You are on page 1of 11

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/254519335

Update on Subsea LNG Pipeline Technology

Article · April 2007


DOI: 10.4043/18542-MS

CITATION READS
1 6,458

4 authors, including:

Clifford Neal Prescott Jeff Zhang


Fluor Enterprises, Inc. 5 PUBLICATIONS   10 CITATIONS   
14 PUBLICATIONS   23 CITATIONS   
SEE PROFILE
SEE PROFILE

All content following this page was uploaded by Clifford Neal Prescott on 08 May 2016.

The user has requested enhancement of the downloaded file.


OTC 18542

Update on Subsea LNG Pipeline Technology


Tom Phalen, C. Neal Prescott, Jeff Zhang, and Tony Findlay, Fluor Corp.

Copyright 2007, Offshore Technology Conference


Introduction
This paper was prepared for presentation at the 2007 Offshore Technology Conference held in Terminals are required for both the loading and offloading of
Houston, Texas, U.S.A., 30 April–3 May 2007.
LNG into tankers. For locations with sufficient deep water
This paper was selected for presentation by an OTC Program Committee following review of
information contained in an abstract submitted by the author(s). Contents of the paper, as
access terminals may consist of jetty structures and
presented, have not been reviewed by the Offshore Technology Conference and are subject to breakwaters where tankers can be moored and offloading can
correction by the author(s). The material, as presented, does not necessarily reflect any
position of the Offshore Technology Conference, its officers, or members. Papers presented at take place via standard loading arms.
OTC are subject to publication review by Sponsor Society Committees of the Offshore
Technology Conference. Electronic reproduction, distribution, or storage of any part of this
Several LNG facilities have the jetty terminal connected
paper for commercial purposes without the written consent of the Offshore Technology to an onshore facility by a short trestle structure, which
Conference is prohibited. Permission to reproduce in print is restricted to an abstract of not
more than 300 words; illustrations may not be copied. The abstract must contain conspicuous supports the LNG and utility piping, and may in some cases
acknowledgment of where and by whom the paper was presented. Write Librarian, OTC, P.O.
Box 833836, Richardson, TX 75083-3836, U.S.A., fax 01-972-952-9435.
support vehicular access to the loading terminal.
Location of the jetty terminal is dependant upon not only
Abstract the requirements for the LNG tanker maneuvering and
The increased interest and rapid development in the positioning with respect to water depths, currents and ship
transportation of LNG world-wide has prompted a fresh look traffic, but also with prevailing winds which may influence the
at how LNG is transferred to/from an LNG carrier that may be location from a safety view point.
moored offshore in various locations. The traditional shore- In the design of the jetty terminal and trestle structure, a
side loading/unloading of LNG to/from marine carriers may major consideration is the final location and layout to satisfy
be prohibited due to proximity to populated areas, safety safety considerations from vapor plumes that may result from
and/or environmental concerns. Also, the extension of an leaks or damage to the LNG piping on the jetty and along the
offshore jetty structure to support the transfer pipelines with trestle structure. [1] Special precautions must also be taken in
related seabed dredging to facilitate vessel access, may be the design of jetty piping for protection against damage that
prohibitively costly. This presentation discusses how new may result in leaks. This may include additional structural
developments in high-strength Nickel alloy cryogenic protection and block valves that isolate segments of the
pipelines and high-efficiency insulation systems have piping. In the U.S. handling requirements for LNG on jetty
significantly improved the prospects for the installation of the structures require full containment to be designed into the
first subsea cryogenic pipeline for LNG service. structure to contain a leak or spillage.
Subsea cryogenic pipelines designs to date focus on the Fixed-Berth Offshore
use of vacuum systems for insulation and Invar™ pipe LNG Off-Loading
Onshore Terminal
materials to control growth and differential stress in the Re-Gas Facility
pipeline systems. This approach, while successful, has also
resulted in high cost systems and welding issues. A new Cryogenic
design approach using ambient pressure, high efficiency Pipelines
on trestle
insulation and high strength Nickel alloys reduces the cost of
the system and improves constructability. The design and
installation techniques are based on proven systems used in
operating high temperature pipelines.
This paper addresses the design, fabrication and
installation of subsea cryogenic pipelines as well as Figure 1- Typical LNG Unloading Jetty
possibilities for inspection, maintenance and real time
monitoring of the installed system. The designs to be reviewed Each of these provisions adds to the cost of the facilities.
focus on the use of new developments in high-strength Nickel In addition, the length of the trestle to the end jetty terminal
alloy cryogenic pipelines and high-efficiency insulation may need to be increased to move the end farther from a
systems. The presentation also discusses the test program potential safety conflict. This too would increase the cost of
employed to certify a Fluor developed ambient pressure the trestle structure.
subsea LNG pipeline for commercial use. When a trestle structure is used for LNG piping, the
design must include provision for expansion or contraction
2 OTC 18542

loops that accommodate thermal movements in the piping facility. There may also be a need to have utility lines added
during operation. This often increases the total length of the to the piping that may transfer potable water and bunkering
LNG piping as much as 20% and adds additional friction in fuel as well as fire-water.
the transfer of the LNG due to the extra length and bends in
the piping. A provision for these thermal loops must be Subsea pipelines – an alternate to trestle piping
made in the trestle structure, which additionally increases the As an alternate to the trestle supported piping, subsea
cost of the facility. pipelines may be considered. A subsea pipeline can be used to
transport the LNG from / to an offshore terminal thereby
Factors influencing trestle costs eliminating the need and cost for a connecting trestle. With
Costs of a typical trestle structure are dependant upon a current subsea cryogenic pipeline designs, LNG can be
number of factors: efficiently transferred over distances of up to 20 miles.

