Professional Documents
Culture Documents
Working Group
C2.13
August 2012
VOLTAGE AND VAR SUPPORT
IN SYSTEM OPERATION
WG C2.13
Members
Copyright © 2012
“Ownership of a CIGRE publication, whether in paper form or on electronic support only infers right
of use for personal purposes. Are prohibited, except if explicitly agreed by CIGRE, total or partial
reproduction of the publication for use other than personal and transfer to a third party; hence
circulation on any intranet or other company network is forbidden. As an exception, CIGRE Collective
Members only are allowed to reproduce the publication.”
Disclaimer notice
“CIGRE gives no warranty or assurance about the contents of this publication, nor does it accept any
responsibility, as to the accuracy or exhaustiveness of the information. All implied warranties and
conditions are excluded to the maximum extent permitted by law”.
ISBN : 978-2-85873-196-1
Voltage and VAr Support in System Operation WG C2.13
Table of Contents
EXECUTIVE SUMMARY 3
CHAPTER 1 5
INTRODUCTION 5
List of Symbols 6
List of Acronyms and Terminology 6
CHAPTER 2 8
ON MAINTAINING A GOOD VOLTAGE PROFILE IN STEADY-STATE AND TRANSIENT SITUATIONS 8
2.1 How to maintain a good Voltage profile 8
2.1.1 What controllable/switchable reactive power sources are available 13
2.1.2 Control schemes 15
2.1.2.1 The hierarchical control scheme 15
2.1.3 Examples 17
2.1.3.1 The Slovenian Control Scheme 17
2.1.3.2 The Chinese hierarchical control scheme 17
2.1.4 TSO and DSO interaction 22
2.1.4.1 The MAVIR system U/Q control 24
2.1.4.2 The current Swissgrid practice 26
2.2 Impact of current and future trends 26
2.2.1 An introductory example: Current situation and perspectives in Slovenian Electric Power System 26
2.2.1.1 Problems in Slovenian Electric Power System 27
2.2.2 Wind power: the example of Germany 28
2.2.3 Higher and more volatile transits: the example of China 30
2.2.3.1 Impact on Steady Operation 30
2.2.3.2 Impact on Transient Stability 31
2.2.4 Underground cables 32
2.2.4.1 Current and future power cable technology 32
2.2.4.2 HV and EHV cable characteristics 32
2.2.4.3 Reactive power compensation 34
2.2.4.4 Voltage profile in steady state 34
2.2.4.5 Transient voltages and currents 34
2.2.4.6 Load sharing 34
2.2.4.7 DC HV cables 35
2.2.4.8 Summary 35
2.2.5 HVDC Links 35
2.2.6 FACTS 36
2.2.7 Incentives for producers and markets of reactive power: the example of Poland 36
CHAPTER 3 37
3.1 Voltage depressions 37
3.1.1 Protection against voltage depressions 39
3.1.2 Fast capacitor switching 39
3.1.3 Under-voltage load shedding 39
3.2 Instabilities 40
3.2.1 Introduction 40
3.3 Voltage collapse 40
3.3.1 Diagnosis 40
Page 1
Voltage and VAr Support in System Operation WG C2.13
Page 2
Voltage and VAr Support in System Operation WG C2.13
EXECUTIVE SUMMARY
Although real power is the primary objective in an Electric Power System (EPS) operation, reactive power
management is crucial in securing a smooth and optimal EPS operation. Nowadays, EPS operate within a set of
constraints, imposed by environmental, economic, and societal considerations. These result in operating EPSs close to
their limits, while, at the same time, trying to minimize costs, and keeping power supply quality at acceptable levels.
Today’s picture is made complex by the market rules, the characteristics of the new types of generation, and
frequently by an increasing severity of weather events. For example, today added challenges to control centres are
posed by the distributed generation and renewables. Also, today the issue of the boundaries between Transmission
System Operators (TSO) and Distribution System Operators (DSO) is more critical than ever. The borders between
different TSOs require special attention. The energy efficiency is at present very important. At the same time, new
technologies have come to maturity in dealing with today’s challenges. HVDC, FACTS devices, smart grid
technologies, are a few examples of present-day available instruments.
Reactive Power Management (RPM) involves key elements, such as Reactive Power Compensation (RPC) equipment,
Optimal Power Flow (OPF) software functionalities, etc, as well as some established practices in power industry.
Reactive power compensation equipment frequently used, are: switched shunt capacitors, shunt reactors, synchronous
condensers, generators, tap-changing transformers, Static VAr Compensators (SVC). Also, grid-topology measures,
such as switching on/off of lines or transformers under no-load conditions, are used for reactive power support in
system operation. OPF software is used in many cases as a day-ahead (D-1) scheduler, but also its use in real-time is
already being implemented, as the case of Tertiary Voltage Regulation (TVR) in China where OPF is the kernel –
details are included further in this document.
Some practices followed in power industry in regard to reactive power management, are:
(a) minimization of the cost of equipment in terms of choosing their most effective positioning (during planning),
type and sizing, or in terms of minimizing their maintenance costs (during operation), and
(b) it is generally accepted as a reactive power dispatching strategy that which results from voltage stability
security-assessment analysis, and which balances reactive power locally on all voltage levels and control areas.
Coordinated Voltage control in transmission networks has in the past also been the subject of another CIGRE
Technical Brochure, TB 310 [1].
In this present Technical Brochure, in line with the current CIGRE Strategic Direction #2 Making the best use of the
existing system [2] and in accordance with the Terms of Reference (ToR) of the WG, we endeavour in and expand:
On maintaining a good voltage profile in steady-state and transient situations, and in particular on:
(a) How to maintain a good Voltage profile, what controllable/switchable reactive power sources are available,
the control schemes, the TSO and DSO interaction, and
(b) The impact of current and future trends in technologies as well as in system practice, including: reference to
European and Chinese Electric Power systems, the impact of decentralized and distributed generation, higher and
more volatile transits, high-voltage underground cables, HVDC, FACTS, and market incentives for reactive power
producers.
Page 3
Voltage and VAr Support in System Operation WG C2.13
Page 4
Voltage and VAr Support in System Operation WG C2.13
Chapter 1
INTRODUCTION
Although real power is the primary objective in an Electric Power System (EPS) operation, reactive power
management is crucial in securing a smooth and optimal EPS operation. Nowadays, EPSs operate within a set of
constraints, imposed by environmental, economic, and societal considerations. These result in operating EPSs close to
their limits, while, at the same time, trying to minimize costs, and keeping power supply quality at acceptable levels.
Reactive power management (RPM) involves key elements, such as reactive power compensation (RPC) equipment,
OPF software functionalities, etc, as well as some established practices in power industry. Reactive power
compensation equipment frequently used, are: switched shunt capacitors, shunt reactors, synchronous condensers,
generators, tap-changing transformers, static VAr compensators. Also, grid-topology measures, such as switching
on/off of lines or transformers under no-load conditions, are used for reactive power support in system operation.
OPF software are used in many cases as a day-ahead (D-1) scheduler, but also the use in real-time is already being
implemented (as the case of TVR in China where OPF is the kernel – details are included further in this document).
Some practices followed in power industry in regard to reactive power management, are:
(a) Minimization of the cost of equipment in terms of choosing their most effective positioning (during planning), or
in terms of minimizing their maintenance costs (during operation), and
(b) It is generally accepted as a reactive power dispatching strategy that which results from voltage stability
security-assessment analysis, and which balances reactive power locally on all voltage levels and control areas.
Coordinated Voltage control in transmission networks has been the subject of another CIGRE Technical Brochure 310
[1].
In this Technical Brochure we endeavour in and expand:
On maintaining a good voltage profile in steady-state and transient situations and in particular on:
(a) How to maintain a good Voltage profile, what controllable/switchable reactive power sources are available,
the control schemes, the TSO and DSO interaction,
(b) The impact of current and future trends in technologies as well as in best system practices, including: reference
to European and Chinese Electric Power systems, the impact of distributed generation, higher and more volatile
transits, underground and submarine cables, HVDC, FACTS, and market incentives for reactive power producers.
On preventing and mitigating interruptions, and in particular on:
(a) Voltage depressions including protection measures, fast capacitor switching, under-voltage load shedding
(UVLS),
(b) Instabilities with reference to rotor angle instability, transient instability, small signal instability, frequency
instability, short-term as well as long-term Voltage instabilities, and
(c) Voltage collapse study cases.
In particular this Technical Brochure includes four chapters, the conclusions at the end, and the references.
The next chapter will begin by dealing with how to maintain a good voltage profile in system operation.
The list of symbols, acronyms, and terminology used herein follows next.
Page 5
Voltage and VAr Support in System Operation WG C2.13
LIST OF SYMBOLS
B Susceptance [S]
δi Voltage angle [º]
I Current [A]
p.u. Per Unit
P Active Power [W]
Q Reactive Power [VAr]
R Resistance [Ω]
U Voltage [V]
X Reactance [Ω]
Page 6
Voltage and VAr Support in System Operation WG C2.13
Page 7
Voltage and VAr Support in System Operation WG C2.13
Chapter 2
Page 8
Voltage and VAr Support in System Operation WG C2.13
TABLE 2: THE TRANSMISSION LINE PARAMETERS FOR THE LOAD FLOW CALCULATION OF THE SHOWN EXAMPLE
ELECTRIC ELECTRIC
POWER SYS. 1 POWER SYS. 2
GENERATION CONSUMPTION
CENTRE CENTRE
Parallel (shunt)
compensation
Figure 2.1. Model of the longitudinal test system consists of double circuit lines.
The series compensation has an impact on the voltage profile as it is seen in Fig. 2.2. It is interesting to note that the
transmitted power doesn’t have a strong impact on voltage profile (compare diagrams in Fig. 2.3 "SC 80%, no PC,
P=0" and "SC 80%, no PC, P=1000 MW"). As the series compensation essentially reduces voltage profile, one
could conclude that only a small portion of the parallel compensation is needed to "fit" voltage into the desired
range of values. Such a conclusion is, however, wrong. The parallel compensation needed (at no load: P=0) is nearly
as much as if there would be no series compensation. This statement can be theoretically proved. The reason is that
parallel compensation and series compensation act in opposite direction regarding reactive power generation.
Page 9
Voltage and VAr Support in System Operation WG C2.13
Voltage / p.u. Voltage Profile of Series and Parallel Compensated 2x400 kV Line
1,2
PC=105 %, SC= 0 %, P=0 MW
1,0
Transmission length / km
0,9
0
100
200
300
400
500
600
700
800
900
1000
1100
1200
1300
1400
1500
1600
1700
1800
1900
2000
2100
2200
2300
2400
2500
2600
2700
2800
2900
3000
Figure 2.2. Voltage profile of series (SC) and parallel (PC) compensated double circuit line sections.
