06-Feb-21 15:16

Power Supply to Al-Alamia 115/13.8kv S/S in Dammam

Activity ID Activity Name Original Duration Start Finish 2021 2022 2023
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

Power Supply to Al-Alamia 115/13.8kv S/S in Dammam 724 30-Dec-20 27-Apr-23 27-Apr-23, Power Supply to Al-Ala

PROJECT MILESTONES 724 30-Dec-20 27-Apr-23 27-Apr-23, PROJECT MILES TONE

Milestone100 Contract Effective Date - Start of Work 0 30-Dec-20 Contract Effect ive Date - S tart of Work, 30-Dec-20

Milestone300 Start of Construction 0 20-May-21 Start of Construction, 20-May-21

Milestone200 Finish Design & Engineering(IFC) 0 21-Sep-21 Finish Design & Engineering(IFC),

Milestone400 Start of Testing and Comissioning 0 09-Jul-22 Start of Testing and Comissioning, 09-Jul-22

Milestone500 Technical Completion- TCC 0 29-Dec-22 Technical Completion- TCC,

Milestone600 Preliminary Acceptance- PAC 0 28-Feb-23 Preliminary Acceptance- PAC,

Milestone700 Final Acceptance- FAC Signed 0 27-Apr-23 Final Acceptance- FAC Signed,

Engineering & Design 224 30-Dec-20 21-Sep-21 21-Sep-21, Engineering & Design
BD - Base Design 114 30-Dec-20 16-May-21 16-May-21, BD - Base Design

BD10 BD - Base Design - Electrical, Protection & SAS, Civil & Mechanical Design Drawings 78 30-Dec-20 30-Mar-21 BD - Base Design - Electrical, Protection & SAS, Civil & Mechanical Design Drawings

BD20 Review of Base Design Package by NG 26 31-Mar-21 29-Apr-21 Review of Base Design Package by NG

BD30 Base Design Review Meeting (BDRM) 10 01-May-21 16-May-21 Base Design Review Meeting (BDRM)
BD - Base Design - Equipment Submittals / Vendor Drawings 78 30-Dec-20 30-Mar-21 30-Mar-21, BD - Base Design - Equipment Submittals / Vendor Drawings

BD-EQP20 BD - Base Design - Equipment Submittals / Vendor Drawings 78 30-Dec-20 30-Mar-21 BD - Base Design - Equipment Submittals / Vendor Drawings

BD-EQP10 BD - Equipment Submittal - 115 kV GIS 78 30-Dec-20 30-Mar-21 BD - Equipment Submittal - 115 kV GIS

BD-EQP30 BD - Equipment Submittal - 115 kV GIS Bus Ducts 78 30-Dec-20 30-Mar-21 BD - Equipment Submittal - 115 kV GIS Bus Ducts

BD-EQP40 BD - Equipment Submittal - LCC 78 30-Dec-20 30-Mar-21 BD - Equipment Submittal - LCC

BD-EQP50 BD - Equipment Submittal - 108 kV Surge arrester 78 30-Dec-20 30-Mar-21 BD - Equipment Submittal - 108 kV Surge arrester

BD-EQP60 BD - Equipment Submittal - 13.8 kV Switchgear 78 30-Dec-20 30-Mar-21 BD - Equipment Submittal - 13.8 kV Switchgear

BD-EQP70 BD - Equipment Submittal 50/67 MVA 115/13.8 kV Power Transformer 78 30-Dec-20 30-Mar-21 BD - Equipment Submittal 50/67 MVA 115/13.8 kV Power Transformer

BD-EQP80 BD-Equipment Submittal-500 KVA,13.8kV/400-230V Aux.Transformer 78 30-Dec-20 30-Mar-21 BD-Equipment Submittal-500 KVA,13.8kV/400-230V Aux.Transformer

BD-EQP90 BD - Equipment Submittal - 13.8 kV XLPE Cable 78 30-Dec-20 30-Mar-21 BD - Equipment Submittal - 13.8 kV XLPE Cable

BD-EQP100 BD - Equipment Submittal - Battery and Battery Charger 78 30-Dec-20 30-Mar-21 BD - Equipment Submittal - Battery and Battery Charger

BD-EQP110 BD - Equipment Submittal - LV Power & Control Cables 78 30-Dec-20 30-Mar-21 BD - Equipment Submittal - LV Power & Control Cables

BD-EQP120 BD - Equipment Submittal - Grounding and Shielding System 78 30-Dec-20 30-Mar-21 BD - Equipment Submittal - Grounding and Shielding System

BD-EQP130 BD - Equipment Submittal - Control and Protection Panels 78 30-Dec-20 30-Mar-21 BD - Equipment Submittal - Control and Protection Panels

BD-EQP140 BD - Equipment Submittal - SAS Panels 78 30-Dec-20 30-Mar-21 BD - Equipment Submittal - SAS Panels

BD-EQP150 BD - Equipment Submittal - Communication System 78 30-Dec-20 30-Mar-21 BD - Equipment Submittal - Communication System

BD-EQP160 BD - Equipment Submittal - Safety & Fire Protection 78 30-Dec-20 30-Mar-21 BD - Equipment Submittal - Safety & Fire Protection

BD-EQP170 BD - Equipment Submittal - Cyber Security System 78 30-Dec-20 30-Mar-21 BD - Equipment Submittal - Cyber Security System

BD-EQP180 BD - Equipment Submittal - CCTV System 78 30-Dec-20 30-Mar-21 BD - Equipment Submittal - CCTV System
DD - Detail Design Package 74 17-May-21 10-Aug-21 10-Aug-21, DD - Detail Design Package

DD10 DD - Detail Design - Electrical, Protection & SAS & Mechanical Design Drawings 60 17-May-21 25-Jul-21 DD - Detail Design - Electrical, Protection & SAS & Mechanical Design Drawings

DD40 Detail Design Civil 30 17-May-21 20-Jun-21 Detail Design Civil

DD50 Detail Design Review for Civil by NG 14 21-Jun-21 06-Jul-21 Detail Design Review for Civil by NG

DD20 Review of Detail Design Package by NG 14 26-Jul-21 10-Aug-21 Review of Detail Design Package by NG
IFC- Issued For Construction Drawing 66 07-Jul-21 21-Sep-21 21-Sep-21, IFC- Issued For Construction Drawing

IFC10 IFC for Civil 14 07-Jul-21 22-Jul-21 IFC for Civil

IFC30 IFC for Electrical 36 11-Aug-21 21-Sep-21 IFC for Electrical

IFC40 IFC for Protection & SAS 36 11-Aug-21 21-Sep-21 IFC for Protection & SAS

IFC20 IFC for Mechanical 14 11-Aug-21 26-Aug-21 IFC for Mechanical

PE - Procurement Material / Equipment Delivery 390 30-Dec-20 03-Apr-22 03-Apr-22, PE - Procurement Material / Equipment Delivery
PE - Delivery - 115 kV GIS & 115/13.8KV, 50/ 67 MVA P ow er Transformers 351 30-Dec-20 16-Feb-22 16-Feb-22, PE - Delivery - 115 kV GIS & 115/13.8KV, 50/ 67 MVA Power Transformers

Actual Level of Effort Remaining Work Milestone Page 1 of 14 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
  06-Feb-21 15:16

Power Supply to Al-Alamia 115/13.8kv S/S in Dammam

Activity ID Activity Name Original Duration Start Finish 2021 2022 2023
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

PROCURE10 Release PO 20 30-Dec-20 21-Jan-21 Release PO

PROCURE11 Manufacturing Period 142 17-May-21 28-Oct-21 Manufacturing Period

PROCURE12 FAT 3 30-Oct-21 01-Nov-21 FAT

PROCURE13 FAT Report by NG 30 02-Nov-21 06-Dec-21 FAT Report by NG

PROCURE14 Release for Shipment 1 07-Dec-21 07-Dec-21 Release for Shipment

PROCURE16 CIF (Seaport) 45 08-Dec-21 29-Jan-22 CIF (Seaport)

PROCURE15 Custom Clearance 14 30-Jan-22 14-Feb-22 Custom Clearance

PROCURE17 Delivery at Site 2 15-Feb-22 16-Feb-22 Delivery at Site


PE - Delivery -108 kV Surge Arr estor 215 17-May-21 22-Jan-22 22-Jan-22, PE - Delivery -108 kV Surge Arrestor

PROCURE19 Release PO 20 17-May-21 08-Jun-21 Release PO

PROCURE18 Manufacturing Period 120 17-May-21 03-Oct-21 Manufacturing Period

PROCURE20 FAT 3 04-Oct-21 06-Oct-21 FAT

PROCURE21 FAT Report by NG 30 07-Oct-21 10-Nov-21 FAT Report by NG

PROCURE22 Release for Shipment 1 11-Nov-21 11-Nov-21 Release for Shipment

PROCURE23 CIF (Seaport) 45 13-Nov-21 03-Jan-22 CIF (Seaport)

PROCURE24 Custom Clearance 14 04-Jan-22 19-Jan-22 Custom Clearance

PROCURE25 Delivery at Site 2 20-Jan-22 22-Jan-22 Delivery at Site


PE - Delivery - 500 KVA, 13.8 kV/400-230V Aux.Transformer 300 30-Dec-20 19-Dec-21 19-Dec-21, PE - Delivery - 500 KVA, 13.8 kV/400-230V Aux.Transformer

PROCURE26 Release PO 17 30-Dec-20 18-Jan-21 Release PO

PROCURE27 Manufacturing Period 150 17-May-21 07-Nov-21 Manufacturing Period

PROCURE28 FAT 3 08-Nov-21 10-Nov-21 FAT

PROCURE29 FAT Report by NG 30 11-Nov-21 15-Dec-21 FAT Report by NG

PROCURE30 Release for Shipment 1 16-Dec-21 16-Dec-21 Release for Shipment

PROCURE31 Delivery at Site 2 18-Dec-21 19-Dec-21 Delivery at Site


PE - Delivery - AC |DC Pa nel s 300 30-Dec-20 19-Dec-21 19-Dec-21, PE - Delivery - AC|DC Panels

