Professional Documents
Culture Documents
James J. Curry
Simulation Modeling in Lean Programs
This presentation provides examples where simu- order. Attributes may include line-item codes and
lation modeling was used as a tool in lean im- amounts, as well as time stamps associated with
provement programs, as a complement to other processing.
techniques such as value stream mapping and kai- It is common to use simulation to evaluate
zen. available capacity, particularly where there are
It is particularly valuable in operations where many products involved. It is also common to use
a mix of products share resources, and it is diffi- it to evaluate balancing of demand with supply,
cult to “get your head around” all the things that with either make-to-stock inventory or make-to-
are happening asynchronously, even in an opera- order lead times to consider.
tion with only moderate complexity. Models also take statistical variability into ac-
Takeaways from this presentation include count for demand, processing times and yields,
setups, and unplanned downtimes that are impor-
Simulation utilizes real historical data to test tant, real-world considerations. The term “monte
lean changes in advance of implementation. carlo” simulation refers to this injection of statisti-
It is valuable for evaluating things that other cal variability into the model runs.
tools cannot, such as product mix, setups,
variability in processes, downtimes, demand SOME TYPICAL REAL BENEFITS
patterns, etc. Some benefits I have seen companies achieve with
Employees such as lean analysts, engineers, simulation modeling as part of their approach in-
planners or six sigma black belts can be clude
trained to use and develop these types of
models. Modeling can become another tool in improvement in service level with inventory
their toolbox. reductions
shift/work center changes
There are sometimes objections in the lean reduction in manpower needed for an opera-
community to using software solutions in lean tion
manufacturing analysis. In this case, simulation end-to-end cycle time improvement
modeling is a valuable complement to, rather than measurement of impacts of late materials on
a replacement for, the traditional tools. For exam- downstream operations
ple, value stream mapping is a key tool; it is a good measurement of variability and product mix
beginning. But it is static and typically only done impacts on capacity.
for high-volume products or classes of products.
Simulation allows the value stream map to become LEAN PROJECT DEMONSTRATIONS
dynamic, and to model the range of probable val- The two example projects presented include an
ues—not just averages. It also allows linkages to improvement project for a plant that manufactures
other tools such as projected capacity utilization in laminated plastic products, and a project to im-
a consistent manner. prove service level and inventory carrying cost for
The presentation includes some background a network in Europe.
to describe simulation, and it has two examples of The projects incorporate lean techniques that
lean projects that used models for testing. One of are simulated and their effects measured, including
the examples is for a lean analysis of a factory, and
the other is for a supply chain network. kanbans
schedules (batching vs. one-piece flow)
SIMULATION: WHAT & WHY EPEI (every-part-every-interval) rhythm cycles
Simulation refers to a software program, and there constant work-in-process (CONWIP)
are different types and uses of it within manufac- setup reduction
turing. This presentation refers to “discrete simu- routing changes
lation” that allows one to visually see and measure shared resources
how processes perform over time, including mate- postponement strategy.
rials, information, and financial flows, and how
probabilistic variables impact them. A discrete
simulation program tracks all attributes of some-
PLASTICS PRODUCTS PLANT
The plant had a record of service-level problems in
thing such as a production order or customer
meeting demand, as well as higher overtime than
2006 International Conference Proceedings, © 2006 APICS—The Educational Society for Resource Management 1
Simulation Modeling in Lean Programs
2006 International Conference Proceedings, © 2006 APICS—The Educational Society for Resource Management 2
Simulation Modeling in Lean Programs
The approach taken was to use a proprietary For each channel, safety stock requirements
methodology to categorize the production lead by product were first estimated using a formula-
times and consistency of those times for each based approach. Then sets of monte carlo simula-
product, and to categorize the demand by volume tions were run to test the service levels with the
and variability. A good statistic to measure relative estimates. In cases where statistical variations re-
variability is the coefficient of variation (CoV), sulted in lower than expected service levels, the
which is computed as the standard deviation safety stocks or production frequency were
(SD)/mean. In this case, weekly SD and mean changed. Chart 8 shows the results of this for the
were used. high volume channel products.