In Fig. 2.3 is necessary to explain the red curve (no PC, SC=0%, P=1000 MW) which shows voltage dependency of
transmission line length during transmission of 1000 MW active power: Figure 2.1 shows the direction of load flow
from generation to consumption centre. In the first section is load flow the highest and causes more losses than in the
second and third section. In the first section transmitted power is higher than SIL – voltage in the middle of the section
is below 1p.u. and in the third section transmitted power is lower than SIL - voltage is above 1p.u.
Voltage / p.u. Voltage Profile of Series Compensated 2x400 kV Line
1,2
1,1
1,0
no PC, SC= 0 %, P=0 MW
100
200
300
400
500
600
700
800
900
1000
1100
1200
1300
1400
1500
1600
1700
1800
1900
2000
2100
2200
2300
2400
2500
2600
2700
2800
2900
3000
Figure 2.3. Voltage profile of series (SC) compensated double circuit line sections.
The parallel compensation rating in the example of 2x1.150 kV is in the range of 50 GVAr (Fig. 2.4), for the whole
system and for the example of 2x400 kV is in the range of 5 GVAr. Figure 2.4 shows how many MVAr of reactive
power for parallel compensation is needed for transmitted power of 0 MW, 2.000 MW, 4.000 MW and 6.000
MW.
Page 10
Voltage and VAr Support in System Operation WG C2.13
50.000
40.000
30.000
20.000
10.000
0
1.000 1.500 2.000 2.500 3.000 3.500 4.000 4.500 5.000 5.500 6.000
Transmission length [km]
Figure 2.4. Reactive power compensation as a Function of the Transmitted Power for the 2x1150 kV line.
Transmission losses are an important factor defining economic benefits of interconnections. The losses are calculated
for power transmission between generation and consumption centre shown in Fig. 2.1. Power of the subsystems
electric power system 1 and electric power system 2 is balanced. Lines are 80% series compensated, the parallel
compensation keeps voltage within limits. Losses as a function of transmitted power, transmission distance and
voltage level are presented in Fig. 2.5÷2.7.
3.500
3.000
2.500
1000 km
2.000
2000 km
3000 km
1.500
4000 km
1.000 5000 km
6000 km
500 30 Deg
S 6000
0
0 1.000 2.000 3.000 4.000 5.000 6.000
Transmitted power [MW]
Figure2.5. Transmission Losses as a Function of the Transmitted Power for the 2x400 kV line.
The curve "30 deg" limits the transmission angle between subsystems to 30 degrees. The transmission angle 30
degrees is set due to operational reasons of the electric power system, the power transmission with angles more than
30 degrees, according to expert point of view, reference [4], can cause stability problems. Also from this point of
Page 11
Voltage and VAr Support in System Operation WG C2.13
view it is obvious that lower voltage levels are not appropriate for power transfer over long distances. Conditions in
which losses exceed 15% of transmitted power or more are not economically reasonable.
Losses [MW] 2x800 kV line
3.000
1000 km
2000 km
2.500
3000 km
4000 km
2.000
5000 km
6000 km
1.500
30 Deg
S 6000
1.000
500
0
0 1.000 2.000 3.000 4.000 5.000 6.000
Transmitted power [MW]
Figure 2.6. Transmission Losses as a Function of the Transmitted Power for the 2x800 kV line.
1000 km
2.500 2000 km
3000 km
2.000
4000 km
5000 km
1.500
6000 km
SC 6000
1.000
500
0
0 1.000 2.000 3.000 4.000 5.000 6.000
Transmitted power [MW]
Figure 2.7. Transmission Losses as a Function of the Transmitted Power for the 2x1.150 kV line.
In the diagrams in Fig. 2.5, 2.6 and 2.7 the dotted curves "SC 6000" are presented. They represent losses at 6.000
km power transmission, but only with the series compensation and without any parallel compensation. Due to large
capacitive currents losses, especially at low transfer powers, the total losses are dramatically high. It means that
parallel compensation is necessary not only for voltage profile maintenance, but also for an economic transmission
when using series compensated lines.
Page 12
Voltage and VAr Support in System Operation WG C2.13
P1 BSVC P2
Q1 Q2
Pload
Qload
Figure 2.8. Model of the transmission system with SVC: network scheme.
Figure 2.9. Model of the transmission system with SVC: network impedance scheme.
With the losses in SVC being neglected, SVC may be represented as a parallel susceptance BSVC corresponding to
SVC operating point. The impedance scheme can be transformed by "Y – D" transformation (dotted-line elements in
Fig 2.9). The parallel reactance XA and XB in the presented case do not play any role thus U1 and U2 are assumed
constant. The effect on the transmission line is in this case the same as though the series compensation with the
impedance
XCSC = –X1·X2·BSVC is used. From this equation it is evident that BSVC is in direct proportion to reduction of the series
system reactance XR = X1·X2·BSVC. Therefore, the transmission characteristic is described by the following equation:
U1 ⋅U 2 U1 ⋅U 2
P1 = sin (δ1 − δ 2 ) P2 = sin (δ 2 − δ1 )
X1 + X 2 − X1 ⋅ X 2 ⋅ BSVC X1 + X 2 − X1 ⋅ X 2 ⋅ BSVC
Page 13
Voltage and VAr Support in System Operation WG C2.13
U 2 = U 2 ⋅ ( cos δ 2 + jsin δ 2 ) ,
δ = δ1 − δ 2 .
*
S1
Again, following the expression I 1 = * , the current I1 can be written as:
U1
I 1 = Re { I 1} + jIm { I 1}
where is
Using the expressions for active and reactive powers (P1, Q1), real and imaginary part of current I1 is written as:
where
U 2 ⋅ X1 + U1 ⋅ X 2 ⋅ cos(δ1 − δ 2 ) U1 ⋅ X 2 ⋅ sin(δ1 − δ 2 )
Re {U SVC } = and Im{U SVC } = .
X1 + X 2 − X 2 ⋅ X 2 ⋅ BSVC X1 + X 2 − X1 ⋅ X 2 ⋅ BSVC
The magnitudes of load voltage U2, dependent on active load power Pload, for various values of BSVC are presented
in Fig. 2.10.
Page 14
Voltage and VAr Support in System Operation WG C2.13
1,1
0,9
0,8
0,7
0,6
U 2 [p.u.]
0,1
Srated = Bsvc=0,6 p.u.
0
0 0,1 0,2 0,3 0,4 0,5 0,6 0,7 0,8 0,9 1 1,1 1,2 1,3 1,4 1,5 1,6 1,7 1,8 1,9 2
P load [p.u.]
Figure 2.10. Voltage magnitude at load bus (U2) for various values of BSVC.
The rated power, which is explained in the section Generic model, of the SVC is determined:
Page 15
Voltage and VAr Support in System Operation WG C2.13
TVR
V g1SET V g2SET
PVR 1 PVR 2
Figure 2.11. Hierarchical voltage control architecture.
The secondary voltage control has been implemented and put into practice in EDF [1]. Up to 1985, almost the whole
French power system has been equipped with secondary voltage controller, including 27 control zones and 250
power plants, with reactive power regulation capacity of 30.000 MVAr. A similar hierarchical control architecture
was put into practice later in Italy [8, 9, 10], which consists of one NVR (National Voltage Regulator), three RVRs
(Regional Voltage Regulators) and 35 REPORTs (Voltage and Reactive Power Regulators) implemented on power
plants, with an overall capability of about 20.000 MVAr [10]. Figure 2.12 shows the schematic diagram of the
Italian hierarchical voltage control system. The most difference from EDF is the implementation of NVR, which an
Optimal Reactive Power Flow (ORPF) for Losses Minimization Control (LMC) computes, in short (the day ahead) or
very short (minutes ahead) terms, the forecasted optimal voltages and reactive levels, starting from the
foreseen/current state estimation. Therefore Tertiary Voltage Regulator (TVR) minimizes the differences between the
actual field measurements and the optimal forecasted references then reset the RVR set-point values [9].
Figure 2.12. Schematic diagram of the Italian hierarchical voltage control system [9].
Page 16
Voltage and VAr Support in System Operation WG C2.13
2.1.3 EXAMPLES
Now some implemented examples of control schemes will be described.
Page 17
Voltage and VAr Support in System Operation WG C2.13
longer fixed according to variation in power systems, which is more suitable for the fast developing Chinese power
grids.
The AVC system based on adaptive zone division has been implemented in Jiangsu provincial power system since
November 2002. And later on, this system has been extended its applications to more than a dozen control centres
in China, such as the North China Power Grid with generating capacity of 119 GW. Now it has been implemented
and online test at PJM control centre, USA, with generating capacity of 164 GW, since February 2010 [13].
Some key technologies implemented in the proposed AVC systems are introduced briefly as follows.
i‐th
SVR
TVR PVR
i‐th
SVR
Figure 2.13. Architecture of the hierarchical AVC system in China.
All the three-level hierarchical voltage control architectures are based on dividing power grid into weak-coupled
control zones, regardless if such a division is done online or offline. Basically, the validity of dividing the system into
voltage control zones is based on the criteria presented below [7]:
The voltage value at the pilot node indeed reflects the change in all the voltage values of the zone.
There is sufficient volume of controllable reactive power in the zone to be able to master the changes in voltage.
Each secondary control zone is sufficient uncoupled from its neighbours for the controls with a zone to be slightly
influenced by the actions carried out in other zones.
Dividing a power grid into some most decoupled zones majorly involves the following two sub-problems: firstly, how
to define the “electrical distance” between each two nodes; secondly, how to merge the nodes into several clusters
according to the distance definition.
Page 18
Voltage and VAr Support in System Operation WG C2.13
The well-known idea of electrical distance, based on sensitivity calculation, was carried out by EDF [7] and widely
accepted by the following researchers. Another electrical distance definition is based on a concept of reactive
control space driven by generator MVAr output [14]. Each load node can be described with a coordination vector in
the reactive control space. Then a novel electrical distance in the reactive control space is defined in a Euclid-space
with high-dimension.
Once the electrical distance is defined, the problem of power network zone division can be transformed into a
clustering analysis problem, which is usually solved by a hierarchical clustering algorithm. It is interesting to note that
reasonable number of control zones can be determined automatically according to characteristics of variation of the
merging distance in the clustering process [7, 14]. Figure 2.14 shows the process of bus merging [12].
The vertical arrow shown in Fig. 2.14 indicates the direction of merging of buses, i.e. from top to down. Firstly each
bus is a zone, so there are lots of zones. With the merging distance becomes larger and larger, zone numbers
become less and less, finally all buses merged into one zone. In the merging process, we can find a flat segment, as
shown in Fig. 2.14, if we want to merge buses from five to four zones, a much larger merging distance is needed. It
means that there are five weak-coupled zones in the systems. So five is an appropriate number of control zones.
Then we can get the zone boundary. The SVRs can be re-configured after a new zone division is gotten, which
supports the online adaptive zone division.
