Professional Documents
Culture Documents
Abstract—The long transmission line energization can cause the installation of metal oxide surge arresters (MOSA) at both
high overvoltage stresses mainly along the transmission line, but line terminals. The effective protection characteristics, the high
also in the supply network. A traditional method of limiting reliability and the high dissipation capabilities of modern
switching overvoltages to acceptable levels is to use circuit
gapless MO surge arresters can meet, in many cases, the
breakers equipped with pre-insertion resistors.
This paper describes a study made in an actual 500 kV AC overvoltage limitation requirements of extra high voltage
transmission system considering two alternatives in order to limit (EHV) transmission lines switching. Further reduction of the
switching surge overvoltages during line energization: the use of switching overvoltage can be achieved by the use of an
metal oxide surge arresters at both line ends and along the line additional arrester in the middle of the line or by the
and the use of synchronized closing of circuit breakers. application of special arresters with lower protection level and
Digital simulations have been made with PSCAD/EMTDC. higher discharge energy capability. [1,2,6]
The degree of shunt compensation is considered as independent
Another method to reduce the switching transient is
parameter.
synchronous switching. It is a method for eliminating transient
Keywords: Synchronized switching, metal oxide surge overvoltages trough time controlled switching operations.
arrester, pre-insertion resistor, PSCAD. Closing commands to circuit breaker are delayed in such a way
that contact separation will occur at the optimum time instant
I. INTRODUCTION related to the phase angle. Successful field experiences have
HE switching transient in a transmission system cannot be been presented during the last years using synchronized
T prevented as well as its total suppression is extremely
difficult. However, its magnitudes have to be limited to
control maneuvers of capacitors banks and shunt reactors in
high-voltage systems. [4,5,7,9]
become compatible with insulation level of the system The objective of this paper is to analyze the overvoltages
equipment. The transmission line energization is a typical levels generated in a transmission line during the energization
maneuver, whose transient magnitude is influenced by the maneuver for distinct mitigation devices. Such survey is basic
system configuration as well as by the equipment to infer the performance of the "conventional methods" as it is
characteristics. Consequently, overvoltage control measures the case of the pre-insertion resistors and/or surge arresters
have to be adopted providing suitable protection for the versus the controlled switching breakers. Finally a comparative
network. analysis of these three trends of overvoltages mitigation is
For long transmission lines, traditionally the switching made and it is determined the best technical conditions for the
transient overvoltages are limited through the adoption of pre- optimization of the energization process.
insertion resistors in the line circuit breakers. Although this is
an effective mitigation method it presents a decreasing II. SYSTEM MODELED
acceptance due to the high cost of implementation and The study was performed in an actual 500 kV power system
maintenance. [1,2,3] with the configuration shown in Fig. 1. The PSCAD/EMTDC
The first alternative analyzed to replace closing resistors is (Power System Computer Aided Design / Electro Magnetic
Transient DC) has been used for the simulations [10].
This work supported by the CAPES – entity from Govern of Brazil to support The line parameters calculated for fundamental frequency
study and research. The authors thank the financial support received from (60 Hz) using the routine LINE CONSTANT do PSCAD and
FAPESP – Fundação de Amparo à Pesquisa do Estado de São Paulo and from
CNPq – Conselho Nacional de Desenvolvimento Científico e Tecnológico.
are presented in the Table I. The line was supposed ideally
P. Mestas is a M.Sc. student at School of Electrical and Computer
transposed and the frequency dependence of the longitudinal
Engineering (FEEC), University of Campinas (UNICAMP), Campinas, São parameters was modeled with frequency dependent (phase)
Paulo, Brazil (e-mail: pmestasv@dsce.fee.unicamp.br). model.
