You are on page 1of 2

LEAD DIAGRAM OF EARTH

REVITALIZATION OF T.P.LINK CANAL BADLY DAMAGED DUE TO EXCESSIVE FLOOD DURING FLOOD 2010.
(Reach RD 44+000)

Spoil of Earth 55+000


RD 55+000

Borrow area

11000 ft

RD 44+000 Site of work

Certified that the Lead provided is correct as per site


LEAD
condition and is nearest available route.
RD 55+000 – 44+000 = 11000

= 11000/ 5000 = 2.2 Mile


Executive Engineer
Sub Divisional Officer
Taunsa Barrage Division
Workshop Sub Division
Kot Addu.
Say = 2 Mile
Kot Adu
LEAD DIAGRAM OF EARTH
REVITALIZATION OF T.P.LINK CANAL BADLY DAMAGED DUE TO EXCESSIVE FLOOD DURING FLOOD 2010
(Bridge Rd 124+000)

RD 124+000 Bridge
Site of work

9000 ft

RD 115+000 spoil

LEAD
Certified that the Lead provided is correct as per site
condition and is nearest available route. RD 124+000 – 115+000 = 9000

= 9000/ 5000 = 1.80 Mile


Sub Divisional Officer Executive Engineer
Taunsa Barrage Division
Say = 2 Mile
Workshop Sub Division
Kot Adu Kot Addu.