No of
zones
Flat Segment
Both for TVR online and as a planning tool offline, ROPF (Reactive Optimal Power Flow) are important modules with
the goal of transmission losses minimization and security constraints in high dimensions as well. Typically, the objective
function of a ROPF model is as
min f = PLoss = ∑
(i,j) ∈ NL
( Pij + Pji )
Page 19
Voltage and VAr Support in System Operation WG C2.13
Where
NL Set of branches
NB Number of buses
NQG Number of control generators
NT Number of transformer tap changers
PGi, QGi Active and reactive power of generator on bus i
PDi, QDi Active and reactive power of load on bus i
Ui , δ i Voltage magnitude and phase angle of bus i
The constraints shown above are the fundamental ones, which are flexible and extendable to satisfy different
application demands. There is a more than thirty-year research history for such an optimal programming problem
since it was presented [15]. Lots of methods, such as Newton method, SQP (Sequential Quadratic Programming)
Method and Interior Point method, were carried out and proved to be of good performance. When used as tool to
calculate real-time control strategy of TVR in China, an efficient hybrid decoupled optimal power flow approach is
adopted to take advantage of the inherent weak coupling characteristics between real and reactive power flows
[16]. The solution to the original optimization problem can be approximated iteratively by solving real and reactive
sub-problems alternately. The reactive sub-problem, based on sparse quadratic programming, is solved iteratively
while the active sub-problem is kept unchanged. The outputs of the TVR are the optimal set-points of the voltages at
the pilot buses. The cycle of execution of ROPF varies from 15 minutes to 1 hour, and is adaptive to the forecasted
daily load demand curve. The result of ROPF can be given out in the CPU time about 3-5 times than that of fast
decoupled load flow.
The SVR, which implemented for one control zone, measures the most important voltages and reactive powers in the
zone and calculates the control strategy by a Proportional Integral Derivative (PID) controller or simple optimal
programming model. Therefore, SVC was proved to be a robust performance on control reliability.
The PID based SVR was carried out by EDF [5], consisting of a voltage control loop and a reactive power control
loop, as shown in Fig. 2.15. The SVR system measures the instantaneous voltage at the zone pilot bus, compares it
with the voltage set-point, and applies a proportional-integral law to determine a signal representing the reactive
power level required for this zone. This signal is then used to calculate a set-point for the reactive-power control
loop of each generating unit. Steady-state reactive power generation is therefore aligned, with each generating
unit contributing to the total reactive power requirement proportionally to its capabilities [17].
Some limitations were found during the operation of SVR [17]. Firstly, coupling between theoretically independent
zone had increased as a result of grid development; Secondly, SVR required reactive-power alignment of
generating units involved only according to their capability, without considering the different control sensitivity of
these units; Thirdly, the internal reactive power control loop at generating units level is a destabilizing factor that
can actually amplify the initial disturbance in the first few instants following certain incidents; Fourthly, SVR was not
Page 20
Voltage and VAr Support in System Operation WG C2.13
able to considering and monitoring all the important operation constraints; Fifthly, control loop parameters were
fixed.
Figure 2.15. Secondary voltage control structure in EDF [4].
To improve the control performance, a CSVC (Coordinated Secondary Voltage Control) model was presented in
Europe [18] and subsequently widely applied in other countries [8, 12, 13, 19, 20]. Most of these CSVC are based
on quadratic programming model considering voltage and reactive power constraints in the zone. Generally, there
are more than one goal in the objective function, for instance, in China [12, 21], the first goal of this model is to
control the voltages at the pilot nodes to follow the optimal set-points, which are updated by the TVC module, and
the second goal with lower priority is to equilibrate MVAr reserve distribution among the generators in each control
zone so as to enhance security of power system. The Voltage/VAr constraints in the corresponding control zone will
be considered in each SVR module as well.
For each zone, a CSVC module is just an optimal problem in small-scale, not based on state estimation but based on
measurement and sensitivity. So it can be solved easily and efficiently. For each zone, just a few necessary
measurements inside its zone are needed, such as voltages on pilot buses, high voltages of plants, reactive outputs of
controlled generators and reactive power flow through tie lines.
As important as generators in power plants, the regulation of reactive power compensators and LTC transformers at
substations is also essential to maintain system voltage profile. These discrete control devices, such as capacitors,
reactors and LTCs, are supposed to provide base reactive power and maximize the spinning reactive power reserve
in case of emergencies. As well as power plants, automatic voltage control for substations has been carried out in
many countries, which are basically classified into two different ways, one is local control scheme implemented at
substation and the other is system-wide control schema implemented at control centre.
The local control scheme is based on local measurements of the substation, including the voltage of all the voltage
levels, the reactive power on different sides of the transformers, the on/off status of the breakers, and so on. In
some cases, some remote signals, such as the generator reactive power if necessary, are also collected in addition
[1]. Typically, some expert rules are embedded into the microprocessor, in which a nine-zone diagram control
scheme is applied most widely [1].
For a system-wide control scheme, the discrete devices are taken into account together with the continuous ones in an
optimization model to seek the global optimal solution. In Belgium [22], a three-step process is used to recommend
Page 21
Voltage and VAr Support in System Operation WG C2.13
capacitor bank switching, tap changing and reactive power production based on OPF. However, the OPF problem is
actually a mix-integer programming model which is a great challenge to solve, because there are more complex
constraints for the discrete devices, such as the maximum action times per day and the minimum time interval
between two actions. So there are many practical methods as well. In Italy [23], the SVR reactive power level qi(t) is
adopted as an indicator to describe the voltage regulation ability. If all the generator units are fixed by their over-
excitation limits, qi(t) will reach +1. To avoid operation at saturated status, all possible reactive power resources
(capacitors, reactors, synchronous or static compensators, etc) installed in the control area are automatically
controlled if qi(t) is near +1. In China, a practical guideline adopted for coordinated control is to adjust discrete
variables firstly to meet the basic reactive power demand and save continuous devices as dynamic reserve [24].
Fourteen 500 kV substations (163 capacitors and 88 reactors) with capacity 13 GVAr are close-looped controlled in
North China Power Gird based on the guideline. Also in the similar way, Tokyo Electric Power Co. (TEPCO) applies
shunt compensation to ensure reactive power reserves at power plants for severe contingencies during peak load
periods as well as to correct load power factor [22].
Figure 2.16. The 5-level hierarchical structure of the control centres in China.
Figure 2.17 shows division of voltage levels controlled by different control centres levels. In general, Provincial Grid
Control Centres are also defined as TSOs and Municipal Grid Control Centres are defined as DSOs.
Traditional AVC system is deployed in transmission system control centre. With the development of smart grid, more
and more attention has been paid on distribution level. For example, in China, a hierarchical control structure is
adopted in power system dispatching, of which TSO and DSO are two important levels. TSO is responsible for the
power networks with 220 kV voltage level and above, and DSO is in charge of the power networks with 110kV and
below. While in Europe, the borders between TSO and DSO are not the same in different countries, and in some
Page 22
Voltage and VAr Support in System Operation WG C2.13
cases the distribution power grids are meshed and coupled with the TSO power grids. But for operational issues it is
still generally accepted to treat distribution grid as a radial grid. The control actions in TSO and DSOs will
inevitably affect each other. In order to get more reasonable reactive power flow and voltage profile in the whole
transmission and distribution grids, coordinated control between TSO and DSOs is necessary.
Figure 2.17. Division of voltage levels controlled by different control centres levels.
From the viewpoint of TSO, the DSOs’ radial power grids can be equivalent to be loads. The reactive power
compensation in DSOs will directly determine the reactive power absorbed from the higher system. On the other
hand, seen from DSOs, the TSO’s power grid can be equivalent to be a generator. The voltage profile on the
interface buses of DSOs will be majorly determined by TSO [25].
In China, a distributed bidirectional coordinated voltage control between provincial and district power networks was
implemented and applied in Jiangsu Province power network, as described in Fig. 2.18 [26].
Figure 2.18. MAS architecture of bidirectional coordinated voltage control between TSO and DSOs.
Multi-agent system (MAS) is adopted as architecture for such coordinated control. The reactive power flows and
voltages on the boundaries of TSO and DSOs are chosen as coordinated variables. The superior TSO agent
determines the voltage controllable ability and reactive power compensation requirement of TSO on the boundaries,
while the DSO agents determine the voltage requirement and reactive compensable ability of DSOs on the
boundaries. All these requirement and ability are considered as coordinated constraints to be sent to the coordinator
agent by communication networks. The coordinator agent checks the operation status on each boundary between
TSO and DSOs, calculates coordination strategy and sends it back to TSO and DSOs. TSO and DSOs receive the
coordination strategy and take it as new constraints to be considered in their TVR and SVR control models.
Page 23
Voltage and VAr Support in System Operation WG C2.13
State Estimator
Supervisory
AVC-S control
(SCADA)
Alarm
U/Q
optimisation processing
[VS]
AVC-U RTU
The U/Q optimisation implements the strategy of the system-wide U/Q control, the actuation is done by the AVC by
knowing the real-time measured values and status indications, with participation and monitoring by the dispatchers.
Control reserve is to be maintained for operating the U/Q control. During iterations, the algorithm calculating the
optimum observes network constraints, device stress available for control purposes, control ranges and priorities.
Figure 20 shows the dispatcher overview display of the U/Q control.
The task of the U/Q optimisation (VS function) is, in normal state, to find the settings for U/Q control devices that
minimise the network active power loss, and in state of limit violation to find the minimum control adjustments for
U/Q control devices that relieve the limit violation.
The VS runs automatically as a part of the real-time sequence:
- periodically (current setting), after each periodic execution of the State Estimator which practically means a
periodicity of 5 minutes, or
- acyclically, after each event-triggered execution of the State Estimator.
It is also possible to initiate the VS manually.
Page 24
Voltage and VAr Support in System Operation WG C2.13
Enabling/disabling the participation of generating units in the optimisation can be set together (global enabling) or
individually. The individual enabling/disabling depends mainly on the state indications coming from the power
stations through telecontrol. Any unit can participate in the control for which the power plant:
- specified busbar control and assigned the busbar control to MAVIR,
- specified unit control and assigned the unit control to MAVIR.
The dispatcher decides about the actual optimisation participation of the unit eligible to participate in the control.
Figure 2.20. Overview display of the U/Q Control Screen.
Enabling/disabling the participation of LTC transformers in the optimisation can be set together (global enabling) or
individually but the global enabling affects only the individually enabled transformers. The global enabling may be
valid for the optimisation to relieve limit violations, for the loss minimisation or both.
The system-wide U/Q control is a new function in the MAVIR system control operation and the dispatchers are still to
become familiar with its operation so a relatively long trial operation phase will follow the commissioning of the
function. The trial operation will serve to establish user procedures, finalise the operator displays of the VS and AVC
functions, fine tune the VS optimisation iteration constants and the matching of AVC command calculation and output
in logics. A most practical way to comprehensively test the function before the trial operation is to do it on the
Dispatcher Training Simulator.
The results of the VS function and the calculated desired values can be actuated only as a whole. The automatic
execution of the central control assumes the commands reach the controlled devices and they execute the commands.