• Length
• Water Depth
• Soils Conditions Dredged
Turning Basin Dredged 9-km Ships
• Number and Sizes of Trestle Piping Channel

• Requirements for Vehicular or Pedestrian Access Onshore


Offshore
Loading
• Site Access Conditions Gas Terminal
Liquefaction
• Environmental Conditions (Waves and Currents
which influence height of structure above the water 6-km
and the strength of the structure to resist the Cryogenic
1.2-km Rock Breakwater
Pipelines
environmental loading)
• Materials used in Facility
Figure 3- Typical Subsea LNG Pipeline with Loading Jetty
• Methods of Construction or Installation
• Safety Requirements.
Buried subsea pipelines that have properly designed
engineering backfill are inherently safer from leaks and
These factors can greatly influence the final cost of the
damage. In addition, having buried cryogenic piping may
structure. A number of trestle structures have been built
improve the thermal performance of the pipeline in hot
around the world for LNG and LPG handling and the lengths
climates. By adding features such as real time monitoring of
of these facilities range from a few hundred meters up to 10-
the performance of the pipeline for structural integrity, thermal
km. The adjusted current costs of these facilities range from
performance and leaks using fiber optic technology, the safety
US$15 million / km to US$54 million / km (US$23 million /
of the subsea pipeline can be further enhanced to provide a
mile to US$87 million / mile).[2] (Indeed this cost range may
final design that has a loss prevention profile equal or better
be low as recent data has suggested that significantly higher
than that of a conventional system.
costs may be more representative. However, this range is
maintained so as to not unreasonably skew the comparisons).
Factors influencing cryogenic piping costs
The installed costs shown are for the structure only and do
Costs of cryogenic piping are dependant upon a number of
not include the cost of the piping, which would be in addition.
factors:
This represents a significant capital cost for a project,
especially in the event there is a need to extend the jetty
• Length
offshore for some distance.
• Wall thickness and diameter
• Whether subsea or above ground on a trestle
Dredged 9-km Ships Channel • Corrosion protection requirements
Dredged • Insulation requirements
Turning Basin
1.2-km Rock • Materials used in configuration
Onshore Gas
Breakwatera
• Methods of Fabrication, Construction and Installation
Liquefaction
Facility • Site Access
6 km Jetty
• Safety Requirements or Enhancements
Offshore Loading
Terminal
Costs of cryogenic piping vary significantly by the type of
insulation and configuration employed in a particular installed
Figure 2- Typical LNG Loading Jetty with Breakwater application. For example, the current practice for above
ground piping is to have either external insulation in the form
Typical piping for a cryogenic terminal may include LNG of polyurethane foam or use vacuum insulated piping. These
piping, LPG piping, vapor return piping and cryogenic cool represent two extreme examples of cryogenic piping. The
down piping. In the case of the illustration above, the piping polyurethane piping would require a significantly thicker
would be supported by the trestle / jetty structure that would insulation to achieve similar thermal performance levels to the
connect the offshore terminal with the onshore gas plant vacuum insulated piping. The amount of insulation, of course,
OTC 18542 3

