu ec~~~~l'lt.relr~~~~·P.~r~i~s,but.~therwJ~el<eptpr!vate ·· . •. ··......... . , ..·. •
g1~1~.Qcfrm~.r1~ecl parto.fthe hlsto(;ieal. database·.for .both .t.lie.• project·.and the.perform
';'.',\\; >_',-':, ... - ,' -- _,';/'../' -.- <-' > - , . . . . •.
;,-,-,,,,;;--:,,-",,-,.,.;,'~>-----,""'-,··-,'"< ·- "/.,_.-"," //.,;,:,-,_,.- --,,, '!"/ -"-' .,,_ ;
i.•·.n.••. 9 .
; ()f9<3:rtiZation •
' ; :>:< ·,, - - ,, ' - ---
c.
. . d.
1 An information m;1n::<1ne>,md~IM!t .<::U<:Ta:>•....
a. identify sta.kehol.ders
b. 81an. s~ak~nqleler>m<:lnagement
c. man.age s~a!Zehokler enga,gement
cl: tontrdl sta~.e.hl)lder engagement
© Janumy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 385
aileenrGJ,amegroupinc.com 719-659-3658
Closing Processes
;,•·:··~~t,:i:P6~~s·~~g~~up:~ ihcl~d~~:·
ire[:/ g;.rriqnitorfog and. controlling ·
It
Ct'
···(l;
~~lfl{kll!!l:~)t;~~~~K!;~~~i~ii
d.•:::dJre~w;,i:ott ma11~ge t}roJe¢two~k·
.. · .· . .• ~~~'~J~Ji\{er~~l~:ate'.~~·~~t~~; of~ .
a:>va.r:... r~~9J~fe' >;•·0·:/i{ ; >\••.·•··. . · . ·
q'Q~\CO.t:t~JO
..ct,·
~!J~".i~()r:,phas1~A·::
./ d ·. ·• ~;rpJ.e.<=t
di (al;li:J roc:tr;iage
r
. . : •/ •• >·············<;
··. ?"'; , .. ;
Pt9J€,!tt W9r'I<
L~~~~~~~J~~l;:~~~~~t(e~··::~~~r~t~c1·.in.~~··di~iioct. Ptia~.~i.'·•t~;~~P.~ri~e~s~ro~P,.siare:
a. tt'l!;! ~attr~·~~ thesep~9J~£t p~ase,s+. > . >
. b; ··nor~~lly'.r;el'.)ceate~ffie<f~h oftfres~phas.e? .••••••.·.·.......·
<. . . . .
. ·.... ·
..
c rercitedto ~~.e.pr9e~rt,nc:t tb;e9~foize 1not.retat~cl to<Jh¢.Jir6Jectphcr~Fs ..•. · . .·
d.· relatec;l.tq proJect•rna~~g.~rne&tand,tberefqre,·r1otrelate~to1 tbe.prpjec:t.•Phases
26. So~~.i~w~:~i·~;; ~AJ~h;!,~~a~~~~;:~r:u;.
proJest"~ ~c;u;J,.dary~ >·
·~r~ n~;~~fiy;~~;if
·· · · · ·· · · · · · · ·
or~~d·~~ternal
· · ·
·i6 thE!
a: Jniti~til'l~J · ·
• b. planning
c. <:~x¢cqtJrrg
d ... mpnitQring andc9ntrolllng
386 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileenrmarnegroupinc.com 719-659-3658
Closing Processes
30. The process group that must provide feedback to implement corrective or
prev~11tive attionJs:
a. planning
b. e?(ecutlng
c.monitoring and:confr()lling
d:. implementation
a: d~yeto13sc!Jedule
c. ·....•· .. · ·•
esttitlat~.act{Vityduratiol:ls
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 387
illls:fl:ili.?2.illr!~illilll!lL£Qfil 7 I 9-6 59-36 58
Closing Processes
3. c.
y c. Organizations often look to their values to help evaluate necessary trade-offs and
make decisions.
N a. The mission of an organization is why the organization exists.
N b. The desired future state of an organization is the organization's vision.
N d. The benefits register should list the expected benefits from a project or program.
4. b.
y Value is achieved when the beneficiaries (often called the customers or end users)
utilize the project benefits.
7. c.
y c. This answer is the exception because of the word "all". The word "all" is extreme.
8. c.
y c. If we have too many l<Pls we become lost in detail and managing l<Pls becomes a
project in its own right.
388 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileerniDamegroupinc.com 719-659-3658
Closing Processes
13. a.
y a. Elevating most project decisions to the project sponsor turns the sponsor into the
project manager. Most projects sponsors do not have the time or interest in being
the project manager.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 389
aileen@amegroupinc.com 719-659-3658
Closing Processes
390 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen1IV,amegroupi11c.(oom 719-659-3658
Cross Cutting Knowledge and Skills
I ill
The ideas discussed below are based on information provided by PMP® Exam Content
Outline (PMI®, June 201 5) and may or may not be directly referenced in the PM BOK® Guide.
Applicable laws and regulations - In order to sit for the PMP® Exam
we need to have agreed to follow the Project Management Institute Code of Ethics and
Professional Conduct. It carries the obligation to comply with all laws, regulations,
and organizational and professional policies that apply. Another place on the exam
we might see a reference to laws and regulations regards the collect requirements
process. As we collect requirements, we should also perform a document analysis.
Laws may help us elicit requirements.
391 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
.illlITI!@fillJffilillJPinc.com 719-659-3658
Cross Cutting Knowledge and Skills
acumen also includes using appropriate business terms when communicating with
others in the organization.
We need to understand how our project, the work we do, and the decisions we make
affect others in the organization and the organization itself.
392 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
ailecnrmarnegnml2.filc.eorn 719-659-3658
Cross Cutting Knowledge and Skills
.. Time constraints
.. Trust
.. Quality
.. Acceptance
There are multiple decision-making models or processes. One six-phase model is:
l. Problem definition - fully explore, clarify, and define the problem
2. Problem solution generation - brainstorming multiple solutions and
discouraging premature decisions
3. Ideas to action - define evaluation criteria, rate pros and cons of alternatives,
select best solution
4. Solution action planning - involve key participants to gain acceptance and
commitment
5. Solution evaluation planning - perform post-implementation analysis,
evaluation and lessons learned
6. Evaluation of the outcome and process - evaluate how well the problem was
solved or project goals were attained (extension of previous phase)
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 393
aileen(Q),amegroupinc.com 719-659-3658
Cross Cutting Knowledge and Skills
judiciously and empathetically. Many believe that emotional intelligence may have a
strong effect on both personal as well as professional success.
394 © Januaiy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
ailecrnq>amegroupinc.com 719-659-3658
Cross Cutting Knowledge and Skills
A peer review process has many benefits. Often, a project manager is too close to
the project to recognize the items; listed above. A peer with experience in project
management may be able to point out things we cannot see. We may later be asked
to provide a peer review of someone else's project.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 395
aileen!ZDame1-,rroupinc.corn 719-659-3658
Cross Cutting Knowledge and Skills
ti
.1. Comr11unication·methods is.a t.ool and.·t~chnique of.what.process?
a: plan qum~nres?urce management . .
b. pl~n communica~ion manage111ent
: c; . identify stakehblders · ·
d. planquality
. . : . . .
4.. C:osH>~riefit
a, egimate c0,sts
b: cleterpine ~Lldgets
t. control costs ·
d. plan q(iality
a:
b.
c.
d,
396 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aikern?Damegrnupinc.corn 719-659-3658
Cross Cutting Knowledge and Skills
©January 2016 AME Group, Inc, author Aileen Ellis, PMP, PgMP 397
aileenrZDameizroupinc.com 719-659-3658
Cross Cutting Knowledge and Skills
..
. .
398 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amer.,>Toupinc.com 719-659-3658
Cross Cutting Knowledge and Skills
· 2~.jDeliv~f~bl~~~;
.a, .•cHrecf ~~d rn~ll~ ·. e.t . . .
l{\'~rl< .
b'. 'Perforirt;Cit1ali~·a~s'-!t:a <:'~· · ·
c, co11yrol qu~lity ·•.·.· .•.•. ·. .•·•. . . . . . . . .·
ct. integrated Ghang.e conttdl
~r~j~~tj~e;fJ.rrpance ~P~;~Js~ts••··~re
rrlattcige St~keholdef e~9agelT1~1'lt
·. · · · p.roJ~C:t<t~a.m . . ·
.· ..· · · . · .pr(JJe<:!tt.~.~111' .... ·. ·
ltldnito(and cqntrat.proJecfwork
Ensuring that
a. control quality
b. perform quality assurance
c. monitor and control projettwork
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 399
~~~~"'-Cf.".~~ 719-659-3658
Cross Cutting Knowledge and Skills
. d, plan ris~ir~sp0,h~e$•! ·.
; "'~ '.
rff}; Ch
·.• f ll~c~~iC9; ;y
.····.~~~r~v~d:;·~~~H9~\i~~;~e~t~~r%~n. •0,~tp.ut
~onltof ar)cl.··~o.n~Jal.·~.roj~.ctwork ·
b. ~~li~.a~~);gppe . . . / •..••..•. .·. .•.•. .•.· • <
· c tof;ftrol <quaJi~X < .. > . . ··. <; •
d. p~rforpl i ~teg.ratecl. <:ha,n.ge.<<:()i:i.tr,BI
38);·····+~~.pf:~jec~··m~~~gem
a. ~tvelqp ·P.r~~~c! .~anei;g~ ..·.. t.p
b. direct ariff1!rJ;:1.~·~~e •. proj~tt.vv9r~
. c. rl')prrtt8r and sw1trol .proje~~.'fOr~
ct: ctrrectant1 manage,proJe<;.tW9Jkali
Chang~/to~tr;ol··~~biJ;at;~~;~dr~~dt~~h~i.JJe~f. wh~t~foces~;
•. cJevelopJ~\8je,cr111~f:l~~E!ft1e,.Dt 1pl~n •
b. directantl m~n~ge pr?J~~t~ot~ · ·
c ·. w() nit~{• (lrd <:()fltr:o.lif:lrQje,dtfll!"9t~ . · · .·.•·
·perforrn···i.nt\:!grat;eC,l•diel;nge cci·f1.ttql ·
. 40. Th~.d<?CtA~~~tthatd~~~~~b~~:~~pficifliw.h at
3
·
· ('.I.. ~rojec;tc.;h~rt~I\. ·· ·· · · · · · ·
p. scqpe stateme~L ·
c, scqp~·m.('.lnage111enfplal1
d. cost baseline
400 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen<(/)arnef.r,roupinc.corn 719-659-3658
Cross Cutting Knowledge and Skills
4~. AO Of t~e .foJlo\lllil1g are .strateQi.es to deal with risks with potentially
im,pacts on projec;t objectiy~s except: · · ·
.. a, . rnitigat~ . .
h: exploit
c. share
· ·d, '•enliance
·. ~·s ... PrE!"-aSsignr1t~nt, ctl~gotiatkmi acqll~sition,, and virfoal' teams are fools and
tecbni.ql,Jes .of: ·. ··. • > (. . .• <• " .
a.. pl;;tp'h1+rna,nresource mt:tnagement
13, .. develop pr9jc;ctt~ar1l
c. acquire projecttea,m
d. mana,ge prnjettt~am
\ '.' ,·
,. ' ''• •' ',·.