Page 25
Voltage and VAr Support in System Operation WG C2.13
Currently the main means of voltage control and reactive power compensation for the Swiss transmission system is
the reactive power dispatching from generators connected to the transmission grid. The power plants connected
directly to the transmission grid are contractually obliged to offer voltage support. As of 01.01.2011, distribution
grids have the option to also participate in the voltage control with their tap-changing transformers or power plants
at lower voltage levels. As an addition to that, 380/220 kV coupling tap-changing transformers, as well as
topological measures (switching on/off of lines or transformers under no-load conditions) are applied, so as to
maintain a healthy voltage profile throughout the grid. Reactive compensations devices exist in lower voltages level
and future investments in such devices for the transmission grid are momentarily in the planning phase.
The reactive power planning is based on minimization of the costs for active losses and reactive energy. The costs for
the delivery of the required reactive power are minimized from the power plant operators.
The Optimal Power Flow program is implemented in the D-1 time frame. The main output of the software is a
voltage plan for every hour of the day ahead and for every node of the Swiss transmission system which is
regulated from a power plant or a distribution grid. On deviations of the grid’s actual situation in comparison to the
forecast, we have the opportunity to issue an intraday voltage plan.
There is no online reactive power dispatching system available at present. The reactive power dispatching of the
power plants is only implied through the target voltage of every node for each hour and monitored from the
dispatchers.
An offline cost-based optimization is applied.
The reactive power sources are only of one kind (generators) and are financially compensated for the voltage
support with a flat tariff. Therefore, our focus is primarily on the good voltage profile of the grid.
Page 26
Voltage and VAr Support in System Operation WG C2.13
Figure 2.21. Transmission power system of Slovenia with 220 and 400 kV voltage level [27].
The production units and interconnection lines are satisfactorily dispersed in the Slovenian high voltage grid. The
peak power demand in Slovenia was about 2 GW. Most production units are in the northeast (Thermal power plant
Šoštanj, chain of hydro power plants on river Drava) and in the east (Nuclear power plant Krško), but the
consumption is mostly in the central part of the country and a lot of energy flows towards Italy. In 2010 pumped
storage power plant Avče was put in operation.
In December 2010 the first phase shift transformer (PST) started with operation which increased the reliability of
operation of 400 kV electricity transmission systems, restriction of uncontrolled big transit of electricity through the
Slovenian power system and the direct reduction of losses in the transmission network. At the same time there will
also be limitation of the uncontrolled transit of electricity from Eastern Europe to Italy and the settlement of
congestion.
Page 27
Voltage and VAr Support in System Operation WG C2.13
Page 28
Voltage and VAr Support in System Operation WG C2.13
voltage and other generating devices to stay connected to the grid. This support is necessary, because otherwise,
infeeds on high/medium voltage level can not support the extra high voltage grid sufficiently. Older wind turbines
consist of an asynchronous generator, which has a (negative) inductive behaviour when voltage recovers. A switching
off of wind turbines should be avoided, because a high outage of wind power infeed destabilises the whole grind.
Two different wind turbine techniques exist: 1. doubly fed induction generator (DFIG) and 2. full converter devices.
DFIG consist of a rotor side converter (RSC) and a line side converter (LSC), which are coupled via a DC-Link. In case
of a voltage dip, an additional capacitive reactive current is fed in via the RSC and DFIG into the grid (some
devices allow an infeed of reactive current via the LSC directly). TSOs demand a deadband control of +-10% for
on-shore and +-5% for off-shore wind turbines. The deadband control should avoid an uncoordinated control of
different DFIG-based wind turbines and transformer tap changers in normal operation. Of course, another control,
e.g. continuous, would be possible for the controller. Deep voltage dips cause DFIG-based wind turbines to deliver a
high current from the RSC through the rotor. This current can be so high, that the RSC must be blocked and the
controllability of the device is lost for a short time (100 ms). In this time the DFIG behaves like a slip ring rotor
asynchronous machine with a reactive power demand from the grid. With additional techniques, the blocking time
period can be reduced to a few milliseconds.
Wind turbines with a full converter consist of a synchronous (permanent field) machine, which’s stator is connected to
a machine side convertor, which is connected to the line side converter (LSC) via a DC link. The LSC affects the
behavior in voltage dip situations. A reactive current can be delivered in stationary and transient (e.g. short circuit)
situations and a Fault-Ride-Through ability is ensured. Voltage control is set similarly to DFIG-based wind turbines
with the aforementioned deadband for the LSC.
Today, both wind turbine technologies are able to deliver a reactive current of 1 p.u. A response time of 30 ms and
a settling time of 60 ms after a step response is recommended. Most manufacturers can guarantee these requests
today or in near future.
Because wind turbines are connected mainly to medium voltage level, a feed-in of reactive current results in a low
voltage support to the high/extra high voltage level due to large transformer impedances. This effect can be
encountered with an increase of the amplification factor of the voltage controller.
To increase the reactive current infeed without enlargement of the converter (which would cause additional costs),
following measures are possible:
- use of overload capability of semiconductor-elements,
- reduction of active current in favour of reactive current.
During operation and also during low wind conditions, converters of wind turbines can be used to deliver reactive
power to the grid. DFIG devices can use the LSC to support voltage (30 % of nominal power), full converter devices
can deliver reactive power approximately to their full rated power output.
If wind turbines should be used for voltage support tasks, it is necessary to have a controllability of the voltage
controller from the network control station. Devices can deliver reactive power and so support voltage best in the
voltage level, they are connected to. Due to high transformer impedances between voltage levels, it is not possible
to support the EHV from the medium voltage level. Concerning transient phenomena, wind turbines should be able to
remain connected to the grid during faults and deliver a reactive current. In the past, manufacturers were able to
equip their wind turbines with the claimed requirements.
Page 29
Voltage and VAr Support in System Operation WG C2.13
Figure 2.22. Regional Grids and the principal power flow directions in Chains EPSs.
Page 30
Voltage and VAr Support in System Operation WG C2.13
station. This brings a challenge to the voltage support capacity of the AC system. Based on the above reasons, it’s
necessary to equip reasonable reactors and capacitors on 500 kV system nearby UHV, which are supposed to
provide reactive power support effectively and improve the voltage stability margin greatly.
Figure 2.23. UHV power and voltage change of the Jingmen bus at 500 kV (left),
UHV power and voltage change of the Jingmen bus at 1.000 kV (right).
Figure 2.24. A simulation of overhead fault on a double circuit UHV line XuZhou-Nanjing 1.000 kV.
Page 31
Voltage and VAr Support in System Operation WG C2.13
Figure 2.25. Cable equivalent circuit.
Page 32
Voltage and VAr Support in System Operation WG C2.13
The parameters and characteristics of underground cables are significantly different form those of overhead lines.
The lower series inductance, because the phase conductors are much closer and especially much higher shunt
capacitance must be taken into account when integrating cables into a transmission system. Higher cable capacitance
is a result of much closer distance of the high-voltage conductor to the ground and several times higher dielectric
constant of electrical insulation than that of air. Shunt elements represent capacitive susceptance and conductance
which reflects dielectric losses. Shunt conductance can be neglected in a system planning considerations. Capacitance
of a single core cable is expressed as:
2⋅ π⋅ε
cb =
r
ln( 0 )
ri
where
cb Capacitance [F/m]
⎡ As ⎤
ε Dielectric constant ⎢ ⎥
⎣ Vm ⎦
r0 Insulation radius [m]
ri Conductor radius [m]
Table 3 shows typical values for the dielectric constant for insulation materials commonly used in transmission cables
[34].
TABLE 3: TYPICAL OHL AND CABLE PARAMETERS FOR NOMINAL VOLTAGE 230 KV, TABLE 6.1 AND 6.2 FROM REFERENCE [34].
The higher dielectric constant means higher cable capacitance. Therefore, in general, XLPE cable has lower shunt
capacitance than HPFF cable but higher capacitance than GIL type cable.
The capacitance is essential for determining the cable charging current which is given by equation
I c = 2 ⋅ π ⋅ f ⋅ C ⋅U
Where
Ic charging current [A]
f frequency [Hz]
U operating voltage, line-to-ground [V]
C capacitance of cable [F].
Page 33
Voltage and VAr Support in System Operation WG C2.13
Page 34
Voltage and VAr Support in System Operation WG C2.13
2.2.4.7 DC HV cables
Long undersea/underground HV cables have high electrical capacitance. Where alternating current is used for
cable transmission, this capacitance appears in parallel with load. Additional current must flow in the cable to
charge the cable capacitance, which generates additional losses in the conductors of the cable. The maximum
distance a cable can transmit power without compensation is limited.
However, when direct current is used, the cable capacitance is charged only when the cable is first energized or
when the voltage is changed; there is no steady-state additional current required. For a long AC cable, the entire
current-carrying capacity of the conductor could be used to supply the charging current alone. The cable
capacitance limits the length and power carrying capacity of AC cables. DC cables have no such limitations.
2.2.4.8 Summary
AC XLPE cables seem to be the most appropriate systems for power transmission now and for the nearest future. At
present numerous high voltage XLPE cable systems with nominal voltages up to 500 kV and circuit length up to 40
km are in operation worldwide. Low dielectric constant of these cables allowed minimization of technical
disadvantages like high electrical capacitance. State of the art extruded EHV cables are characterized by super-
clean insulation in a triple extrusion and dry curing process.
Higher transfer capability is achievable at present with second generation of GIL which use a mixture of nitrogen
and SF6.
Environmental issues and restriction on land-use will stay as a main driver for widespread application of
underground transmission. The high population density and limited space for new infrastructure, as well as visual
objections against overhead lines in scenic landscapes will probably generate a tendency for more extra high
voltage cables.
New and improved technologies of underground transmission will cause increasing tendency to go underground
particularly at the lower transmission voltages where the cost differential with overhead lines is less severe.
Page 35
Voltage and VAr Support in System Operation WG C2.13
2.2.6 FACTS
FACTS devices offer wide control possibilities. Let’s take a glance at Q-sources and Voltage control means.
Shunt capacitors at the transmission-distribution border, at the TSO command, allows the minimization of reactive
power flow on the TSO network, minimizing the active power losses and keeping a good voltage at the DSO.
The use of shunt reactors at the TSO network allows the voltage not to exceed the equipment tolerance.
The problem with this type of equipment is that since they are static, the reactive contribution depends on the
quadratic of the voltage: Q= B·U2, when the voltage goes down, the reactive output is less when we need more
reactive power to boost the voltage up to the previous value. That’s why we need generators with voltage control to
react immediately to an event.
The static VAr compensation, besides the loss minimization, is used to give some reactive slack to the generation, with
VAr control, to have more spare reactive power to cope with the events.
Static VAr sources are adequate for steady-state but not for transient situations, for that you need FACTS devices
that are able to react fast to voltage dips, like STATCOM. The main problem is the cost of these devices. Economic
justification based on voltage quality issues is very difficult to assess.
Due to the large extent of the analysis required for a rigorous treatment of FACTS devices, this is presented
separately in the Chapter 4 – solely on FACTS at the end (see section 4.1). The SVC has been thoroughly presented
in Section 2.1.1 above.
