Action Taken against the Area of Concerns-Discussed during the Meeting dated 18th Apr'21 at Package-C

Tentative Availability
Sr. No Description Area of Concerns Action Taken Action By Status
Date
1 FBE Spools Delivery of 39 nos. FBE Spools to site Received at Nizwa for coating and painting. Mr. Lolu 24-Apr-21 Open

24"- CS Clamp missing - 02 No's


2 Installation of CS Supports Refabrication of missing clamp informed to Open
48"- CS Clamp missing - 03 No's Mr. Suraj Will be confirmed shortly.
Nizwa team.
3 Installation of SS Supports 12"- DSS Clamp missing - 04 No's Open
4 Manual Torque wrench 1300 Nm - 01 No  Urgently required. Material Sent from Muscat Mr. Durai 18-Apr-21 Closed
5 Drill Bit 6mm x 200 mm Long 20 Nos required urgently Cash Purchase instead of PO Placement Mr. Durai 22-Apr-21 Open

6 Tap Set - 1 No Required 1.1/4" one set and 1.1/8" one set Delivery expected by 20-Apr'21 however due to Mr. Durai 22-Apr-21 Open
VAT implementation likely to delay one or two
days

NDT to completed by 19th Apr'21. Discussed with TPI & Tentative date to be
7 Spreader Beam required for Valve Erection Mr. Mathew 22-Apr-21 Open
Load Test & TPI to be arranged at Package-A confirmed based on the Welding & NDT
clerance.

 PO No: 20121030086. Materials are ready for


8 U - Clamps Delivery to be done. Mr. Durai Will be update shortly. Open
delivery and held up due to payment issues.

Delivery date will be informed


9 Filling foam-100 Nos Delivery to be done. PR No. 10P08641012100068. Still under PO Mr. Durai Open
shortly.
process.
10 33 KVA Termination PO to be raised for manpower. Order expected to release by 21st April-21 and Mr. Durai 28-Apr-21 Open
try to mobilize by early next week.
6 mm x 200 mm long Drill bit required - 20 no's Cash Purchase instead of PO Placement Mr. Durai 22-Apr-21 Open
11 Roof Sheeting Works
Stanley Rivet Gun - 02 Material Sent from Muscat Mr. Durai 18-Apr-21 Closed

12 Hydraulic Torquing Hose for the Hydraulic torquing machine. Machine brought to Package A for checking the Mr. Swarup To be checked Open
availability of Missing hose.
13 Support for Mechanical Completion Requirement of Piping Engineer Mr. Jitendra Sahoo will report to Package-C Mr. Suraj 20-Apr-21 Open
14 Painting Supervisor-Mr. Santosh Clerance from Saipem HSE to be taken for Access cardDiscussed with Saipem HSE & they had given the C Mr. Anyen 19-Apr-21 Closed
Action Taken against the Area of Concerns-Discussed during the Meeting dated 18th Apr'21 at Package-C

Sr. No Description Concern Raise Action By Action Date Status