47. ·Alterrfatiye
a:· eollect requireJn
IJ. ·define scope ·
c: <:?llecfr~quiremenf:sal1d d.efine
d~ .defineactlV.itles
© .Tanumy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 401
ailcenr(/)amegroupinc.corn 719-659-3658
Cross Cutting Knowledge and Skills
The risks pla«;:ed oil aVl{atch list for contirmed monitoring. usually indude:
a. risk~ reqµiring a ~ear-tel'f'rl>respopse . . . . ·. > .· .
b. risks assessed· as irnportant,.ha~ed 2n qualJtative risk·allalysis
c. risks ~ssess.ed . as ~otirnrortan~.;~cl~ed qualitative risk· analy~is. cm
·· d. riskr~quiring
·· .. ·.:-: .. ·.· ··-.·-
•,.·.
additiunaJanalysis
·.··. . · .' ..
and.response
.. ·
;·
. . - . .
52. Tljfcorifigµrati()n mana,~~Tent plan is an output of what process?
a;<d~v~l.qp pr:9jec,:t mC:ln~gem.~nt pl~n · ·
• b; inJegrated·change CCJl"ltrol . ·••·· · )
.r··rpdp1tor.and~s9ntrol prctJt~tll\/orK ··.
cl\ plancort:irn"mtcC:Itions · ·· · ·
~p~~~ . . . .. . .·
402 © Janumy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
ai!een@amegroupinc.com 719-659-3658
Cross Cutting Knowledge and Skills
•;
58. Yourmanitgement fa going through their quarterly . of
In the past~he orgaf1izatiQn has ah111ays used. ben~flt measurement ...,..,. .. ,..,,,,..""
projects .. It.seems now they want tcn~s~ constrained
metbod;b¢1.ow is yol,lr organizadon MO!$t.likely to use .now?
a. COfl1PC1i'ati\je. approaches
b. SCOJihg m~(lel
c. lif)earprogra01111ing al.gofithm
d .. <murder•board
59'. .As it, ptpject ma~ager in th.e electronks fi~I~. . is dear. that your projetts are rot
.. top. priority. •After sp~akj with your•mani:),g~m.~~t it is dear that tit~ re,al i~su~j!$
that yol,I ~(ac,ts a~e not .•..·... ne~ with the r~~e .objectiyes. \!~µ c<;m~'~ce ¥~fir
···organ ~~t .on.e apprO:*cb•tol;\4:Hp wi~ .... · . .. m.~nt is to . adopttf1~:1VlClr1agemetat
. by Q · ~0) concept dev~l9ped by: ~ef~r pr.usker. All oftl)e fQJl«:>wing are
ide~ .. · . . . . . with th~. objectives e~cep:t: ·
9.,.f()5t.t$~d ti\lities .
P' $i;>edfi~ . .· .. · . ·
ffii~ime
ole
Gp:•:•itter.s:v~rjf:mO
q~~.traet. The co9t.ract
b~sed .cm· ~ll~"'9h1g
· a•.. ffrirtJixed ~r.ic~ .·
b•. ;f.i.*ed price llJ~E!htlve fee
c.···•f.ixedprice 1Nit~@<:or;iornlc.· price. a,djus~111~1'.i!
d. time .and materials · · ·
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 403
::iileen!a)arnq,'l·mminc.com 719-659-3658
Cross Cutting Knowledge and Skills
64. 'During . . . qualjtY}t h;;is been determined that, several the d~liyerables
dt1e topay .de>~ot meet the. teclmical specifications. A change request has been
geoerat~d ~nd. willb~ aeproved .or rejected in which process?
• a.. monitor and cc>rJtrol project work. .·
b. petform iT}tegratedchangeconfrol
· c. validate scope
d. direct and tnarla9e ptoJecf1/vork
' ··;, ·,_,·'-. )' - ,_···:· ; ', - ',.'
404 © Janumy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen!c/)amegroupinc.corn 719-659-3658
Cross Cutting Knowledge and Skills
ut ns
1. b. PMBOK® Guide: Figlllre 10-1
Y b. Communication methods is a tool and technique of the plan communications
management process, the manage communications process, and the manage
stakeholder engagement process.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 405
=-'-"=;::'-"-"~=="'-== 719-659-3658
Cross Cutting Knowledge and Skills
406 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileern<'/)amcvrnupinc.com 719-659-3658
Cross Cutting Knowledge and Skills
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 407
ai!eern(/)amegrnupinc.com 719-659-3658
Cross Cutting Knowledge and Skills
408 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amei..,rroupinc.com 719-659-3658
Cross Cutting Knowledge and Skills
53. a. Verma, Human Resource Skills for the Project Manager, page 218
y a. Consultative in a group refers to group decision-making where the project
manager invites ideas and suggestions of team members in a meeting. If the project
manager does not take these ideas into account when making the decisions, though,
the PM runs the risk of being perceived as doing "lip service" and not really using
the team members input.
N b. Consensus refers to sharing problems with team members in a group and then
reaching a decision by consensus.
N c. Autocratic style refers to the project manager making a decision without input
from others.
N d. Directing style refers to the project manager telling others what to do.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 409
aileen1Q,amcgroupinc.com 719-659-3658
Cross Cutting Knowledge and Skills
62. d. Verma, Human Resource Skills for the Project Manager, pages 24-25
y d. Communication blockers must be dealt with so that they do not interrupt the
project.
N a., b., and c. These statements are all true. The question is asking for the exception.
63. c. Verma, Human Resource Skills for the Project Manager, page 61
y c. Creative work is how the workplace can help meet the Maslow's hierarchy of
needs for self-actualization.
N a. Rest periods and adequate compensation can help meet Maslow's physiological
needs.
N b. Safe working conditions can help meet Maslow's safety/security needs.
410 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
ai leenrZDarnegroupinc.com 719-659-3658
Cross Cutting Knowledge and Skills
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 41 l
aiken@arnegroupinc,curn 719-659-3658
Full Sample Test
Before you take this full sample test we strongly suggest that you review the sample
questions at the end of initiating, planning, executing, monitoring and controlling,
and closing one last time. See if you score higher than your first attempt.
111111
412 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
ailecnri'Dameg;roupinc.com 719-659-3658
Full Sample Test
tis~ ap~~tlie •
ri~f<{tot~l'a~t;e .
. c~.; ri.skthreshold •.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 413
aileerl!a!amegroupinc.corn 719-659-3658
Full Sample Test
,l\004~ Y9ur organization has .justbeen awar.:ied the largest .conttac~ .in its 4:0·year
history~·.. Because ~f Y()~r ·1O~y~;:tr history with th~ organization, you. have. been
5elected.tp leadtflepr0Je5t~ Bas~9>onrumors .you have heard, you expectthe proJ~ct
ta l<;tst .ov~r Syear~ ~n.cl t!) ~<;tve at lea.st 300 sta~eh 0!d.ers from doze11s of .countries~
PerfcmniQg on .sch~~~IE! i.s fZfitkah.<·~Vel'.I thpughr19.spon~or has.IJeen. assig.ned, yo~
b~~~nworf<on the.t:>r,oJe~t~harter. ~o.wever,yqur l'fianagertellsyouthere.isn't time
tq "1'orry ~bout acl'f~rt~r,.~nd din~~~s you to b~ginJNorldng on the. pr9jec:t plan inst ea~.
What s~oulcf you d~.. nolN'?·> . \> > .. .. .. • ·. · · .·•·•. . · ·
.> • >
a. be ~appyto be nar1~9 ~he pr9j~ct .rran:ager and begJ~working ontbe project.plan
b; develop a project;Ghat::ter oh yql.lr own l.:lµtdon't .Worry.thatyqu bave no sponsor to
J:i~~.ct~~~l;;~tint' ~nr•1u~~~~~·~~Y~tJ~~YnJi~~~li1•.
Tfief'ff ·;;t.•tf.>u.rnamentisa~~l4.~t(),~~~i£:y~ve~·
.J~<li1\·~e¥eral. 4!1~ff;~t::~r)tiC:OMl'l:!~.le~ .••.7I"~~ ·
tou~~aijl~~~ ~rlitt;Q~· 1here·~~~~S..t~ '?2nfp~i9r'l· on
basi~!issue:s; QusiogfQr tf;te a~hlete.s. ~· sf:tPLtld ycm
Ao~~~¥~~!~~[~~~i~:l~c~~i~1~ts~ri'~~J~~~~J~;;~~~- . 1nt~>rn11a1t101rv
relate~·t~Yr~ /; < . . . . .
s
a~ ~pecia[~al!se~ .•.
b; cRmmQ:6 ca.uses .•.
c~ a.ssi~na~le G(lus~s .....
d. · unnatur:alpatterns
.u2:~if~1\ow•~~~·~'i~~~~~*~&~~(.
· · Pred1Hsess°:r
9P.;;i1Qu,75~411!l.
i·su~c~~s9r,:c: DuratJo~ .