2.2.7 INCENTIVES FOR PRODUCERS AND MARKETS OF REACTIVE POWER: THE EXAMPLE OF POLAND
In Poland, in accordance with Polish Grid Code Requirement, all power plants connected to transmission system have
to be equipped with secondary voltage control system (ARNE). Available reactive power is determined for each
power plant by the generators capability curve. Power plant can get additional profit whenever TSO dispatch
centre remotely activate ARNE system. There is a fix rate (PLN/hour) for this kind of ancillary service.
Page 36
Voltage and VAr Support in System Operation WG C2.13
Chapter 3
Page 37
Voltage and VAr Support in System Operation WG C2.13
A basic understanding of voltage dependency on increasing load can be presented on the two bus system shown in
Fig. 3.1.
The first bus is slack bus with constant voltage magnitude U1=const. and voltage angle is set to zero δ1 = 0 . The
second bus is load bus with known active Pload and reactive Qload. The generator – slack bus is connected to a load
bus through a lossless – transmission line (resistance of the line R=0) with known reactance (jX).
The relation between active P2, reactive Q2 power and voltage U2 and angle δ 2 at the end of the line give
equations:
We consider that the load power Pload = P2 gradually increases and that the reactive power is linear dependent on
active power: Q2 = P2 · 0,2. With increase of the load Pload the voltage U2 at the load bus decreases and reaches a
critical value that corresponds to the maximum power transfer. In general this maximum power transfer is related to
voltage instability if the load is constant power type. Beyond this point there is no equilibrium. However if the load is
other than constant power then the system can operate below this critical voltage, but draws higher current for the
same amount of power transfer.
1,1
0,9
0,8
0,7
0,6
U 2 [p.u.]
0,5
0,4
0,3
R = 0; X = 0,3
0,2
0,1
0
0 0,1 0,2 0,3 0,4 0,5 0,6 0,7 0,8 0,9 1 1,1 1,2 1,3 1,4 1,5 1,6 1,7 1,8 1,9 2
P load [p.u.]
Figure 3.2. Voltage dependency on active power Pload.
With consideration of equation for P2 and Q2 and initial values for U2=1 p.u. and δ 2 = 0 the load flow procedure
based on Newton-Raphson method calculates the final value of load bus voltage U2 and angle δ 2 . Figure 3.2 shows
the results, so called P-U ( P − δ ) curve for the two bus system according to parameters:
U1= 1 p.u. δ1 = 0 Urated = U1= 1 p.u.
Page 38
Voltage and VAr Support in System Operation WG C2.13
In a real EPS operation the voltage curves before voltage collapse are not as smooth and predicable as shows Fig.
3.2. The diagram of measured voltages in Fig. 3.3 [37] shows how the voltage collapse spread in the Greek EPS on
12th of July 2004.
Figure 3.3. Voltage collapse in Greece, July 12, 2004 [37].
Page 39
Voltage and VAr Support in System Operation WG C2.13
Reference [38] states guidelines for UVLS schemes. Main conclusions are that UVLS schemes should be automatic and
should be properly coordinated with other load shedding schemes within the same system and neighbouring systems.
The following design considerations are given [38]:
1. Load shedding scheme should be designed to coordinate with protective devices and control schemes for
momentary voltage dips, sustained faults, low voltages caused by stalled air conditioners, etc.
2. Time delay to initiate load shedding should be in seconds, not in cycles. A typical time delay varies between 3
to 10 seconds.
3. UVLS relays must be on PTs that are connected above automatic OLTCs.
4. Voltage pick-up points for the tripping signal should be set reasonably higher than the “nose point” of the
critical P-V or Q-V curve.
5. Voltage pick-up points and the time delays of the local and the neighbouring systems should be checked and
coordinated.
6. Redundancy and enough intelligence should be built into the scheme to ensure reliable operation and to
prevent false tripping.
7. Enough load should be shed to bring voltages to minimum operating voltage levels or higher. Maintain VAr
margin according to WSCC’s Voltage Stability Criteria.
3.2 INSTABILITIES
3.2.1 INTRODUCTION
In the report [41] developed by a Task Force, set up jointly by the CIGRE Study Committee 38 and the IEEE Power
System Dynamic Performance Committee is addressed the issue of stability definition and classification in power
systems from a fundamental viewpoint. The report [41] aims to define power system stability more precisely,
provide a systematic basis for its classification, and discuss linkages to related issues such as power system reliability
and security.
The report [41] also describes the term of voltage collapse:
“Voltage collapse is the process by which the sequence of events accompanying voltage instability leads to a
blackout or abnormally low voltages in a significant part of the power system. Stable (steady) operation at low
voltage may continue after transformer tap changers reach their boost limit, with intentional and/or unintentional
tripping of some load. Remaining load tends to be voltage sensitive, and the connected demand at normal voltage
is not met.”
3.3.1 DIAGNOSIS
The following measured quantities can be used as input values to detect an instable voltage situation:
* Voltages on different voltage levels (primary +secondary side of EHV/HV- and HV/MV-transformers)
* Taps of transformer tap-changers
* Reactive power flow of EHV/HV- and HV/MV-transformers
Page 40
Voltage and VAr Support in System Operation WG C2.13
Voltages must be regarded on all voltage levels both as absolute values and as time depending dU/dt-values.
Especially voltage differences after a tap-change are of importance.
Transformer tap-changes have to be monitored, too. Absolute values and an average value (with a sliding time
frame) can be recommended. The behaviour of automatic tap-changing’s of single transformers and a transformer
collective within a certain network group is necessary to observe. Reactive power flows on transformers provide an
indication of voltage instabilities. Absolute flows and (time) gradients should be watched, too.
3.3.3.1 Clearing (of the applied provisions) and return into “normal state”
The removal of the realised measures must happen in reversed to the above order.
Page 41
Voltage and VAr Support in System Operation WG C2.13
TSO to shed 80 MW of load, because Voltages were still falling (down to: 133 kV, and 125 kV), which was done at
12:30 hours. But, the situation did not improve, and a further 200 MW was shed. At this time the load stood at
9.320 MW. To make things worse one more thermal generating unit went off, this time at the Aliveri power station.
At 12:39 hours the separation of the North part of the system from the South part of the system was complete and
the Southern part of the Greek power system went into a complete Blackout. At the time just before this, the total
load was 9.370 MW, 3.173 MW of which was in Attica and 890 MW in Peloponese. The reactive demand was
6.096 MVAr total out of which 1.655 MVAr was in Attica and 609 MVAr in Peloponese.
The analysis of this case revealed that there was too little reactive power support available in the South part of the
system. Substantial plant in the system had been down for maintenance. An operator’s action for increasing the
reactive power output of a thermal plant at the expense of its real power output had negative overall result since it
loaded more the North-to-South transmission corridor and increased the lack of reactive power more! The main
generators are in the North (Ptolemaida) and the bulk of power is transmitted by the North-to-South 400 kV
corridor. So, due to the impossibility to transmit reactive power over long distance, the reactive power demand of
the South was impossible to be met. Also, decisions for load shedding proved to be taken too late.
Page 42
Voltage and VAr Support in System Operation WG C2.13
Voltage stability margin dropped to 1.3%. Number of generators at power plant reached maximum of available
reactive power capacity. As a result, there were further reductions in voltage due to significant losses on the
transmission of reactive power from remote areas.
The event that directly initiated a voltage collapse was emergency shutdown of two 200 MW generators in
Ostrołęka power plant. It was caused by improper operation of generator stator current limiters of AVR’s. In a few
minutes four other generators and SwePol HVDC link to Sweden were tripped. Recordings of 400 kV network
voltages are shown in Fig. 3.4.
400 16000
[M W]
[kV]
390
15000
380
14000
370
13000
360
350 12000
06:00
07:00
08:00
09:00
10:00
11:00
12:00
13:00
14:00
15:00
16:00
17:00
18:00
19:00
20:00
Conclusions from the analysis included the ad-hoc, short-term and long term. The long-term actions include:
- speed up investments in transmission system carried on,
- complete installation of new reactive power sources in the transmission system,
- speed up new investments in transmission system by removing administrative barriers,
- include extreme summer conditions in planning procedures,
- include the whole 110 kV network in on line monitoring and analyses (exchange of on line data with DSOs),
- improve operational planning procedures accordingly,
- strive for new legal regulations in the area of reactive power management,
- include local generation in must run where necessary,
-introduce undervoltage load shedding,
-implement training simulator,
- reorganize region al control centres.
Page 43
Voltage and VAr Support in System Operation WG C2.13
Chapter 4
FACTS DEVICES
4.1 FACTS
Beyond the SVC which was thoroughly presented in Section 2.1.1 above.
The aim of this section is to present how with FACTS devices the voltage profile at the load bus can be modified.
Such modification can play a significant role in the voltage stability margin enhancement. In order to be able to
determine suitable parameters of FACTS devices static models based on to bus – generic model are developed. The
interdependence between the power transmission characteristic, the simplified system parameters and controllable
parameters of relevant, in operational point of view, FACTS device are resumed from the reference [40].
Figure 4.1. Model of the transmission system with CSC: network scheme.
KCSC being the so-called “series compensation degree” is defined with expression:
X CSC
KCSC = −
X1 + X 2
U1 ⋅U 2
P = P1 = − P2 = ⋅ sin (δ1 − δ 2 ) for active power
(1 − KCSC ) ⋅ ( X1 + X 2 )
and with
Page 44
Voltage and VAr Support in System Operation WG C2.13
*
S1
Following the expression I 1 = * , the current I1 can be written as
U1
I 1 = Re { I 1} + jIm { I 1}
where
Using the expressions for active and reactive powers (P1, Q1), real and imaginary part of current I1 can be written
as:
U1 ⋅ sin(δ1 − δ 2 ) U1 ⋅ cos(δ1 − δ 2 ) − U 2
Re { I 1} = Im{ I 1} =
(1 − KCSC ) ⋅ ( X1 + X 2 ) ( KCSC − 1) ⋅ ( X1 + X 2 )
Voltage on the left side of CSC (UA) is written as:
U A = U 1 − jI 1 ⋅ X1 = Re {U A } + jIm{U A }
U1 ⋅ ( KCSC ⋅ ( X1 + X 2 ) − X 2 ) ⋅ cos(δ1 − δ 2 ) − U 2 ⋅ X1
Re {U A } =
( KCSC − 1) ⋅ ( X1 + X 2 )
and the imaginary of UA is:
KCSC ( X1 + X 2 ) − X 2
Im{U A } = U1 ⋅ ⋅ sin(δ1 − δ 2 ) ,
( KCSC −1) ⋅ ( X1 + X 2 )
finally the magnitude of UA determines expression:
U A = Re {U A } + Im {U A } .
2 2
U B = U A − jI 1 ⋅ X CSC = Re {U B } + jIm {U B }
where:
U B = Re {U B } + Im {U B } .