PROCURE32 Release PO 17 30-Dec-20 18-Jan-21 Release PO

PROCURE33 Manufacturing Period 150 17-May-21 07-Nov-21 Manufacturing Period

PROCURE34 FAT 3 08-Nov-21 10-Nov-21 FAT

PROCURE35 FAT Report by NG 30 11-Nov-21 15-Dec-21 FAT Report by NG

PROCURE36 Release for Shipment 1 16-Dec-21 16-Dec-21 Release for Shipment

PROCURE37 Delivery at Site 2 18-Dec-21 19-Dec-21 Delivery at Site


PE - Delivery - Protection & Control Panels 350 30-Dec-20 15-Feb-22 15-Feb-22, PE - Delivery - Protection & Control Panels

PROCURE38 Release PO 17 30-Dec-20 18-Jan-21 Release PO

PROCURE39 Manufacturing Period 200 17-May-21 04-Jan-22 Manufacturing Period

PROCURE40 FAT 3 05-Jan-22 08-Jan-22 FAT

PROCURE41 FAT Report by NG 30 09-Jan-22 12-Feb-22 FAT Report by NG

PROCURE42 Release for Shipment 1 13-Feb-22 13-Feb-22 Release for Shipment

PROCURE43 Delivery at Site 2 14-Feb-22 15-Feb-22 Delivery at Site


PE - Delivery -Substation Au tomati on S ys tem 350 30-Dec-20 15-Feb-22 15-Feb-22, PE - Delivery -Substation Automation System

PROCURE44 Release PO 17 30-Dec-20 18-Jan-21 Release PO

PROCURE45 Manufacturing Period 200 17-May-21 04-Jan-22 Manufacturing Period

PROCURE46 FAT 3 05-Jan-22 08-Jan-22 FAT

PROCURE47 FAT Report by NG 30 09-Jan-22 12-Feb-22 FAT Report by NG

PROCURE48 Release for Shipment 1 13-Feb-22 13-Feb-22 Release for Shipment

PROCURE49 Delivery at Site 2 14-Feb-22 15-Feb-22 Delivery at Site

Actual Level of Effort Remaining Work Milestone Page 2 of 14 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
  06-Feb-21 15:16

Power Supply to Al-Alamia 115/13.8kv S/S in Dammam

Activity ID Activity Name Original Duration Start Finish 2021 2022 2023
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
PE - Delivery -13.8 kV Switchgear 350 30-Dec-20 15-Feb-22 15-Feb-22, PE - Delivery -13.8 kV Switchgear

PROCURE52 Release PO 17 30-Dec-20 18-Jan-21 Release PO

PROCURE53 Manufacturing Period 200 17-May-21 04-Jan-22 Manufacturing Period

PROCURE54 FAT 3 05-Jan-22 08-Jan-22 FAT

PROCURE55 FAT Report by NG 30 09-Jan-22 12-Feb-22 FAT Report by NG

PROCURE56 Release for Shipment 1 13-Feb-22 13-Feb-22 Release for Shipment

PROCURE57 Delivery at Site 2 14-Feb-22 15-Feb-22 Delivery at Site


PE - Delivery -Capacitor Bank 329 30-Dec-20 22-Jan-22 22-Jan-22, PE - Delivery -Capacitor Bank

PROCURE58 Release PO 20 30-Dec-20 21-Jan-21 Release PO


PROCURE59 Manufacturing Period 120 17-May-21 03-Oct-21 Manufacturing Period

PROCURE60 FAT 3 04-Oct-21 06-Oct-21 FAT

PROCURE61 FAT Report by NG 30 07-Oct-21 10-Nov-21 FAT Report by NG

PROCURE62 Release for Shipment 1 11-Nov-21 11-Nov-21 Release for Shipment

PROCURE64 CIF (Seaport) 45 13-Nov-21 03-Jan-22 CIF (Seaport)

PROCURE65 Custom Clearance 14 04-Jan-22 19-Jan-22 Custom Clearance

PROCURE66 Delivery at Site 2 20-Jan-22 22-Jan-22 Delivery at Site


PE - Delivery -Batteries & Battery Charger 329 30-Dec-20 22-Jan-22 22-Jan-22, PE - Delivery -Batteries & Battery Charger

PROCURE67 Release PO 13 30-Dec-20 13-Jan-21 Release PO

PROCURE68 Manufacturing Period 120 17-May-21 03-Oct-21 Manufacturing Period

PROCURE69 FAT 3 04-Oct-21 06-Oct-21 FAT

PROCURE70 FAT Report by NG 30 07-Oct-21 10-Nov-21 FAT Report by NG

PROCURE71 Release for Shipment 1 11-Nov-21 11-Nov-21 Release for Shipment

PROCURE72 CIF (Seaport) 45 13-Nov-21 03-Jan-22 CIF (Seaport)

PROCURE73 Custom Clearance 14 04-Jan-22 19-Jan-22 Custom Clearance

PROCURE74 Delivery at Site 2 20-Jan-22 22-Jan-22 Delivery at Site


PE - Delivery - Communication System 350 30-Dec-20 15-Feb-22 15-Feb-22, PE - Delivery - Communication System

PROCURE75 Release PO 20 30-Dec-20 21-Jan-21 Release PO

PROCURE76 Manufacturing Period 200 17-May-21 04-Jan-22 Manufacturing Period

PROCURE77 FAT 3 05-Jan-22 08-Jan-22 FAT

PROCURE78 FAT Report by NG 30 09-Jan-22 12-Feb-22 FAT Report by NG

PROCURE79 Release for Shipment 1 13-Feb-22 13-Feb-22 Release for Shipment

PROCURE80 Delivery at Site 2 14-Feb-22 15-Feb-22 Delivery at Site


PE - Delivery - Fire Protection 335 11-Feb-21 13-Mar-22 13-Mar-22, PE - Delivery - Fire Protection

PROCURE81 Release PO 20 11-Feb-21 06-Mar-21 Release PO

PROCURE82 Manufacturing Period 150 11-Aug-21 01-Feb-22 Manufacturing Period

PROCURE83 FAT 1 02-Feb-22 02-Feb-22 FAT

PROCURE84 FAT Report by NG 30 03-Feb-22 09-Mar-22 FAT Report by NG

PROCURE85 Release for Shipment 1 10-Mar-22 10-Mar-22 Release for Shipment

PROCURE86 Delivery at Site 2 12-Mar-22 13-Mar-22 Delivery at Site


PE - Delivery - HVAC 188 28-Aug-21 03-Apr-22 03-Apr-22, PE - Delivery - HVAC

PROCURE92 Release PO 2 28-Aug-21 29-Aug-21 Release PO

PROCURE87 Manufacturing Period 150 30-Aug-21 20-Feb-22 Manufacturing Period

PROCURE88 FAT 3 21-Feb-22 23-Feb-22 FAT

PROCURE89 FAT Report by NG 30 24-Feb-22 30-Mar-22 FAT Report by NG

PROCURE90 Release for Shipment 1 31-Mar-22 31-Mar-22 Release for Shipment

Actual Level of Effort Remaining Work Milestone Page 3 of 14 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
  06-Feb-21 15:16

Power Supply to Al-Alamia 115/13.8kv S/S in Dammam

Activity ID Activity Name Original Duration Start Finish 2021 2022 2023
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

PROCURE910 Delivery at Site 2 02-Apr-22 03-Apr-22 Delivery at Site


PE - Delivery - LV Power and Control Cables 158 11-Aug-21 10-Feb-22 10-Feb-22, PE - Delivery - LV Power and Control Cables

PROCURE93 Release PO 2 11-Aug-21 12-Aug-21 Release PO

PROCURE94 Manufacturing Period 120 14-Aug-21 30-Dec-21 Manufacturing Period

PROCURE95 FAT 3 01-Jan-22 03-Jan-22 FAT

PROCURE96 FAT Report by NG 30 04-Jan-22 07-Feb-22 FAT Report by NG

PROCURE97 Release for Shipment 1 08-Feb-22 08-Feb-22 Release for Shipment

PROCURE98 Delivery at Site 2 09-Feb-22 10-Feb-22 Delivery at Site


PE - Delivery -MV Power Cable 158 11-Aug-21 10-Feb-22 10-Feb-22, PE - Delivery -MV Power Cable

PROCURE99 Release PO 2 11-Aug-21 12-Aug-21 Release PO

PROCURE100 Manufacturing Period 120 14-Aug-21 30-Dec-21 Manufacturing Period

PROCURE101 FAT 3 01-Jan-22 03-Jan-22 FAT

PROCURE102 FAT Report by NG 30 04-Jan-22 07-Feb-22 FAT Report by NG

PROCURE103 Release for Shipment 1 08-Feb-22 08-Feb-22 Release for Shipment

PROCURE104 Delivery at Site 2 09-Feb-22 10-Feb-22 Delivery at Site


PE - Delivery -Cable Tray 128 11-Aug-21 06-Jan-22 06-Jan-22, PE - Delivery -Cable Tray

PROCURE105 Release PO 2 11-Aug-21 12-Aug-21 Release PO

PROCURE106 Manufacturing Period 90 14-Aug-21 25-Nov-21 Manufacturing Period

PROCURE107 FAT 3 27-Nov-21 29-Nov-21 FAT

PROCURE108 FAT Report by NG 30 30-Nov-21 03-Jan-22 FAT Report by NG

PROCURE109 Release for Shipment 1 04-Jan-22 04-Jan-22 Release for Shipment

PROCURE110 Delivery at Site 2 05-Jan-22 06-Jan-22 Delivery at Site


PE - Delivery -Lighting System 158 11-Aug-21 10-Feb-22 10-Feb-22, PE - Delivery -Lighting System

PROCURE111 Release PO 2 11-Aug-21 12-Aug-21 Release PO

PROCURE112 Manufacturing Period 120 14-Aug-21 30-Dec-21 Manufacturing Period

PROCURE113 FAT 3 01-Jan-22 03-Jan-22 FAT

PROCURE114 FAT Report by NG 30 04-Jan-22 07-Feb-22 FAT Report by NG

PROCURE115 Release for Shipment 1 08-Feb-22 08-Feb-22 Release for Shipment

PROCURE116 Delivery at Site 2 09-Feb-22 10-Feb-22 Delivery at Site


PE - Delivery -Plumbing and Pump System 125 11-Aug-21 03-Jan-22 03-Jan-22, PE - Delivery -Plumbing and Pump System