. Task A·· ·. <T B /•·;. · . 5, days
· Task.B · · C,Q · 3 days·
Task C ~·.•· ·. l:days
Task.D .E ·. .. 2 d~ys
Task E Finish 9 days
414 © Januaty 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileeni2Vamegroupinc.com 719-659-3658
Full Sample Test
. a,
b.
c
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 415
aileerna)amer:roupinc.com 719-659-3658
Full Sample Test
A013~ You have been assigned the proJe~tmaliager ofa project to replace an eJdsdn~
bri.dg~ on a major road thro~gh Colorado Spring~. You have manag~d seve.ral shnilar
project~ irf.the past andiar:~ exdt~d abou! h<:lying alJ()ther hi~hly visible project to
. rnanaQ{!•,The .project•wi.llinclude worldng. . V1fith manyorganiz~tions, ·indudingthe
dty;t~~.county, the ~qlicedepartment, al)d s~veral suppliers •.. ··· .. ·. . ·. .•.. . .·••
Yc:mr sp<>rfsor, WhQ is very invoh1ed1.h;.ts/already issued a pr()Ject d1iitrten:· He ha~ralso
helped y0ut;1avigate the. political env;rpnrnent. <You have a co111plete project 1)1c1n
indudln~ ~a5:~iines rot,>.scope,d111e, and c;ost~.·iAs ti'\e work.• pro~resses you issue
st~tus·.rep()r.~~ ~nd hold P~()gres.simeelin!Jsf?:rallintetested stakehol~ers.
After twely,e\mpnths, tfte:~ri(fge is coi'.l~tr;ucted<V1fithin.budgetand Of! sche~uh\; All
··.requirertien~$~ave. bee•'\tn~~;·· pur:in9.Y~U~.fina1Jes$()n.sle~medm~¢ting, yo~•·.pr~sent
· t~~lt~~ ?pr~J~.~t e~pe~f ··~···· ••.. (1ha~g.e, /r~quests ·.than Qthe,r··•c()tt}Pa.t~l)le
p~qj~c~~~ ~!~~Ztr'PSt Ii~{ 17 ~as~ / • . · · · > ....·• • .•· .·. ·
c;t. yoprs}'.)op$grjCfidno.t . ,. ~ehold~rs .·•·•· ··· . .•.•. · .....· •• <
416 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
ai!eenil/)amegroupinc.com 719-659-3658
Full Sample Test
~9.1&~.•. . •. ~e~eral 'St .~~~r\~~~·,~;~p~r:~ . A~~~ ~<?•. ·m~~e;·J~to proJe.ct .•. . ~aJ~~e.~~;t
po~it,ions. All ~ill ~e t~k,it1g>t~e ~J.\Pl'1J~'~'f~l11 5:~qr~IY;an~;ilr~ c1J~tentl}( s~udying, .!h~ ·
1
b, rnQnitQ[ andqp~.~~~IWqje·ctw9rk··
c. p~rforrn integta.t~i:I ~~a,nge .control
d; close. project o~ plja.s¢
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 417
ailccn@amegroupinc.com 719-659-3658
Full Sample Test
•. ~~~.1qnJ·~·¥~tir«ite~~. ·~~~~~··~~~
Performt,1nce reportju$t . ct···
~4Y~'.~~of',~1d ·x~u re$P9t'l¢1:
~,· au ~ta,1<t1hold.ers······
b, ·a11;~~y·~t~t<eholtle,
c:'. aHproj. · .·.· · · ·.
cL. f oUow thfi
" ,'" '
418 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileernmamegroupinc.com 719-659-3658
Full Sample Test
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 419
aileen!i:vamegrmrpinc.com 719-659-3658
Full Sample Test
A3o,. It .seems that your .tfi!am does a greafJob .. . plann.ing projects. but
loses insight into the pr()Ject. ~uring exe<;1Jting. Therefore, you have. dec.ided to
more effq~t i.nto monitoring <and controlling the prqject. . You recogni:tre
· ·monitoriog ;a~d controlling• inyolves all· of following except:
Fl·• validflWS.cope · ·
· b. contro,I risk
c. ma.nag~stakt:holder ~n;gag~rnent
d; coQtrol. stakeholdfi!r¢ngag:ement
420 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc.com 719-659-3658
Full Sample Test
·I
A035. The project is to design a '~fUture car" that em1pn1as1ze~s
also. ~omfort .a~~ tq~t. An impe>rtant ~art of the
determinin~ whktl combination of suspension .. and
plea:sur,abl~ ride •chara,(:t~ristiq at .. son able
combination, the ~11gi11eerswm mostfikely use a(n):
re,
a. Pareto . chart · ·
b: · controlchart
of experiment
tactory•isdrawingtoaclo$e. Ttlefa4:;tory's
ring the w~fers~ba~1 aft~r pro.ces~i#gwiU b~
.
~n~~h·~~~~ws~ in;Ol,l.r .·• ·• >•.··•>Y 01Uf:)UtefS~;;.AS the.~~fer~,pas5:th.ro~gh .each
· 11;i~ce of/eqY:iJfment·tUl t,he f(t~to~y.floor,. tra~king p~rformance over:. tirnetof these
~~ocesses i$ · · . ··.•...•.. ~o enstlte the~e processes are stable. Which ()f the
~~sic <IPJ:t.lit~ ...·..· ·.· . . ate~e lil<ely.to useiq the tracking.process?
· ct:,· tci.us~;,ancfeff~(!.diagrams · ·
~'.··htstpgrams . <·. ·
cc scatte.r~diqgram:;
ct ··control charts
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 421
aileen@amegroupinc.com 719-659-3658
Full Sample Test
A04:\i~AproJedreptil'tls
a. form.a!Written . ·
b. infotmalwritt~n
c. formal Y:el"'bal .....
d. informal verbal
,_ - ' '
A045 •. Yoy have been studying for the PMP®Exam for ttiel(l~tseveralmonihs ... for
you, thebeststudymeth°:d.,storeview rnanysampl~ qu~s,tions andJearnfrom ea:ch
one. To guide and focus youtstudies¥ouw~uld like ~o.°'e ableto seethe·fr~~uency
that you are missing questions by knowledgE! area. "fO do so; you win.most li.kefy use
a:
a. Pareto diagram
b. cause and effect diagram
c. >flow chart
d, scatter diagram
422 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc.com 719-659-3658
Full Sample Test
A0-47. \\(heh you first· planlt~d da~ developm~nt of your organizatiPn.'s ne~ rne,~ical
qevh:e, it.seemed that most c>ftheacth1;ities contained float; Yem rnetwithY;ourte'm
t(> ~~velQP}he schedule and <;a~plained flo~ttoaU team mern~ers~ . ~ow y~~)~~~
rurtn.i11g with several c;ritital Paths with< more pat11s becoming. crhk~d ea<::h 111!(:Jnth.
The lik~ly cc(~se of tliis is: · ·
a. P~rkil}sohTheory
b. laey.t:ear,rl>n:iembers
c tritkal. chain
d./critic(ll path r,rjethod
, ; '',>' ',' • >> ,/, N >; ,' "ui,/,-:,:, >'
A050. You have sp~rt~ l'rJont~s with YC)tff team 1Jlan11in9.vour project{ and it is.now
time to begin.. the .executin9 w.~l:"l<.~ Exe~uting· invc::dves all of following ·pnJCE~SS•es
except:
a. perform integrated than~e control
b. perform quality aS$.f.!t<'.l.['fCf!
c. acquire project tea,m
d. manage stakeholder er1gagemer,it
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 423
aileen@ame1-,rroupi11c.corn 719-659-3658
Full Sample Test
,£\QSl ~ you are t~e·.~a.11agerofthe desigri/bui Id 0,f a large manu{<ttturihg facility, With
··your cu~tom~r, ycm h,ave ~igned a Fix,ed Price Incentive Contract. Yoll recogni:ze that
in thil:~ t}fpe· of contract thE! ri$ck is shC1red ·be~w~~IJ .the bt1yer and the seller. The time
at which y.our organizatio1'1. picks up the financial risk is called the:
a< contractaward •.·.
b, con.tra('.t breach
· c'. C()tltractterminafi~W
d. · pqint of totata,ssumption
424 © Januaty 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc.com 719-659-3658
Full Sample Test
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 425
aileernmamegroupinc.corn 719-659-3658
Full Sample Test
A06?. Your organiz<ltioq Juas become very • good at assessing . and evaluating
c:ha{<\Ct~ristks of i.nd,iyi(;luafproje~t risks~ 1111anagement is riow <lsk;ing yo~ to provide
an ~stimate of the overall effect of .. risk ·on the projec:t obJ~ctives. Management
really asking yop tQ:
a.·· perfotpiq.ualittitlveriskanalysis
b. (non.it()ranq ccH;ttrol .risks
• c. plan ris~.fesponses . > .·
. d. performquantitativer:i.skanalv?is
' \ ,·, -<
-. - >· .' ..
. ·~o~3~·····~~~ij;.:~~i~g}r~······
.. •5l•·• Jill vv?~~ ii;~planned
~:: ~~i:tr1:~~1l'i:\Ai;or:~·i.s .... > ..•
·.:iL~~.a·ruture:.vvo~·~·1s{F)r~~ne(Jat:a:~igh~r1~ve•1••
· c, nf:!~f t~rll'l'•w<:>rl<).~ planf'l . t:!.f ·leyel§tnd lcmgterm vvor~· is plP,tln.e~ itl/~etail
d. ·. all··wor!5fs·Pl<inn~dat.~
~~~,~~~~~i{~(i~,,~V~~~~~~,.ji~f
(l; f9rm~l~Pc;iw~r · · ···
'~~1~~~t~i~'p6~fti~n
· · ·
b~.• . re~(;l.rq pe>VRer.
c p~1·f~ltypower::•
···ct. expe,rtpovver
'
\.
· ;
,:',;"·· .,,,
AQ~~;j·~9ur
~.~.!!ili~~t .t()P
· p9p~ljttion ·
im:tude•aU
a.jn~·t~~tt
b, J:b~ tes .... )~ex
c. ; ~h.e testin!=J~l ·
·d. Jhete~ting.ts.
-- /.;;x,- :,,/.:>··;,,<_,.. .'--(,"..·.)+, .-:,_.· ,_.. ., ~., :>:.:?.'.:-·-"'·,_.· ---/·.