is dependant upon the level of thermal protection that is cases where it is convenient to situate the LNG Regasification
needed to limit thermal boil off from the cryogenic product to facilities onshore.
economic levels, given cycling times between tanker loadings.
Costs for trestle supported cryogenic piping in today’s Subsea Cryogenic Pipelines
market range from US$13 - US$15 million / km (US$20 - Subsea cryogenic pipelines are emerging technologies that are
US$23 million / mile). This is exclusive of the cost of the essential for the new generation of offshore LNG loading and
trestle structure. Costs of subsea cryogenic pipelines range receiving terminals. The major challenges for these systems
from US$11 - US$16 million / km (US$18 - US$26 million / include, the managing of pipeline contraction due to the low
mile). In both cases these are installed costs and vary temperature of the LNG, the thermal efficiency of the
depending upon the factors noted above. These are general insulation system chosen, the reliability of the system, the ease
costs that are dependant upon the type of final configuration of construction and the ability to monitor, inspect and, if
selected. [2] necessary, repair in a timely manner.
It can be seen that effectively, the cost of the trestle Many types of subsea pipeline configurations are now
supporting structure can be saved if subsea pipelines were being considered for use in offshore applications. To illustrate
employed, since the relative costs of the trestle supported the differences between available subsea cryogenic pipeline
piping is comparable to the cost of a subsea pipeline systems, eight configurations have been compared on the basis
alternative. On this basis subsea pipelines offer an of cost and thermal performance. These configurations are:
economically attractive solution for LNG terminal
applications. 1. Vacuum Insulated pipe-in-pipe with 9% Ni product
pipe and 9% Ni casing.
Offshore LNG Terminals – an alternate 2. Vacuum Insulated pipe-in-pipe with bellows and
In case the conditions are less favorable due to shallow stainless steel product pipe and steel casing.
waters, congested shipping and / or mooring situations, but 3. Aerogel filled annular space pipe-in-pipe with 9% Ni
also because of lack of community acceptance and permitting product pipe and steel casing pipe.
difficulties, offshore terminals are a very attractive alternative. 4. Aerogel blanket pipe-in-pipe with 9% Ni product
Although such terminals exist - they have been widely used pipe and steel casing pipe.
for loading of crude oil and oil products for many years - no 5. Fumed silica insulated pipe-in-pipe with vacuum and
offshore terminals for LNG are in use. Invar™ product pipe and steel casing pipe.
6. Aerogel blanket pipe-in-pipe with Invar™ product
pipe and steel casing pipe.
SPM
7. Polyurethane insulated pipeline with Invar™ and
HDPE casing.
8. Polyurethane insulated pipe-in-pipe with 9% Ni
product pipe and steel casing.
Gas Plant

Subsea LNG Pipeline Handling contraction


For subsea applications it is not practical to consider the
inclusion of expansion loops in the subsea pipeline
configuration as there would be too many for practical
installation. Although it is common to include expansion
loops at the tie-ins of subsea hot oil lines, a preferred approach
for cryogenic pipelines is to eliminate the subsea expansion
Figure 4- Typical Subsea LNG Pipeline and Single Point Mooring loops and configure a system that incorporates a straight run
of pipe. At present, there are mainly two methods to
The most dominant advantages of LNG offshore accommodate this contraction:
terminals are the lower costs for construction and operation,
and the possibility to locate the terminal in deeper water • Use of InvarTM or other alloy with ultra-low thermal
thereby eliminating the need for dredging. In addition, the expansion coefficient, or
increased availability, safety and reduced voyage time as LNG • Use of bellows, one in each segment (about 15-m
carriers need not enter and maneuver in congested waters. long) of the pipeline, which is a self-contained pipe-
LNG carrier berths can be located away from confined in-pipe segment with vacuum insulation, and one
waterways, thereby increasing safety and security while at the larger bellows on the external casing pipe in larger
same time preventing costly civil works. Furthermore, intervals (about 150-m long).
impairment of new and existing shipping traffic will be
minimized. [3] While technically feasible, both methods suffer major
A number of LNG import facilities are currently planned disadvantages in cost, reliability, durability, or maintenance
in various parts of the U.S. employing offshore Floating requirement. InvarTM is an alloy steel containing
Regasification Units. The solution outlined above may approximately 36% Nickel (Ni) and with Ni prices tripling
represent a technically viable and cost effective alternate in over the last year (2006), the cost of Invar™ type materials
has soared. In addition, production schedules for the
4 OTC 18542

manufacture of the sizes and amount of tonnage required for a Preferred Technical Configuration
typical LNG export or import terminal would require the full A new pipeline configuration has been developed to address
production of existing mills for a period of 3-years. Therefore the disadvantages noted above. The configuration (patent
a project schedule would be driven by the long production pending)[4] is the culmination of Fluor Corporation (Fluor)
output of existing mills. Although extensive testing of conceptual designs, which began in the 70’s with the design of
production and field welds of InvarTM has been conducted a subsea LPG pipeline and which continued into the 80’s with
over the last few years, there still remains a question as to the their first subsea LNG pipeline for an arctic LNG ship system.
high-cost of quality repetitive field welds using this system. This new design, however, takes advantage of recent
Bellows are known to have a high cost and there has been developments in insulation technology and uses a highly
a continuing question on the reliability and maintenance of efficient thermal nano-porous insulation in the annular space
large-diameter thin-walled bellows if used in a subsea between the inner and outer pipes. This material is kept in an
application, where installation stresses may damage the units. ambient pressure environment, which is produced through
A more robust configuration would be preferred in a subsea sealing by metallic bulkheads. The bulkheads also act to
application. transfer the contraction induced axial tension load on the inner
Therefore, the following may be summarized. cryogenic carrier pipe to the external jacket pipe. The resulting
pipeline bundle is a structural element, which accommodates
• InvarTM the thermal contraction and expansion loads without resorting
– High Cost / Production Difficulty / Weld to expansion bellows or expensive ultra-low thermal
Issues expansion alloys. As an example, the LNG carrier pipe would
• Bellows be of 9% Nickel steel, while the jacket pipe can be carbon
– High Cost / Low Reliability / High steel, unless the owner prefers double cryogenic containment
Maintenance in which case 9% Nickel steel can also be employed as the
outer pipeline. The thermal insulation would be a high
Addressing thermal performance performance nano-porous Aerogel product, approximately 50-
At present, there are several methods for addressing mm to 75-mm thick, in blanket or granular form installed
thermal performance for low temperature cryogenic pipelines: within the annular space without vacuum and under ambient
pressure.[5]
• Use of conventional polyurethane or similar
insulation systems such as fumed silica.
• Use of high efficiency Aerogel insulation systems Aerogel Insulation
(Cabot NanogelTM
• Use of vacuum insulated pipe-in-pipe. Expansion PackTM)