PROCURE117 Release PO 2 11-Aug-21 12-Aug-21 Release PO

PROCURE118 Manufacturing Period 120 14-Aug-21 30-Dec-21 Manufacturing Period

PROCURE119 Release for Shipment 1 01-Jan-22 01-Jan-22 Release for Shipment

PROCURE120 Delivery at Site 2 02-Jan-22 03-Jan-22 Delivery at Site


PE - Delivery - S/S Doors and Hardwares 85 07-Jul-21 13-Oct-21 13-Oct-21, PE - Delivery - S/S Doors and Hardwares

PROCURE121 Release PO 2 07-Jul-21 08-Jul-21 Release PO

PROCURE122 Manufacturing Period 80 10-Jul-21 10-Oct-21 Manufacturing Period

PROCURE123 Release for Shipment 1 11-Oct-21 11-Oct-21 Release for Shipment

PROCURE124 Delivery at Site 2 12-Oct-21 13-Oct-21 Delivery at Site


PE - Delivery -GIS Room Crane 83 17-May-21 21-Aug-21 21-Aug-21, PE - Delivery -GIS Room Crane

PROCURE125 Release PO 2 17-May-21 18-May-21 Release PO

PROCURE126 Manufacturing Period 60 19-May-21 27-Jul-21 Manufacturing Period

PROCURE127 FAT 3 28-Jul-21 31-Jul-21 FAT

PROCURE128 FAT Report by NG 15 01-Aug-21 17-Aug-21 FAT Report by NG

PROCURE129 Release for Shipment 1 18-Aug-21 18-Aug-21 Release for Shipment

Actual Level of Effort Remaining Work Milestone Page 4 of 14 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
  06-Feb-21 15:16

Power Supply to Al-Alamia 115/13.8kv S/S in Dammam

Activity ID Activity Name Original Duration Start Finish 2021 2022 2023
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

PROCURE130 Delivery at Site 2 19-Aug-21 21-Aug-21 Delivery at Site


PE - Delivery - Cyber Security 344 30-Dec-20 08-Feb-22 08-Feb-22, PE - Delivery - Cyber Security

PROCURE131 Release PO 2 30-Dec-20 31-Dec-20 Release PO

PROCURE132 Manufacturing Period 120 11-Aug-21 28-Dec-21 Manufacturing Period

PROCURE133 FAT 3 29-Dec-21 01-Jan-22 FAT

PROCURE134 FAT Report by NG 30 02-Jan-22 05-Feb-22 FAT Report by NG

PROCURE135 Release for Shipment 1 06-Feb-22 06-Feb-22 Release for Shipment

PROCURE136 Delivery at Site 2 07-Feb-22 08-Feb-22 Delivery at Site

CONSTRUCTION 541 30-Dec-20 26-Sep-22 26-Sep-22, CONSTRUCTION


CV- Civ il Work s 286 20-May-21 18-Apr-22 18-Apr-22, CV- Civil Works
MAIN BUILDING 224 20-May-21 05-Feb-22 05-Feb-22, MAIN BUILDING
Sub Structure works 64 20-May-21 02-Aug-21 02-Aug-21, Sub Structure works

CV-MB-Sub1000 Excavation works 5 20-May-21* 25-May-21 Excavation works

CV-MB-Sub1013 Backfilling & compaction 4 26-May-21 30-May-21 Backfilling & compaction

CV-MB-Sub1014 Lean Concrete 1 31-May-21 31-May-21 Lean Concrete

CV-MB-Sub1001 Applying membrane water proofing system 4 01-Jun-21 05-Jun-21 Applying membrane water proofing system

CV-MB-Sub1002 Pouring screed above waterproofing 3 06-Jun-21 08-Jun-21 Pouring screed above waterproofing

CV-MB-Sub1003 Steel and form works for raft foundation 10 09-Jun-21 20-Jun-21 Steel and form works for raft foundation

CV-MB-Sub1004 Concrete pouring for raft foundation 1 21-Jun-21 21-Jun-21 Concrete pouring for raft foundation

CV-MB-Sub1005 Deshuttering for raft foundation 2 22-Jun-21 23-Jun-21 Deshuttering for raft foundation

CV-MB-Sub1006 Steel and form works for columns and basement walls 14 24-Jun-21 10-Jul-21 Steel and form works for columns and basement walls

CV-MB-Sub1007 Concrete pouring for columns and basement walls 1 11-Jul-21 11-Jul-21 Concrete pouring for columns and basement walls

CV-MB-Sub1008 Deshuttering for columns and basemnet walls 4 12-Jul-21 15-Jul-21 Deshuttering for columns and basemnet walls

CV-MB-Sub1009 Steel and form works for basement slab 14 17-Jul-21 01-Aug-21 Steel and form works for basement slab

CV-MB-Sub1011 Basement Wall water proofing 8 17-Jul-21 25-Jul-21 Basement Wall water proofing

CV-MB-Sub1012 Outer backfilling 6 26-Jul-21 01-Aug-21 Outer backfilling

CV-MB-Sub1010 Concrete pouring of basement slab 1 02-Aug-21 02-Aug-21 Concrete pouring of basement slab
Super Structure works 83 26-May-21 30-Aug-21 30-Aug-21, Super Structure works

CV-MB-SS1000 Manufacturing of precast Columns 20 26-May-21 17-Jun-21 Manufacturing of precast Columns

CV-MB-SS1001 Manufacturing of precast Beams 20 07-Jun-21 29-Jun-21 Manufacturing of precast Beams

CV-MB-SS1002 Manufacturing of precast TT slab 20 19-Jun-21 11-Jul-21 Manufacturing of precast TT slab

CV-MB-SS1003 Manufacturing of precast Holow core slab 20 30-Jun-21 22-Jul-21 Manufacturing of precast Holow core slab

CV-MB-SS1004 Erection for beams and columns 6 15-Aug-21 21-Aug-21 Erection for beams and columns

CV-MB-SS1005 Over head crane installation 6 22-Aug-21 28-Aug-21 Over head crane installation

CV-MB-SS1006 Erection for slabs 2 29-Aug-21 30-Aug-21 Erection for slabs


Finishing works 161 02-Aug-21 05-Feb-22 05-Feb-22, Finishing works

CV-MB-FW1001 Walkway and ramp activities 25 02-Aug-21 30-Aug-21 Walkway and ramp activities

CV-MB-FW1003 Installation of Conducits, JunctionBox for Telephone system, Fire Alaram & Fire Fighting45System
12-Aug-21
& Lighting
03-Oct-21
System Installation of Conducits, JunctionBox for Telephone system, Fire Alaram & Fire Fighting System & Lighting System

CV-MB-FW1011 Roof waterproofing works WITH SCREED 15 31-Aug-21 16-Sep-21 Roof waterproofing works WITH SCREED

CV-MB-FW1000 Cementitious coation for basement walls 7 05-Sep-21 12-Sep-21 Cementitious coation for basement walls

CV-MB-FW1004 Block works for staire cases at basement 10 05-Sep-21 15-Sep-21 Block works for staire cases at basement

CV-MB-FW1005 Block works for ground floor 15 16-Sep-21 03-Oct-21 Block works for ground floor

CV-MB-FW1006 Interior plastering works 10 04-Oct-21 14-Oct-21 Interior plastering works

CV-MB-FW1007 Interior painting works for walls and ceilling 14 16-Oct-21 31-Oct-21 Interior painting works for walls and ceilling

CV-MB-FW1009 Doors installation 4 16-Oct-21 19-Oct-21 Doors installation

Actual Level of Effort Remaining Work Milestone Page 5 of 14 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
  06-Feb-21 15:16

Power Supply to Al-Alamia 115/13.8kv S/S in Dammam

Activity ID Activity Name Original Duration Start Finish 2021 2022 2023
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

CV-MB-FW1008 Epoxy coating for ground floor. 6 01-Nov-21 07-Nov-21 Epoxy coating for ground floor.

CV-MB-FW1010 Exterior painting works 20 01-Nov-21 23-Nov-21 Exterior painting works

CV-MB-FW1002 Cable support and cable trays installation 25 08-Jan-22 05-Feb-22 Cable support and cable trays installation
TRANSFORMERS 156 02-Aug-21 30-Jan-22 30-Jan-22, TRANSFORMERS
115 Kv t ransformers 81 02-Aug-21 03-Nov-21 03-Nov-21, 115 Kv transformers
Tran sfo rmer # T 601 55 02-Aug-21 04-Oct-21 04-Oct-21, Transformer # T601

CV-Trans-01-1000 Excavation works 3 02-Aug-21 04-Aug-21 Excavation works

CV-Trans-01-1009 Backfilling & compaction 3 05-Aug-21 08-Aug-21 Backfilling & compaction

CV-Trans-01-1010 Lean Concrete 1 09-Aug-21 09-Aug-21 Lean Concrete

CV-Trans-01-1011 Applying membrane water proofing system 4 10-Aug-21 14-Aug-21 Applying membrane water proofing system

CV-Trans-01-1012 Pouring screed above waterproofing 1 15-Aug-21 15-Aug-21 Pouring screed above waterproofing

CV-Trans-01-1013 Steel and form works for raft foundation 6 16-Aug-21 22-Aug-21 Steel and form works for raft foundation

CV-Trans-01-1014 Concrete pouring for raft foundation 1 23-Aug-21 23-Aug-21 Concrete pouring for raft foundation

CV-Trans-01-1015 Deshuttering for raft foundation 2 24-Aug-21 25-Aug-21 Deshuttering for raft foundation

CV-Trans-01-1016 Steel and form works walls and transformer pad 10 26-Aug-21 06-Sep-21 Steel and form works walls and transformer pad

CV-Trans-01-1001 Concrete pouring for walls and transformer pad 1 07-Sep-21 07-Sep-21 Concrete pouring for walls and transformer pad