!\Q~dt~trihµl~4
f,l.
1"1!«,,~~~~~i~~~~~ri~~~s~1i~~
a.11~, •.....• , . ut~d <> . .· • > /
is
426 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc.com 719-659-3658
Full Sample Test
If a project is n110>1rtnrrm1iio
defined:
a: b)t~~e cv.stOmer
b. 1.ri. ~he c9~tra,ct er~visi()~s·
c.. ~YW~P.~~form1~ 9 or9 ~9 izat1on
d. bytne proJect.m~ncrger
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 427
aileernl:/)amegroupinc.com 719-659-3658
Full Sample Test
Aots. comf,Uon.tause~ ·
>a•.~pecial causes
· b> unusual f!Ve~ts
c.•c.:ontrollirnits
· d. · random catlse.S
c.
d.
A078. Your tech~ofogy transf~r.proJect is Wrapping up and you are detertnining the
CIJrrent. !),tatus. of t.he project's. sce>pe. Completicm of. proje<;t scope is: ·.measured
against C;lllof the following except ~he: ·
a~ projectmanagementplan
b. scope statement
c WBS
d ... productrequirelilellts
428 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aikt".n@arnegroupinc.com 719-659-3658
Full Sample Test
;~8J,~:1~;R~~!~s$~~~1~~~[~:.ii~~J~:~~~~~i~l~~~~fui91tgy:~ian#~er
~r~jeqt.. Jhe·tfJC2~n~J9QY.~w;Jil 1bE! . e\l Sweden ·andJh,~n1,tran~ferredto
· r11anJ,1f~cturir,g .fa~Uities.J~< . 1
/ ,. • •i~~;'C:hinab .. vr~u h~ve
a~Pf:<>;xi~l;lt.ely~~P()•·p'~()Ple;w;prl<lng.cj~ ·9+~~~in~~rs fror;t;l e~cn<of
the B;1;1(lm,1fa<;~Yrin9,1.l,0¢~ti?ns'..!VJost t~ . . .. . . . ~.~f()Ugh~lectrof1k m~al'is,
~nd tlle~~ is freque · mfjcfl:~e.a,!~~¥ . . .. . . 11. . ., .. r. . . ; :< . > · .;./ . ·. .
Yol,lr spo~S();f h~s . .· . . fully ei'lgaged thrc>~ghou.tthe l.ife ofth~ 1Pt()Ject~:. Yo~ have a
5ig~ec;t~hcirt~~ and,.a fuH l'.)rOJect p•~.n J~<:Jucli~~'~ase · · · . . s()o~e, c::est* an.dttme.
Yo.or ·ide11tift~dst~k,e.~()lders 1 haye b~enfu!IY 1i11 .. · .,u~~«?~t tlie>life. 9fth.~
p
. ·
,t.
· · ~ tr~~~f~ris;()<:<:llr~in.g or1 $~.~edule
A.S;you. \Afrap up•tb~fil'l~I trart .
manufap:uri~.~.f~cm~tesjo tr:.el · <>:1:1............ . e y!lili t'l~t fl~ u~in~
in 1 91,1~gek ~II
. die . r~ti
quirements
. m.:t~ag~r at
b€!Jll9. tr(_(nsferr~tt< ffe.staI ........... hl'.l~l~g)( ts al~~~dy.put~i:ltE!yj.•.
thi~ l!er~~fl aj"ICJ.are:~iu; . ... l;)~;~is.c::omf!le[l$;•. On~.likE:iJY co:tu~.e
f~rth · . u~!firnernotu~ing th~~ro!=ft1cto ... 1,1rprc:Jject i~; · · ·
~b you,r sponsor did;~ot f~l'y eng~Qe all st~ke~Ql~ers./ · ·•• ············•··· . . . // .·• • .· .... /
b:·t~e;.proJeq: pl~.~ di9; 9()t8~oyi~e,~11.011~n·.~~t,~.H.on· Q.o\111. !o ex,~~u~i; .~he pr9Ject
.. f;:. YJ>U f~eam wa5•.t90 l~rge.tO ·m~na£11,,.~sp~~i(llly5i~p~ .tt••t9duc;lex:l.w~~ple from sev,eral
co4~tfies . . >· . : • . ........ •< . •> >'• > . ••. · · •· . .. ·. · .. ·. .. .·•·
.d .....;At;le~stone.J<ey
_, '- ,,,,.
sta!<eh61cle~was
.. ...qve~looked Whenjden.tif.Ying
-· ·- - .st. ctk. ehol~ers
-
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 429
aileen@amegroupinc.corn 719-659-3658
Full Sample Test
A084. Benefits analysis shpuld, ensure. ·. . the projecf aligns With the organizatfonal
. strategy. organi:t(lti{)IJ(:tl !Strategy is th~·.result of:
a: reviewing th~ .. 9rga.ntzati.on'.s f:>?rtfolios aQd deterlr!init1g strat~gy based ·.on/ the
anti~ipatedoutcoine~ qf these ;portf9lios. . . .•. · . . . . . . ..
. b, the strate~icplarnlng cycle '11{.~ere the orga~Jzatior's visronand mls~io.n a~e translated
ir1to a<stra~egicplan .. > . .· •.·•· · · . · < . ·. · • ..... . .. · . ··• .•·•
~·•• ~.yearly revie1!1f .9fth~ qr:igolrJ!jJOp.erations that produe;;evalue a,.nt:l Jhe,prograins cttfcl
proJe.cts th~tlncreas.e v~lµe.pr?ctuqfon ca,p~billtv
d. customer~focused. grQgra,rns •t11a,t:cleterminethe orgahiz:ations stt(t(egic plan
,·.; ..·,:·.";__: <.. ,'."··'·::,_~-,:· ?<'·>:.::.·/_;'. ·- __ ,,>-:,~_ •.. .,:.-.-: ..-:,:_;'. - __ -_:.-_- ____ -_:.:.'':-··. ,:··:~-'.·;--/ -,·._,
''~t~~i~,~~Jj~~~·~··'P~tZ~(~~~td~~;11··. !~~.1~~
.. ·. . YH.,. ll'{~qt ~9 l>e. cle~r on the Rflarity x~.i:t ~hquJd ·~ · ·•· ·. ·.·....
.s(l Y:Otl 5¢:af<: · r'tl1.e sta~eh. · ister. Yowanen~reali~e
i~ .... J'i ~}(i~ r•J.t~e; pn:>je . ;y.ou ar~ "~~<~(f'~ll~
.:Y.~9 u~e :r~s . · · · · .. 1~~)~·.fof do~µirt~llt$,
~r: <sta~~ho(q~~;regf$terip theti > · ·
·• '~~~{;::~~~:n1W:~bt,atl:~~L~JL~~~i~i~~~
~ilrlY1 $ · J~l;e. WJ;le rt . ·.··· •. ..··. ... .. lat~,
·· · · fables w . th~Y.:~o. det:iv~ th~
e(J; ~~~~·~()~•$qnsi~er · m~lerneriting
.type pf sy~te~?: · ··
; ;, , ,-
430 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
uileern(1)arncgroupinc.com 719-659-3658
Full Sample Test
A09(). Yo ff J;tav~•·· peen. 11artiedt~.e· p~oj~ct m,atJ~ge:r ~f\.a· proJedt() ·desi·~n,•bl).ild .·and
~~t up .a cust~m«)!r call ·Cfe~ter, .;mis call cem~rhas. b.~~n ~~e(tled to be vital ~o dr;.i!ing
t.he organi;z~ticm's •strategy•f~~"~r:~~·,l\ft~rith~f)toJ~<1tis C:()r1']P~ete, your•organlz~.tior
wiU}rack th~ nurJ'lber of newcqs~0;mer~·bgts~C19n tne sJ1.cces.sof the call center. The
t14fi1b~r C,>f fl~W c~st.omers is ~Qnsiq~r.eda(I)):.
a. key perf:t'.Jrmance \119:!~fl,t~r(Kpl) ··
b. l§ey succ~ssJ<;tctor{~S.Jil <
· c.,.c:1Jtic~r.~y~ces$f9ttqr·.<~$.~}; >:·•
ti.··· costcp~(for·maneeJndeX{Gl?I)··
, ,'_,~,· : .\>',' ', > <:' ::'.';,,',;'>',:,,::::~:/;:>/,:,::,,-:-->:,'': >,,'\,' ,'\ '.'
~:;~ 7
'jl~o~~ ;~0
~4~~~f~i~~~ji.~~ini~~~~t~f~~iJ~~;il,t~~~r rei~i!Rnshf'1
rn~·~~~~m¢nt. sys;~~fl)S i~tQ ()~r··~l'!~rpri~~~vv!~le •.$'f~tem, 1ttt?Yo~!$?J~•very . techniq~I Jr
n~tur~'~nd. Nkh~~~s.wasctJos~ll·~~:~n~ proJ.e,ct · er~.dueto . ~tr<>n9 . tec~?:k:al
~<;iuc.«i~i~n·ai:i~ ~xperiem:e... .fAs pa~t ?f. mana;gin f'lli . . . lasm,ust. i11t~{aft
VV:ith n;i~ltiple~usitj~!iS ~.nit l~~~er~thro ... gh9:l,lt .· ...... .. ion•~q µnd~rstan~;h9:w
his acti9ns anq.d~dsipns,affect .t~E:!h' busin~~~ u;nit > ·....• Ni~h~la$.has si,rong
t~~~~k;al~~jlls1.he is str~ggUng ;\Jllith re$~ect tothe;ap(.lr"'~ria!:~ t~.rmin<>lt)gy,tpµse·
whert>i.-itert{~i~gwith theseoth;[ leaders•. ·At thi!) poh1WNich~las.maywa.ntto f<:>c.us
mo~e\~n: . ·. <• >. > ·. /.
a. th~ tech~i.c;atvvo.rk of t~e project
l::i: • .. t m<J.ni:igement,.s~iJls
c.. ... . .meS"s.1a,:c:tJ.lrl~n
cE berfefits realization
),:;C:< <~/} :,\,, , ,':'.i:~~>>"/;,~'. , ,
,'., ,_.,',,,:,· ",',";,'/'. :'"
. ~dg~•.'*·" .or~1~1litktion
I?~Heyesin: .•· .· ;. •·:;._ <
a, socfal.mobility/•·: ?•••··
.b. direct Co91m un•jC<:\tieh .•••• . ..
