Activity Activity Revised Pevised Revised Current Current Current 2008

ID Description Plan Plan Plan Forecast Forecast Forecast JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
Duration Start Finish Duration Start Finish 30 6 13 20 27 3 10 17 24 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28
Wellhead Platform 6
000033 Relocate DB27 for WH6 beach pull 1 16JAN08 16JAN08 1 08MAR08 08MAR08 Relocate DB27 for WH6 beach pull

000012 Shore pull and lay to KP 92.2 9 17JAN08 25JAN08 9 09MAR08 17MAR08 Shore pull and lay to KP 92.2

000013 Lay 610 79 26JAN08 13APR08 79 18MAR08 04JUN08 Lay 610

000016 Install Riser 9 14APR08 22APR08 9 05JUN08 13JUN08 Install Riser

000017 Remove Temporary Deck 2 24APR08 25APR08 2 15JUN08 16JUN08 Remove Temporary Deck

000019 Deck Installation 3 26APR08 28APR08 3 17JUN08 19JUN08 Deck Installation

000014 Flood, Gauge, Gel Clean, Hydrotest 30 29APR08 28MAY08 30 20JUN08 19JUL08 Flood, Gauge, Gel Clean, Hydrotest

000027 Hook-Up and Mechanical Completion 58 29APR08 25JUN08 58 20JUN08 16AUG08 Hook-Up and Mechanical Completion activities
activities

000020 Install Wyes 14 10MAY08 23MAY08 14 01JUL08 14JUL08 Install Wyes

000040 MC activities WH6 pipeline 33 29MAY08 30JUN08 33 20JUL08 21AUG08 MC activities WH6 pipeline

000029 Mechanical Acceptance WH6 Facilities 0 30JUN08 0 21AUG08 Mechanical Acceptance WH6 Facilities

Wellhead Platform 8
000021 DB27 mobilise to SITE 2 01JAN08* 02JAN08 3 20JAN08A 22JAN08A DB27 mobilise to SITE

000011 Shore pull and lay to Dolphin xing 14 03JAN08 16JAN08 14 24FEB08* 08MAR08 Shore pull and lay to Dolphin xing

000035 Relocate DB27 for WH8 pipeline 1 13APR08 13APR08 1 14JUN08 14JUN08 Relocate DB27 for WH8 pipeline

000015 Lay 811 61 23APR08 22JUN08 61 14JUN08 13AUG08 Lay 811

000023 Install Riser 11 25JUL08 04AUG08 11 14AUG08 24AUG08 Install Riser

000024 Remove Temporary Deck 3 08AUG08 10AUG08 3 25AUG08 27AUG08 Remove Temporary Deck

000025 Deck Installation 3 11AUG08 13AUG08 3 28AUG08 30AUG08 Deck Installation

000022 Flood, Gauge, Gel Clean, Hydrotest 19 23JUN08 11JUL08 30 31AUG08 29SEP08 Flood, Gauge, Gel Clean, Hydrotest

000028 Hook-Up and Mechanical Completion 63 17AUG08 18OCT08 63 31AUG08 01NOV08 Hook-Up and Mechanical Completion activities
activities

000026 Install Wyes 14 14AUG08 27AUG08 14 11SEP08 24SEP08 Install Wyes

000053 MC activities WH8 pipeline 42 28AUG08 08OCT08 30 30SEP08 29OCT08 MC activities WH8 pipeline

000030 Mechanical Acceptance WH8 Facilities 0 31OCT08 0 01NOV08 Mechanical Acceptance WH8 Facilities

Start Date 01DEC07 OFFU Sheet 1 of 1


Revised Plan
Finish Date 01NOV08 RasGas Company Limited Date Revision Checked Approved
Current Forecast
Run Date 24FEB08 10:00 24FEB08 Rev. 00 CJB ACG
Progress Bar
Train 6 Facilities Installation
Critical Activity

By platform

© Primavera Systems, Inc.