Kick-off meeting commenced at 12noon.

Project duration is 6 months.

Major buildings are

1) Admin Building

2) Gatehouse

3) Perimeter Fence

4) 2 Nos. Hostels

5) 1 No. Bdrm Flat

6) Dining & Kitchen

7) Workshop Building

8) School Halls

9) Clinic

10) 3 Bdrm Bungalow

11) Block of Flats

12) Gen House

Others are the landscaping, road, football field, volleyball and lawn tennis courts, 1 industrial
borehole, solar systems & kerbs.

Site has been hoarded.

Site layout and Topo is available. To be sent by surveyor Sam to all stakeholders.

Geotechnical investigation to commence tomorrow most likely.

Deltec to forward bill for review and supervision today.

Road project to be handled by DELTEC and will commence in about 2-3 months from project start
date.

Setting out of all buildings to commence tomorrow.

Survey equipment to be bought for use on the site with all contractors to bear the cost.

All materials (sand, granite, cement, blocks & iron rods to be supplied by BRASBY VENTURES (Sister
arm of GOBEL).