c. i~I~ asmor§ilrlP9rtcl.ntthan 'tvite"
d; keeping opinions to oneself···
A093. Mo~t
of your project wjth team's "'"""'""'"' t~a~ [$Y~truggjfog ~i~h,'the
Rich has tr?uble controtling,.0:111~ r~dJrecting his df5,~ vie behaviors
as well a(laptingtochangingsi~~O:ltion~: Bas~dJm /a.ni~I
for emotio~al. intelligence, &icll .IJ~eds work more.on: ·
a. self-awareness .
b .. s~lf-regulatlbn
social skills
d. empathy
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 431
aileen\(/)arnegroupinc.com 719-659-3658
Full Sample Test
A094. All of the following are e){amples ite111s no.rm ally placed under configuration
ccmtrol except::
a. physiCal items
b .. d()cuments
c. forms cind records
d•tools and techniques
•.· .. ·.· •·· ...· .•.• ·. .. • :. > : .. ·.. . the/ e~~·of i6~.pr.~J~'.gfat1~cti~ve::'f,~g~n 2ompiting all ~f.}lout
less?n~.•·. re~rnetl:· Cpl! ..·. . • il'lq less9ns·· l~~rrretl;islmportantJn.·order . to~
. a. identify who 1JVas/a~c9untabl,f9r ~Uproj~~~·err?rs···· > ........· <·· ...•.. ·.· ·
b. provide (locum~n~;ltiori; ?n.any}pereeived late deHv~ri.es·qr <:ostm~erruns
c. update y()urenterprise envirpnrnental fac~prs for fut~r~ proj~cts
cL compare plan. to actualso ct? to i111pr9ve projec;testima.ting OIJ future pr()Jects
432 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
ailecn12V,amegroupi11c.com 719-659-3658
Full Sample Test
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 433
aileern(/)amegroupinc.com 719-659-3658
Full Sample Test
Al0'7. ·. r"Jot:ific~tion fron1.t~e customer that the terms. of the contract have been
is clone during wh,ich process?
a .. clqseproject
b, plan procurements
t. vaHc:f.C\te scope
d; control quality
A 1T.3. The vast majority cifthe project budget is spenfc.iuring which process group?
~L initiating · ·
b~ plahning
c. executing
d. m(}nitoring and controlling
434 © Janumy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
nileen@amegroupinc.com 719-659-3658
Full Sample Test
Al W
tile 1.evel
a. cont,rol •tju~li~y
b. v~llda,te scgpe
ctq~.~ proc~rernent
cpntrol sc;ope
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 435
aileen@amegroupinc.com 719-659-3658
Full Sample Test
Af~z~ ··~~l!r
Ciuali~Y~ ··
a.. c~ij~~.·~~
6.·:nowC:h:~rt~·;:.fY';«·i,···..··
. c. ea,.retdf:Jiag{l~~~> .
q,.)l l!a.litY aµd.lt~r 1 ····
A1~3/¥~.tij~~J~~;~~i~ri~dt,{~"1c~~.·wn1rn ·--·'"'
o~~n'm1~~.as'.."1t~lli:ts ~.•lof1gli!;it ot\1.1n(3QIJ~.t<>;.fled
·""·'°':'-
<U.1rusc>n!lrotiedl ct
~l~o.kgoli'(n; ~.s: < · · · · ·
a;, CO$t1gtqV11fu,•;{•.······
p.: s~~~~41~ ~r~~th
. c;. sc9~,e cr.~~p. ' •. ·.
a~< scope: cha,nges ·
Al
a. .. ....·
b·•·.. l .. ,'.· ...•• /<!
c." grea~erJ!lM l
d; Jess than v·
At~:¥"C~~~~t~~~~:;~.;ili1~i~i~~~~~P~t~f~~ pr0j~~~~~":~~,{~~~t,¥Jur
cu~tomer.·is as~ing for 01Qltiple•. ~£()P~ changes.< As . yo.~ . ~evi~yv .th~s~ ~harages, y;ou
ar~ trying;~o ~eterrraine the·true.rnagnitude of: thesed1angeS,,:YQu ~re most•lik:ely· to··
review what.document? · ·
a; scOpe.rrH:l!'lagem~ntplah
b; was ·
c. project.charte,r
d. cost managemetlt plan
436 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc.com 719-659-3658
Full Sample Test
·.
. j.\l3J .. ~n em~rgency has o.ccur,.ed and youurge~tly need .a safety c9ntractor. to. do
S()llU:?.c9lil~"'Jti~gwprkfor you. 111 thi~ .circumstanc.e, you likely
a, fi~edprice . .· ·
· b. fixep prlce incentive.
c. cost plus il)centive
. d. Wnea!"ld mate:ri~ls
Al32.
~L EV
b; EAC
c. B:AC
PV
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 437
aileen@amegroupinc.com 719-659-3658
Full Sample Test
. .
fl.fss. You are a project manager who ....·. . equipment installati.oris
autcnyiobile mamJfa.cturif'lg facility.. Early• in t.he planni11g process, you
· generate)dee1s for• improveme.r1t11.n~ to pr()vide a basts by which to
performance. ·You are most likely to use~
a, cpntrol ch~rts
b, Pa}eto charts · ·
. c. scatteridlawcims
d; benchrnarkii;ig
438 © Janumy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amel!Jlllillinc.com 719-659-3658
Full Sample Test
a. $ 80
be$ 140
$• 840
$1.200
/J.. lft'.2. ·~ fi~C>~,~r~111ent ~u 1dit: <•<·· ....•... ·. ·' 1 •.•.... · .. , ..••... ·• .·.. <· ........
~·. identifies i1rlY\l\(e~k~~s~e;s.inthe,,~~ller'~\!\fork.prqcesses deliverables ?F
b••. d~~eflTJin~s w11et;h~nrrpJec;t aqiviti,~5 . cqmplywith org<lni.zation~Jand project policies,
PWC~
c~·d"1
nd profe~:1:.trey< • ' r .· · · · . . . . . .
> .·· ...••..· .•····· .··
·..·.t~e 1ef;te,c~iv~ne.~s qfri~.~r~spc~msesindealiq9.Wi}h iq~ntifiect·risks and.tn~ir
ft~ .)Nel 1j;l:$ t~e:eff7ctlVe ne$s pf.tis!<,.~ ar}G!~ e 111ent 1 P:t()Cer~es
1
rq~essesfrorntheplanproc;urernent'prqc-esst~r9ughtne'control procurement
PrOceS.S,_.: · · · :_':: :__ ·./ ·. ·.- ; / ./ -· -,,. :· ·. ·
Al43.
, J·~; ·ji;wy
. .s~v~r~l~f >:h 1 ):h,i:f · < ......•· .· ·•. .
~:l(~~"~ngin~~~~;~r~c;opst~ntly showin~ 1 up!at~for . .work. Vl{~en
. . ·· .· .•. .
..
.<
they do finally ar .. ·. . . heya;re dresS:~cl<V~rY<Ylf:~H,. much bette.r<in'.f~ct than. is stand;;\r:d
practicein your: firm, Yem.wonder ilwhatypu areri.otic:ing i.~ really a warning sign
tha~they have. bee">interviewin.g wit~.ot~ercqmpcv,nies~ Another.flame for a warning
sign is .a: · · ·
a. risk event
b. riskimpact
c. risk s.core
d.<risk trigger
Al44. Cost
a. useless
b. les;. reliabtet11p.n dgcurn¢hted perforrnance
mo.r:e. reliable tharu:lqcument~d performance
the most reliable.fdrm of estimating
© Janumy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 439
aileen@amegroupinc.com 719-659-3658
Full Sample Test
You are struggling to. get your team members focused on your project. Jt
seems that priorities across the projects in the pr<?grarn. ar~ undear, Setting
priorities across projects. inside a program is most often hancUed by:
a. Jhe project manager
b. the project st<.'!kehold!'ffS
c. seniormanagernertt
d. the program manager
. . . . . . . -
, .·· .. ·. ·:·
Al.49,··.The pfoJect is to provide .dean· safe drinking water tc> an isolated c;:~mmunity
that. has pe~n hit by massive ~roughts> The CPI is .90.. The project is two weeks
!)ehinci schedule and the project has over 30 stakeholders. Where should yqu
increase youtemphasls?
