REQUEST FOR QUOTATION (RFQ) RFQ Ref. No. MSTP-RFQ-SUB-007 Rev.0
Job No: SS-2474
Page: 1 of 2
STATEMENT OF REQUIREMENTS
1.0 Background
Samsung had built steam plant at Ma’aden Aluminium and plant is running for more than 3yrs now.
As a part of warranty; Samsung is planning to do some repair works at Absorber Unit 1/2/3 & 4 of boiler package.
This repair work shall be executed during planned shutdown work.
2.1.1 To Supply and erect tower scaffolding for the following area:
a. Absorber #1 ~ 4m (L) x 4m (W) x 24m (H)
b. Absorber #2 ~ 4m (L) x 4m (W) x 24m (H)
c. Absorber #3 ~ 4m (L) x 4m (W) x 24m (H)
d. Absorber #4 ~ 4m (L) x 4m (W) x 24m (H)
e. Scaffold safety access
f. Scaffold barricade
Volume Volume
No Item Size Description Qty Unit Remarks
(1 Unit) (4 unit)
-Internal Scaffold
(Confined Space)
1 Tower Scaffolding 4m (L) x 4m (W) x 24m (H) 4 EA 384 m3 1,536 m3 -30days duration
-One unit at a time as
per shutdown schedule
-Internal Scaffold
4 Scaffold Barricade As per site condition 1 EA 1EA 4EA
-30days duration
No Category Remarks
-Before commencement of any scaffolding activity inside Maaden Facility, Contractor has to submit Scaffolding
design for Maaden review and approval, Specifically for Absorber Unit (Internal Scaffolding) in Refinery Steam
Plant.