Professional Documents
Culture Documents
12052
Wahyu Widi Widayat
P0 P1 P2 P3
0 2 2 7
Waktu
1. FCFS (First-come, first-Served)
TurnAround Time:
(2+1+4+4)/4 = 2,75
2. Shortest Job First (SJF)
P0 P1 P2 P3
0 2 2 7 9
AWT (Average Waiting Time) :
Process Wait Time :
Service Time - Arrival Time
P0 0-0 = 0
P1 2-1 = 1
P2 2 – 3 = -1
P3 7–5=2
TurnAround Time:
(2+1+4+4)/4 = 2,75
3. Shortest Remaining Time First (SRTF)
P0 P1 P2 P3
0 1 3 5 7
TurnAround Time:
=(1+2+2+2)/4
= 1,75
4. Round Robin
Quantum time = 52
P0 P1 P2 P3
0 52 104 156 208
TurnAround Time:
=(52+103+153+203)/4
= 127,75