CV-Trans-01-1002 Deshuttering for walls and transformer pad 4 08-Sep-21 12-Sep-21 Deshuttering for walls and transformer pad

CV-Trans-01-1003 Cementitious coating 2 13-Sep-21 14-Sep-21 Cementitious coating

CV-Trans-01-1007 Outer side water proofing 6 13-Sep-21 19-Sep-21 Outer side water proofing

CV-Trans-01-1004 Steel grating installation 5 15-Sep-21 20-Sep-21 Steel grating installation

CV-Trans-01-1008 Outer side Backfilling 10 20-Sep-21 30-Sep-21 Outer side Backfilling

CV-Trans-01-1005 PU coating 10 21-Sep-21 02-Oct-21 PU coating

CV-Trans-01-1006 Laying gravel 2 03-Oct-21 04-Oct-21 Laying gravel


Tran sfo rmer # T 602 55 02-Aug-21 04-Oct-21 04-Oct-21, Transformer # T602

CV-Trans-02-1000 Excavation works 3 02-Aug-21 04-Aug-21 Excavation works

CV-Trans-02-1009 Backfilling & compaction 3 05-Aug-21 08-Aug-21 Backfilling & compaction

CV-Trans-02-1010 Lean Concrete 1 09-Aug-21 09-Aug-21 Lean Concrete

CV-Trans-02-1011 Applying membrane water proofing system 4 10-Aug-21 14-Aug-21 Applying membrane water proofing system

CV-Trans-02-1012 Pouring screed above waterproofing 1 15-Aug-21 15-Aug-21 Pouring screed above waterproofing

CV-Trans-02-1013 Steel and form works for raft foundation 6 16-Aug-21 22-Aug-21 Steel and form works for raft foundation

CV-Trans-02-1014 Concrete pouring for raft foundation 1 23-Aug-21 23-Aug-21 Concrete pouring for raft foundation

CV-Trans-02-1015 Deshuttering for raft foundation 2 24-Aug-21 25-Aug-21 Deshuttering for raft foundation

CV-Trans-02-1016 Steel and form works walls and transformer pad 10 26-Aug-21 06-Sep-21 Steel and form works walls and transformer pad

CV-Trans-02-1001 Concrete pouring for walls and transformer pad 1 07-Sep-21 07-Sep-21 Concrete pouring for walls and transformer pad

CV-Trans-02-1002 Deshuttering for walls and transformer pad 4 08-Sep-21 12-Sep-21 Deshuttering for walls and transformer pad

CV-Trans-02-1003 Cementitious coating 2 13-Sep-21 14-Sep-21 Cementitious coating

CV-Trans-02-1007 Outer side water proofing 6 13-Sep-21 19-Sep-21 Outer side water proofing

CV-Trans-02-1004 Steel grating installation 5 15-Sep-21 20-Sep-21 Steel grating installation

CV-Trans-02-1008 Outer side Backfilling 10 20-Sep-21 30-Sep-21 Outer side Backfilling

CV-Trans-02-1005 PU coating 10 21-Sep-21 02-Oct-21 PU coating

CV-Trans-02-1006 Laying gravel 2 03-Oct-21 04-Oct-21 Laying gravel


Tran sfo rmer # T 603 55 02-Aug-21 04-Oct-21 04-Oct-21, Transformer # T603

CV-Trans-03-1000 Excavation works 3 02-Aug-21 04-Aug-21 Excavation works

CV-Trans-03-1009 Backfilling & compaction 3 05-Aug-21 08-Aug-21 Backfilling & compaction

CV-Trans-03-1010 Lean Concrete 1 09-Aug-21 09-Aug-21 Lean Concrete

Actual Level of Effort Remaining Work Milestone Page 6 of 14 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
  06-Feb-21 15:16

Power Supply to Al-Alamia 115/13.8kv S/S in Dammam

Activity ID Activity Name Original Duration Start Finish 2021 2022 2023
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

CV-Trans-03-1011 Applying membrane water proofing system 4 10-Aug-21 14-Aug-21 Applying membrane water proofing system

CV-Trans-03-1012 Pouring screed above waterproofing 1 15-Aug-21 15-Aug-21 Pouring screed above waterproofing

CV-Trans-03-1013 Steel and form works for raft foundation 6 16-Aug-21 22-Aug-21 Steel and form works for raft foundation

CV-Trans-03-1014 Concrete pouring for raft foundation 1 23-Aug-21 23-Aug-21 Concrete pouring for raft foundation

CV-Trans-03-1015 Deshuttering for raft foundation 2 24-Aug-21 25-Aug-21 Deshuttering for raft foundation

CV-Trans-03-1016 Steel and form works walls and transformer pad 10 26-Aug-21 06-Sep-21 Steel and form works walls and transformer pad

CV-Trans-03-1001 Concrete pouring for walls and transformer pad 1 07-Sep-21 07-Sep-21 Concrete pouring for walls and transformer pad

CV-Trans-03-1002 Deshuttering for walls and transformer pad 4 08-Sep-21 12-Sep-21 Deshuttering for walls and transformer pad

CV-Trans-03-1003 Cementitious coating 2 13-Sep-21 14-Sep-21 Cementitious coating

CV-Trans-03-1007 Outer side water proofing 6 13-Sep-21 19-Sep-21 Outer side water proofing

CV-Trans-03-1004 Steel grating installation 5 15-Sep-21 20-Sep-21 Steel grating installation

CV-Trans-03-1008 Outer side Backfilling 10 20-Sep-21 30-Sep-21 Outer side Backfilling

CV-Trans-03-1005 PU coating 10 21-Sep-21 02-Oct-21 PU coating

CV-Trans-03-1006 Laying gravel 2 03-Oct-21 04-Oct-21 Laying gravel


Fire walls 39 20-Sep-21 03-Nov-21 03-Nov-21, Fire walls

CV-Trans-FW1000 Excavation works 1 20-Sep-21 20-Sep-21 Excavation works

CV-Trans-FW1005 Backfilling & compaction 2 21-Sep-21 22-Sep-21 Backfilling & compaction

CV-Trans-FW1006 Lean Concrete 1 23-Sep-21 23-Sep-21 Lean Concrete

CV-Trans-FW1007 Steel and form works for raft foundation 4 25-Sep-21 28-Sep-21 Steel and form works for raft foundation

CV-Trans-FW1008 Concrete pouring for raft foundation 1 29-Sep-21 29-Sep-21 Concrete pouring for raft foundation

CV-Trans-FW1009 Deshuttering for raft foundation 1 30-Sep-21 30-Sep-21 Deshuttering for raft foundation

CV-Trans-FW1010 Steel and form works walls stage 1 6 02-Oct-21 07-Oct-21 Steel and form works walls stage 1

CV-Trans-FW1011 Concrete pouring for walls stage 1 1 09-Oct-21 09-Oct-21 Concrete pouring for walls stage 1

CV-Trans-FW1012 Deshuttering for walls stage 2 2 10-Oct-21 11-Oct-21 Deshuttering for walls stage 2

CV-Trans-FW1001 Steel and form works walls stage 2 10 12-Oct-21 23-Oct-21 Steel and form works walls stage 2

CV-Trans-FW1002 Concrete pouring for walls stage 2 1 24-Oct-21 24-Oct-21 Concrete pouring for walls stage 2

CV-Trans-FW1003 Deshuttering for walls stage 2 3 25-Oct-21 27-Oct-21 Deshuttering for walls stage 2

CV-Trans-FW1004 Surface preparartion and coal tar epoxy 6 28-Oct-21 03-Nov-21 Surface preparartion and coal tar epoxy
Service station transformers 85 24-Oct-21 30-Jan-22 30-Jan-22, Service station transformers
Tran sfo rmes fo und atio n 55 24-Oct-21 26-Dec-21 26-Dec-21, Transformes foundation

CV-SS-Trans.F1016 Excavation works 2 24-Oct-21 25-Oct-21 Excavation works

CV-SS-Trans.F1001 Backfilling & compaction 3 26-Oct-21 28-Oct-21 Backfilling & compaction

CV-SS-Trans.F1002 Lean Concrete 1 30-Oct-21 30-Oct-21 Lean Concrete

CV-SS-Trans.F1003 Applying membrane water proofing system 4 31-Oct-21 03-Nov-21 Applying membrane water proofing system

CV-SS-Trans.F1004 Pouring screed above waterproofing 1 04-Nov-21 04-Nov-21 Pouring screed above waterproofing

CV-SS-Trans.F1005 Steel and form works for raft foundation 6 06-Nov-21 11-Nov-21 Steel and form works for raft foundation

CV-SS-Trans.F1006 Concrete pouring for raft foundation 1 13-Nov-21 13-Nov-21 Concrete pouring for raft foundation

CV-SS-Trans.F1007 Deshuttering for raft foundation 2 14-Nov-21 15-Nov-21 Deshuttering for raft foundation

CV-SS-Trans.F1008 Steel and form works walls and transformer pad 10 16-Nov-21 27-Nov-21 Steel and form works walls and transformer pad

CV-SS-Trans.F1000 Concrete pouring for walls and transformer pad 1 28-Nov-21 28-Nov-21 Concrete pouring for walls and transformer pad

CV-SS-Trans.F1009 Deshuttering for walls and transformer pad 3 29-Nov-21 01-Dec-21 Deshuttering for walls and transformer pad

CV-SS-Trans.F1010 Cementitious coating 2 02-Dec-21 04-Dec-21 Cementitious coating

CV-SS-Trans.F1011 Steel grating installation 4 05-Dec-21 08-Dec-21 Steel grating installation

CV-SS-Trans.F1012 PU coating 6 09-Dec-21 15-Dec-21 PU coating

CV-SS-Trans.F1013 Laying gravel 2 16-Dec-21 18-Dec-21 Laying gravel

Actual Level of Effort Remaining Work Milestone Page 7 of 14 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
  06-Feb-21 15:16

Power Supply to Al-Alamia 115/13.8kv S/S in Dammam

Activity ID Activity Name Original Duration Start Finish 2021 2022 2023
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

CV-SS-Trans.F1014 Outer side water proofing 4 19-Dec-21 22-Dec-21 Outer side water proofing