2 2
Page 45
Voltage and VAr Support in System Operation WG C2.13
The magnitude of load bus voltage U2 depends on active power Pload for various compensation degrees KCSC and is
presented in Fig. 4.2 (CSC is positioned in the electrical middle of a line, X1 = X2). One must be aware that in this
case, CSC has a symmetrical effect on voltage magnitudes on both sides of CSC. This can be explained by studying
a corresponding phasor diagram, depicted in Fig. 4.3.
1,1
0,9
0,8
0,7
0,6
U 2 [p.u.]
0,5
R = 0; X = 0,3
pu
0,4
Kcsc = 0,0
0,3
Kcsc = 0,1
0,2
Kcsc = 0,2
0,1
Kcsc = 0,3
0
0 0,1 0,2 0,3 0,4 0,5 0,6 0,7 0,8 0,9 1 1,1 1,2 1,3 1,4 1,5 1,6 1,7 1,8 1,9 2
P load [p.u.]
Figure 4.2. Voltage amplitude at the load bus U2 for various values of compensation degree KCSC (X1 = X2).
The rated power, which is explained in the section 3.1 Voltage depression, of the CSC is determined:
Figure 4.3. Phasor diagram referring to model in Fig. 4.1.
Page 46
Voltage and VAr Support in System Operation WG C2.13
U1 USTATCOM U2
X1 X2
P1 P2
Q1 Q2
IQ Pload
Qload
Figure 4.4. Model of the transmission system with STATCOM: network impedance scheme.
U1 ⋅U 2 ⋅ sin(δ1 − δ 2 ) ⎛ I Q ⋅ X1 ⋅ X 2 ⎞
P1 = ⋅ ⎜1 + ⎟
X1 + X 2 ⎜ U 2
⋅ X 2
+ U 2
⋅ X 2
+ 2 ⋅ U ⋅ U ⋅ X ⋅ X ⋅ cos(δ − δ ) ⎟
⎝ 1 2 2 1 1 2 1 2 1 2 ⎠
U1 ⋅U 2 ⋅ sin(δ 2 − δ1 ) ⎛ I Q ⋅ X1 ⋅ X 2 ⎞
P2 = ⋅ ⎜1 + ⎟
X1 + X 2 ⎜ U 2
⋅ X 2
+ U 2
⋅ X 2
+ 2 ⋅ U ⋅ U ⋅ X ⋅ X ⋅ cos(δ − δ ) ⎟
⎝ 1 2 2 1 1 2 1 2 2 1 ⎠
U1 ⎛ I Q ⋅ X 2 ⋅ (U1 ⋅ X 2 + U 2 ⋅ X1 ⋅ cos(δ1 − δ 2 ) ) ⎞
Q1 = ⋅ ⎜U1 − U 2 ⋅ cos(δ1 − δ 2 ) − ⎟
X1 + X 2 ⎜ U 2
⋅ X 2
+ U 2
⋅ X 2
+ 2 ⋅ U ⋅ U ⋅ X ⋅ X ⋅ cos(δ − δ ) ⎟
⎝ 1 2 2 1 1 2 1 2 1 2 ⎠
U2 ⎛ I Q ⋅ X1 ⋅ (U 2 ⋅ X1 + U1 ⋅ X 2 ⋅ cos(δ 2 − δ1 ) ) ⎞
Q2 = ⋅ ⎜ U 2 − U1 ⋅ cos(δ 2 − δ1 ) + ⎟
X1 + X 2 ⎜ U 2
⋅ X 2
+ U 2
⋅ X 2
+ 2 ⋅ U ⋅ U ⋅ X ⋅ X ⋅ cos( δ − δ ) ⎟
⎝ 1 2 2 1 1 2 1 2 2 1 ⎠
Figure 4.5. Model of the transmission system with STATCOM referring to model in Fig 4.4.
U 1 = U1 δ1 = 0
U 2 = U 2 ⋅ ( cos δ 2 + jsin δ 2 )
δ = δ1 − δ 2
Page 47
Voltage and VAr Support in System Operation WG C2.13
U STATCOM − U 2
I2 =
jX 2
I 2 = I1 − I Q
U1 −U 2 X2
I1 = + IQ ⋅
j ( X1 + X 2 ) X1 + X 2
U STATCOM = U 1 −
(U 1 − U 2 ) ⋅ X1 − jI ⋅
X1 ⋅ X 2 X ⋅X
= U S − jI Q ⋅ 1 2
Q
X1 + X 2 X1 + X 2 X1 + X 2
U S X1 ⋅ X 2 ⎛ I Q X1 ⋅ X 2 ⎞
U STATCOM = U S + I Q ⋅ ⋅ = U S ⋅ ⎜1 + ⋅ ⎟⎟
US ( X1 + X 2 ) ⎝ US ( X1 + X 2 ) ⎠
⎜
It can be noticed that new variable US has been introduced. It is in fact the STATCOM terminal voltage if STATCOM
US
is out of operation (is not connected to the system, i.e. IQ = 0). IQ is shifted by 90o regard to US ( being unity
US
phasor in US direction).
As US is defined as:
U S = U1 −
(U 1 − U 2 ) ⋅ X1
X1 + X 2
It is possible to obtain
⎛ U ⋅ X + U1 ⋅ X 2 ⋅ cos(δ1 − δ 2 ) ⎞ ⎛ X1 ⋅ X 2 ⎞
Re {U STATCOM } = ⎜ 2 1 ⎟ ⋅ ⎜1 + ⋅ IQ ⎟
X1 + X 2 ⎠ ⎜⎝ U1 ⋅ X 2 + U 2 ⋅ X1 + 2 ⋅U1 ⋅U 2 ⋅ X1 ⋅ X 2 ⋅ cos(δ1 − δ 2 ) ⎟
2 2 2 2
⎝ ⎠
U1 ⋅ X 2 ⋅ sin(δ1 − δ 2 ) ⎛ X1 ⋅ X 2 ⋅ I Q ⎞
Im {U STATCOM } = ⋅ ⎜ X1 + X 2 + ⋅ ( X1 + X 2 ) ⎟
( X1 + X 2 ) ⎜ ⎟
2
⎝ U12 ⋅ X 2 2 + U 22 ⋅ X12 + 2 ⋅U1 ⋅U 2 ⋅ X1 ⋅ X 2 ⋅ cos(δ1 − δ 2 ) ⎠
The voltage magnitudes at load bus U2 dependent on active load power P2 for various values of IQ are presented in
Fig. 4.6.
Page 48
Voltage and VAr Support in System Operation WG C2.13
1,1
0,9
0,8
0,7
0,6
U 2 [p.u.]
0,5
R = 0; X = 0,3
pu
0,4
0
0 0,1 0,2 0,3 0,4 0,5 0,6 0,7 0,8 0,9 1 1,1 1,2 1,3 1,4 1,5 1,6 1,7 1,8 1,9 2
P load [p.u.]
Figure 4.6. Voltage amplitude at load bus U2 for various values of IQ.
The rated power, which is explained in the section 3.1 Voltage depression, of the STATCOM is determined:
Figure 4.7. Model of the transmission system with SSSC: network impedance scheme.
U 1 = U1 δ1 = 0
U 2 = U 2 ⋅ ( cos(δ 2 − δ1 ) + jsin(δ 2 − δ1 ) ) ,
δ = δ1 − δ 2
Page 49
Voltage and VAr Support in System Operation WG C2.13
I1 = I 2 = I =
1 ⎛ (U − U 2 ) ⎞ = j (U 2 − U 1 ) ⋅ ⎛1 − USSSC
⋅ ⎜ (U 1 − U 2 ) − USSSC ⋅ 1
⎞
⎟ ⎜ ⎟
j ( X1 + X 2 ) ⎝⎜ U 1 − U 2 ⎠⎟ X1 + X 2 ⎜⎝ U 1 − U 2 ⎟
⎠
In the last equation “(U1 – U2)” represents the phasor difference between U1 and U2. Without SSSC this would be the
voltage drop on reactance X = X1 + X2. The phasor of the injected voltage USSSC has the same direction as it is a
U1 −U 2
reactive voltage source (Fig. 4.8). This direction is determined by the term . Multiplication with the injected
U1 −U 2
voltage magnitude USSSC mathematically describes the phasor USSSC. The difference between (U1 – U2) and USSSC is
the sum of voltage drops on reactance X1 and X2 in the SSSC presence.
Figure 4.8. Model of the transmission system with SSSC referring to model in Fig. 4.7.
it is possible to calculate the current I, where one must be aware that only one of two solutions for I is the correct
one: the one with a minus sign. Therefore:
I = Re { I } + jIm { I }
where
⎛ USSSC ⎞
U1 ⋅ sin(δ1 − δ 2 ) ⋅ ⎜1 − ⎟
⎜ U 2
+ U 2
− 2 ⋅ U ⋅ U ⋅ cos(δ − δ ) ⎟
Re { I } = ⎝ 1 2 1 2 1 2 ⎠
X1 + X 2
⎛ USSSC ⎞
(U 2 − U1 ⋅ cos δ ) ⋅ ⎜⎜1 − ⎟
⎝ U12 + U 2 2 − 2 ⋅U1 ⋅U 2 ⋅ cos(δ1 − δ 2 ) ⎠⎟
Im { I } =
X1 + X 2
U1 ⋅U 2 ⋅ sin(δ1 − δ 2 ) ⎛ USSSC ⎞
P1 = ⋅ ⎜1 − ⎟
X1 + X 2 ⎜ U 2
+ U 2
− 2 ⋅ U ⋅ U ⋅ cos(δ − δ ) ⎟
⎝ 1 2 1 2 1 2 ⎠
Page 50
Voltage and VAr Support in System Operation WG C2.13
U1 ⋅U 2 ⋅ sin(δ 2 − δ1 ) ⎛ USSSC ⎞
P2 = ⋅ ⎜1 − ⎟
X1 + X 2 ⎜ U 2
+ U 2
− 2 ⋅ U ⋅ U ⋅ cos(δ − δ ) ⎟
⎝ 1 2 1 2 2 1 ⎠
U 22 − U1 ⋅U 2 ⋅ cos(δ 2 − δ1 ) ⎛ USSSC ⎞
Q2 = ⋅ ⎜1 − ⎟
X1 + X 2 ⎜ U 2
+ U 2
− 2 ⋅ U ⋅ U ⋅ cos(δ − δ ) ⎟
⎝ 1 2 1 2 2 1 ⎠
U A = U 1 − jI ⋅ X 1 = Re {U A } + jIm {U A }
where:
USSSC ⋅ X1
⋅ (U1 ⋅ cos(δ1 − δ 2 ) − U 2 ) + U 2 ⋅ X1 + U1 ⋅ X 2 ⋅ cos(δ1 − δ 2 )
U + U 2 − 2 ⋅U1 ⋅U 2 ⋅ cos(δ1 − δ 2 )
2 2
Re {U A } = 1
X1 + X 2
⎛ USSSC ⋅ X1 ⎞
U1 ⋅ sin(δ1 − δ 2 ) ⋅ ⎜ X 2 + ⎟
⎜ U 2
+ U 2
− 2 ⋅ U ⋅ U ⋅ cos(δ − δ ) ⎟
Im {U A } = ⎝ 1 2 1 2 1 2 ⎠
,
X1 + X 2
U A = Re {U A } + Im {U A } .