The impact of lead time and demand variabil- The simulations included both the safety
ity on how much safety stock (SS) is required can stock and cycle stock required to support the re-
be demonstrated by Chart 2. It shows how the plenishment cycles. The resulting inventory cost
amount of SS varied to achieve the same level of could then be compared to a baseline actual inven-
service as lead time and demand variability in- tory value.
creases. It should be noted that the chart assumes The results of the simulations follow:
no variability in lead time.
Actually, there is variability in lead time, so The high-volume channel products with level
that is one of the reasons simulation is used. biweekly supply showed service levels close to
100 percent, with 60 percent less inventory vs.
METHODOLOGY the baseline.
The proprietary methodology used consisted of a The high-cost channel with postponement
several step analytical process to categorize the showed that, on average, service levels of 97+
products based on demand volume, demand vari- percent could be reached with 30 percent less
ability, inventory cost, and production/supply. inventory than the baseline.
Charts 3 – 6 summarize these data. The low-volume/low-cost products with con-
The analysis also consisted of consideration of sistent production patterns could result in im-
unit costs by product, since there was a wide varia- proved service levels at about the same level of
tion in the unit costs. The operational cost of a inventory.
separate labeling step was also considered, as well
as the one-time capital investment cost to create a Chart 9 shows the overall service levels from
separate labeling facility. The result was a pro- the simulation for all countries and all products
posed design to manage the supply chain as three Within the high volume channel, further
channels: analysis of the products and customers who pur-
chased them was conducted. Some of the high-
A high-volume channel included 14 country est-volume customers with consistent volumes
labeled products and accounted for 66 percent were selected for direct delivery form the plant,
of volume, 26 percent of inventory. These bypassing the country inventory.
products would be produced biweekly.
A high-cost channel included 23 “white label” POSTPONEMENT RESULTS
products and accounted for 18 percent of For the high-cost products selected for possible
volume but 63 percent of inventory. These postponement of labeling, the simulation showed a
products would be produced every four to benefit resulting from the combination of short-
eight weeks depending on volume. Kanbans ened/consistent lead times, and the reduced vari-
for country labeled stock would drive the la- ability in the aggregated demand (at the European
beling process. “white label”) level.
Low-volume/low-cost channels were the re- For example, one product sold in seven coun-
mainder, with 16 percent of volume, 11 per- tries had CoVs ranging from .95 to 2.85 at the
cent of inventory. These would be produced country level and was replenished by the plant only
every six months and were products spread semi-annually for most countries.
over the year. The new process for this product had white
label product produced every six weeks, and the
Chart 7 summarizes the channel breakout to be tested. CoV Europe-wide was 65. Chart 2 shows the rela-
tive differences in stock required to provide 98
SIMULATION percent service for this product.
Separate sets of simulations were run for each The kanbans set up for labeled stock were
channel using a replenishment model, as shown in pallet sizes for each product, and lead times to
Figure 7. label and ship were one week.
2006 International Conference Proceedings, © 2006 APICS—The Educational Society for Resource Management 3
Simulation Modeling in Lean Programs
The simulation showed that for this product dents, so the learning curves for employees may
about a 98 percent service level to the end cus- not be as long as they might have previously.
tomer demand could be achieved with about 28 I have been teaching graduate students to de-
percent less inventory, considering both safety velop Extend models as part of supply chain de-
stock and cycle stock. sign and lean manufacturing courses for five years.
The students get about 15 hours of classroom
SUMMARY instruction and several model building exercises in
A model supported methodology such as the one a semester. Most of the students are capable of
described includes a traditional continuous im- modeling a simple manufacturing operation after
provement program, where the multi-functional that, and some have fairly advanced skills. It takes
team uses the model to test scenarios and evaluates a person about a year to develop the expertise to
the relative benefits of process changes. Models develop a model from scratch for the type of op-
have also been shown to have continuing value for eration described in this case study. On-the-job
decisions about how to schedule an operation, or training and doing it is the most important aspect
capacity planning for the operation, using a base- of gaining the experience.
line set of volumes with incremental changes.