M. C. Tavares is with the School of Electrical and Computer Engineering TABLE I
(FEEC), University of Campinas (UNICAMP), Campinas, São Paulo, Brazil BASIC LINE UNITARY PARAMETERS – 60 HZ
(e-mail: cristina@dsce.fee.unicamp.br). components longitudinal (Ω/km) transversal (µS/km)
non homopolar 0.0161 + j 0.2734 j 6.0458
Presented at the International Conference on Power Systems
Transients (IPST’07) in Lyon, France on June 4-7, 2007
homopolar 0.4352 + j 1.4423 j 3.5237
Fig. 1. 500 kV Transmission line details
The procedure to energize the line is to energize each and 95 % shunt compensation and for the four surge arresters
section from one extremity (B1 or B5), assuming that the cases considered as follows:
previous busbar was already stabilized in adequate voltage
level, before the following section is energized. - Without any surge arrester;
The monitored maneuver presented in this paper - Surge arrester at line ends only;
corresponds to the last line section energization in the - Surge arresters at line ends and midpoint;
direction B4 Ø B5. The pre-switching voltage at the sending - Surge arresters at line ends and two additional
end was 1.00 p.u. and 0.95 p.u. for 70 % and 95 % shunt arresters.
compensation, respectively. The transient overvoltages had
been registered in 7 points of the line section B4-B5, being the Metal oxide arrester rated 420 kV.
two terminals and 5 intermediate points. As seen from the figure 2, using 420 kV rated arrester for
the 95 % shunt compensation line, the line overvoltage along
III. SURGE ARRESTER the line is not reduced. At the remote terminal the overvoltage
The surge arrester is used basically to protect the value is reduced only in 1,1%.
transmission line and connected equipments against switching The 70 % shunt compensation line energization (Fig. 3)
and lightning overvoltages. In this paper only switching resulted in higher overvoltages as expected and therefore the
overvoltage protection is considered. surge arresters played some role in reducing the overvoltages.
Considering that up-to-date ZnO arresters may have low At the remote terminal the overvoltage value is reduced in 5%.
protective levels and high dissipation capabilities, they can be 2
applied as economical devices to mitigate transmission line No overvoltage control
MOSA at line ends
switching surges. Further reduction of switching overvoltage 1.9
MOSA at line ends and midpoint
can be achieved by the use of additional arresters in the middle MOSA at line ends + 02 additionals
of the line or along the line or by the application of special 1.8
Overvoltages (p.u.)
2
No overvoltage control 1.4
MOSA at line ends
1.9 MOSA at line ends and midpoint
1.3
MOSA at line ends + 02 additionals 0 10 20 30 40 50 60 70 80 90 100
1.8
Distance (% of line length)
Overvoltages (p.u.)
1.7
Fig. 6. Overvoltage profile along the line with 95% shunt compensation using
arrester Ur=360 kV Class 3.
1.6
1.5
No overvoltage control
2.1
MOSA at line ends
MOSA at line ends and midpoint
1.4
2 MOSA at line ends + 02 additionals
1.3
0 10 20 30 40 50 60 70 80 90 100
1.9
Distance (%of line length)
Overvoltage (p.u.)
2
1.6
1.9
Overvoltages (p.u.)
1.5
1.8
1.4
0 10 20 30 40 50 60 70 80 90 100
1.7 Distance (% of line length)
1.6
Fig. 7. Overvoltage profile along the line with 70% shunt compensation using
arrester Ur=360 kV Class 3.
No overvoltage control
1.5 MOSA at line ends
MOSA at line ends and midpoint
MOSA at line ends + 02 additionals
1.4
0 10 20 30 40 50 60 70 80 90 100
Distance (% of line length)
Fig. 5. Overvoltage profile along the line with 70% shunt compensation using
arrester Ur=396 kV Class 5.
It can be observed in Table II that the energy absorption Controlled switching - closed each phase crosses consecutives zero
capacity of the arresters has not been exceeded in any Controlled switching - closed with 60°delay.
1.44
simulation, even in the cases of arrester with Ur = 360 Class 3
(2.8 MJ). The energy absorption levels are far below the 1.43
arresters capability.
1.42
Overvoltage (p.u.)
TABLE II 1.41
ENERGY CONSUMPTION
1.4
Rated Energy 95% Shunt 70% Shunt
Arrester (MJ) Compensation Compensation 1.39
Energy (MJ) Energy (MJ)
420 kV 6,5 0,006 0,120 1.38
IV. SYNCHRONIZED CIRCUIT-BREAKER In Fig. 10 and Fig. 11 the voltage waveform at receiving
Controlled switching is the method of switching each pole end is presented for line energization without mitigation
individually at the optimal point-of-wave to reduce the method and with synchronized switching. It can be observed
switching overvoltage. This is achieved by special control that not only the overvoltage was reduced with the
circuit that initiate commands based on information from the synchronized switching but also the waveform has low
system and the characteristics of the circuit breakers. [8,9] harmonic content.
