Updating contract subline results in re-calculating subtotal amount with wrong result.

In below screenshot you will find a example.

For this contract subtotal for subline 1.1 was 3600 which was correct.
After updating subline “Line ref” subtotal was changed to 216000.

This also happens with contract with status Active after opening for update.
Requery of contract results in change of line level subtotal as well.