The examples in this presentation are from ABOUT THE AUTHOR
models developed by OpStat in Extend™, a dis- Jim Curry is CEO of the OpStat Group and has
crete simulation program from Imagine That Inc. consulted for multi-national companies in operations
Many undergraduate and graduate programs are and supply chain improvement since 1987.
now including instruction in Extend to their stu-
2006 International Conference Proceedings, © 2006 APICS—The Educational Society for Resource Management 4
Simulation Modeling in Lean Programs
Before process
Packaging is critical
constrained resource
Laminating Demand
Extrusion Repair Packaging
& cutting
Repair 60 +
Centers finished
Centers Limited
storage products
space
MRP Signal 3 Passes on
the same
equipment
Proposed Process
Rhythm Cycle Product Group Allotment
EPE Rhythm
Cycle
LIGHT 80
LIGHT 55
LIGHT 25
FULL 80
FULL 55
FULL 25
Triggered by Schedule to
kanban maintain
replenishment CONWIP Demand
Forecasts
Extrusion Laminating Cutting
Repair Packaging & actual
Centers orders
2006 International Conference Proceedings, © 2006 APICS—The Educational Society for Resource Management 5
Simulation Modeling in Lean Programs
OEE Metrics
Total Operating Time
No
Performance Availability
•Failures
B – Running time •Setup
C – Target output
•Minor
Stoppages
D – Actual output •Reduced
Speed
•Scrap/
effectiveness
rework
F – Good output •Startup
loss
OEE = B / A x D / C x F / E
Availability rate Performance rate Quality rate
2006 International Conference Proceedings, © 2006 APICS—The Educational Society for Resource Management 6
Simulation Modeling in Lean Programs
Graphics Example
Cycle times
increasing due
to bottleneck
Volumes &
Bottleneck is in fulfillment: not
the 3rd operation meeting demand
Metrics Example
Track utilization of
each set of
equipment in a
work center
Work center
performs better
than takt
requirement
2006 International Conference Proceedings, © 2006 APICS—The Educational Society for Resource Management 7
Simulation Modeling in Lean Programs
Demand Variability
Amount
Time between Receipts
Amount Plant
or DC
25
Weeks of SS Required
20
15
10
5
0
0 5 10 15 20 25 30
Lead Time: Weeks
2006 International Conference Proceedings, © 2006 APICS—The Educational Society for Resource Management 8
Simulation Modeling in Lean Programs
70.0%
60.0%
50.0%
40.0%
30.0%
20.0%
10.0%
0.0%
Demand Category > 200 - 100 - 48 - 26 - 11 -
< 11
Units per Week 1,000 1,000 200 100 48 26
% of Demand 66.1% 20.1% 7.0% 3.7% 1.8% 0.9% 0.4%
% of Inventory 26.2% 42.4% 11.2% 6.7% 5.9% 2.8% 4.9%
Number of 14 28 28 28 28 28 44
Products
70.0% 3.00
60.0% 2.50
Average Coefficient of
50.0%
% of Demand
2.00
40.0%
1.50
Variation
30.0%
1.00
20.0%
10.0% 0.50
0.0% 0.00
Demand Category > 200 - 100 - 48 -
26 - 4811 - 26 < 11
Units per Week 1,000 1,000 200 100
% of Demand 66.1% 20.1% 7.0% 3.7% 1.8% 0.9% 0.4%
Demand Variability 0.57 1.14 1.20 1.45 1.80 1.76 2.83
Number of 14 28 28 28 28 28 44
Products
2006 International Conference Proceedings, © 2006 APICS—The Educational Society for Resource Management 9
Simulation Modeling in Lean Programs
4.00
Coefficient of Variability
3.00
Weekly
variation
1.00 < 100%
0.00
1 10 100 1,000 10,000
20
15
10
0
Demand Category 200 - 100 - 48 -
Units per Week > 1,000 26 - 48 11 - 26 < 11
1,000 200 100
Max Shipments 17 18 10 5 4 13 4
Min Shipments 2 1 1 1 0 0 0
Avg Shipments 8 6 3 2 2 1 1
2006 International Conference Proceedings, © 2006 APICS—The Educational Society for Resource Management 10
Simulation Modeling in Lean Programs
80%
60%
40%
20%
0%
High Volume High Cost Other
% of Demand 66% 18% 16%
% of Inventory 26% 63% 11%
Candidate
Candidate
14
14 2323 36
36
Presentations
Products (11White
(11 Generic)
Label) Generic
White Label Generic
White Label
2006 International Conference Proceedings, © 2006 APICS—The Educational Society for Resource Management 11
Simulation Modeling in Lean Programs
2006 International Conference Proceedings, © 2006 APICS—The Educational Society for Resource Management 12