For this work, the synchronized circuit-breaker control was
ENERGIZAÇÃO DO TRAMO 4-5
LINE ENERGIZATION -> BARRA 5 4-5 > BAR 5
SECTION
implemented using the components SEQUENCERS that are Phase A Phase B Phase C
800
part of a special group of PSCAD/EMTDC control elements 600
with two variants: 400
Voltage [kV]
- The closing order was given when the voltage of each 200
the switching due to transient. In the specific case of the Time [s]
system in study the difference is minimum as shown in Fig. 10. Receiving end. Line energization without overvoltage control.
Fig. 8, at the receiving terminal, i.e. in B5. In Fig. 9 it is
presented the voltage profile for the two cases when a line is LINE ENERGIZATION - SECTION 4-5 > BAR 5
95 % shunt compensated. 600
Phase A Phase B Phase C
400
Voltage [kV]
200
-200
-400
-600
0.350 0.375 0.400 0.425 0.450 0.475 0.500 0.525 0.550 0.575
Time [s]
Fig. 11. Receiving end. Line energization with synchronized controlled
switching.
1.8 2.1
No overvoltage control No overvoltage control
1.75 Controlled switching Closing resistor
2
Controlled switching + MOSA at line ends Closing resistor + MOSA at line ends
1.7
1.9
Overvoltage (p.u.)
Overvoltage (p.u.)
1.65
1.8
1.6
1.7
1.55
1.6
1.5
1.5
1.45
1.4
1.4
1.3
1.35 0 10 20 30 40 50 60 70 80 90 100
0 10 20 30 40 50 60 70 80 90 100
Distance (% of line length) Distance (% line length)
Fig. 12. Overvoltage profile along the line with 95 % shunt compensation Fig. 14. Overvoltage profile along the line with 95 % shunt compensation
using controlled switching. using pre-insertion resistor.
2 2.1
2
1.9
1.9
1.8
Overvoltage (p.u.)
Overvoltage (p.u.)
1.8
1.7
1.7
1.6
1.6
1.5
1.5
Fig. 13. Overvoltage profile along the line with 70% shunt compensation Fig. 15. Overvoltage profile along the line with 70 % shunt compensation
using controlled switching using pre-insertion resistor.
[1] LEGATE, A.C.; BRUNKE, J.H.; RAY J.J.; YASUDA E.J. “Elimination
of closing Resistors on EHV circuit breakers”, IEEE Transactions on
VIII. BIOGRAPHIES
Power Apparatus and Systems, Vol. 3, No. 1, pp. 223-231-157, Janeiro Patricia Mestas: was born in Peru. She obtained her Mechanical
1988. Electrical Engineering degree from San Agustín University of Arequipa
[2] RIBEIRO, J.R.; MCCALLUM M.E.; “An application of metal oxide (UNSA), Perú. At present she is working toward the M.Sc. degree in School
surge arresters in the elimination of need for closing resistors in EHV of Electrical and Computer Engineering of University of Campinas
breakers”, IEEE Transactions on Power Delivery, Vol. 4, No. 1, pp. 282 (UNICAMP), Brazil. Her research area includes study of electromagnetic
-291, Janeiro 1989. transients.
[3] Bladow, J.K.; Weaver T.L, “Switching surge control for the 500 kV Maria C. Tavares: Electrical engineering (1984) at UFRJ – University of
California – Oregon Transmission Project”, CIGRE, Paper 13-304, Rio de Janeiro, Brazil, M.Sc. (1991) at COPPE/UFRJ, PhD (1998) at
Agosto 1990. UNICAMP. Worked as consulting engineering firms, with power systems
[4] CARVALHO, A.C.; LACORTE, M.; KNUDSEN O., Improved EHV analysis, HVDC, models development at EMTP and electrical transmission
Line Switching Surge Control by Application of MO-arrester and planning. Presently assistant professor of University of Campinas
Controlled Switching, International Conference on Energy Management (UNICAMP, Brazil). Her main research interests are power system analysis,
and Power Delivery, Proceedings of EMPD’95, 1995. long distance transmission and computer application to analysis of power
[5] FROEHLICH, K.; CARVALHO, A.C.; AVENT, B.L.; HOELZL, C.; systems transients.