2 2
U B = U 2 + jI ⋅ X 2 = Re {U B } + jIm {U B }
where:
⎛ USSSC ⎞
X 2 ⋅ ⎜1 − ⎟ ⋅ (U1 ⋅ cos(δ1 − δ 2 ) − U 2 )
⎜ U 2
+ U 2
− 2 ⋅ U ⋅ U ⋅ cos(δ − δ ) ⎟
Re {U B } = U 2 + ⎝ 1 2 1 2 1 2 ⎠
X1 + X 2
⎛ USSSC ⎞
U1 ⋅ X 2 ⋅ sin(δ1 − δ 2 ) ⋅ ⎜1 − ⎟
⎜ U 2
+ U 2
− 2 ⋅ U ⋅ U ⋅ cos(δ − δ ) ⎟
Im {U B } = ⎝ 1 2 1 2 1 2 ⎠
X1 + X 2
U B = Re {U B } + Im{U B }
2 2
The amplitude for both voltages UA and UB, dependent on angle δ = δ1 − δ 2 , for various values of USSSC are
presented in Fig. 4.9 (SSSC is positioned in the electrical middle of a line, X1 = X2). One must be aware that in this
case, SSSC has a symmetrical effect on voltage magnitudes on both sides of SSSC. This can be explained by
studying a corresponding phasor diagram, depicted in Fig. 4.8.
Page 51
Voltage and VAr Support in System Operation WG C2.13
1,1
0,9
0,8
0,7
0,6
U 2 [p.u.]
R = 0; X = 0,3 p.u.
0,5
0
0 0,1 0,2 0,3 0,4 0,5 0,6 0,7 0,8 0,9 1 1,1 1,2 1,3 1,4 1,5 1,6 1,7 1,8 1,9 2
P load [p.u.]
Figure 4.9. Voltage amplitudes U2 for various values of USSSC.
The rated power, which is explained in the section 3.1 Voltage depression, of the STATCOM is determined:
SSSSC rated = USSSC ⋅ I rated = USSSC .
Figure 4.10. Model of the transmission system with PST: network impedance scheme.
Page 52
Voltage and VAr Support in System Operation WG C2.13
Figure 4.11. Model of the transmission system with PAR referring to model in Fig. 4.10.
As the controllable PAR parameter, the terminal voltage phasors separation (i.e. the angle α ) may be assumed.
According to basic relations the following equations can be written:
u PST1 = u1 − j ⋅ I 1 ⋅ X1
u PST2 = u PST1 ⋅ e jα
u PST2 − u 2
I 2 = I 1 ⋅ e jα =
j ⋅ X2
As already mentioned, PST powers are balanced. Therefore PAR input and output powers are equal i.e.
* *
u PST1 ⋅ I 1 = u PST2 ⋅ I 2 . From this relation it is easy to prove that the phasors I1 and I2 are shifted for the same angle α
as the PAR terminal voltages, whereas their magnitudes remain equal. Using above equations it is possible to
calculate I1 and consequently I2 as follows:
-1
I1 = j
X1 + X 2
( )
⋅ u1 − u 2 e-jα = Re {I 1} + jIm{ I 1}
-1
I2 = j
X1 + X 2
( )
⋅ u1e jα − u 2 = Re { I 2 } + jIm {I 2 }
where
and
U1 ⋅ sin (α + δ ) U 2 − U1 ⋅ cos (α + δ )
Re { I 2 } = Im {I 2 } =
X1 + X 2 X1 + X 2
Page 53
Voltage and VAr Support in System Operation WG C2.13
U1 ⋅U 2
P1 = P2 = P = ⋅ sin (δ + α )
X1 + X 2
where
and
U 2 ⋅ X1 + U1 ⋅ X 2 ⋅ cos (α + δ ) U1 ⋅ X 2 ⋅ sin (α + δ )
Re {u PST2 } = Im{u PST2 } =
X1 + X 2 X1 + X 2
Influence of PAR can be seen from Fig. 4.12, which has been obtained by placing PAR in the middle of the line (X1 =
X2). One must keep in mind that PAR changes only phase between u PST1 and u PST2 . Therefore, amplitude remains the
same and the graphs in Fig. 4.12 are the same for both voltages in question.
A device is denoted as “symmetrical” when transmission characteristics does not depend on orientation (how the PST
terminals are connected to the system – Fig. 4.10) and as “non-symmetrical” in the opposite case. The equations
describing PAR have been derived taking “orientation 1” into consideration. If they should also be valid for
“orientation 2”, then the system in Fig. 4.10 should be observed in the opposite direction, i.e. U1 should be replaced
with U2, X1 with X2, α with −α and δ with −δ . If those replacements are done, then in case of a “symmetrical”
device transmission characteristic remains unchanged (power flowing in opposite direction of the model, therefore
negative sign). Of course for a “non-symmetrical” device this is not the case.
Taking the above into consideration, PAR can be considered as a symmetrical device also in case of system voltage
influence.
Figure 4.12. Voltage amplitudes u PST1 and u PST2 for various values of α .
Page 54
Voltage and VAr Support in System Operation WG C2.13
u PST1 = u1 − j ⋅ I 1 ⋅ X 1
1
u PST2 = u PST1 ⋅ e jα ⋅
cos α
u PST2 − u 2
I 2 = I 1 ⋅ e jα ⋅ cos α =
jX 2
uPST1
uT
α uPST2
Figure 4.13. Model of the transmission system with QBT: corresponding phasor diagram.
* *
Following the fact, that power conditions are balanced also in the case of QBT (i.e. u PST1 ⋅ I 1 = u PST2 ⋅ I 2 ) expressions
for I1 and I2 can be written:
-1 ⎛ u ⎞
I1 = j ⋅ ⎜ 1 − u 2 ⋅ e-jα ⎟ = Re { I 1} + jIm{ I 1}
⎛ X1 ⎞ ⎝ cos α ⎠
⎜ cos α + X 2 ⋅ cos α ⎟
⎝ ⎠
-1
I2 = j
⎛ X1 ⎞
(u ⋅ e
1
jα
)
− u 2 ⋅ cos α = Re { I 2 } + jIm {I 2 }
⎜ cos α + X 2 ⋅ cos α ⎟
⎝ ⎠
where
sin δ cos δ
U 2 ⋅ sin α + U1 ⋅ U 2 ⋅ cos α − U1 ⋅
Re { I 1} = cos α Im{ I 1} = cos α
⎛ X1 ⎞ ⎛ X1 ⎞
⎜ cos α + X 2 ⋅ cos α ⎟ ⎜ cos α + X 2 ⋅ cos α ⎟
⎝ ⎠ ⎝ ⎠
and
U1 ⋅U 2
P1 = P2 = P = ⋅ sin (δ + α )
X1
+ X 2 ⋅ cos α
cos α
Page 55
Voltage and VAr Support in System Operation WG C2.13
where
Consequently, also regarding voltage influence, QBT can be considered as a non-symmetrical device. This can be
seen in Fig. 4.14 and Fig. 4.15, which have been obtained by placing QBT in the middle of the line (X1 = X2).
α=
+ 60º
Abs (uPST1) [p.u.]
+ 30º
2.00 0º
1.75 - 30º
1.50 - 60º
1.25
1.00
0.75
0.50
0.25
δ
[radian]
-1 0 1 2 3
Page 56
Voltage and VAr Support in System Operation WG C2.13
u UPFC2 = u UPFC1 + uT
u UPFC2 − u 2
I2 = = I1 − I Q − I T
jX 2
{ *
}
where (injected active power is balanced by IT i.e. Re u T ⋅ I 2 = u UPFC1 ⋅ I T ):
*
IT =
(
Re u T I 2
∗
)
∗
u UPFC1
Figure 4.16. Model of the transmission system with UPFC: network impedance scheme.
Figure 4.17. Model of the transmission system with UPFC: referring to model in Fig. 4.16.
Page 57
Voltage and VAr Support in System Operation WG C2.13
By splitting all complex quantities to their real and imaginary part and by replacing IQ with a parallel susceptance,
it is possible to determine currents I1 and I2 as functions of system parameters and UPFC controllable parameters.
Then it is easy to calculate voltages u UPFC1 and u UPFC2 . Derivation is quite comprehensive and is out of scope of this
work. Nevertheless, the result for real and imaginary part of I1 is given (physically correct solution is with a positive
sign):
K E2 ± eE1 ⋅ DET
Re { I 1} = −
2 ⋅ KE1
dE2 ⋅ eE1 ⋅ eE2 − dE2 ⋅ eE22 − 2 ⋅ dE0 ⋅ eE1 ⋅ eE3 ± eE2 ⋅ DET
Im{ I 1} = −
2 ⋅ KE1
where
KE22 − 4 ⋅ K E1 ⋅ KE3
DET =
eE12
and
dE0 = X1 ⋅ X 2 ( X1 ⋅ X 2 ( B2 + B3 + BT ) − X1 − X 2 )
( (
dE1 = X 2 ⋅ U 2 ⋅ X1 − UT ⋅ X1 ⋅ cos φT (1 − X 2 ⋅ B3 ) − U1 ⋅ cos δ ⋅ X 2 + 2 ⋅ X1 ⋅ (1 − X 2 ⋅ ( B2 + B3 + BT ) ) ))
( (
dE2 = X 2 ⋅ UT ⋅ X1 ⋅ sin ϕT (1 − X 2 ⋅ B3 ) + U1 ⋅ sin δ ⋅ X 2 + 2 ⋅ X1 ⋅ (1 − X 2 ⋅ ( B2 + B3 + BT ) ) ))
(
dE3 = U1 ⋅ X 2 U 2 ⋅ cos δ − U1 ⋅ (1 − X 2 ⋅ ( B2 + B3 + BT ) ) − UT ⋅ cos (ϕT − δ ) ⋅ (1 − X 2 ⋅ B3 ) )
eE1 = −U1 X 22 ⋅ sin δ
eE2 = − X 2 ⋅ (U 2 ⋅ X1 + U1 ⋅ X 2 ⋅ cos δ )
As in the case of UPFC three different control parameters exist, influence of all three on voltages u UPFC1 and u UPFC2
will be shown. One must keep in mind, that orientation 1 is used for obtaining the following graphs.
First, let us take a look at the influence of UT, where IQ and ϕT are set to zero.
Page 58
Voltage and VAr Support in System Operation WG C2.13
Next, let us take a look at the influence of ϕT , where IQ is set to zero and UT to its maximum value of 0,5. In this
way, the influence of ϕT variation can be best seen.
Page 59
Voltage and VAr Support in System Operation WG C2.13
Finally, let us observe also the influence of IQ, where UT is set to zero. In this way, ϕT has no effect, as it is a phase
angle of injected voltage uT. It os obvious that since UT = 0, u UPFC1 equals u UPFC2 .
