Report of the Project Engineer as of: January 15, 2021

Target Accomplishment 52.8438%


Percent of Work Accomplished 52.8438%
Slippage -
Target Date of Completion March 03, 2021
Contract Time 150 CD
Time Elapsed 85 Days

Manpower 16 - Workers
1 - Foreman
11 -Skilled
4 - Laborers

Previous Activities:

- Installation of steel tracks and studs


- Installation of dry wall partition
- Installation of steel hangers for ceiling boards
- Electrical wirings for power and lightings

On-going Activities:

- Tile works 97%


- Installation of ceiling boards 90%
- Electrical works 80.94%
- Installation of ACU 70%
- Painting works 20%
- Carpentry works 80%

Projected Activities:

- Fabrication of office partition


- Fabrication of Lighting Fixtures
- Fabrication of Panel Boards

Submitted by:

Christian B. Canlas
Project Engineer