Although vacuums have inherently a higher thermal


performance level than ambient pressure systems with
insulation, there is a penalty to pay for higher maintenance Concrete Weight
ASTM 553 Type 1
costs and reliability through the life of the system to ensure (9% Ni Steel)
Coating (if required)

that the vacuum is maintained. If there is a leak, this Product Pipe


External Carbon Steel
effectively eliminates any thermal performance. Casing Pipe (or 9% Ni
Steel if required)
Conventional insulation systems suffer from the fact that
they are not as thermally efficient as a vacuum system or an Figure 5 – Fluor Subsea LNG Pipeline
Aerogel insulation system. Its use therefore requires a larger
amount of insulation for equivalent thermal performance and a The features of the subsea pipeline configuration are as
resultant larger outer casing pipe. This places this follows:
configuration into question when attempting to build pipe-in-
pipe systems offshore when the internal product pipe is in the
• Metallic Bulkheads at each End
order of 30” to 36” in diameter (762 – 914 mm). Therefore in
summary: • 9% Ni Steel for Product Line
• Vacuum • Ambient Pressure in Annular Space
– High Efficiency BUT High Maintenance • Aerogel Insulation
• Conventional Insulation • Simple Fabrication and Assembly
– Low Efficiency therefore more Insulation • Proven Installation Techniques
• Patent Pending Design
Ambient pressure systems are preferred due to their
higher reliability; and when coupled with high-efficiency The configuration is very simple in that it incorporates
Aerogel insulation and a configuration that includes 9% Ni proven fabrication and installation techniques developed in the
steel as the product carrying pipe, these are found to be the offshore industry over the last 20-years. Using the high-
most cost effective. These are the subsea pipeline efficiency thermal insulation systems that have been recently
configurations that are preferred. [2] made commercial and the high-strength cryogenic piping
systems that also have been developed recently using 9% Ni
OTC 18542 5

steels, the cryogenic pipeline configuration is an attractive In the Table above, it can be seen that by using various
low-cost option for offshore LNG terminals. insulation systems, the outer casing pipe diameter varies
depending upon the thermal performance of the insulation. In
Yield this comparison equivalent thermal performance was the goal,
Relative Cost Stress but in the vacuum cases where the thermal performance is
Material
(in January 2007) (MPa) @ very efficient, the configuration is limited by the constraints of
0 oC assembly and fabrication. In Cases 3 and 4, Nanogel®
Invar
TM
– 36% Ni 24 270 Aerogel as developed and manufactured by Cabot
Corporation, was used as a reference material.
316L Stainless Steel 10 250
The Table above compares similar vapor boil-off rates for
9% Ni Steel 4 585 a standard 24-inch (610 mm) diameter pipeline. The
differences are substantial and influence the overall cost of the
API X52 Carbon Steel 1 359 configuration.
When the costs of the comparative configurations are
Table 1 - Relative Cost and Yield Stress Comparisons of Materials evaluated, it can be seen that there are three systems that stand
As can be seen in the Table above high Nickel content out as lower cost options. These are high-lighted through
materials such as InvarTM and 316L stainless steel have a much shading in the Table below.
higher relative cost as well as a lower yield stress. 9% Ni
Steel has inherent advantages when used as a cryogenic
material. It has a higher strength and it has a relatively low Insulation Product Casing Cost
Case
cost compared to the other options. Description Pipe Pipe Ranking
As indicated, the cost of an InvarTM pipeline is currently 6
times that of a 9% Nickel Steel pipeline. Additionally, the 9% Vacuum PIP with
1 9% Ni 30” 9Ni 3
Bulkheads
Nickel Steel has a greater strength than the relatively low
strength 36% Nickel Steel which would further compound the Vacuum PIP with
2 304 SS 36” CS 5
Bellows
cost differential due to the increased wall thickness
requirement in a pressure containing pipeline. In the past year 3 Nanogel® Annular Fill 9% Ni 32” CS 1
(2006) there has been a significant increase in the cost of
Nickel with prices that tripled thus broadening the difference 4 Nanogel® Blankets 9% Ni 34” CS 2
in cost between the 36% Nickel Steels such as InvarTM as
compared to 9% Ni Steels proposed by Fluor. Fumed Silica Panels
5 36% Ni 30” CS 8
with Vacuum
The advantages of 9% Ni Steels are further
emphasized by a comparison with other available LNG subsea 6 Aerogel Blankets 36% Ni 34” CS 7
systems.
Polyurethane Foam
7 36% Ni 48” HDPE 6
(10pcf)