1.75
1.50
IQ =
1.25
-1.0
1.00 -0.5
0
0.75
0.5
0.50 1.0
0.25
δ
[radian]
-1 0 1 2 3
Figure 4.22. Voltage amplitudes u UPFC1 and u UPFC2 for various values of IQ.
Page 60
Voltage and VAr Support in System Operation WG C2.13
Conclusion
Voltage and Reactive Power Support is a vital issue in System Operation. This problem is a complicated one in the
case of a large interconnected system. This issue has been examined in the past and a CIGRE TB was published five
years ago. But, the reality in electric power systems is developing in such a very fast pace that it was decided to
examine anew this issue and report the latest developments. Thus this Technical Brochure dwells within the context of
the Technical Issue #8 New Tools for system Technical performance assessment, because of new Customer, Generator
and Network characteristics of the CIGRE Technical Committee’s Project “Network of the Future” [3]. In accordance
with the Terms of Reference (ToR) of WB C2.13, it takes into account the issues of Distributed Generator
characteristics, the evolution of power system control at Continental, Country, Regional, and Local level, as well as
the increased level of automation in Control Centres, and last but not least the available now latest technological
means and ways, and reports best practices within Europe and China. Very valuable information is provided for all
the interested on the subject professionals in electric power systems and the electricity sector at large.
Page 61
Voltage and VAr Support in System Operation WG C2.13
Bibliography/References
[1] CIGRE Task force C4.602, “Coordinated voltage control in transmission networks”, February 2007
[2] CIGRE technical activities, “Strategic Directions 2010-2012”, ELECTRA no. 249, pp. 6-12, April 2010
[3] CIGRE TC Advisory Group Report, “CIGRE WG – Network of the Future. Electricity Supply Systems of the
future”, ELECTRA no. 256, pp. 42-49, June 2011
[4] R. Mihalič, D. Povh, "Limits of long distance power transmission", Proceedings on 4th International Conference
on Deregulated Electricity Market Issues in South-Eastern Europe, DEMSEE 2009, Belgrade, Serbia, September 17-
18, 2009
[5] J.P. Paul, J.T. Leost, and J.M. Tesseron, “Survey of the Secondary Voltage Control in France: Present
Realization and Investigations,” IEEE Transactions on Power Systems, vol. 2, no.2, pp. 505-511, 1987
[6] M. D. Ilic, “Secondary Voltage Control Using Pilot Information”, IEEE Transactions on Power Systems, vol.3,
no.2, pp. 660-668, 1988
[7] P. Lagonotte, J. C. Sabonnadiere, J.Y. Leost, J.P. Paul, “Structural analysis of the electrical system: application
to secondary voltage control in France”, IEEE Transactions on Power Systems, vol.4, no.2, pp.479-486, 1989
[8] V. Arcidiacono, S. Corsi, A. Natale, C. Raffaelli, “New Developments in the Applications of ENEL Transmission
System Automatic Voltage and Reactive Control”, CIGRE, Report 38/39-06, Paris 1990
[9] S. Corsi, M. Pozzi, C. Sabelli, et al. The coordinated automatic voltage control of the Italian transmission grid -
Part I: Reasons of the choice and overview of the consolidated hierarchical system. IEEE Transactions on Power
Systems, vol.19, no.4, pp.1723-1732, 2004
[10] S. Corsi, M. Pozzi, M. Sforna, et al. The coordinated automatic voltage control of the Italian transmission grid -
Part II: Control apparatuses and field performance of the consolidated hierarchical system. IEEE Transactions on
Power Systems, vol.19, no. 4, pp.1733-1741, 2004
[11] Hongbin Sun, Boming Zhang, Qinglai Guo, Zhixin Yang, Xiaoying Wang, Haifeng Li, “Design For system-wide
Optimal Voltage Control System Based On adaptive Zone Division”, Automation of Electric Power Systems, vol.27,
no.8, pp. 16-20, 2003 (In Chinese)
[12] Hongbin Sun, Qinglai Guo, Boming Zhang, Wenchuan Wu, Jianzhong Tong, “Development and Applications of
System-wide Automatic Voltage Control System in China”, IEEE PES Genenral Meeting, Calgary, Alberta, Canada,
Invited Panel Paper, Paper Number: 09GM0707, July 26-30, 2009
[13] Qinglai Guo, Hongbin Sun, Jianzhong Tong, Mingye Zhang, Bin Wang, Boming Zhang, “Study of System-wide
Automatic Voltage Control on PJM System”, IEEE PES General Meeting, Minneapolis, Minnesota, USA, Paper
Number: 2010GM0918, July 25-29, 2010
[14] Qinglai Guo, Hongbin Sun, Boming Zhang, Wenchuan Wu, “Power Network Partitioning Based on Clustering
Analysis in Mvar Control Space”, Automation of Electric Power Systems, vol.29, no.10, pp.36-40, 2005 (In Chinese)
[15] J.Carpentier, ”Optimal Power Flows”, Int. J. Elec. Power and Energy Syst., 1(1): 3-15, April 1979
[16] Z. Yan, N. D. Xiang, B. M. Zhang, S. Y. Wang and T. S. Chung, “A Hybrid Decoupled Approach to Optimal
Power Flow”, IEEE Transactions on Power Systems, vol.11, no. 2, pp.947-954, 1996
[17] H. Lefebvre, D. Fragnier, J. Y. Boussion, et al. “Secondary Coordinated Voltage Control System: Feedback of
EDF”, IEEE summer meeting, SEATTLE, 2000
Page 62
Voltage and VAr Support in System Operation WG C2.13
[18] H. Vu, P. Pruvot, C. Launay, et al. “An Improved Voltage Control on Large-scale Power System”, IEEE
Transactions on Power Systems, 11(3): 1295-1303, 1996
[19] J. L. Sancha, J. L. Fernandez, A. Cortes, “Secondary Voltage Control: Analysis, Solutions and Simulation Results
for the Spanish Transmission System”, IEEE Transactions on Power Systems, 11(2): 630-638, 1996
[20] A. Conejo, M. J. Aguilar, “Secondary voltage control: nonlinear selection of pilot buses, design of an optimal
control law, and simulation results”, IEE Proceedings: Generation, Transmission and Distribution, 145(1): 77-81, 1998
[21] Qinglai Guo, Hongbin Sun, Boming Zhang, Wenchuan Wu, Qin Li, “Study on Coordinated Secondary Voltage
Control”, Automation of Electric Power Systems, vol.29, no.23, pp.19-24, 2005 (In Chinese)
[22] J. Van Hecke, N. Janssens, J. Deuse, and F. Promel, “Coordinated Voltage Control Experience in Belgium”,
CIGRÉ, paper 39-111, 2000
[23] S. Corsi, M. Pozzi, U. Bazzi, M. Mocenigo, P. Marannino, “A Simple Real-Time and On-Line Voltage Stability
Index Under Test in Italian Secondary Voltage Regulation”, CIGRÉ, paper, 38-115, 2000
[24] Qinglai Guo, Hongbin Sun, Boming Zhang, Wenchuan Wu, Bin Wang, Zhuhua Li, Lei Tang, “Coordination
method between continuous variables and discrete variables for automatical voltage control -- Part II: coordinated
voltage control among power plants and substations”, Automation of Electric Power Systems, vol.32, no.9, pp.65-68,
2008 (In Chinese)
[25] Hongbin Sun, Boming Zhang, “Distributed Power Flow Calculation for Whole Networks Including Transmission
and Distribution”, Proceedings of 2008 IEEE PES Transmission and Distribution Conference and Exposition, , Chicago,
USA, Paper Number: 08TD0258, pp.157-162, April 21-24 2008
[26] Bin Wang, Qinglai Guo, Hongbin Sun, Boming Zhang, Haifeng Li, Jianyu Luo, “Reserach and implementation
of bidirectional coordinated voltage control between provincial and district power networks”, Automation of Electric
Power Systems, vol34, no12, pp.53-57, 2010 (In Chinese)
[27] ELES, www.eles.si, current web page of the Slovenian TSO
[28] Ye Jian, Li Mingjie, Zhou Ji, "Research on Reactive Power and Voltage Control Strategies for the UHV AC
Demonstration Project", Proceedings of the CSEE, 2009, V29, No.22, p25-29
[29] Liu Mengxin, Xu Lei, Yang Peng, "Analysis of the Security and Stability of Ease China Power System after
Constructing UHV AC Grid", High Voltage Engineering, V36, No.1, pp.296-300, 2010
[30] G. E. Balog, K. Bjorlow-Larsen, “Long three core XLPE power cables”, CIGRE Symposium, System development
and asset management under restructuring”, Osaka Japan, November 01-04, 2007
[31] M. Del Brenna, F. Donazzi, A. Mansoldo, “Long length EHV underground cable systems in the transmission
Network”, CIGRE Session, B1-304, 2004.
[32] P. Coventry et al., “New generation of GIL, Characteristics and applications”, CIGRE Session B1-103, 2004
[33] CIGRE Task Force 38.01.11, “Superconducting cables. Impact on network structure and control”, Electra, No
200, February 2002
[34] P. Kundur, “Power System Stability and Control”, book, McGraw-Hill, 1994
[35] CIGRE Joint Working Group 21/22.01, ‟Comparison of high voltage overhead lines and underground
cables”, Report No. 110, December 1996
[36] C. W. Taylor, “Voltage Stability Analysis with Emphasis on Load Characteristics and Undervoltage Load
Shedding”, IEEE/PES Summer Meeting, Long Beach, CA, July 10, 1988
Page 63
Voltage and VAr Support in System Operation WG C2.13
[37] C. Vournas, “Technical Summary on the Athens and Southern Greece Blackout of July 12, 2004”, Electrical
Energy Systems Lab., School of Electrical & Computer Engineering, National Technical University of Athens, 2004
[38] IEEE Power System Relaying Committee, Substation Protection Subcommittee, Working Group K12 - M.
Begovic, J. Bright, T. Domin, S. Easterday-McPadden, A. Girgis, W. Hartmann, C. Henville, M. Ibrahim, K.Kozminski, R.
Marttila, G. Michel, K. Mustaphi, D. Novosel, B.Pettigrew, M. Sachdev, H. Shuh, P. Solanics, J. Williams, “Voltage
Collapse Mitigation Report to IEEE Power System Relaying Committee”, December 1996
[38] WECC, “Undervoltage Load Shedding Guidelines”, June 1999
[39] PSE-Operator S.A., www.pse-operator.pl
[40] R. Mihalič, D. Povh, P. Žunko, "Flexible ac transmission systems (FACTS), Chapter 11, Transient stability
control", edited by Yong Hua Song and Allan T. Johns, The Institution of Electrical Engineers, London, UK, 1999
[41] IEEE/CIGRE Joint Task Force on Stability Terms and Definitions, “Definition and Classification of Power System
Stability”, IEEE transactions on Power Systems, vol. 19, no. 2, May 2004
Page 64