CV-SS-Trans.F1015 Outer side Backfilling 3 23-Dec-21 26-Dec-21 Outer side Backfilling


Fire wall 30 27-Dec-21 30-Jan-22 30-Jan-22, Fire wall

CV-SS-FW1000 Excavation works 1 27-Dec-21 27-Dec-21 Excavation works

CV-SS-FW1004 Backfilling & compaction 2 28-Dec-21 29-Dec-21 Backfilling & compaction

CV-SS-FW1005 Lean Concrete 1 30-Dec-21 30-Dec-21 Lean Concrete

CV-SS-FW1006 Steel and form works for raft foundation 3 01-Jan-22 03-Jan-22 Steel and form works for raft foundation

CV-SS-FW1007 Pouring raft with deshuttering 3 04-Jan-22 06-Jan-22 Pouring raft with deshuttering

CV-SS-FW1008 Steel and form works walls stage 1 4 08-Jan-22 11-Jan-22 Steel and form works walls stage 1

CV-SS-FW1009 Concrete pouring for walls stage 1 1 12-Jan-22 12-Jan-22 Concrete pouring for walls stage 1

CV-SS-FW1010 Deshuttering for walls stage 2 2 13-Jan-22 15-Jan-22 Deshuttering for walls stage 2

CV-SS-FW1011 Steel and form works walls stage 2 6 16-Jan-22 22-Jan-22 Steel and form works walls stage 2

CV-SS-FW1001 Concrete pouring for walls stage 2 1 23-Jan-22 23-Jan-22 Concrete pouring for walls stage 2

CV-SS-FW1002 Deshuttering for walls stage 2 2 24-Jan-22 25-Jan-22 Deshuttering for walls stage 2

CV-SS-FW1003 Surface preparartion and coal tar epoxy 4 26-Jan-22 30-Jan-22 Surface preparartion and coal tar epoxy
Out door Foundations 58 24-Oct-21 29-Dec-21 29-Dec-21, Out door Foundations
GIB foundation 38 24-Oct-21 06-Dec-21 06-Dec-21, GIB foundation

CV-OD.F-GIB1000 Excavation works 3 24-Oct-21 26-Oct-21 Excavation works

CV-OD.F-GIB1002 Backfilling & compaction 4 27-Oct-21 31-Oct-21 Backfilling & compaction

CV-OD.F-GIB1003 Lean Concrete 1 01-Nov-21 01-Nov-21 Lean Concrete

CV-OD.F-GIB1004 Steel and form works for raft foundation 6 02-Nov-21 08-Nov-21 Steel and form works for raft foundation

CV-OD.F-GIB1005 Concrete pouring for foundation 1 09-Nov-21 09-Nov-21 Concrete pouring for foundation

CV-OD.F-GIB1006 Deshuttering for foundation 2 10-Nov-21 11-Nov-21 Deshuttering for foundation

CV-OD.F-GIB1007 Steel and form works for Pedestal 10 13-Nov-21 23-Nov-21 Steel and form works for Pedestal

CV-OD.F-GIB1008 Concrete pouring for Pedestal 1 24-Nov-21 24-Nov-21 Concrete pouring for Pedestal

CV-OD.F-GIB1009 Deshuttering for Pedestal 4 25-Nov-21 29-Nov-21 Deshuttering for Pedestal

CV-OD.F-GIB1001 Surface preparartion and coal tar epoxy 6 30-Nov-21 06-Dec-21 Surface preparartion and coal tar epoxy
Lighting and lightning foundations 31 24-Nov-21 29-Dec-21 29-Dec-21, Lighting and lightning foundations

CV-OD.F-LT1000 Excavation works 3 24-Nov-21 27-Nov-21 Excavation works

CV-OD.F-LT1002 Backfilling & compaction 4 28-Nov-21 01-Dec-21 Backfilling & compaction

CV-OD.F-LT1003 Lean Concrete 1 02-Dec-21 02-Dec-21 Lean Concrete

CV-OD.F-LT1004 Steel and form works for raft foundation 4 04-Dec-21 07-Dec-21 Steel and form works for raft foundation

CV-OD.F-LT1005 Concrete pouring for foundation 1 08-Dec-21 08-Dec-21 Concrete pouring for foundation

CV-OD.F-LT1006 Deshuttering for foundation 2 09-Dec-21 11-Dec-21 Deshuttering for foundation

CV-OD.F-LT1007 Steel and form works for Pedestal 7 12-Dec-21 19-Dec-21 Steel and form works for Pedestal

CV-OD.F-LT1008 Concrete pouring for Pedestal 1 20-Dec-21 20-Dec-21 Concrete pouring for Pedestal

CV-OD.F-LT1009 Deshuttering for Pedestal 2 21-Dec-21 22-Dec-21 Deshuttering for Pedestal

CV-OD.F-LT1001 Surface preparartion and coal tar epoxy 6 23-Dec-21 29-Dec-21 Surface preparartion and coal tar epoxy
CAPACITOR BANK 42 02-Dec-21 19-Jan-22 19-Jan-22, CAPACITOR B ANK
Foundation for Capacitor Bank1 32 02-Dec-21 08-Jan-22 08-Jan-22, Foundation for Capacitor Bank1

CV-CB1-F1000 Excavation works 3 02-Dec-21 05-Dec-21 Excavation works

CV-CB1-F1003 Backfilling & compaction 2 06-Dec-21 07-Dec-21 Backfilling & compaction

CV-CB1-F1004 Lean Concrete 1 08-Dec-21 08-Dec-21 Lean Concrete

CV-CB1-F1005 Steel and form works for raft foundation 6 09-Dec-21 15-Dec-21 Steel and form works for raft foundation

CV-CB1-F1006 Concrete pouring for foundation 1 16-Dec-21 16-Dec-21 Concrete pouring for foundation

Actual Level of Effort Remaining Work Milestone Page 8 of 14 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
  06-Feb-21 15:16

Power Supply to Al-Alamia 115/13.8kv S/S in Dammam

Activity ID Activity Name Original Duration Start Finish 2021 2022 2023
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

CV-CB1-F1007 Deshuttering for foundation 2 18-Dec-21 19-Dec-21 Deshuttering for foundation

CV-CB1-F1008 Steel and form works for Pedestal 6 20-Dec-21 26-Dec-21 Steel and form works for Pedestal

CV-CB1-F1009 Concrete pouring for Pedestal 1 27-Dec-21 27-Dec-21 Concrete pouring for Pedestal

CV-CB1-F1001 Deshuttering for Pedestal 4 28-Dec-21 01-Jan-22 Deshuttering for Pedestal

CV-CB1-F1002 Surface preparartion and coal tar epoxy 6 02-Jan-22 08-Jan-22 Surface preparartion and coal tar epoxy
Foundation for Capacitor Bank2 32 02-Dec-21 08-Jan-22 08-Jan-22, Foundation for Capacitor Bank2

CV-CB2-F1000 Excavation works 3 02-Dec-21 05-Dec-21 Excavation works

CV-CB2-F1002 Backfilling & compaction 2 06-Dec-21 07-Dec-21 Backfilling & compaction

CV-CB2-F1003 Lean Concrete 1 08-Dec-21 08-Dec-21 Lean Concrete

CV-CB2-F1004 Steel and form works for raft foundation 6 09-Dec-21 15-Dec-21 Steel and form works for raft foundation

CV-CB2-F1005 Concrete pouring for foundation 1 16-Dec-21 16-Dec-21 Concrete pouring for foundation

CV-CB2-F1006 Deshuttering for foundation 2 18-Dec-21 19-Dec-21 Deshuttering for foundation

CV-CB2-F1007 Steel and form works for Pedestal 6 20-Dec-21 26-Dec-21 Steel and form works for Pedestal

CV-CB2-F1008 Concrete pouring for Pedestal 1 27-Dec-21 27-Dec-21 Concrete pouring for Pedestal

CV-CB2-F1009 Deshuttering for Pedestal 4 28-Dec-21 01-Jan-22 Deshuttering for Pedestal

CV-CB2-F1001 Surface preparartion and coal tar epoxy 6 02-Jan-22 08-Jan-22 Surface preparartion and coal tar epoxy
Foundation for Capacitor Bank3 32 02-Dec-21 08-Jan-22 08-Jan-22, Foundation for Capacitor Bank3

CV-CB3-F1000 Excavation works 3 02-Dec-21 05-Dec-21 Excavation works

CV-CB3-F1002 Backfilling & compaction 2 06-Dec-21 07-Dec-21 Backfilling & compaction

CV-CB3-F1003 Lean Concrete 1 08-Dec-21 08-Dec-21 Lean Concrete

CV-CB3-F1004 Steel and form works for raft foundation 6 09-Dec-21 15-Dec-21 Steel and form works for raft foundation

CV-CB3-F1005 Concrete pouring for foundation 1 16-Dec-21 16-Dec-21 Concrete pouring for foundation

CV-CB3-F1006 Deshuttering for foundation 2 18-Dec-21 19-Dec-21 Deshuttering for foundation

CV-CB3-F1007 Steel and form works for Pedestal 6 20-Dec-21 26-Dec-21 Steel and form works for Pedestal

CV-CB3-F1008 Concrete pouring for Pedestal 1 27-Dec-21 27-Dec-21 Concrete pouring for Pedestal

CV-CB3-F1009 Deshuttering for Pedestal 4 28-Dec-21 01-Jan-22 Deshuttering for Pedestal

CV-CB3-F1001 Surface preparartion and coal tar epoxy 6 02-Jan-22 08-Jan-22 Surface preparartion and coal tar epoxy
Fence for capacitor bank 16 02-Jan-22 19-Jan-22 19-Jan-22, Fence for capacitor bank

CV-CB-CB.F1000 Fence foundation works 10 02-Jan-22 12-Jan-22 Fence foundation works

CV-CB-CB.F1001 Fence installation and tightining 4 13-Jan-22 17-Jan-22 Fence installation and tightining