a. schedule
b. cost
c. stakeholder 111anagement
d. · conflictmanagement
440 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileenr{/)arnegrnupinc.com 719-659-3658
Full Sample Test
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 441
aileen@amegroupinc.corn 719-659-3658
Full Sample Test
$~" Tli.#
·"'meetr ~;,~if¥~~inil;~\riiti;~~r;
~ Atthi~pf>ipt;.~h~ ~ ·
1191;{11fi\~: 9\!'i~l'·"v.Pt~~ct.~eil".~l~~
ls. ~qQsideri~!}f<?:iu~ qeW;prpje~ts·T~e proj~~ts
ares ·. l«lf:il'lr:J~t~~e•, Th.~·p . .· .·... Jerenc(}i~tfieirPc:l~m .•..· ·. od~~roj~~tf\~Cl:~
a.payback perib(f gf. C>;nth~.•..• Proje~t' . ae~y~a~~ peri.P /?·.··l()<W(;)ilths.,•>Prqje9t
o ~as a. pavb~C:f{ pe . .· . . otl'~ rnQ~t9~· ..... · . / D fo,~~ a p~y~a~~:p~riod of '.22 months:
. Based o°'t~is Ii mite~ h•f<;>rrnatioll, tliep~pject '!lPsfiikeJy.~f;» be.~~le<;t~d is:
a. project}\ · · · · · · · · ·
b. prdje!=t.B
c: project C:
d. projectp
442 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc.com 719-659-3658
Full Sample Test
Al • You were selected to lead the groject .· will move thebrQ,anization . ·.. a
leadership role in soda! media. j\llany stakeholders from b()th inside . outside the
orga11i:zation have been i.nvolved. Your. sp()ns9r issued t~e charter, ~nd
stakeholclers .taave been kept i.nformed thrqughout th~ life gf the project;
n1onthly status ~eeti.ngs have goon well ~(t.d everyone frn1oh1ed.s~ems ~lieasecEYc.ur
project has been running on schedule, am:i \j\lithin buqge~, a11d the requirements
bei.ng achieved ·!Elccqrding tQ. plan. A~ you prepare. for YO!Jr·las~·d~Jiverel,ble, YOa.J .hear
that the .solution .~eveloped has. bee.n rejected and the .project cal'!celled. Tile most
likely reason for this. is: .··••··· ••. ·... . . . .( .. . . .· ·.· .·.·. .. ·. . . . . . .·
a;· yoursponsor was notat~high em> ugh l~yel in th.e org~nization to support.your project
b. yourtimeline was not ag£Jr:~s~iY~<E!!iQ~9p.for the r:narRet ......... · ..·•
c. yo1;1 did. not contr9Jyot1r PIJP9J3t~o thE!'l~yel requi[:§dfor suchala~ge i:JrdJect
d; a cr.itical stakeholder was/11J>ti.nvolved·or not h'lvolved early enough
A16Q,Ydur ..risk ~anag •·.··11k~~tou~~~*pect~~· ;~ri~t~ry valL(~to qul~~ify.fi~k,
1-J<?weveh~~me.ofyour .. ·. . .keholders\s~e'll l<1.ignoteexf?:.et!ed ~cmeta~yalu~ an.d
in~tea~.bas~.~.~~ir .risk·.d~d~ionsQ.;t .. th~;~~Jis,fa~t,ion th~Y;deriv.e(rpm e.act:r.opti~i::t·
1"his theory f~. ~alled: · · · · ·· · · ·
a.
0:, • hY t>fn~e<;I~; ' .
· c. utilityt ......
(l:. expectancy.theQrY •.· ; . • .. • < > • C . . . . ... .
J9i·n~clyo~~t~~~·;··.·Hea.ndyo~r:;~~b~bfW.&rk~d··.t6gether
ihaP:re~ipu.s~br:gan.i ·.. ·....· .· . Whe11e~er•¥()U.~}rectt,he wor~p~th~!e"':m, .brings up n.e
\j\lbat ~e.a,ppar~ntlythi~~s w~ spo11sor ,\/\/~~Id .1i1$e. the te~ftitO do....A~ a. result, the
. rJ1erttber~ 9f y«:1pr te~111~re ~«)hfuse~ e&st9 f~~m. wt;lom th~}f . s~~uJ~ .receiye direction.
Ttte p9w~r Pf!i°'g e)l;erc;ised by your ne.w·tedtnician is an>~X~l;npl~ .of:
.<i.:l·.:.· w. ···. . e..•.
. f'.
1110.
b. t .P'.91/11~[
c, t(P?Y\f.~r
· ck ·f:~r~~I p:Qwer
<: ~ ~~o#<:Juc~ing
.. lessons. lear.ned on your project.• final SPI T~e
rJ•}zf~· "f'~~f~\IV~re. J 50 g~ograp~it~lly cUspersed• team. m~mbers.
r~q~~trte~Jltefinal pro~IJ<:t,.~l:te cust.omer h.as decided to shelve
.··. · .............•.. > .. • ril~{(!focus,4ha,n you did?
· .....•..•.·
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 443
aileenrGJ,amegroupinc.cum 719-659-3658
Full Sample Test
A164. The. conflkt resolution . technique th,a~ wm, without f~H. resolve a .conflkt
quickJybutsh?uld only used a last resort is:
.·a. C,ompromising
b. farting ·. ·
c. confronting
d ..•··w.ithdrawing
-.. ,.. __ •''-'·· ,.•,
~·;~~'.~.~~· /·
l!lflu,f!n~~·· ••. ·•· ·•
;~~ .~J~~~~~d·;~ i;<#j~1i~~~ h¢. ~~ril;,~t~IY.
·~ar~.est fQ~. the Prf:)i~c;t)rnanager:t() ififluence{o ·
a, .c:l.irectc:osts .•·....
b:;ir1dif[~Ct:~?:S~~
c, · varlal'Sl.e co~ts \ •·
d .. •fixed·.8osts
. c::
d.
• ·· . · ··>.···.'. . ••····c·;"·· ..·).<·····.o>>; ·• ·>•·····
A169. .)'outcontr~(~qrisJeP(lfting costj:jerfofmance ttiyou ()0 a monthly lla~is usirlg
CPL Hi~tory has ~hown that the projeq1s CPI often becomes stable when what
percent of the .workJs c;ompl~te1
a: · l 5%~20% ··
b: 25%-30%
c. 30%~45%
d. 30%·50%
444 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
ai leen@amegroupinc.com 719-659-3658
Full Sample Test
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 445
ailecnr(1)arnegroupinc.com 719-659-3658
Full Sample Test
ib~.··~cJirec;t.cgsfto.tne·6~~~r:c:mly;0 ifthetiuy~r.doe5,·n.otbuyf[prnthe;~eller
: c. a:.t1•r~q9~stt~.~lit~.P!JY:e~9f~l¥<.ifthe ·buverc.~oes•pyy:fr?:rn·.th,fs~~l:~r:·
· d... ~;qJr:e9t<;O~ttdtfl~.l)uyer'.rega,rc(l.e§spfwhetb.er tl;l~1~4Yer·puysrrarn
;~~ir;t~ii~~\1~~~~,h~r~J~~~:i~r~?~~,&¥~;·. •.
. a; 1neap ·qf·~s:n·e~.1.ff. · uDp.~r · get · · · · ·
b, ah~.ad9f;scbe.aur ·. ; . (wet. . et.·
c.<9ehi~d,scH~~uleafrpuncterb. g:~~····
; d.• bebing.schedt.tle ano over.bud;g(;!t .
::~~~-~·,r·······
$400
$200
.,.,,._,,,,~~ffm~=-,,~,,,,,,,,_,~"-'""'n'"""'-""~'"~"""""'"'~""·"-""v""~"m;mm
···~·;~i~~i;~fJ~1J~~~~'_€,"z• .
ch< ~erzherg'~ hygiene tt1eJ>:t't <; •.. ·. ·•· . ..·
". .. -\-~.>:·; ;>:::~:;\~\;~:"}~~;:~~.·::.-;.::-;/_--;-. > -/·~~-'-.>.<:·'
446 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc.cmn 719-659-3658
Full Sample Test
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 447
aileen1(/)amc2.roupinc.com 719-659-3658
Full Sample Test
. Al8J~< ~ ·pr()J~S~'.~;riager h~S b.~en fua)'ta€Ji.r19 ·a Jong term trahling. proJe~t~ ...... {he
traini~g.•is ti'\fer, ~pd~$he js tr~i~~\~o ~lose out ~er project•.•• The··.~ituationJs nl)t, go~d~
Altho4JJU ~IJ re·.···· · mel'l.t~ .~.a\le~eE!r1 .• metf·~~e ·c4stomer. is·· ri<:»l;.satisfied.• •i;~e
cus,torn~r stit. · the0 re$~!t~.()f:.the training were not what they expected. one
UR. e.'t.c. .·.a.•. ~.s~.o.J. ·.· ·~· .c ..• ·;. • · · •..· •·• <.·.
a. tll~;Jtj~trHct . ; · .. > < . •·•·.·· ·
· b; . . th~·~~p~o . • er¢:~o~ tU"frjed·i6to r~qulrem ents
c. • th~ ~1,i.sto Q't~r:.i . . . . ,}"in~?t9 ~ > /. }t·~he ~'intra.ct
go
d. •.the ~raining clJc;iH;pt Jnto· en64g.hd.efail
j\:l~Q~ yoijr comp~ f:.l~~sm~tj'1 ,{\;;sociates,, is: i.n·~he fi~al ·~tages of theH.~~i9/1/bu ii d
ofa semit tit() . for amf;lJOr customer.. At the las~ custom,er l'.11~~ting;tbe
~~~pan¥<,:. >, •• e .·. .. · .• .... . m,entkmedJ~~ possi~iHty o,t ~tJildi":Q. anQ.tl'J~rf~ct~•y ir1
·tffo 11ear ~ut~~~';.Jhis istf!f)••l:>Pf'()~unityyo~r cornpanY•.¥'Clnts, ·The. mostlif{~ly st~ategy
YC)U af:~ tq u ~~ ~(J;g~t..tt:Jis .p~oJec.t .is: ·•
a,· eXP.l.<:>:it • .·. ···· ·· · · · ··
: b.> mitigat.~>
· c tran sfer · ·
. d. avoid.
Al 90.The theory that pe~plec.:h~6se. behaviors th~t tltey.believe will lead ·to.desired
. rewards or outcomes is:
a~ (V1aslciw's hierar~hy
b. McGregor's Theory Y
c. Vroomls expectaricytheory
d. Ouchi's TheoryZ
448 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aiieen@ame12roupinc.com 719-659-3658
Full Sample Test
A,192. One of your project1 s<~ey r~soun::es is being pulled .,.way to. a higher pdority
Pf()jec;t.. This resourc~· is working on activity A on your project. Activity A h,as.
early f~nishof J2> days i!ttd ~ late finish of JO days. This means:
~· Ac:~iytWA haS<2 .dav,~pf total float ·
~·· Activity~has a(ag of2 day~·
•· c, Activity A hasj\ cluratiPl'l of 2 d~ys
d~ A.~.iyi.W A ha~ a +2;days of fl.oat
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 449
~=;:~~~'"~= 719-659-3658
Full Sample Test
AJ~7. The pr9ject isto tran~fer teC:h":ol9gy developed irryour factory in Sc«;>l':and to
an operations facility inChina.<There are approximately 3,000 stakeholders inyohr~d
in the proj~c:t livi11g. in J2 differen.t. C()!Jntries,. Your sponsor is v~ry involved and
cornr-o~okates regt1larlyl1Vit~ you, ~he project . man~geroentteam, and t~.e· key
stak~hol~ers•.Your·CPlis.·.9~an~·.th~·projectis .• running.· 14 w~eks.behindsclled.ufe;
Based •c:m .~his scenario what sh.Quid yoy be most concerned. about? · ·
a, .sch~dule · ·
b; c::ost. • · . •····.···. •·
·c···
d .•
sfa~e~ofdt?r·.m~nagerileni
sponso~.managemeht
~~~~hf<11tl~~~vi~Wi~~~~~t;i~~~.t¢01~diiA;;~~ti~f~~~~~t(qri~~l:cli~n:f~
::t.Piec.~of~ · · entt~~t·~y · e proc~~$:.me~? is#fength·of42~3sme~e,rs·
The;M#~et · · · · :is 4~¥.. . •. .. ... ~ne:IQ1Afer: cH~trot li~it.i~.41 .. ~~· "fhe·l'~'.es~
CJ~ta •r. s ce is: .92, 4:2-~8 75, 42.~2, 4~,01;. 41;;~.z•. 4J~ss,:.~2.30, 42,09, 41..95,
··Ero awec~rr:.s1a.r~=i!c ·i
· a; ·. · ~f~pntrg1'.; \ .•.