Insulation Thickness Casing U Polyurethane Foam


8 9% Ni 48” CS 4
Case (10pcf)
Description (inches) Pipe (W/m2/K)
Table 3 - Cost Ranking – Same Boil-off/Km for 24” OD Pipeline
Vacuum PIP with
1 2.5 30” 9Ni 0.070
Bulkheads
Cases 1, 3 and 4 are the Fluor 9%Ni cryogenic pipeline
Vacuum PIP with solutions that use either a vacuum insulation system or a high-
2 5.5 36” CS 0.035
Bellows
efficiency Nanogel® Aerogel insulation system. In Case 1,
Nanogel® Annular both the product and casing pipe are considered to be 9%Ni
3 3.5 32” CS 0.134
Fill steel in the vacuum pipe-in-pipe application. This was
4 Nanogel® Blankets 4.0 34” CS 0.131
implemented to ensure that if in the event that the vacuum was
lost and cryogenic temperatures reached the outer pipe, a
Fumed Silica Panels cryogenic resistant material would prevent a secondary failure.
5 2.0 30” CS 0.120
with Vacuum It can be seen that the 36%Ni steels (InvarTM) were the
highest cost options, whether the option used a partial vacuum
6 Aerogel Blankets 4.0 34” CS 0.131
with fumed silica insulation or with Aerogel blankets in an
Polyurethane Foam ambient pressure system. In this comparison, even
7 11.5 48” HDPE 0.132 Polyurethane insulation systems were less expensive than the
(10pcf)
Polyurethane Foam InvarTM configurations.
8 11.5 48” CS 0.132 Once insulation thicknesses of all the options are
(10pcf)
compared, it can be seen there is a disadvantage of using
Table 2 - Insulation and Casing Sizes for 24” OD Pipeline Polyurethane insulation for long subsea pipeline distances.
For example, the Table below compares the relative insulation
thickness that is required for each configuration when
6 OTC 18542

compared to several typical lengths that may be expected for Max Max
an offshore LNG terminal. Using these larger insulation Same
Insulation Boil-Off Boil-Off
thicknesses creates a situation wherein it becomes physically Case Boil-Off
Description for for
more difficult, if not impossible, to install a Polyurethane per km
2 km 8 km
foam insulation system pipe-in-pipe configuration in a subsea Vacuum PIP with
1 3 4 1
application using current installation practices. The weight of Bulkheads (9%Ni)
the pipe-in-pipe combined with the physical size becomes a Vacuum PIP with
fabrication and installation issue. For this reason, the 2 Bellows 5 5 4
(Stainless Steel)
Polyurethane applications are not considered practical for
Nanogel® Annular Fill
longer lengths of subsea pipeline. 3
w/ 9% Ni
1 1 3
®
Nanogel Blankets w/
4 2 2 2
9% Ni
Same Max Max
Insulation Fumed Silica Panels
Case Boil-Off Boil-Off Boil-Off
Description 5 with Vacuum 8 8 6
per km for 2 km for 8 km w/ 36% Ni
Aerogel Blankets w/
Vacuum PIP with 6 7 7 8
1 2.5 2.5 2.5 36% Ni
Bulkheads
Polyurethane Foam
Vacuum PIP with 7 6 6 7
2 5.5 5.5 5.5 (10pcf)
Bellows
Polyurethane Foam
8 4 3 5
3 Nanogel® Annular Fill 3.5 1.5 6.5 (10pcf)