CV-CB-CB.F1002 Doors installation and alighnment 2 18-Jan-22 19-Jan-22 Doors installation and alighnment
DUCT BANK and Manholes 67 26-Jul-21 11-Oct-21 11-Oct-21, DUCT BANK and Manholes
Capacitot bank 61 02-Aug-21 11-Oct-21 11-Oct-21, Capacitot bank
Duct Bank 14 02-Aug-21 17-Aug-21 17-Aug-21, Duct Bank

CV-DB.MH-DB1000 Excavation 4 02-Aug-21 05-Aug-21 Excavation

CV-DB.MH-DB1001 Pipe installation 6 07-Aug-21 12-Aug-21 Pipe installation

CV-DB.MH-DB1002 Backfilling 4 14-Aug-21 17-Aug-21 Backfilling


Manholes 47 18-Aug-21 11-Oct-21 11-Oct-21, Manholes

CV-DB.MH-MH1000 Excavation works 4 18-Aug-21 22-Aug-21 Excavation works

CV-DB.MH-MH1007 Backfilling & compaction 3 23-Aug-21 25-Aug-21 Backfilling & compaction

CV-DB.MH-MH1008 Lean Concrete 1 26-Aug-21 26-Aug-21 Lean Concrete

CV-DB.MH-MH1009 Applying membrane water proofing system 4 28-Aug-21 31-Aug-21 Applying membrane water proofing system

CV-DB.MH-MH1010 Pouring screed above waterproofing 1 01-Sep-21 01-Sep-21 Pouring screed above waterproofing

CV-DB.MH-MH1011 Steel and form works for raft foundation 6 02-Sep-21 08-Sep-21 Steel and form works for raft foundation

CV-DB.MH-MH1012 Concrete pouring for raft foundation 1 09-Sep-21 09-Sep-21 Concrete pouring for raft foundation

Actual Level of Effort Remaining Work Milestone Page 9 of 14 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
  06-Feb-21 15:16

Power Supply to Al-Alamia 115/13.8kv S/S in Dammam

Activity ID Activity Name Original Duration Start Finish 2021 2022 2023
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

CV-DB.MH-MH1013 Deshuttering for raft foundation 2 11-Sep-21 12-Sep-21 Deshuttering for raft foundation

CV-DB.MH-MH1014 Steel and form works for walls 7 13-Sep-21 20-Sep-21 Steel and form works for walls

CV-DB.MH-MH1001 Concrete pouring for walls 1 21-Sep-21 21-Sep-21 Concrete pouring for walls

CV-DB.MH-MH1002 Deshuttering for walls 2 22-Sep-21 23-Sep-21 Deshuttering for walls

CV-DB.MH-MH1003 Steel and form works for slab 4 25-Sep-21 28-Sep-21 Steel and form works for slab

CV-DB.MH-MH1004 Concrete pouring of slab 1 29-Sep-21 29-Sep-21 Concrete pouring of slab

CV-DB.MH-MH1005 Wall water proofing 6 30-Sep-21 06-Oct-21 Wall water proofing

CV-DB.MH-MH1006 Outer backfilling 4 07-Oct-21 11-Oct-21 Outer backfilling


115 KV duct banks 14 26-Jul-21 10-Aug-21 10-Aug-21, 115 KV duct banks

CV-DB.MH-115DB1000 Excavation 4 26-Jul-21 29-Jul-21 Excavation

CV-DB.MH-115DB1001 Pipe installation 6 31-Jul-21 05-Aug-21 Pipe installation

CV-DB.MH-115DB1002 Backfilling 4 07-Aug-21 10-Aug-21 Backfilling


13.8 KV duct banks 14 11-Aug-21 26-Aug-21 26-Aug-21, 13.8 KV duct banks

CV-DB.MH-13.8DB1000 Excavation 4 11-Aug-21 15-Aug-21 Excavation

CV-DB.MH-13.8DB1001 Pipe installation 6 16-Aug-21 22-Aug-21 Pipe installation

CV-DB.MH-13.8DB1002 Backfilling 4 23-Aug-21 26-Aug-21 Backfilling


13.8 KV Manhole 36 28-Aug-21 07-Oct-21 07-Oct-21, 13.8 KV Manhole

CV-DB.MH-13.8MH1000 Excavation works 2 28-Aug-21 29-Aug-21 Excavation works

CV-DB.MH-13.8MH1007 Backfilling & compaction 1 30-Aug-21 30-Aug-21 Backfilling & compaction

CV-DB.MH-13.8MH1008 Lean Concrete 1 31-Aug-21 31-Aug-21 Lean Concrete

CV-DB.MH-13.8MH1009 Applying membrane water proofing system 2 01-Sep-21 02-Sep-21 Applying membrane water proofing system

CV-DB.MH-13.8MH1010 Pouring screed above waterproofing 1 04-Sep-21 04-Sep-21 Pouring screed above waterproofing

CV-DB.MH-13.8MH1011 Steel and form works for raft foundation 4 05-Sep-21 08-Sep-21 Steel and form works for raft foundation

CV-DB.MH-13.8MH1012 Concrete pouring for raft foundation 1 09-Sep-21 09-Sep-21 Concrete pouring for raft foundation

CV-DB.MH-13.8MH1013 Deshuttering for raft foundation 2 11-Sep-21 12-Sep-21 Deshuttering for raft foundation

CV-DB.MH-13.8MH1014 Steel and form works for walls 5 13-Sep-21 18-Sep-21 Steel and form works for walls

CV-DB.MH-13.8MH1001 Concrete pouring for walls 1 19-Sep-21 19-Sep-21 Concrete pouring for walls

CV-DB.MH-13.8MH1002 Deshuttering for walls 2 20-Sep-21 21-Sep-21 Deshuttering for walls

CV-DB.MH-13.8MH1003 Steel and form works for slab 6 22-Sep-21 28-Sep-21 Steel and form works for slab

CV-DB.MH-13.8MH1004 Concrete pouring of slab 1 29-Sep-21 29-Sep-21 Concrete pouring of slab

CV-DB.MH-13.8MH1005 Wall water proofing 3 30-Sep-21 03-Oct-21 Wall water proofing

CV-DB.MH-13.8MH1006 Outer backfilling 4 04-Oct-21 07-Oct-21 Outer backfilling


LV and communication duct banks 5 28-Aug-21 01-Sep-21 01-Sep-21, LV and communication duct banks

CV-DB.MH-LV. DB 1000 Excavation 2 28-Aug-21 29-Aug-21 Excavation

CV-DB.MH-LV. DB 1001 Pipe installation 2 30-Aug-21 31-Aug-21 Pipe installation

CV-DB.MH-LV. DB 1002 Backfilling 1 01-Sep-21 01-Sep-21 Backfilling


Site development 165 09-Oct-21 18-Apr-22 18-Apr-22, Site development
General facilities works 55 09-Oct-21 11-Dec-21 11-Dec-21, General facilities works

CV-SD-GFW1000 Septic tank 20 09-Oct-21 31-Oct-21 Septic tank

CV-SD-GFW1001 Ground water tank 20 01-Nov-21 23-Nov-21 Ground water tank

CV-SD-GFW1002 Sewer system completion 15 24-Nov-21 11-Dec-21 Sewer system completion


Outer fence works 54 13-Jan-22 16-Mar-22 16-Mar-22, Outer fence works

CV-SD-OFW1000 Fence foundation works 40 13-Jan-22 28-Feb-22 Fence foundation works

CV-SD-OFW1001 Fence installation and tightining 10 01-Mar-22 12-Mar-22 Fence installation and tightining

CV-SD-OFW1002 Doors installation and alighnment 4 13-Mar-22 16-Mar-22 Doors installation and alighnment

Actual Level of Effort Remaining Work Milestone Page 10 of 14 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
  06-Feb-21 15:16

Power Supply to Al-Alamia 115/13.8kv S/S in Dammam

Activity ID Activity Name Original Duration Start Finish 2021 2022 2023
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Inner fence works 17 01-Mar-22 20-Mar-22 20-Mar-22, Inner fence works

CV-SD-IFW1000 Fence foundation works 10 01-Mar-22 12-Mar-22 Fence foundation works

CV-SD-IFW1001 Fence installation and tightining 5 13-Mar-22 17-Mar-22 Fence installation and tightining

CV-SD-IFW1002 Doors installation and alighnment 2 19-Mar-22 20-Mar-22 Doors installation and alighnment
Grading and backfilling works up to Basecourse level 32 31-Jan-22 08-Mar-22 08-Mar-22, Grading and backfilling works up to Basecourse level

CV-SD-BL1000 Survey works and preparation 3 31-Jan-22 02-Feb-22 Survey works and preparation

CV-SD-BL1001 Grading and compaction 25 03-Feb-22 03-Mar-22 Grading and compaction

CV-SD-BL1002 Compaction test and handover 4 05-Mar-22 08-Mar-22 Compaction test and handover
Base course works 6 09-Mar-22 15-Mar-22 15-Mar-22, Base course works

CV-SD-BW1000 Grading and compaction 4 09-Mar-22 13-Mar-22 Grading and compaction

CV-SD-BW1001 Compaction test and handover 2 14-Mar-22 15-Mar-22 Compaction test and handover
Grounding system & Shielding System 29 16-Mar-22 18-Apr-22 18-Apr-22, Grounding system & Shielding System

CV-SD-GS1000 Excavation 15 16-Mar-22 02-Apr-22 Excavation

CV-SD-GS1001 Laying of Cable and Earth Rods 15 16-Mar-22 03-Apr-22 Laying of Cable and Earth Rods

CV-SD-GS1002 Thermo Welding,Cleaning &Make Denso Tape 8 03-Apr-22 12-Apr-22 Thermo Welding,Cleaning &Make Denso Tape

CV-SD-GS1003 Make raiser and Back fill 5 12-Apr-22 18-Apr-22 Make raiser and Back fill
Asphalt works 18 16-Mar-22 05-Apr-22 05-Apr-22, Asphalt works

