INSTALLATION OF WELLHEAD JACKETS

Plan Actual Variance


WH No. Duration Duration Duration
Start Finish Start Finish Start Finish
(Days) (Days) (Days)
WH4 18 28-Nov-03 15-Dec-03 9 06-Jan-04 14-Jan-04 -9 39 30

WH5 10 18-Jul-03 27-Jul-03 8 09-Jun-03 16-Jun-03 -2 -39 -41

WH6 9 26-Apr-04 04-May-04 10 20-May-04 29-May-04 1 24 25

WH7 21 11-Jan-02 31-Jan-02 9 04-Jan-02 12-Jan-02 -12 -7 -19

WH8 8 27-Jul-05 03-Aug-05 11 01-Aug-05 11-Aug-05 3 5 8

WH9 12 19-Oct-04 30-Oct-04 6 02-Oct-04 07-Oct-04 -6 -17 -23

WH10 7 24-Oct-06 30-Oct-06 11 16-Nov-06 26-Nov-06 4 23 27

WH11 15 16-Jun-07 30-Jun-07 8 17-Jun-07 24-Jun-07 -7 1 -6

Average 12.5 9.0 -3.5