4 Nanogel® Blankets 4.0 2.0 7.0 Table 5 - Cost Ranking for Different Length – 24”OD Pipeline

Fumed Silica Panels Fluor Subsea LNG Pipeline Design Description


5 2.0 1.0 4.0
with Vacuum Fluor’s technology utilizes an inner carrier pipe manufactured
6 Aerogel Blankets 4.0 2.0 7.0 in high strength 9% Nickel Steel with the annulus filled with a
highly efficient Nanogel® aerogel insulation at ambient
Polyurethane Foam pressure (i.e. without the requirement for critical maintenance
7 11.5 3.5 23.5
(10pcf)
of the vacuum throughout the service life of the facility).
Polyurethane Foam Contraction stresses in the carrier pipe are accommodated at
8 11.5 3.5 23.5
(10pcf)
each end of the pipeline by bulkheads shaped to provide
optimum strength while minimizing heat transfer. The
Table 4 -Comparison of Insulation Thicknesses (inches)
external pipeline is manufactured in normal strength Carbon
Steel, unless double containment is required by the owner, in
After comparison of the costs of these various which case 9% Nickel Steel can be employed for both inner
configurations for different lengths, it is clear which and outer pipes.
applications are preferred. Two interesting aspects become
more apparent.
Testing
The 9%Ni steel solutions are seen to be the lower cost Fluor has conducted two test programs:
options, and, as the length increases, the vacuum system with
9%Ni steel becomes more attractive. In the case of the
vacuum system, the Fluor configuration uses 9%Ni steel for • At AGL Resources Cherokee LNG Plant in Georgia in
the product and casing pipe and incorporates metallic March/April 2004 - Pipe in Pipe (6-inch in 12-inch) both
bulkheads at the ends of the pipeline and at regular intervals 316L Stainless Steel - flowing LNG was employed as the
throughout the pipeline, acting as containment and isolation cryogenic test medium. Aerogel blankets were used as
bulkheads. This configuration is essentially the same as that the insulation. Instrumentation of the Pipe in Pipe was
of the Fluor ambient pressure pipeline configuration with the fiber-optic sensors and cabling. A total of 22 Fiber-Bragg
and heat-flux sensors were used.
Nanogel® insulation, but without the Nanogel® insulation.
However, it does incorporate a cryogenic vent line if in the • At Delta Engineering, Houston, Texas in January 2006 -
event the system needs to be bled. This same vent line can be Pipe in Pipe (6-inch in 12-inch) both 316L Stainless Steel
used to maintain the vacuum on the system. - Liquid Nitrogen was employed as the test medium.
As can be seen in the cost comparison for the various Nanogel® aerogel expansion packs were used as the
lengths, the configuration using the Aerogel blankets with insulation.
36%Ni steel product pipeline in an ambient pressure actually
becomes comparatively more expensive as the length
increases.
OTC 18542 7

Figure 6 - Fluor LNG Pipeline under Test at AGL Georgia


Figure 8- Certificate of “Approval in Principal” from DNV

Insulation
The insulation material proposed for the Fluor Subsea LNG
pipeline configuration is a high-efficiency aerogel
manufactured by Cabot Corporation under the trade name
Nanogel® and deployed in their proprietary Expansion Pack™
system. As ultra-low conductivity insulation, Nanogel®
provides the very high thermal performance required for
cryogenic LNG pipeline flow-assurance.
Conductivity of Nanogel® insulation for cryogenic
applications is in the range of 11 mW/m-K. Moreover, since
the Nanogel® Expansion Pack insulation completely fills the
annular space (unlike a blanket or panel), the effective
insulation value is greater than a material of equivalent
conductivity that requires an air gap.
The nano-porous insulation is also mechanically strong,
eliminating the need for heat-bridging centralizers and is
hydro-phobic which means it does not absorb water and
Figure 7- Fluor LNG Pipeline under Test at Delta - Houston therefore does not degrade in the presence of moisture the way
materials such as microporous silica, Polyurethane foam and
Both the above test programs successfully proved the concept other insulations do.
and validated analytical predictions of the pipeline’s Recent tests of the insulation system in a Pipe in Pipe
contraction behavior and stress loading. configuration confirmed the thermal performance of the
insulation. Water intrusion tests were performed where a
• A further full scale component test is planned again at simulated leak was introduced and the thermal performance of
Delta Engineering employing Pipe in Pipe (24-inch in 32- the insulation in this application was validated, exceeding
inch) internal pipe 9% Nickel Steel and external pipe expectations.
Carbon Steel – conservatively Liquid Nitrogen will be
employed as the test medium. Bulkhead
Fluor’s subsea LNG pipeline design utilizes 9% Nickel Steel
Qualification of New Technology forging and fabrication technology including a dedicated
Two Certification Agencies, the American Bureau of Shipping welding procedure designed to reduce residual stresses in the
(ABS) and Det Norske Veritas (DnV) reviewed the concept bulkhead due to the welding process. The technology is
and witnessed the latter series of tests performed in January developed by Brück Pipe-connections B.V. of the
2006. “Approval in Principle” for the concept was received Netherlands.
from both agencies in April 2006. The bulkheads are used at the ends of the pipeline to
effectively seal the annular space and to allow transfer of the
contraction induced axial compression loads on the inner
cryogenic carrier pipe to the external jacket pipe. The Pipe-in-
Pipe system functions as a structual column, with thermal
insulation maintained in the annular space in an ambient
pressure environment.
8 OTC 18542