CV-SD-AW1000 Applying of MC1 1 16-Mar-22 16-Mar-22 Applying of MC1

CV-SD-AW1001 1st Layer 2 17-Mar-22 19-Mar-22 1st Layer

CV-SD-AW1002 Applying of RC2 1 20-Mar-22 20-Mar-22 Applying of RC2

CV-SD-AW1003 2ND Layer 4 21-Mar-22 24-Mar-22 2ND Layer

CV-SD-AW1004 Asphaly marking and sign board installation 10 26-Mar-22 05-Apr-22 Asphaly marking and sign board installation
EW - Electrical Installation Works 541 30-Dec-20 26-Sep-22 26-Sep-22, EW - Electrical Installation Works
EW - Installation of 115kV GIS 70 30-Dec-20 21-Mar-21 21-Mar-21, EW - Installation of 115kV GIS

Elec.W-115GIS1000 Packing List Box Check 2 30-Dec-20 31-Dec-20 Packing List Box Check

Elec.W-115GIS1007 GIS Room Cleaning 3 02-Jan-21 04-Jan-21 GIS Room Cleaning

Elec.W-115GIS1008 GIS Foundation Check 2 02-Jan-21 03-Jan-21 GIS Foundation Check

Elec.W-115GIS1009 Material Box Check 3 04-Jan-21 06-Jan-21 Material Box Check

Elec.W-115GIS1010 GIS Box Open (10 Bays) 4 06-Jan-21 11-Jan-21 GIS Box Open (10 Bays)

Elec.W-115GIS1011 GIS Assembly 29 11-Jan-21 14-Feb-21 GIS Assembly

Elec.W-115GIS1012 Main Resistance Measurement 29 11-Jan-21 14-Feb-21 Main Resistance Measurement

Elec.W-115GIS1003 Vaccum & GAS Filling Works 34 11-Jan-21 20-Feb-21 Vaccum & GAS Filling Works

Elec.W-115GIS1004 Gas Dew Point & Leakage Check 34 11-Jan-21 20-Feb-21 Gas Dew Point & Leakage Check

Elec.W-115GIS1013 GIS Line (E/DS) & C/H Tank Box Open 22 12-Jan-21 07-Feb-21 GIS Line (E/DS) & C/H Tank Box Open

Elec.W-115GIS1014 GIS Line (E/DS) & Accessory part(LCC,Platform,Gas Pipe,Earhting Shunt bar) 22 12-Jan-21 07-Feb-21 GIS Line (E/DS) & Accessory part(LCC,Platform,Gas Pipe,Earhting Shunt bar)

Elec.W-115GIS1001 GIB Bushing Box Open & Assembly 12 14-Jan-21 28-Jan-21 GIB Bushing Box Open & Assembly

Elec.W-115GIS1002 Platform box Open & Assembly/cable tray fixing 9 16-Jan-21 25-Jan-21 Platform box Open & Assembly/cable tray fixing

Elec.W-115GIS1005 Control Cable Pulling & Termination 30 14-Feb-21 21-Mar-21 Control Cable Pulling & Termination

Elec.W-115GIS1006 Grounding of 115 kV GIS 7 13-Mar-21 21-Mar-21 Grounding of 115 kV GIS


EW - Installation of 13.8kV Metal clad swgr. With SF6 Circu it Breakers 67 16-Feb-22 04-May-22 04-May-22, EW - Installation of 13.8kV Metal clad swgr. With SF6 Circuit Breakers

Elec.W-13.8SWGR1000 Marking and measurement 2 16-Feb-22 17-Feb-22 Marking and measurement

Elec.W-13.8SWGR1001 Installation of 13.8 kV Bus 1 Breaker Cubicles 4 19-Feb-22 22-Feb-22 Installation of 13.8 kV Bus 1 Breaker Cubicles

Elec.W-13.8SWGR1002 Installation of Bus Tie A304 Including Bus Riser with Removable link 1 23-Feb-22 23-Feb-22 Installation of Bus Tie A304 Including Bus Riser with Removable link

Elec.W-13.8SWGR1003 Installation of 13.8 kV Bus 2 Breaker Cubicles 4 24-Feb-22 28-Feb-22 Installation of 13.8 kV Bus 2 Breaker Cubicles

Elec.W-13.8SWGR1004 Alignmnet ,Fixing and Torqueing 6 01-Mar-22 07-Mar-22 Alignmnet ,Fixing and Torqueing

Actual Level of Effort Remaining Work Milestone Page 11 of 14 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
  06-Feb-21 15:16

Power Supply to Al-Alamia 115/13.8kv S/S in Dammam

Activity ID Activity Name Original Duration Start Finish 2021 2022 2023
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

Elec.W-13.8SWGR1005 Control Cable pulling & Termination 50 08-Mar-22 04-May-22 Control Cable pulling & Termination

Elec.W-13.8SWGR1006 Grounding of Switchgear 5 30-Apr-22 04-May-22 Grounding of Switchgear


Protection & SAS, Control System 90 16-Feb-22 31-May-22 31-May-22, Protection & SAS, Control System

Elec.W-Prot.S AS .CS10 Placement of Panels 7 16-Feb-22 23-Feb-22 Placement of Panels

Elec.W-Prot.S AS .CS20 Fixing and Alignmnet of Panels 5 24-Feb-22 01-Mar-22 Fixing and Alignmnet of Panels

Elec.W-Prot.S AS .CS40 Control & Power Cable Pulling & Termination 78 02-Mar-22 31-May-22 Control & Power Cable Pulling & Termination

Elec.W-Prot.S AS .CS30 Grounding 5 26-May-22 31-May-22 Grounding


Installation of 115/13.8 Power Transformers (50/67 MVA) 76 17-Feb-22 17-May-22 17-May-22, Installation of 115/13.8 Power Transformers (50/67 MVA)

Elec.W-115Trans10 Installation of Main Body (T601, T602 ) 2 17-Feb-22 19-Feb-22 Installation of Main Body (T601, T602 )

Elec.W-115Trans20 Removal and testing of Imapct Recorder 1 20-Feb-22 21-Feb-22 Removal and testing of Imapct Recorder
T601 43 21-Feb-22 12-Apr-22 12-Apr-22, T601

T601-1000 Installation of Radiators 2 21-Feb-22 23-Feb-22 Installation of Radiators

T601-1001 Installation of Conservator Tank 1 23-Feb-22 24-Feb-22 Installation of Conservator Tank

T601-1002 Installation of Transformer Accessories (PRV, Bucholz Relay, Drain Valves & Piping) 2 24-Feb-22 27-Feb-22 Installation of Transformer Accessories (PRV, Bucholz Relay, Drain Valves & Piping)

T601-1003 Installation of Transformer Bushing / Surge Arrestor 2 27-Feb-22 01-Mar-22 Installation of Transformer Bushing / Surge Arrestor

T601-1004 Vacuuming & Oil Filling after Filtration 6 01-Mar-22 08-Mar-22 Vacuuming & Oil Filling after Filtration

T601-1006 Fixing of Cable Support for 1Cx630mm2 Cable 10 08-Mar-22 20-Mar-22 Fixing of Cable Support for 1Cx630mm2 Cable

T601-1005 Control Cable Pulling/Termination 30 08-Mar-22 12-Apr-22 Control Cable Pulling/Termination

T601-1007 1Cx630mm2 Cable Laying(13.8 KV) and Termination 20 20-Mar-22 12-Apr-22 1Cx630mm2 Cable Laying(13.8 KV) and Termination
T601-1008 Grounding of the Transformer 2 20-Mar-22 22-Mar-22 Grounding of the Transformer
T602 60 08-Mar-22 17-May-22 17-May-22, T602

T602-1000 Installation of Radiators 2 08-Mar-22 10-Mar-22 Installation of Radiators

T602-1004 Vaccuming & Oil Filling after Filtration 6 08-Mar-22 15-Mar-22 Vaccuming & Oil Filling after Filtration

T602-1001 Installation of Conservator Tank 1 10-Mar-22 12-Mar-22 Installation of Conservator Tank

T602-1002 Installation of Transformer Accessories (PRV, Bucholz Relay, Drain Valves & Piping) 2 12-Mar-22 14-Mar-22 Installation of Transformer Accessories (PRV, Bucholz Relay, Drain Valves & Piping)

T602-1003 Installation of Transformer Bushing / Surge Arrestor 2 14-Mar-22 16-Mar-22 Installation of Transformer Bushing / Surge Arrestor

T602-1006 Fixing of Cable Support for 1Cx630 mm2 Cable 10 15-Mar-22 27-Mar-22 Fixing of Cable Support for 1Cx630 mm2 Cable

T602-1008 Grounding of the Transformer 2 27-Mar-22 29-Mar-22 Grounding of the Transformer

T602-1007 1Cx630mm2 Cable Laying(13.8 KV)and Termination 20 12-Apr-22 05-May-22 1Cx630mm2 Cable Laying(13.8 KV)and Termination

T602-1005 Control Cable Pulling/Termination 30 12-Apr-22 17-May-22 Control Cable Pulling/Termination


Communication System 19 27-Apr-22 18-May-22 18-May-22, Communication System

Elec.W-Comm.Sys1000 Placement of Panel & Accessories 4 27-Apr-22 01-May-22 Placement of Panel & Accessories

Elec.W-Comm.Sys1001 Control , Power Cable Pulling & Termination 15 02-May-22 18-May-22 Control , Power Cable Pulling & Termination

Elec.W-Comm.Sys1002 DC Panel Installtion,Fixing & Alignmnet 2 02-May-22 03-May-22 DC Panel Installtion,Fixing & Alignmnet

Elec.W-Comm.Sys1003 DC Cable Pulling and Termination 3 04-May-22 07-May-22 DC Cable Pulling and Termination

Elec.W-Comm.Sys1004 Grounding 2 08-May-22 09-May-22 Grounding


Installation of 13.8kV/380/220 V Station Service Transformers with Cab le 48 01-Jan-22 24-Feb-22 24-Feb-22, Installation of 13.8kV/380/220 V Station Service Transformers with Cable

Elec.W-SS. Trans1000 Placement of Transformer 1 01-Jan-22 01-Jan-22 Placement of Transformer

Elec.W-SS. Trans1001 Fixing of Cable Support 7 12-Feb-22 19-Feb-22 Fixing of Cable Support

Elec.W-SS. Trans1002 13.8 kV Cabel Laying and Termination 5 20-Feb-22 24-Feb-22 13.8 kV Cabel Laying and Termination