~- t~~ > is • . , ~rol , :~ .; ? \ , ·
c.·· ~~etol~~al'lc~ JirnnsS;f:t?H}ct·9~.ti~f)ter ·
d. tfue.toliit'ance limrt:scsh.ould.be•·wlder
d~wiatiQ.n
;. ' ............ ·..... ·.· .for:..Activity Ais:
n .·. . .·... .
· o= 2 s'~~~
c. fj d~ys ./.
d.. l2 da:ys /
",<:< :'.,~, ,;: ' .'.'; / ',' ~<,',\
450 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aiteernmamegroupinc.com 719-659-3658
Full Sample Test
I I
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 451
aileen@amc~roupinc.corn 719-659-3658
Full Sample Test
452 © Janumy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc.com 719-659-3658
Full Sample Test
1 5 6 8
Start
Finish
1 5 6 8
16 24
14 15
Now let's calculate the float of D. The float (also called total float, or slack, or total slack) of
D= late finish of D-early finish of D= l 5-10=5. D has 5 days of float.
© .Tanumy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 453
aileen!q)amcgroupinc.com 719-659-3658
Full Sample Test
N b. A request for proposal is a document used to request proposals from sellers. This
document will not allow the seller to begin work.
N c. A purchase agreement sets the terms and conditions that apply to transactions
between parties. A seller generally will not begin work until there is a contract in
place.
454 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
uilee1HiDarnegroupinc.com 719-659-3658
Full Sample Test
N a. Total float is the total amount of time that a scheduled activity may be delayed
from its early start without delaying the project finish date. This question has
nothing to do with float.
N b. Free float is the amount of time that a schedule activity can be delayed without
delaying the early start of any immediately following schedule activity. The question
has nothing to do with free float.
N c. Lead is a modification of a logical relationship that allows a sucessor activity to be
accelerated. The question is the exact opposite of a lead.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 455
aileen@ame1.,rroupinc.com 719-659-3658
Full Sample Test
N a. The PMBOK® Guide is a standard, not a regulation. It does not have to be followed.
It is suggested that a project management team tailor the information in the PMBOK®
Guide to their specific project.
0
N b. PMl publishes a tremendous amount of information. It is the responsibility of the
project management team to determine what is appropriate for any given project.
0
N d. PMl standards are standards, not regulations. They do not have to be followed.
456 © Januaty 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@ameizroupinc.com 719-659-3658
Full Sample Test
N d. The WBS is updated when approved changes affect the project scope. This
scenario described in the questio~ does not imply a change in scope and therefore
the WBS is not updated.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 457
aileen1i/)mnegrnupinc.corn 719-659-3658
Full Sample Test
458 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileerna)amegroupinc.com 719-659-3658
Full Sample Test
Y d. Perform integrated change control is the process that maintains baseline integrity.
Here we address the approved changes and ensure that all the approved changes are
incorporated into the baseline.
N a. Develop project management plan is the process of documenting the actions
required to plan and manage the project. This answer is valid but is not the best
answer. Look for a more specific answer.
N b. Direct and manage project work is the process of implementing the work of the
project plan.
N c. Monitor and control project work is the process of measuring the work against the
project plan and initiating corrective action if needed. Requested changes, not
approved or rejected changes, are an output of this process.
A045. a. 8.1.2.3
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 459
aileen!Zuamef_,JToupinc.com 719-659-3658
Full Sample Test
Y a. Pareto charts show how many defects (or missed questions) were generated by
type or category of identified cause and so help rank order to guide corrective action.
N b. Cause and effect diagrams help us understand how various factors may be linked
to potential problems.
N c. Flow charts show how items in a system relate to one another.
N d. A scatter diagram can suggest various kinds of correlations between variables
with certain confidence level.
460 © Januaiy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
ai Ieenr(1)amegroupinc.com 719-659-3658
Full Sample Test
A054. d. Verma, Human Resource Skills for the Project Manager, page 70
Y d. Theory Y represents a positive view of workers by management.
N a., b., and c. These statements all represent a negative view of workers from
management. Therefore, these statements represent the McGregor's Theory X and
not Theory Y.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 461
aileen@amegroupinc.com 719-659-3658
Full Sample Test
462 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
ailecnrc/Jarnegroupinc.corn 719-659-3658
Full Sample Test
;
A061. c. PMBOK® Guide: Figure 12·11
Y c. Control procurements is the process of managing procurement relationships,
monitoring contract performance, and making changes and corrections as needed.
N a. Plan procurements is the process of documenting project purchasing decisions,
specifying the approach, and identifying potential sellers. This is too early for the
contract change control system.
N b. Conduct procurements is the process of obtaining seller responses, selecting a
seller, and awarding a contract. This is too early for the contract change control
system.
N d. Close procurements is the process of completing each project procurement. This
is too early for the contract change control system.
A064. d. Verma, Human Resource Skills for the Project Manager, Figure 7-9
Y d. Expert power is derived from one's knowledge, not one's position.
N a., b., and c. Formal, reward, and penalty power may all be associated with or derived
from one's position in the organization.
© Janumy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 463
aileen!l/)arnegroupinc.com 719-659-3658
Full Sample Test
!Will the seller's fee be increased or decreased for Decreased by the seller's % of the
an overrun? overrun. (qo to share ratio-take 2nd%)
Decreased by how much? 40% of $5,000= $2,000
Seller fee=target fee-adjustment Seller fee= $8,000-$2,000
Seller fee= $6,000
Is fee between max and min fee? Yes, so Seller fee=$6,000
464 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileernZ1),amei:.11·oupinc,com 719-659-3658
Full Sample Test
N b., c., and d. The sender encodes ;the initial message, and the receiver decodes the
initial message.
A074. a. Verma, Human Resoun::e Skills for the Project Manager, Table 4-1
Y a. Smoothing involves emphasizing areas of agreement and avoiding points of
disagreement.
N b. Collaborating is a technique to manage conflict in which multiple ideas and
viewpoints are incorporated in a solution.
N c. Withdrawing involves pulling away from a conflict.
N d. Forcing involves making the other party do it your way.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 465
aileen@amegroupinc.com 719-659-3658
Full Sample Test
N a. and c. In a matrix (weak, balanced, or strong) the worker has a functional manager
and at least one project manager.
A083. b.
Y b. For a benefit to have value, it must be realized in a timely manner even if this is
after the project closeout.
A084. b.
Y b. Organizational strategy is the result of the strategic planning cycle where the
vision and the mission of the organization are translated into a strategic plan.
N a., c., and d. All three of these answers are reactive, not proactive. Organizational
strategy should drive these three ideas, not the other way around.
A086. b.
Y b. Just-in-time means to produce, deliver, or purchase only the materials required,
in only the amounts required, only when required. To successfully adopt JIT, you
must know what you need, how many, and when. The best way to monitor these
three elements of JIT is to ensure that each "next-process" takes only the necessary
items, in the necessary quantity and only when required, from the "previous-process".
This is called a "pull" system.
A088. a.
Y a. Relying on human memory is often the riskiest ways to capture knowledge. People
forget, change positions, or leave the organization.
A089. a.
y a. Searchable databases are a technology used to apply the transfer of knowledge.
N b., c., and d. These are methods for assessing the value or benefits of knowledge
transfer and not technologies for applying transferred knowledge.
A090. a.
466 © January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc.com 719-659-3658
Full Sample Test
Y a. A KPI measures the success of the project or elements of the project. If the call
center's success will be measured by tracking the number of new customers, then
this is a f(PI.
N b. and c. The terms key success factors and critical success factors (CSF) mean
exactly the same thing. They are factors that must go right for an organization to
achieve its mission.
N d. Cost performance index (CPI) is the earned value divided by the actual cost. The
CPI is not related to this question.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 467
aileen!i:/)arnef:mrnpinc.com 719-659-3658
Full Sample Test
N c. The critical path assumes unlimited resources while the critical chain assumes
limited resources.
N d. The critical path method has been around for decades while the term critical chain
was created in the l 990's.
468 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
ai!een@arnegroupinc.com 719-659-3658
Full Sample Test
N d. If the project were behind schedule, the SPI would be less than 1. The project is
over budget since the CPI is less th:'an 1.
0
A 105. d. PMBOK Guide: Section 8.1.2.3
Y d. Pareto charts show how many defects were generated by type or category of
identified cause and help rank order them so as to guide corrective action.
N a. Control charts help us understand the limits of our process.
N b. Process flowcharts help show how various elements of a system interrelate.
N c. Cause and effect diagrams illustrate how various factors might be linked to
potential problems.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 469
ai ken((/)arneg:roupinc.com 719-659-3658
Full Sample Test
A 11 5. c. PMBOK® Guide: Section 4.5 (not dearly expressed i111 PMBOK® Guide)
Y c. Evaluate the change request is the first thing we do when a change request comes
to us, regardless of where the change request originated.
N a. and b. We don't want to meet with our management or sponsor until we have
information about the impact of the requested change and we are able to recommend
alternatives.
N d. Every change request must be evaluated, even if it comes from the customer. We
do not make any changes unless an evaluation has been completed.
EMV of Venture
!Total= $1 ,000
470 © Januaty 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileenrmarnegruupinc.com 719-659-3658
Full Sample Test
Y a. SV= EV-PV. If this answer is a positive number, meaning that EV> PV, then your
project is running ahead of schedr;'.tle.