The 9% Nickel Steels are available in two heat-treated


conditions. They can be used in quenched and tempered (QT)
condition and the double normalized and tempered (NNT)
tempered. The metallographic structure of QT is a mixture of
matensite / bainite with hardness of 400Hv. This procedure
results in steel with higher yield to tensile ratio.
The minimum acceptable operating temperature of the
ASTM 333 Grade 8 (double normalized and tempered, or
quenched and tempered) is that of liquid nitrogen (-195 ºC or -
320 ºF). Additionally, the Charpy impact test temperature is
specified in ASTM A333 as that of liquid nitrogen (-195 ºC or
Figure 9 - Typical Cross Section of Pipeline Bulkhead -320 ºF). This is within the operating temperatures of LNG
service.
The bulkhead is configured on a case by case basis to EBK has qualified manufacturing processes for 9% Ni
satify the dimensional and loading conditions while Steel Pipe, and is capable of producing pipe to an API 5L
minimizing heat lose. Fininte Elelement Analysis (FEA) is Grade X-80 Standard required for a typical LNG project.
employed to derive the bulkhead configuration and verify that
the selected bulkhead and Pipe-in-Pipe system satisfy all 9% Nickel Steel Pipe Welding
stress, strain, buckling, fatigue and brittle fracture criteria. Specialty welding consumables required will be supplied by
FEA analysis has shown that only one conical element is the manufacturer of the 9% Nickel Steel pipe. Fluor has
needed for design for the loadings anticipated, however, this focused on welding technology from EBK who has developed
design allows for an additional margin of safety with the and optimized several welding techniques to achieve
inclusion of a second element. Thermal analysis has overmatched welds for 9% Nickel Steel pipe.
determined that the external casing pipe at the bulkhead will
be at external ambient temperature eliminating the need for Construction
external insulation; however, 9%Ni steel will be used in this The Pipe-in-Pipe configuration chosen is similar to the
area near the bulkhead not only for its cryogenic properties, bundled pipeline configurations that have been installed
but also for its strength. throughout the world over the last 20-years, thus the
It is planned that the bulkhead sections would be construction techniques used are familiar to the marine
manufactured in a controlled condition in a specialty forging construction industry. Installation of pre-fabricated and
and fabrication facility and delivered to the construction site assembled pipelines can be implemented by numerous well
where they would be inserted in to the line using conventional known methods, especially including the bottom pull or towed
welding practices developed for the material. methods of installation. Alternatively, the pipeline may also be
installed by a laybarge.
The method of installation would depend upon the final
location of the pipeline and the resultant weight for the
specific site application. Similar pipeline bundle
configurations have been built for bottom tow and controlled
depth towed methods of installation in maximum lengths
between 11 and 16 km and towed to an installation site over a
distance of between 700 and 900 km.
The configuration of the Pipe-in-Pipe system chosen
allows it to be fabricated in sections in an onshore make-up
and assembly site for projects where the bottom pull method
of installation is used. In this type of activity, the pipe is often
make up in “strings” or “sections”, which may be several
hundred meters in length. Each “string” is then assembled
Figure 10 -Cross Section of Bulkhead Showing Insulation into one long continuous “section” on a rail system that will
allow the full length of pipeline to be launched into the sea.
9% Ni Steel Pipe A typical make-up site and rail launch system is shown in
The use of 9% Nickel Steel in cryogenic application is well the following photograph of a past Fluor project where this
proven having been employed for several decades in method has been used to install a 44-inch OD oil pipeline with
extremely low temperature tankage. Also processes used in 5-inches thick concrete coating that was 5.6-km in length,
the manufacture of the 9% Nickel Steel pipe from plate which is similar to a LNG subsea pipeline application for
supplied from current producers are not new technology. loading and off-loading terminals. The length of each of the
Currently certain manufacturers, including the German strings for this particular project was 700-feet (213-m).
specialty mill Eisenbau Kraemer (EBK) are expanding their
capacity to accommodate the anticipated demand for pipe
manufactured in 9% Nickel Steel.
OTC 18542 9

A cross-sectional view of a typical buried PIP system


showing general locations of fiber-optic sensors is shown
below. The system employed would allow, not only leak
detection, but also external intrusion monitoring.

Back-Filled Trench Fiber-Optic Sensors

Figure 11 – Typical Pipeline Stringing Site

For the case where there is an onshore make-up site, the


offshore subsea pipelines is launched directly into the sea. A Leak Path
typical rail launch system using an offshore pull-barge for the
Figure 13 – Cross Section – Buried PIP
installation is shown in the following photograph.
A previous and similar installation of a monitoring system
was used for an oil and gas bundle system in the Gulf of
Mexico. It employed a system that would shut-in the
producing wells if a situation developed that would indicate
leaks or intrusions into the system. The monitoring system
was tied to the Control Room on the offshore facilities as a
safety feature for Operations.
As a result of advances in fiber-optic sensing
capabilities, these types of sensing devices would be proposed
to provide real-time strain, temperature, vibration, and flow
monitoring for the subsea and Trestle supported cryogenic
pipelines. Fiber-optic sensors are attractive in these
applications because of their multiplexing capability,
immunity to electro-magnetic interference, ruggedness and
long distance signal transmission ability.
Feasibility of using fiber-optic sensors offshore has been
Figure 12 – Typical Pipeline Bottom Pull demonstrated through full scale riser deployment in the Gulf
of Mexico on steel centenary risers and drilling risers. [6]
It is anticipated that the subsea LNG pipeline will be
buried to provide additional protection from wave action and Conclusions
dropped objects as well as assisting in restraining some of the Currently Liquid Natural Gas (LNG) is transported to or from
contraction loads. Again conventional techniques will be LNG tankers to shore based facilities by means of trestle
employed. supported pipelines which require large contraction loops to
accommodate the temperature variation (typically +50oC air
Additonal Enhancements - Online Inspection and temperature to -162oC LNG storage temperature). The cost of
integrity Monitoring the structures to support the pipelines alone (which due to
Conventional inspection survey techniques would be bathymetry constraints can be several kilometers long), is a
employed to monitor the pipeline service life condition. In significant cost element of any LNG import or export facility.
addition a comprehensive non-intrusive monitoring system is Reduction and / or elimination of contraction loops is
recommended to monitor the integrity of the operating possible with the newer LNG pipeline designs, and these have
pipeline. Fluor has been working with Astro Technology, Inc. cost advantages when considered for either trestle supported
for the development of such a system. This would encompass or subsea applications. With the need to address ever
a series of fiber-optic sensors and data gathering equipment to increasing costs of trestle construction in remote areas, the
not only monitor for leaks, but also to monitor the thermal application of subsea pipelines is being considered for
efficiency of the insulation system and to provide a system for lowering cost and improving delivery schedules.
detecting any intrusions to the system that may compromise With the dramatic rise in Nickel prices over the last year
the structural integrity. (2006) and Nickel prices remaining at all time peaks, alternate
alloy steels for cryogenic service are becoming more of an
10 OTC 18542