Elec.W-SS. Trans1003 Low Voltage Cable Laying from Secondary Side of Transoformer to ACDB Panel 5 20-Feb-22 24-Feb-22 Low Voltage Cable Laying from Secondary Side of Transoformer to ACDB Panel

Elec.W-SS. Trans1004 Grounding of Transformer 2 20-Feb-22 21-Feb-22 Grounding of Transformer


Installation fo AC Power Supply System 58 20-Dec-21 24-Feb-22 24-Feb-22, Installation fo AC Power Supply System

Elec.W-AC. PW1000 Panel Support Installtion 3 20-Dec-21 22-Dec-21 Panel Support Installtion

Elec.W-AC. PW1001 Placement of Main ACDB 1 23-Dec-21 23-Dec-21 Placement of Main ACDB

Actual Level of Effort Remaining Work Milestone Page 12 of 14 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
  06-Feb-21 15:16

Power Supply to Al-Alamia 115/13.8kv S/S in Dammam

Activity ID Activity Name Original Duration Start Finish 2021 2022 2023
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

Elec.W-AC. PW1002 Placement of Sub ACDB 2 25-Dec-21 26-Dec-21 Placement of Sub ACDB

Elec.W-AC. PW1003 Fixing and Alignmnet of Main &Sub ACDB 2 27-Dec-21 28-Dec-21 Fixing and Alignmnet of Main &Sub ACDB

Elec.W-AC. PW1004 Cable Laying and Termination 50 29-Dec-21 24-Feb-22 Cable Laying and Termination

Elec.W-AC. PW1005 Grounding of AC Power Supply System 2 23-Feb-22 24-Feb-22 Grounding of AC Power Supply System
Installation of DC Power Supply System. 65 23-Jan-22 07-Apr-22 07-Apr-22, Installation of DC Power Supply System.

Elec.W-DC. PW1000 Installation of Battery Racks 1 23-Jan-22 23-Jan-22 Installation of Battery Racks

Elec.W-DC. PW1001 Placement of Battery 3 24-Jan-22 26-Jan-22 Placement of Battery

Elec.W-DC. PW1002 Battery Liquid Filling & Buss Bar Interconnection 2 27-Jan-22 29-Jan-22 Battery Liquid Filling & Buss Bar Interconnection

Elec.W-DC. PW1003 Battery Charger Installation 2 30-Jan-22 31-Jan-22 Battery Charger Installation

Elec.W-DC. PW1004 Placement of DCDB &Sub DCDB 5 01-Feb-22 06-Feb-22 Placement of DCDB &Sub DCDB

Elec.W-DC. PW1005 Fixing and Alignment 2 07-Feb-22 08-Feb-22 Fixing and Alignment

Elec.W-DC. PW1006 Cable Laying and Termination 50 09-Feb-22 07-Apr-22 Cable Laying and Termination

Elec.W-DC. PW1007 Grounding 2 06-Apr-22 07-Apr-22 Grounding


Indoor Outdoor Lighting System 90 12-Feb-22 26-May-22 26-May-22, Indoor Outdoor Lighting System

Elec.W-I N/OD.LS1000 Installation of Indoor & Outdoor Lighting System 90 12-Feb-22 26-May-22 Installation of Indoor & Outdoor Lighting System
Telephone System 10 28-May-22 07-Jun-22 07-Jun-22, Telephone System

Elec.W-TS1000 Panel Installation 2 28-May-22 29-May-22 Panel Installation

Elec.W-TS1001 Conduiting 2 30-May-22 31-May-22 Conduiting

Elec.W-TS1002 Wire pulling(Main) 2 01-Jun-22 02-Jun-22 Wire pulling(Main)

Elec.W-TS1003 Telephone Installation 2 04-Jun-22 05-Jun-22 Telephone I nst allation

Elec.W-TS1004 Cable Termination on both Side 2 06-Jun-22 07-Jun-22 Cable Termination on both Side

Elec.W-TS1005 Grounding 1 07-Jun-22 07-Jun-22 Grounding


Modification Remote end Substation 75 02-Jul-22 26-Sep-22 26-Sep-22, Modification Remote end Substation

Elec.W-Mod.RES1000 Installation of Communication Panel Support 3 02-Jul-22 04-Jul-22 Installation of Communication Panel Support

Elec.W-Mod.RES1001 Placement of Communication Panels 7 05-Jul-22 12-Jul-22 Placement of Communication Panels

Elec.W-Mod.RES1002 Fixing and Alignmnet of Communication Panels 3 13-Jul-22 16-Jul-22 Fixing and Alignmnet of Communication Panels

Elec.W-Mod.RES1003 Cable Laying and Termination 47 17-Jul-22 08-Sep-22 Cable Laying and Termination

Elec.W-Mod.RES1004 Grounding 3 06-Sep-22 08-Sep-22 Grounding

Elec.W-Mod.RES1005 Modification of SAS System 15 10-Sep-22 26-Sep-22 Modification of SAS System


Cyber Secuirty System 60 02-Jul-22 08-Sep-22 08-Sep-22, Cyber Secuirty System

Elec.W-CSS1000 Installation of Cyber Secuirty System 60 02-Jul-22 08-Sep-22 Installation of Cyber Secuirty System
MW -Electro Mechanical Work. 134 14-Mar-22 16-Aug-22 16-Aug-22, MW -Electro Mechanical Work.
MW - HVAC 116 04-Apr-22 16-Aug-22 16-Aug-22, MW - HVAC

Elec.MW-HVA C1000 Support Installation 20 04-Apr-22 26-Apr-22 Support Installation

Elec.MW-HVA C1003 Placement of Ducts 13 27-Apr-22 11-May-22 Placement of Ducts

Elec.MW-HVA C1004 Tightening and Torquing of Ducts 7 12-May-22 19-May-22 Tightening and Torquing of Ducts

Elec.MW-HVA C1005 Insulation of Ducts 15 21-May-22 06-Jun-22 Insulation of Ducts

Elec.MW-HVA C1006 PACU Installation 5 07-Jun-22 12-Jun-22 PACU Installation

Elec.MW-HVA C1007 Supply & Return Duct Installation 3 13-Jun-22 15-Jun-22 Supply & Return Duct Installation

Elec.MW-HVA C1008 HVAC Control Panel Installation 3 16-Jun-22 19-Jun-22 HVAC Control Panel Installation

Elec.MW-HVA C1009 Conduiting and Wiring to All Devices 20 20-Jun-22 12-Jul-22 Conduiting and Wiring to All Devices

Elec.MW-HVA C1010 Power Supply Arrangement for PACU Units 5 13-Jul-22 18-Jul-22 Power Supply Arrangement for PACU Units

Elec.MW-HVA C1001 Cable Termination 25 19-Jul-22 16-Aug-22 Cable Termination

Elec.MW-HVA C1002 Grounding 5 11-Aug-22 16-Aug-22 Grounding


MW - Fire Fighting / Fire Detection 65 14-Mar-22 28-May-22 28-May-22, MW - Fire Fighting / Fire Detection

Actual Level of Effort Remaining Work Milestone Page 13 of 14 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
  06-Feb-21 15:16

Power Supply to Al-Alamia 115/13.8kv S/S in Dammam

Activity ID Activity Name Original Duration Start Finish 2021 2022 2023
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

Elec.MW-FF1000 Placement of Hydrant 10 14-Mar-22 24-Mar-22 Placement of Hydrant

Elec.MW-FF1001 Piping and Supports 30 26-Mar-22 28-Apr-22 Piping and Supports

Elec.MW-FF1002 Panel Installation 10 30-Apr-22 10-May-22 Panel Installation

Elec.MW-FF1003 Cable Termination 15 11-May-22 28-May-22 Cable Termination

Elec.MW-FF1004 Grounding 3 25-May-22 28-May-22 Grounding

Testing and Commissioning 532 13-Apr-21 29-Dec-22 29-Dec-22, Testing and Commissioning

T&C1000 115kV Switchgear 50 13-Apr-21 15-Jun-21 115kV Switchgear

T&C1009 13.8kv Metal Clad Switchgear 55 05-May-22 07-Jul-22 13.8kv Metal Clad Switchgear

T&C1010 Transformers (2) nos.(T601 & T602) 45 05-May-22 27-Jun-22 Transformers (2) nos.(T601 & T602)

T&C1014 Control System - Complete 180 01-Jun-22 27-Dec-22 Control System - Complete

T&C1015 Protection Systen - Complete 180 01-Jun-22 27-Dec-22 Protection Systen - Complete

T&C1016 Substation Automation System (SAS) 180 01-Jun-22 27-Dec-22 Substation Automation System (SAS)

T&C1003 Communication Equipmnet 35 01-Jun-22 11-Jul-22 Communication Equipmnet

T&C1004 Fire Detection / Alarm and Safety & Fire Protection System Complete with Accessories.20 01-Jun-22 23-Jun-22 Fire Detection / Alarm and Safety & Fire Protection System Complete with Accessorie

T&C1012 AC Power Supply System 30 27-Jun-22 01-Aug-22 AC Power Supply System

T&C1013 125V DC Auxiliary Power System 16 01-Aug-22 20-Aug-22 125V DC Auxiliary Power System

T&C1005 HVAC - Complete 30 01-Nov-22 06-Dec-22 HVAC - Complete

T&C1002 Remote End Substation 30 23-Nov-22 27-Dec-22 Remote End Substation

T&C1006 Cyber Security Testing 17 03-Dec-22 21-Dec-22 Cyber Security Testing

T&C1011 Station Service Transformer 500KVA (2 nos). 10 17-Dec-22 27-Dec-22 Station Service Transformer 500KVA (2 nos).

T&C1001 Telephone System 5 22-Dec-22 27-Dec-22 Telephone S ystem

T&C1007 Stability/End to End test/Interlock test 6 22-Dec-22 28-Dec-22 Stability/End to End test/Interlock test

T&C1008 Substation ready for Energization 1 29-Dec-22 29-Dec-22 Substation ready for Energization

Actual Level of Effort Remaining Work Milestone Page 14 of 14 TASK filter: All Activities