N b. The EV would be less than PV if the project were behind schedule.
N c. and d. AC is required information to determine cost variances since CV=EV-AC.
A118. c
0
PMBOK Guide: Section 7.4.2.4
y c. Trend analysis examines project performance over time to determine if
performance is improving or deteriorating
N a. Variance analysis compares actual project performance to planned performance.
N b. Earned value analysis compares actual cost and schedule performance to planned
performance.
N d. Cost-benefit analysis compares a project's costs to a its benefits. In general we
only work on projects with benefits that outweigh costs.
© Janumy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 471
~==='--"==== 719-659-3658
Full Sample Test
Y b. CPl=EVI AC. If the project is running on budget, EV=AC , meaning that CPI= l.
N a. CPI= 0. We do not think of indexes as being zero. If the "cost variance" were zero,
the project would be operating right on budget.
N c. CPI> l when the project is running under budget.
N d. CPl<l when the project is running over budget.
472 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amev:roupinc.com 719-659-3658
Full Sample Test
N c. A cost plus incentive contract is a complex contract to set up and thus is not often
used in an emergency.
© Janumy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 473
:Jileenr(j)amegroupinc.com 719-659-3658
Full Sample Test
Y d. The BAC for your project is the total project budget. The question states that you
have a budget of $200/month for six months. The total project budget is therefore
$1 ,200.
Y a., b., and c. These are distractor answers.
474 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aiken12Vame&,'roupinc.com 719-659-3658
Full Sample Test
N a., b., and c. These statements are all true. The question is looking for the false
J
statement.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 475
aileen@amcgroupinc.com 719-659-3658
Full Sample Test
476 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc.corn 719-659-3658
Full Sample Test
A161. b. Verma, Human Resource Skills for Project Manager, page 233
y b. Referent power is derived from the strengths of one's relationships.
N a. Expert power is derived from one's knowledge.
N c. Penalty power refers to the negative things a project manager might do in
retaliation.
N d. Formal power, often called legitimate power, is derived from one's position in an
organization.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 477
aileerna)amem-irnpinc.com 719-659-3658
Full Sample Test
N b. Since the CPI is above l .0 we did not need to focus more on managing the budget.
N c. The issue in the question is that the product is being shelved. Nothing in the
question suggests that we had issues with our team members.
A 163. c.
y c. Holding a meeting with our stakeholders to determine a solution is often a better
solution when are stakeholders cannot agree on the path forward.
N a., b. and d. It is not likely we will receive stakeholder buy-in with these ideas.
Therefore, it is less likely that these ideas will lead to a successful outcome.
A164. b. Verma, Human Resource Skills for Project Managers: Table 4-1
and PMBOK® Guide: Section 9.4.2.3
Y b. Forcing involves pushing one viewpoint at the expense of another. This technique
is often used in an emergency situation. In response to forcing, hard feelings may
manifest themselves in other forms as some future time.
N a. Compromising is giving something up to receive something in return. Both parties
gain some degree of satisfaction.
N c. Confronting, also called problem solving, treats conflict as a problem to be solved.
This technique provides ultimate resolution.
N d. Withdrawal involves giving up, pulling out, or retreating. This technique does not
solve the problem.
478 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileen@amegroupinc.com 719-659-3658
Full Sample Test
N d. The process develop project management plan has the project management plan
as an output.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 479
aileen1ZDame1,,,roupinc.com 719-659-3658
Full Sample Test
A 179. b. Verma, Human Resource Skills for the Project Manager, pages 65-73
Y b. Ouchi's Theory Z is based on Japanese styles and philosophies and states that
high levels of trust, confidence, and commitment to workers on the part of
management leads to a high level of motivation and productivity on the part of
workers.
N a. Vroom 's expectancy theory states that people choose behaviors that they believe
will lead to desired results and that they will be rewarded attractively for those results.
N c. McGregor's Theory X describes management's view that most workers dislike their
work and try to avoid it.
N d. Herzberg's hygiene theory states that some job factors lead to satisfaction,
whereas others can only prevent dissatisfaction and so are not sources of satisfaction.
Hygiene factors related to the work itself, if provided appropriately, prevent
dissatisfaction. Motivational factors related to the work itself can increase job
satisfaction.
480 © Janumy 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aiteen@amegroupinc.com 719-659-3658
Full Sample Test
N a. Nothing in the question suggests that the issue of too many change requests is
due to of a lack of a project manag~r in each country. Do not read information into
the question that is not there.
N b. The SPI is 1.03. The project is ahead of schedule.
N c. The CPI is 1 .04. The project is running under budget.
A183. a. Verma, Human Resource Skills for the Project Manager, page 64
y a. Some job factors called motivational factors, lead to satisfaction, whereas others,
called hygiene factors, can only prevent dissatisfaction.
N b., c., and d. If provided appropriately, hygiene factors can prevent dissatisfaction
but cannot lead to satisfaction. Motivational factors related to the work itself can
lead to job satisfaction, but cannot prevent dissatisfaction. They are not on the same
continuum.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 481
aileerli(1)amegroupinc.com 719-659-3658
Full Sample Test
N d. Nothing in the question suggests that the training did not go into enough detail.
In fact, the requirements were met, and so this is not the likely explanation.
A190. c. Verma, Human Resource Skills for the Project Manager, page 65-73
y c. Vroom's expectancy theory states that people choose behaviors that they believe
will lead to desired results and that they believe they will be rewarded attractively for
those results.
N a. Maslow's hierarchy is a model of motivation that suggests that each of us has a
hierarchy of five types of needs. The bottom level is physiological needs. Level two
is safety, level three is social, level four is esteem, and the top level is self-
actual ization.
N b. McGregor's Theory Y describes management's view that most workers are self-
disciplined, can direct and control themselves, desire responsibility, and accept
responsibility willingly.
N d. Ouchi's Theory Z is based on Japanese styles and philosophies and states that
high levels of trust, confidence, and commitment to workers on the part of
management leads to a high level of motivation and productivity on the part of
workers.
482 © Januaty 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileenritiamegrrw_pinc.com 719-659-3658
Full Sample Test
y a. On a cost plus fixed fee contract the seller's profit remains the same when the
contract runs over the estimated costs. On a cost plus percentage cost contract the
seller's profit increases if the contract overruns the estimated costs. Your contract's
manager is probably assuming the contract will overrun the estimated costs and is
pushing for the cost plus percentage cost so as to obtain the extra profit.
N b. On a cost plus percentage cost contract the seller's profit goes decreases if the
contract runs under the estimated costs. If your contract's manager is assuming the
contract will under run the estimated cost, he would not push for a cost plus
percentage cost contract because this will result in a lower profit. On a cost plus
fixed fee, the seller's profit does not decrease if the contract runs under its estimated
costs.
N c. The cost plus percentage cost has more buyer risk than the cost plus fixed fee.
N d. The cost plus percentage cost provides the buyer, not the seller with more risk,
than the cost plus fixed fee.
A 196. c. Verma, Human Resource Skills for the Project Manager, page 2] 8
Y c. Autocratic style refers to the project manager making a decision without input
from others. You are less likely to use this style with a very senior group of people.
N a. Consensus refers to sharing problems with team members in a group and then
reaching a decision by consensus.
N b. Consultative in a group refers to group decision-making where the project
manager invites ideas and suggestions of team members in a meeting and the project
manager makes the final decision.
N d. Facilitating refers to coordinating the work of the team.
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 483
aileen@amei,,>Toupinc.com 719-659-3658
Full Sample Test
484 © .I anuary 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
ailee1w1)amer...11·oupinc.com 719-659-3658
Full Sample Test
Ferraro, Gary P. The Cultural Dimension of International Business. (3rd ed.). Upper Saddle
River, N.J.: Prentice Hall, 1998
Fleming, Quentin W. and Joel M. l<offleman. Earned Value Project Management. (4th ed.).,
Newtown Square Penn.: Project Management Institute, 2010
Frame, J. Davidson. Managing Projects in Organizations: How to Make the Best Use of Time,
Techniques and People. Rev. ed. San Francisco: Jossey-Bass, 1995.
Maslow, Abraham H. Motivation and Personality. New York Harper and Row, 1954
McGregor, Douglas. The Human Side of Enterprise. New York, NY McGraw-Hill, 1960
Meredith, Jack R., & Mantel, Jr., Samuel J. Project Management: A Managerial Approach, (5th
ed.). New York: John Wiley and Sons, 2003
Project Management Institute A Guide to the Project Management Body of l<nowledge, (S'h
0
ed.) (PMBOK Guide). Newtown Square Penn.: Project Management Institute. 2012.
Rosen, Robert, Patricia Digh, Marshall Singer, and Carl Phillips. Global Literacies: Lessons on
Business Leadership and National Cultures. New York: Simon 81 Schuster, 2000
Verma, Vijay I<. Human Resource Skills for the Project Manager. Volume 2 of The Human
Aspects of Project Management. Upper Darby, Penn.: Project Management Institute, 1996
Verma, Vijay K. Organizing Projects for Success. Volume 1 of The Human Aspects of Project
Management. Upper Darby, Penn.: Project Management Institute, 1996
Walker, Danielle Medina and & Walker, Thomas. Doing Business Internationally: The Guide
to Cross-Cultural Success. New York: McGraw-Hill, 2003
Wideman, R. Max, Project and Program Risk Management: A Guide to Managing Project
Risks and Opportunities. , Newtown Square Penn.: Project Management Institute, 1992
I
0
Congratulations to you on making the commitment to obtain your PMP credential. This
designation, and the knowledge gained by achieving it, will set you apart from your peers
and help you achieve higher levels in the performance of your work.
Aileen hopes this book benefits you greatly on your path to success. Please send any
comments or suggestions for improvement directly to the author at aileen@aileenellis.com.
Finally, good luck in all your future endeavors!
©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP 485
aileen@amegroupinc.com 719-659-3658
Full Sample Test
486 ©January 2016 AME Group, Inc. author Aileen Ellis, PMP, PgMP
aileerncvamegroupinc.com 719-659-3658
Made in the USA
Columbia, SC
JO May 2017