ID Description Plan Plan Plan Forecast Forecast Forecast JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
Duration Start Finish Duration Start Finish 30 6 13 20 27 3 10 17 24 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28
Wellhead Platform 6
000033 Relocate DB27 for WH6 beach pull 1 16JAN08 16JAN08 1 08MAR08 08MAR08 Relocate DB27 for WH6 beach pull
000012 Shore pull and lay to KP 92.2 9 17JAN08 25JAN08 9 09MAR08 17MAR08 Shore pull and lay to KP 92.2
000017 Remove Temporary Deck 2 24APR08 25APR08 2 15JUN08 16JUN08 Remove Temporary Deck
000014 Flood, Gauge, Gel Clean, Hydrotest 30 29APR08 28MAY08 30 20JUN08 19JUL08 Flood, Gauge, Gel Clean, Hydrotest
000027 Hook-Up and Mechanical Completion 58 29APR08 25JUN08 58 20JUN08 16AUG08 Hook-Up and Mechanical Completion activities
activities
000040 MC activities WH6 pipeline 33 29MAY08 30JUN08 33 20JUL08 21AUG08 MC activities WH6 pipeline
000029 Mechanical Acceptance WH6 Facilities 0 30JUN08 0 21AUG08 Mechanical Acceptance WH6 Facilities
Wellhead Platform 8
000021 DB27 mobilise to SITE 2 01JAN08* 02JAN08 3 20JAN08A 22JAN08A DB27 mobilise to SITE
000011 Shore pull and lay to Dolphin xing 14 03JAN08 16JAN08 14 24FEB08* 08MAR08 Shore pull and lay to Dolphin xing
000035 Relocate DB27 for WH8 pipeline 1 13APR08 13APR08 1 14JUN08 14JUN08 Relocate DB27 for WH8 pipeline
000024 Remove Temporary Deck 3 08AUG08 10AUG08 3 25AUG08 27AUG08 Remove Temporary Deck
000022 Flood, Gauge, Gel Clean, Hydrotest 19 23JUN08 11JUL08 30 31AUG08 29SEP08 Flood, Gauge, Gel Clean, Hydrotest
000028 Hook-Up and Mechanical Completion 63 17AUG08 18OCT08 63 31AUG08 01NOV08 Hook-Up and Mechanical Completion activities
activities
000053 MC activities WH8 pipeline 42 28AUG08 08OCT08 30 30SEP08 29OCT08 MC activities WH8 pipeline
000030 Mechanical Acceptance WH8 Facilities 0 31OCT08 0 01NOV08 Mechanical Acceptance WH8 Facilities
By platform