Tentative Availability
Sr. No Description Area of Concerns Action Taken Action By Status
Date
1 FBE Spools Delivery of 39 nos. FBE Spools to site Received at Nizwa for coating and painting. Mr. Lolu 24-Apr-21 Open
6 Tap Set - 1 No Required 1.1/4" one set and 1.1/8" one set Delivery expected by 20-Apr'21 however due to Mr. Durai 22-Apr-21 Open
VAT implementation likely to delay one or two
days
NDT to completed by 19th Apr'21. Discussed with TPI & Tentative date to be
7 Spreader Beam required for Valve Erection Mr. Mathew 22-Apr-21 Open
Load Test & TPI to be arranged at Package-A confirmed based on the Welding & NDT
clerance.
12 Hydraulic Torquing Hose for the Hydraulic torquing machine. Machine brought to Package A for checking the Mr. Swarup To be checked Open
availability of Missing hose.
13 Support for Mechanical Completion Requirement of Piping Engineer Mr. Jitendra Sahoo will report to Package-C Mr. Suraj 20-Apr-21 Open
14 Painting Supervisor-Mr. Santosh Clerance from Saipem HSE to be taken for Access cardDiscussed with Saipem HSE & they had given the C Mr. Anyen 19-Apr-21 Closed
Action Taken against the Area of Concerns-Discussed during the Meeting dated 18th Apr'21 at Package-C