interest. The current cost of InvarTM pipe material is currently References


[1]
6 times that of an equivalent pipe using 9% Nickel Steel. SANDIA Report SAND2004-6258 “Guidance on Risk Analysis
Additionally, the 9% Nickel Steel has a greater strength than and Safety Implications of a Large LNG Spill over Water”,
the relatively low strength 36% Nickel Steel which would December, 2004
[2]
further compound the cost differential due to the increased Cryogenic Piping for LNG Workshop, Houston, Texas, Zeus
Development Corporation, “An Update on Subsea LNG
wall thickness requirement in a pressure containing pipeline. Technology, Neal Prescott, Fluor Corporation, August 2006.
Various subsea pipeline configurations are being [3]
21st International Conference on LNG, LPG, and Natural Gas,
considered for use in LNG applications, each of which have GASTECH 2005, Bilbao Spain, “Ship to Shore Transfer of LNG
been compared on the basis of cost and thermal performance. – A New Approach”, Neal Prescott, Fluor Corporation; Max
Of the subsea pipeline configurations that have been Krekel, Bluewater Offshore Production Systems (USA) Ltd,
contemplated, there is a significant cost advantage using the March 14 ~ 17, 2005.
[4]
Fluor configuration, which utilizes 9%Ni steels and the high- US Patent Office Provisional Application No. 60/556535,
efficiency Aerogel insulation systems in an ambient condition. Cryogenic Pipeline Configurations and Methods, Fluor –
For long distance applications 9%Ni vacuum systems may be Clifford Prescott, et al
[5]
OTC 17338 “An Ambient Pressure Insulated LNG Pipeline for
considered. Subsea Environments, C. Neal Prescott, Fluor Corporation; Jeff
Although vacuums have inherently a higher thermal Zhang, Fluor Corporation; David V. Brower, Astro Technology,
performance than ambient pressure systems with insulation, Inc., May 2005
there is a cost penalty for higher maintenance and questions on [6]
Subsea Rio 2004 “Real Time Subsea Monitoring and Control for
reliability through the life of the system in ensuring that the Pipelines”, by Neal Prescott, Fluor Corporation and David V.
vacuum is maintained. If there is a leak, and the vacuum is Brower, Astro Technology, Inc., June 2004
lost then all thermal performance is lost. Ambient pressure
systems are preferred due to their reliability since tests have
demonstrated that, in the unlikely event of puncture damage to
the casing pipe, the Nanogel® insulated pipeline system will
retain some functionality, unlike a vacuum. This reduced
functionality can eliminate the need for an immediate
operational shutdown making it possible for pipeline repairs to
be deferred to a later time.
The evolving technology and the application of proven
design techniques has allowed the development of cost
effective subsea LNG pipeline designs for marine operations
associated with both offshore and onshore LNG terminals.
New techniques have been developed to address the double
containment issues and the management of high temperature
differences in a cost effective pipe in a pipe approach.

Acknowledgements
The authors would like to thank Fluor Corporation
management for the permission to publish this paper. Grateful
acknowledgement is given to Eisenbau Kramer for the
development of their pipeline and welding manufacturing
processes for the 9%Ni used for the cryogenic pipeline
solution and for their permission to publish information
pertaining to this technology. Grateful acknowledgement is
also given to Brück Pipeconnector for manufacturing and
assembly technology used in the 9%Ni bulkheads and to
Cabot Corporation for the development of their high
efficiency Nanogel® Aerogel insulation system used in the
qualification testing program, and their permission to publish
information pertaining to their technology. Grateful
acknowledgement is also given to Astro Technology, Inc. for
their continued research and development of sensor
monitoring technology during the sensor benchmark tests in
cryogenic temperatures and their permission to publish this
information. Last but not least, our gratitude goes to our
colleagues at Fluor Corporation for their contributions and
constructive comments while writing this paper.

View publication stats

You might also like